C107C1 - CAT TH580B Chain Shackles - Dist PDF
C107C1 - CAT TH580B Chain Shackles - Dist PDF
C107C1 - CAT TH580B Chain Shackles - Dist PDF
Reference: #C107C1
August 1, 2007
ATTENTION: This notice is being issued to advise you of the requirement to update certain
Caterpillar (“CAT”) Telehandlers that were manufactured by JLG Industries,
Inc. (“JLG”). This program must be completed as soon as possible on all
affected machines.
PROBLEM:
Reports indicate that the boom chains are being incorrectly adjusted during boom servicing.
Incorrect adjustment of the chains may cause premature failure of the chain shackles. The
failure of both chain shackles will result in the inability to retract the boom or uncontrolled
restraint of the outer boom sections when the boom angle is below horizontal. This could result
in a crushing hazard or loss of load.
AFFECTED PRODUCTS:
This issue affects certain CAT Telehandlers Model TH580B manufactured by JLG. The affected
machines have the following serial numbers:
Page 1 of 3
PARTS NEEDED:
The following parts must be ordered to accomplish this update:
ACTION REQUIRED:
Parts Stock
Remove all original shackles (#2197084) from dealer parts stock.
Affected Machines:
- Perform the enclosed Chain Shackle Replacement Procedure:
- Replace the original boom retract chain shackles with new chain shackles designed to
reduce the risk of incorrect adjustment.
- Adjust the chain shackles using the new adjustment procedure.
- Order a new Operation and Maintenance Manual using the enclosed Manual Order Form.
- Remove and discard the original Operation and Maintenance Manual. Install the new
Operation and Maintenance Manual on the machine prior to returning it to service.
Page 2 of 3
PARTS DISPOSITION:
Handle the parts in accordance with your Warranty Bulletin on warranty parts handling.
CONTACTS:
A copy of this Service Letter will be available on the JLG-CAT Alliance website. If you have any
questions or need further information, please contact the JLG Product Safety and Reliability
Department by:
Email: [email protected]
Telephone: +1 717 485 6591
Enclosures:
Chain Shackle Replacement Procedure
Manual Order Form
Page 3 of 3
PROCEDURE: Chain Shackle Replacement, Service Letter #C107C1
MODELS: CAT Telescopic Material Handlers Model TH580B
Parts/Material Required:
- Cotter, #3B4605, quantity 4
- Pin, #3072248, quantity 2
- Shackle, #3072247, quantity 2
- Updated Operation and Maintenance Manual, quantity 1
Procedure:
1. Position machine on a firm and level surface. Fully retract and raise the boom to
approximately 5 degrees above horizontal. Turn off engine and apply park brake.
2. Locate and remove the locking nut (outer nut) from the single extension chain
shackle. Reference Figure 1. Loosen, but do not remove the adjusting nut from
the same shackle. Leave adjusting nut engaged on the last two threads of the
shackle.
Figure 1
Page 1 of 11
3. Loosen and remove the fastening nuts from the two boom retract chain shackles
located on the underside of the second boom section toward the front of the
machine. Reference Figure 2.
Figure 2
4. Remove the service cover from the rear of the machine to access the boom
retract chain pulleys.
5. Locate the retract chain pulleys in the rear of the boom. Reference Figure 3.
Figure 3
Page 2 of 11
6. Remove the pulley pin retaining bolts (A) and the pulley pins (B). Reference
Figure 4.
Figure 4
Figure 5
Page 3 of 11
8. Push the threaded end of the shackles through the holes toward the center of the
boom. Reference Figure 6.
Figure 6
9. Start the machine. Telescope the boom out by approximately 150 mm and shut
down the machine. Reference Figure 7.
Figure 7
Page 4 of 11
10. Pull both shackles out from the front of the boom. Reference Figure 8.
Figure 8
11. Remove the cotters and chain attachment pins from both shackles and remove
the shackles.
12. Install the new shackles (#3072247), chain attachment pins (#3072248), and
cotters (#3B4605).
13. Replace the shackles through the locating holes. Place a string through the
shackle between the chain attachment pin and the end of the shackle. Use the
string to pull the shackle back through the locating hole. Reference Figures 9
and 10.
Figure 9
Page 5 of 11
Figure 10
14. Once the shackles are through the positioning holes, add the washers and nuts
to prevent the shackles from slipping back through the anchor point. Only attach
the nuts by 5 mm of thread.
15. Start the machine and slowly raise the boom to approximately 45 degrees. Then
fully telescope the boom inward.
16. Lower the boom to 5 degrees above horizontal and shut down the machine.
17. Replace the retract chain pulleys and pulley pins at the rear of the boom. Ensure
that the grease fittings are facing outward, and the fastening bolts are located on
the flat part of the pin.
18. Grease the retract chain pulleys with the type and amount of grease specified in
the Operation and Maintenance Manual for the machine.
19. Before beginning the boom chain adjustment procedure, ensure the machine is
on firm, level ground with the park brake applied.
20. Lower the stabilizer legs (outriggers) and fully extend the boom. If necessary,
raise it to an appropriate height to allow access to the retraction chain shackles
on the underside of the boom.
21. Place a suitable stand underneath the boom for additional support, and turn off
the engine.
22. Remove the locknuts from all seven (7) of the boom chain shackles.
23. Loosen the adjustment nuts on all chain shackles until the end of the shackle is
flush with the end of the nut. Ensure no threads are protruding from any of the
adjustment nuts.
Page 6 of 11
24. Start the engine and retract the boom 200 mm (7.87 in). Once the boom is
retracted, turn off the engine.
25. Adjust the retraction chains underneath the first boom section such that 30 mm
(1.18 in) of thread is exposed between the outer face of the nut and the end of
the thread on the shackle. Reference Figure 11.
Figure 11
26. Adjust the retraction chain shackles underneath of the second boom section until
15 mm (0.59 in) of thread is exposed between the outer face of the nut and the
end of the thread on the shackle. Reference Figure 12.
Page 7 of 11
Figure 12
Page 8 of 11
27. Tighten the extension chain nuts on the first section evenly, regularly switching
from left to right, until the clearance between each chain and the boom section is
90 mm (3.54 in). Reference Figures 13 and 14.
Figure 13
90mm
Figure 14
Page 9 of 11
28. Tighten the extension chain on the second section until the clearance between
the chain and the boom section is 90 mm (3.54 in). Reference Figures 14 and
15.
Figure 15
29. Remove the stand and all tools from the working area and start the machine.
30. Fully retract the boom and then fully extend the boom. Retract the boom again,
only by 200 mm (7.87 in).
31. Turn off the machine, and replace the stand beneath the boom.
32. Check the clearance between all extension chains and the boom sections. For
each extension chain, the proper adjustment measurement is 90 mm (3.54 in).
Reference Figure 14.
33. If the adjustment is less than 90 mm (3.54 in), tighten the appropriate extension
chain shackles to achieve the required adjustment (90 mm). Reference Figures
13 and 15.
34. Fully retract the boom and then fully extend the boom.
35. With the boom at full extension, verify the clearance between the chain and the
boom is, at minimum, 90 mm (3.54 in).
Page 10 of 11
36. If this is not the case, repeat the adjustment procedure, until proper adjustment in
each chain is consistently achieved.
37. Add and tighten the lock nuts on all chain shackles.
38. Before the machine is returned to service, ensure all shackles are lying straight
within the box section if the boom and are not twisted.
40. Discard the original Operation and Maintenance Manual. Install an updated
Operation and Maintenance Manual in the appropriate location on the machine.
42. The machine may be returned to service once proper operation is confirmed.
Page 11 of 11
MANUAL ORDER FORM
Reference #C107C1
Specify Operation and Maintenance Manual (Limit one per serial number):
Languag
(3) Language Part Number Qty. (3) e
Part Number Qty.
Submitted by:
Name:
Company:
Address:
Address:
Country: Tel #:
Signature: Date: