General: The City of
General: The City of
General: The City of
1. GENERAL
This Section specifies requirements for excavating trenches, and backfilling for
installation of pipelines, sewers, conduits, and appurtenances.
1.2 Definitions
.2 Rock Excavation: Rock excavation shall be paid for when the material
encountered consists of mass or bedrock or a boulder of volume greater
than 0.75 cubic meters. Such rock excavation is divided into two
V2005.0
THE CITY OF TRENCH EXCAVATION, BACKFILL, Section 02315
RED DEER AND COMPACTION Page 2 of 11
categories; (A) and (B), contingent upon its hardness and difficulty
experienced in excavation. It shall be the Contractor’s responsibility to
demonstrate, to the Engineer’s satisfaction that the material cannot be
removed or that difficulty is being experienced through excavation by
conventional means. In doing so, the Contractor may be required by the
Engineer to seek and explore planes of weakness or layers that may ease
the excavation process. Frozen material is not classified as rock.
.5 Initial Backfill: Material placed within the trench, above the spring line of
the pipe to 300 mm above the crown of the pipe.
Class A
V2005.0
THE CITY OF TRENCH EXCAVATION, BACKFILL, Section 02315
RED DEER AND COMPACTION Page 3 of 11
Class B
1.3 Protection
V2005.0
THE CITY OF TRENCH EXCAVATION, BACKFILL, Section 02315
RED DEER AND COMPACTION Page 4 of 11
.4 Access
.5 Flooding
Protect open excavation against flooding and damage from surface water
run-off.
V2005.0
THE CITY OF TRENCH EXCAVATION, BACKFILL, Section 02315
RED DEER AND COMPACTION Page 5 of 11
.2 Trench depth shall be the vertical distance between the ground surface
immediately prior to excavation and the pipe invert as measured at
V2005.0
THE CITY OF TRENCH EXCAVATION, BACKFILL, Section 02315
RED DEER AND COMPACTION Page 6 of 11
Tendered unit price for each crossing shall include all extra costs,
including but not limited to, support of the utility, utility crossing
agreements, and utility inspection charges over and above normal
V2005.0
THE CITY OF TRENCH EXCAVATION, BACKFILL, Section 02315
RED DEER AND COMPACTION Page 7 of 11
excavation costs.
2. PRODUCTS
.2 40 mm screened rock,
.4 16 mm crushed gravel, or
.1 To minimize fill settlement under self weight, excavated soil with a water
content exceeding the plastic limit of the soil by more than 10% should
not be used as fill unless the moisture content is lowered.
.2 Wet fill material should be dried or blended with drier material prior to
use as a trench backfill. If this is not practical, the wet material should be
wasted or used in landscape areas and berms where bearing capacity is not
required.
V2005.0
THE CITY OF TRENCH EXCAVATION, BACKFILL, Section 02315
RED DEER AND COMPACTION Page 8 of 11
3. EXECUTION
.1 Remove trees, shrubs, vegetation, fences, and other obstructions, ice and
snow, from surfaces to be excavated within limits indicated.
.2 Strip top soil from within limits of excavation and stockpile as directed,
for respreading after backfilling.
3.2 Dewatering
3.3 Excavation
V2005.0
THE CITY OF TRENCH EXCAVATION, BACKFILL, Section 02315
RED DEER AND COMPACTION Page 9 of 11
approved location.
.2 Granular Bedding
V2005.0
THE CITY OF TRENCH EXCAVATION, BACKFILL, Section 02315
RED DEER AND COMPACTION Page 10 of 11
.6 Place material by hand under, around, and over pipe until 300 mm
of cover is provided. Dumping material directly on pipe will not be
permitted.
3.6 Backfilling
.1 This Clause shall apply to the installation of power, gas, telephone, and
V2005.0
THE CITY OF TRENCH EXCAVATION, BACKFILL, Section 02315
RED DEER AND COMPACTION Page 11 of 11
.4 It is the intent of this Clause that the 90% Standard Proctor Density
be achieved using a rubber-tired backhoe or similar construction
equipment.
.4 Allow 48 hours curing time prior to working over top of fill concrete.
3.9 Restoration
V2005.0