SECTION 2700 Final
SECTION 2700 Final
SECTION 2700 Final
2701 REQUIREMENTS
2701.1 Design of a drainage system for buildings and structures shall aim to
provide self cleansing conduits for the conveyance of soil, waste,
surface or sub surface waters and for the removal of such wastes
speedily and efficiently to a sewer or other outlet, without risk of
nuisance and hazard to health.
2701.3 Normally a sewer shall be designed for discharging three times the dry
weather flow, flowing half full with a minimum self cleansing velocity of
0.75 metres/sec. Approximate gradients which generate this velocity
for the sizes of pipes likely to be used in building drainage and
corresponding discharges when flowing half-full are given in Table
2700.1
2701.6 Work specifications for the works involved in various drainage works
such as earth excavation, brick work, cement concrete, plastering etc.
shall be followed as described under different sections of Part I of
Technical Specifications.
TABLE 2700.1
2702.1.1 For all sewers and drains, glazed stone ware pipes shall be used as far
as possible, in preference to other types of pipes. These are suitable
particularly where acid effluents or acidic sub soil conditions are likely
to be encountered.
2702.2 Trenches
2702.2.1 Trenches shall be so dug that the pipe can be laid to the requirement
alignment and at the required depth. Under a roadway or track
formation a minimum cover / cushion of 90 cm is recommended.
Trenches shall be shored and drained to ensure safety and efficiency
of workmen. Trench excavation shall precede pipe laying only to the
extent permitted by Engineer.
b) for all diameters, for all depths above 120 cms. = dia of pipe in cm
+ 40 cm.
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 2 of 17
Specifications RVNL
c) notwithstanding (a) and (b), total width of trench shall not be less
than 75 cm for depths exceeding 90 cm.
2702.3 Laying
2702.4 Pipes shall be carefully laid to alignments, level and gradients shown
on plans and sections. Sand is to be prevented from entering into the
pipes. Pipes between two manholes shall be laid truly in a straight line
without vertical or horizontal undulation. Pipes shall be laid with socket
up the gradient. Pipes shall, for their entire length rests on an even bed
of concrete and recesses shall be formed in concrete by scooping to
receive socket of the pipe.
2702.5 Where the floor of the trench consists of rock or very hard ground that
cannot be easily excavated to smooth surface, the pipe shall be laid on
a levelling course of concrete.
2702.6 Where SW pipes are used for storm water drainage, no concrete will
normally be necessary. Cement mortar for jointing will be 1:3 (1
cement : 3 fine sand). Testing of joints will also not be done.
2702.7 Jointing
2702.7.1 Tarred gasket of hemp yard soaked in thick cement slurry shall first be
placed round the spigot of each pipe and the spigot shall then be
slipped home well into the socket of a previously laid pipe. The pipe
shall then be adjusted and fixed in the correct position and the gasket
should then be caulked tightly home so as to fill not more than ¼ of the
total depth of the socket.
2702.7.2 The remainder of the socket shall be filled with a stiff mixture of cement
mortar in the proportion of (1 cement: 1 fine sand). When the socket is
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 3 of 17
Specifications RVNL
filled, a fillet shall be formed round the joint with a trowel forming an
angle of 45 degree with the barrel of the pipe. While each pipe is fitted,
it should be seen that no extraneous material is left inside the pipe.
2702.7.3 After a day’s work any extraneous material left shall be removed from
inside of pipe and the end temporarily closed to prevent entry of any
such material or creature. Newly made joints shall be cured.
2702.8.1 Stoneware pipes used for sewers shall be subjected to a test pressure
of 2.5 m head of water at the highest point of the section under test.
The test shall be carried out suitably, plugging the lower end of the
drain and the ends of the connection, if any and filling the system with
water. A knuckle bend shall be temporarily joined in at the top end
and a sufficient length of vertical pipe joined to it , so as to provide the
required test head or the top may be plugged with a connection to a
hose ending in a funnel which could be raised or lowered till the
required head is obtained and fixed suitably for observation.
2702.8.2 If any leakage is visible, the defective part of the work shall be cut out
and made good. A slight amount of sweating which is uniform may be
overlooked, but excessive sweating from a particular pipe or joint shall
be watched for and taken as indicating a defect to be made good. Any
joint found leaking or sweating shall be rectified or embedded in 15 cm
layer of cement concrete (1:2:4), 30 cm in length and section re-tested.
2702.9 Refilling
Where pipes are not bedded on concrete, special care shall be taken in
refilling trenches to prevent displacement and subsequent settlement.
Backfill shall be packed by hand under and around the pipe, and
rammed with a shovel and light tamper. Refilling shall be done in
layers and should rise evenly on both sides of the pipe, continued upto
60-cm above the top of pipe, so as not to disturb the pipe. No tamping
should be done within 15 cm from top of pipe.
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 4 of 17
Specifications RVNL
2702.11 Rate
Rate shall include cost of materials and labour involved in all the
operations described above excluding cost of trenches, refilling and
cement concrete wherever required which shall be paid for separately
under relevant items of work unless otherwise specified.
The pipes shall conform to IS:458, be of the specified class and be with
or without reinforcement. Reinforced cement concrete pipes shall be
manufactured by Centrifugal (or spun) process; un-reinforced cement
concrete pipes shall be manufactured by spun or pressure process. All
pipes shall be true to shape, straight, perfectly sound and free from
cracks and flaws. External and internal surfaces of the pipes shall be
smooth and hard. Pipes shall be free from defects arising from
imperfect grading of aggregate mixing or moulding.
2703.2 Trenches
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 5 of 17
Specifications RVNL
TABLE 2700.2
CONCRETE PIPES
2703.3 Laying
2703.3.1 If pipes have spigot and socket joints, socket ends shall face upstream.
In case of pipes with collar joints, the collars shall be slipped on before
the next pipe is laid. Laying shall preferably be from lower end.
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 6 of 17
Specifications RVNL
2703.3.2 At locations where natural foundation is inadequate, the pipes shall be
laid either in concrete cradle, supported on proper foundations or any
other suitably designed structure. If concrete cradle bedding is used,
the depth of concrete below the bottom of the pipe shall be at least
1/4th of the internal diameter of the pipe subject to a minimum of 10 cm
and maximum of 30 cm. Concrete shall extend upto the sides of the
pipe at least to a distance of 1/4 th outside diameter of pipes 300 mm
and over in diameter. The pipe shall be laid in this concrete bedding
before the concrete has set. In other cases, also the base shall be well
compacted preferably by spreading a layer of gravel or coarse sand
and base formed to receive the pipes.
2703.3.3 When a pipe is laid in a trench in rock, hard clay, shale or other hard
material, the space below the pipe shall be excavated and replaced
with an equalising bed of concrete, sand or compacted earth of 15 cm
thickness or as decided by the engineer. In no place shall the pipe be
laid directly on such hard material .
Joints are generally of rigid type. Where specified flexible type joints
may also be provided as per IS:783.
The spigot of each pipe shall be slipped home well into the socket of
the pipe previously laid and adjusted in the correct position. The
opening of the joint shall be filled with a stiff mixture of cement mortar
1:2 (1 cement : 2 ordinary sand) which shall be rammed with caulking
tool.
The collar shall be slipped on pre-laid pipe before the next pipe is laid.
The two adjoining pipes shall then be butted against each other and
adjusted in the correct position; the collar is brought over the joint
covering both pipes equally. The caulking space between the collar
and pipes, shall be uniform all round. The annular space shall be filled
with stiff mixture of cement mortar 1:2 (1 cement : 2 ordinary sand)
which shall be rammed with caulking tool.
2703.4.3 After a joint is made, any surplus material shall be removed from inside
of pipe and the newly made joint shall be cured for at least 10 days.
2703.5 Testing
For pressure pipes, the completed pipe line shall be tested for pressure
(site test pressure) which shall not be less than the maximum pipe line
operating pressure plus the calculated surge pressure, but in no case
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 7 of 17
Specifications RVNL
shall it exceed the hydrostatic test pressure. For non-pressure pipes
the joints shall be tested as per procedure laid down in Sub Clause
2702.8.
Stipulations made in Sub Clause 2702.10 shall hold good here also.
2703.8 Rate
Rate shall include cost of all labour and materials involved in all the
operations described above.
2704 MANHOLES
2704.1 General
Sewers of unequal sectional area shall not be joined at the same invert
in a manhole. The invert of the smaller sewer at its junction with main
shall be at least 2/3 diameter of main above invert of main. The branch
sewers shall deliver sewage in the manhole in the direction of main
flow and the junction must be made with care so that flow in main is not
impeded.
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 8 of 17
Specifications RVNL
No drain from house fittings, e.g. gully trap or soil pipe etc. to manhole
shall normally exceed a length of 6 m, unless unavoidable and
approved by engineer.
2704.3 Construction
2704.3.1 Excavation – The man hole shall be excavated true to dimensions and
levels shown in the drawings or as directed by engineer.
2704.3.2 Bed concrete – This shall be of cement concrete mix 1:4:8 (1 cement :
4 coarse sand : 8 graded stone aggregate 40 mm nominal size).
Thickness of bed concrete shall be :
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 9 of 17
Specifications RVNL
2704.3.3 Brick Work – This shall be with class designation bricks in cement
mortar 1:5 ( 1 cement : 5 fine sand).
The external joints of brick masonry shall be finished smooth, and the
joints of the pipe with the masonry shall be made perfectly leak proof.
For arched type and circular manholes, brick masonry in arches and
arching over the pipes shall be in cement mortar 1:3 (1 cement : 3
sand).
All manholes deeper than 0.8 m shall be provided with M.S. foot-rests.
These shall be embedded 20 cm deep in 20x20x10 cm block of cement
concrete 1:3:6 (1 cement: 3 coarse sand: 6 graded stone aggregate 20
mm nominal size). Foot rests which shall be of 20x20 mm square
M.S. bars shall be fixed 30 cm apart vertically and staggered laterally;
they shall project 10 cm beyond surface of wall. The top footrest shall
be 45 cm below the manhole cover.
Foot rests shall be painted with coal tar and, the portion embedded in
masonry to be painted with cement slurry before fixing.
The covers and frames shall be cleanly cast and they shall be free from
air and sand holes and from cold shuts. All castings shall be free from
voids due to any cause.
The covers shall be capable of easy opening and closing and shall be
fitted in the frames in workman-like manner. The covers shall be gas-
tight and water-tight.
2704.7 Rate
Rate shall include cost of labour and materials for all the operations
described above but shall exclude the cost of
i) Excavation
2705.1 Materials
Gully traps shall conform to IS:651. They shall be sound, free from
visible defects such as fire cracks or hair cracks. The glaze of the
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 11 of 17
Specifications RVNL
traps shall be free from crazing. They shall give a sharp clear note
when struck with light hammer. There shall be no broken blisters.
Each gully trap shall have one CI grating of square size corresponding
to dimensions of inlet gully trap. It will also have a water-tight CI cover
with frame, inside dimensions 300 mm x 300 mm, the cover weighing
not less than 4.5 kg and frame not less than 2.70 kg. The grating cover
and frame shall be of sound and good casting and shall have truly
square machined seating faces.
2705.2 Fixing
After fixing and testing the gully and branch drain, a brick masonry
chamber shall be built round the gully trap from the top of the bed
concrete upto ground level. The chamber works will be in brick
masonry in cement mortar 1: 5 (1 cement: 5 fine sand). The space
between the chamber walls and the trap shall be filled with cement
concrete of the same mix as for the bed concrete. The upper portion of
the chamber i.e. above the top level of the trap shall be plastered
inside with cement sand mortar 1:3 (1 cement: 3 coarse sand) with
water proofing compound added finished with a floating coat of neat
cement. The corners and bottom of the chamber shall be rounded off
so as to slope towards the grating.
2705.4 CI Cover
CI cover with frame 300 x 300 mm (inside) shall then be fixed on top of
the brick masonry with cement concrete 1:2:4 (1 cement: 2 coarse
sand : 4 stone aggregate 20 mm nominal size) and rendered smooth.
The finished top of cover shall be left about 4 cm above the adjoining
ground level so as to exclude surface water from entering the gully
trap.
2705.5 The structural details such as chambers size, thickness of bedding, mix
of concrete and mortars in plastering and brick work, C.I. cover frame
size shall hold good unless otherwise specified under the item of work,
indicated in drawings or as directed by engineer.
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 12 of 17
Specifications RVNL
The work shall be enumerated as a unit. Excavation shall be
measured separately under relevant item of earthwork.
2705.7 Rate
Rate shall include cost of all labour, fixture and material involved in all
the operations described above except earthwork, which shall be paid
for separately.
i) Horizontal
ii) Vertical
The structural details i.e. size, thickness of bed concrete, concrete mix,
brick work, finishing of walls, grating details etc. shall be as shown in
approved drawings or as directed by engineer. All works shall be
carried out to the requirements of specifications stipulated for the
individual item.
2706.3 Rate
Rate shall include cost of all labour, and material involved in all the
operations except cost of excavation and connection pipes, which shall
be paid for under separate items of works.
2707.2 Vent shaft shall be provided at the starting point of the main sewer and
at such points where the flow of sewage is disturbed, i.e. at falls,
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 13 of 17
Specifications RVNL
siphons etc. As far as possible, the location shall be such that the
place receives sunrays for the maximum period of the day.
2707.3 Fixing
TABLE 2700.3
The vent shaft shall then be erected at the centre of the pit, true to
plumb, with the help of sheer legs, pulleys, tackles, ropes etc.
2707.3.2 Connection with sewer manhole shall be made using 150 mm dia
cement concrete pipe. After the connection is completed and approved
by engineer, the pit shall be filled with cement concrete 1:4:8 (1
cement: 4 fine sand: 8 graded stone aggregate 40 mm nominal size)
round the vent shaft upto ground level, except top 15 cm which shall be
filled with cement concrete 1:2:4 (1 cement: 2 coarse sand: 4 graded
stone aggregate 20 mm nominal size) and rendered smooth. The
junction of vent shaft with cement concrete shall be grouted with
cement mortar 1:1 (1 cement: 1 fine sand). Concrete work shall be
cured for at least 7 days.
2707.5 Rate
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 14 of 17
Specifications RVNL
Rate shall include cost of all labour and materials involved in all
operations excluding the cost of excavation and refilling around the
vent shaft, which shall be paid for under relevant items of work.
2708.1 the open drains shall be of the size, as specified in the schedule item
and laid to such gradients and at such locations as may be shown in
the relevant drawing or as directed by Engineer. They shall be built in
conformity with standard drawings. Where drawings are not supplied
the contractor will submit drawings for proposed sections and obtain
Engineer’s prior approval.
The size of drain as specified shall be the width of the drain at the top,
measured between the masonry walls. Depth will depend upon local
ground levels drain invert levels and required self-cleansing gradient.
The drain shall be given, as far as possible, uniform slope from the
starting point to the discharge point.
2708.3 Rate
Rate shall include cost of all labour and materials required for all the
operations described above, suitable deduction or extra payment per
cm basis shall be made in case there is a variation in average depth as
given in the item of work (including excavation and filling).
2709.2 Every septic tank shall be providing with C.I. cover of adequate
strength. The cover shall be 500 mm dia (medium duty) or 610 mm x
455 mm (L.D) or as indicated in drawings. The specification for C.I.
cover and frame shall be as described under sub clause 2704.9.
2709.3 The tank shall be provided with cast iron or asbestos cement
ventilating pipe as specified of at least 50 mm diameter. The top of the
pipe shall be provided with a cowl or suitable cage of mosquito proof
wire mesh. The height of pipe shall be as given in drawing (2 meter
normally) in case when the septic tank is at least 15 m away from the
nearest building.
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 15 of 17
Specifications RVNL
2709.4 All individual items to be carried out for construction of tank shall
conform to relevant clauses of these specifications described under
relevant sections of part I and part II of technical specifications.
2709.5 Testing
Before the tank is commissioned for use, it shall be tested for water-
tightness by filling it with water and allowing water to stand for 24
hours. It shall then be topped up, if necessary, and allowed to stand for
a further period of 24 hours, during which time the fall in the level of the
water shall not be more then 1:5 cm.
2709.7 Rate
The rate shall include the cost of materials and labour involved in all
the operations for carrying out construction work of tank as per item of
work including excavation refill, disposal of surplus earth and
preparation of detail design and drawings, is necessary.
2710.1 Soak pit of given size shall be constructed as per approved drawings or
as directed by Engineer.
During the construction of pit, the construction of shaft and filling of the
bats and the brick ballast shall progress simultaneously.
2710.2 Materials
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 16 of 17
Specifications RVNL
Soak pit shall be enumerated as units under appropriate sizes
capacities.
2710.4 Rate
Rate shall include the cost of labour and materials involved in all the
operations including the earth work.
__________________________________________________________________ __________________________________
Part B - Buildings - Drainage Page 17 of 17