Instruction Manual
Instruction Manual
Instruction Manual
INSTRUCTION MANUAL
FOR
Description:
1.00 GENERAL
12.00 CERTIFICATES
Hamworthy Moss AS
Ordre no: 130959 Chapter: 1
Rev: 00 Date:
TABLE OF CONTENTS 20060912
Description: Page:
1.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 1
This danger always exists, due to the fact that all three elements needed to
start a fire or explosion, will be present.
If any of the three elements can be eliminated, the danger of explosion is also
eliminated, and this is the philosophy behind the Inert Gas System.
When looking for the simplest element to remove one will find that:
1. The fuel part can never be eliminated, due to the nature of the cargo,
which itself is highly flammable.
The cargo will always evaporate explosive hydrocarbon vapors, which
will fill any void spaces in the tanks and mix with air, entering the tanks
through open hatches, etc.
On ballast voyages the empty tanks are also filled with a mixture of air,
drawn in when unloading and vapor from the cargo remain in the tank.
2. The energy spark to set off an explosion is also very difficult to eliminate
completely.
Exhaustive studies have been made by maritime bodies worldwide. No
exact conclusion has been drawn, but it is a recognized fact that the most
dangerous source of ignition is that of static electricity, which may be cre-
ated in various ways inside the tank.
1-1
Hamworthy Moss AS
CHAPTER 1 - GENERAL
3. The only element left is the oxygen to support combustion. This is always
present as 21% of the earth's atmosphere.
However, the percentage of oxygen inside the cargo tank can be control-
led by replacing the air with an inert gas, namely, a gas with an oxygen
content low to form an explosive mixture regardless of the amount of
petroleum gas in the atmosphere of the tank.
BELOW the lower explosive limit, the mixture is too lean to burn.
ABOVE the upper explosive limit, the mixture is too rich to burn.
1-2
Hamworthy Moss AS
CHAPTER 1 - GENERAL
1-3
Hamworthy Moss AS
CHAPTER 1 - GENERAL
Whilst discharging cargo (or ballast from cargo tanks), the liquid pumped out
of the tanks is replaced by inert gas. At all times the pressure of the inert gas
in the tanks is maintained slightly above atmosphere pressure.
From one dry-docking to the next, the ship is constantly protected by inert gas.
The only exception being in the case of work having to be done inside one of
the tanks, or inerting from gas free condition which requires the inert gas to be
replaced by air. During air venting the tank atmosphere must never reach in
flammable zone (see diagram page 1.3).
This procedure means a greater all-round safety in the operation of the ship,
not only during tank cleaning, loading and discharging operations, but also dur-
ing voyages.
The inert gas used on this ship can be produced in the following ways:
1. As a conventional Flue Gas Plant - by cooling and cleaning gas from boil-
er uptakes.
2. As a conventional independent Generator System - by burning fuel oil at
a very low excess of air, to be used during voyages to obtain overpres-
sure.
The gas consisting mainly of Nitrogen N2 and Carbon Dioxide CO2, is cooled
and cleaned of soot and SO2 by Seawater in a scrubber unit, and subsequently
distributed to the tanks through a deck piping system by means of centrifugal
blowers.
The full capacity running as flue gas plant requires a certain minimum fuel oil
flow to the boiler.
The diagram can decide this minimum oil consumption on the following page.
WARNING
WHEN RUNNING AS FLUE GAS PLANT WITH THE BOILER ON TOO LOW
LOAD, THE FLUE GAS BLOWER MAY SUCK FRESH AIR DOWN THE
BOILER FUNNEL.
1-4
Hamworthy Moss AS
CHAPTER 1 - GENERAL
1-5
Hamworthy Moss AS
CHAPTER 1 - GENERAL
To cater for such variations in discharge rate, the inert gas system capacity has
been sized on the nominal pumping rate multiplied by at least 1.25.
Oxygen levels:
LESS THAN
5% OXYGEN: BEST OXYGEN LEVEL
for good operation vessel. The I.G.S. operation in the fol-
lowing sections refers to this level.
1-6
Hamworthy Moss AS
CHAPTER 1 - GENERAL
NOTE!
AN OXYGEN DEFICIENT ATMOSPHERE MAY NOT ONLY BE PRESENT
WITHIN A CARGO TANK, BUT ALSO IN ADJACENT CARGO PUMP
ROOMS, PERMANENT BALLAST TANKS, VOID SPACES, AT GAS EXITS
AND WITHIN INERT GAS PLANTS TO BE OVERHAULED.
Measurement is the only way to detect the presence of these toxic gases. How-
ever, if the hydrocarbon gas content of an inerted tank exceeds approximately
2% by volume before beginning of gas freeing, dilution of toxic components of
inert gas as gas freeing progresses can be correlated with the readings of an
approved combustible gas indicator. If ventilation of the compartment results in
a lower flammable limit reading of 1% or less in conjunction with an oxygen
reading of 21% by volume, toxic gases will have been diluted to a concentra-
tion, which will be safe to enter, and disregarding the initial hydrocarbon gas
content, continue ventilating a steady oxygen reading of 21% by volume is
reached.
1-7
Hamworthy Moss AS
CHAPTER 1 - GENERAL
Cargo tanks are usually in an inerted condition and electrostatic ignition is not
a consideration unless the oxygen content of the tank atmosphere is increased
by the entrance of air, or unless it is necessary to inert a tank already contain-
ing a flammable atmosphere.
An external examination of any unit, such as the inert gas scrubber, must not
be performed without following the standard recommendations for entering
enclosed spaces. Blind flanges should be fitted where applicable or the plant
should be completely isolated.
1-8
Hamworthy Moss AS
Order no: 130959 Chapter: 2
Rev: 00 Date:
TABLE OF CONTENTS 20060912
Description: Page:
2.4 Utilities. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 - 2
Hamworthy Moss AS
CHAPTER 2 - TECHNICAL DATA
Rev: Date:
2. TECHNICAL DATA
2.1 Performance Flue Gas System
Nominal capacity: 9.400 m³/h
N2-content: Balance
O2-content: No change
CO2-content: No change
N2-content: Balance
2-1
Hamworthy Moss AS
CHAPTER 2 - TECHNICAL DATA
N2 + Ar: Balance
Air for ignition burner can be taken from other sources than for instrument air
reservoir.
2.4 Utilities
Fuel oil
(500 Nm³/h Inert Gas at 3% by vol. O2 by consumption of ambient air)
2-2
Hamworthy Moss AS
CHAPTER 2 - TECHNICAL DATA
Seawater (raw)
Capacity
(cooling tower): Approx. 150 m³/h (filtered to 3 mm) for Flue
Gas
Approx. 35 m³/h for Topping Up
Pressure
(cooling tower): Approx. 2 bar g at plant inlet for Flue Gas
and Topping Up
Capacity
(Deck Water Seal): Approx. 3 m³/h
Pressure
(Deck Water Seal): Approx. 1 bar g at D.W.S. inlet
2-3
Hamworthy Moss AS
Order no: 130959 Chapter: 3
Rev: 00 Date:
TABLE OF CONTENTS 20060912
Description: Page:
Description: Page:
The oil is directed to the orifice through some tangentially slots, thus the oil gets
a rotating motion and the oil to the burner leaves the nozzles as a thin rotating
membrane which is atomized just after the nozzle. The atomized oil forms a
cone, in which the top angle depends on the nozzle type and oil pressure.
When oil pressure and thereby oil quantity is increased, the rotating velocity
increases, and the atomizing cone increases (higher oil pressure = higher oil
quantity = higher rotating velocity = greater atomizing cone).
The oil gun is adjustable in axial direction to find the best position for the oil
nozzle.
A stuffing box around the oil gun with asbestos gasket avoid gas leakage.
The combustion air is supplied tangentially to the burner. This means that the
air, already when entering the outer gas chamber, is brought in rotation.
The rotation is strengthened at the same time as the velocity increases through
a number of vanes on the way via an exactly circular distribution opening (burn-
er neck) into the combustion chamber, where combustion air and fuel oil are
mixed. A small part of air passes through a tube around the oil gun as "primary
air".
The "primary air" blowing along the oil gun prevents settling of uncombustioned
oil particles on the fuel oil nozzle. For complete combustion it is necessary to
mix the atomized fuel oil and combustion air as good as possible. This is
obtained by high relative velocity between oil and gas. The axial air velocity at
the oil nozzle must, however, not be higher than the rate of combustion, as this
would mean that the flame would be blown away from the nozzle. Therefore,
as mentioned before, a high velocity is obtained even at a low axial velocity at
the center of the burner. For further increase of the relative velocity between oil
and air they are given oppositely directed rotation.
3-1
Hamworthy Moss AS
CHAPTER 3 - DESCRIPTION OF EACH UNIT
In the front of the burner, there are openings for oil gun, ignition burner and
view ports with glasses and gate valves for flame control and inspection.
The top plate to which the oil nozzle and glow plug are fixed, is removable by
opening a cap nut. In the oil supply line one solenoid operated shut-off valve
(item No. 158) is mounted.
The 10-15 cm long pilot flame is coming out through the tube, which is connect-
ing the ignition burner to the front plate of the main burner.
Time from ignition glow plug is activated and to the main burner is supplied with
fuel oil is approximately 35 seconds.
When the gas leaves the central tube in the bottom part of the scrubber and
turns 180°C, it flows upwards through a stainless steel wet filter (Item No. 130)
fitted in the lower part of the scrubber.
After passing the wet filter, the gas is forced further upwards through a spray
of Seawater coming from a set full cone spray nozzles, (Item No. 117), fitted in
a Seawater distributing ring in the upper half of the scrubber.
The purpose of the wet filter is to obtain a good contact between the hot gas
and the cooling water.
After having been effectively cooled and cleaned, the gas finally passes
through a stainless steel demister (Item No. 131) before it leaves the scrubber
through the outlet duct on the upper part of the tower.
3-2
Hamworthy Moss AS
CHAPTER 3 - DESCRIPTION OF EACH UNIT
Access openings are provided in the tower, just above both the wet filter and
the demister, for easy inspection, maintenance and possible cleaning or
changing Seawater nozzles.
Oil pump with electric motor (Item Nos. 82, 83), duplex oil filter with double
three-way valves (Item No. 81), flow meter (Item No. 202) and oil pipings. Con-
nection to oil gun is made by a flexible hose (Item No. 84). The oil supply to the
main burner pipeline is fitted with one solenoid valve each (Item Nos. 153,
156). The oil pump is equipped with a pressure regulating valve, and is directly
connected to the electric motor via a flexible coupling.
During stop of plant solenoid valve (Item No. 157) is energized for a few sec-
onds in order to air flush the oil gun, except in air venting mode, "EMERG.
STOP" or "FLAME FAILURE" alarm.
Blower with electric motor, silencers, air filter and expansion joint. The blower
is driven by an electric motor.
Blower and electric motor is mounted on a common base plate, which is laid
on resilient mountings.
The air quantity to the burner is adjusted with the valve Item No. 12.
A control valve (Item No. 50) is mounted in the s.w. line to cooling jacket -
adjusted and locked.
3-3
Hamworthy Moss AS
CHAPTER 3 - DESCRIPTION OF EACH UNIT
NOTE!
THIS VALVE SHOULD ONLY BE OPERATED BY QUALIFIED PERSON-
NEL.
This is obtained by fitting an overboard shut-off valve (Item No. 14) at a level
of minimum 3,0 m below the light ship water line.
3-4
Hamworthy Moss AS
CHAPTER 3 - DESCRIPTION OF EACH UNIT
3-5
Hamworthy Moss AS
CHAPTER 3 - DESCRIPTION OF EACH UNIT
3-6
Hamworthy Moss AS
CHAPTER 3 - DESCRIPTION OF EACH UNIT
The gas leaves the central tube in the bottom part of the scrubber, turns 180°,
to run upward through polypropylene wet filter (Item No. 130) in the lower part
of the scrubber.
After the wet filter, the gas is forced further upward through a fine spray of Sea-
water droplets coming from a set of full cone spray nozzles, (Item No. 117), fit-
ted in a Seawater distributing ring in the upper half of the scrubber tower.
After having been effectively cooled and cleaned by the Seawater sprays, the
gas finally passes through a polypropylene demister (Item No.131) before it
leaves the scrubber tower through the outlet duct on the upper part of the
scrubber.
The scrubber tower is manufactured in mild steel, internally coated with a 800
- 1000 microns layer of G.R.P. Below the wet filter, an effluent water outlet is
provided, which is led via a drain line down to a none return valve and an over-
board shut off valve (Item No. 14), fitted well below the light ship water line.
Access openings are provided in the tower, just above both the wet filter and
the demister, for easy inspection, maintenance and possible cleaning or
changing Seawater nozzles.
The blowers are the only flue gas transporters in the system.
3-7
Hamworthy Moss AS
CHAPTER 3 - DESCRIPTION OF EACH UNIT
They draw the gas from the boiler uptake, through the scrubber, and deliver to
the deck distributing pipe system with sufficient overpressure to ensure a high
velocity gas jet is forced into the cargo tanks.
The blowers characteristics are such that they can not generate sufficient head
to over-pressurize the cargo tanks and cause unnecessary lifting of relief
valves within the system.
The blower casing are made of 6 mm steel plate, grit blasted and internally pro-
tected by a 800 - 1000 microns layer of G.R.P.
Blower impellers are made of acid resistant steel AISI 316L with impeller shaft
in SIS 2244 material. The blower casing is provided with water spray nozzles
and drains.
The blower and motor are mounted on common base plate resting on resilient
mountings.
Two valves mounted close to the boiler uptake duct and one valve downstream
sealing air pipeline connection.
At uptake valve soot blowing air/steam nozzles for valve cleaning shall be
mounted by yard.
A shut off butterfly valve, (Item No. 4) is installed in this sealing airline, operated
by a double acting pneumatic actuator, controlled by a solenoid valve.
When the boiler uptake valves are closed, the sealing air valve is open and vice
versa.
3-8
Hamworthy Moss AS
CHAPTER 3 - DESCRIPTION OF EACH UNIT
For gas freeing of cargo tanks, a fresh air intake is arranged at scrubber inlet.
The fresh air intake is arranged with hinged hatch with limit switch, Item No.
260.
The valve is also operated by the oxygen analyzer, i.e. leading gas to atmos-
phere, when gas analysis is not within set limits.
The valve is operated from the main control panel and will automatically open
when the gas analysis meets the requirements, otherwise closed.
During start-up and shut-down the valve is automatically forced to closed posi-
tion.
Downstream I.G. main control valve a vent valve, Item 47, is fitted on I.G. main
line. This valve is open when plant is shut down for the purpose to vent the I.G.
line.
3-9
Hamworthy Moss AS
CHAPTER 3 - DESCRIPTION OF EACH UNIT
The gas inlet center tube is leakage secured by an internal double tube. The
small tube w/goose neck on water seal top indicates if any leakage.
The water seal is equipped with manholes and inspection glass for water level
control, level switch, Item No. 194 for low-level alarm.
The mesh demister in the upper part of the water seal is effectively preventing
carry over of water droplets to/or less than 1 g/kg dry gas under all flow condi-
tions.
Any back pressure from the cargo tank area will induce an overpressure in the
reservoir chamber above the water level, and force water into the center tube.
Here the water level in the center tube will rise, and thus preventing gas from
leaking past the seal.
When the plant is operating, and inert gas is admitted to the deck distribution
system, the pressure from the blowers will empty the center tube into the res-
ervoir, letting the gas flow freely through the top part of the reservoir chamber.
Here gas is forced through a demister, where possible water droplets are sep-
arated from the gas and led back to the water reservoir.
The deck water seal shell is manufactured in mild steel, internally lined with
Glass Reinforced Polyester (GRP).
One of the pumps must always supply the deck seal with water.
3-10
Hamworthy Moss AS
CHAPTER 3 - DESCRIPTION OF EACH UNIT
A main shut off valve (Item No. 5) is mounted on inlet nozzle to scrubber. To
avoid water hammering in the S.W. system, the valve will open 10 secs. prior
to start of s.w. pump.
NOTE!
WHEN S.W. AUX. SUPPLY IS SELECTED, VALVE (ITEM NO. 19) MUST BE
OPENED CAREFULLY TO AVOID WATER HAMMERING.
3.3.4 Non return valve in main deck line (Item No. 64)
and for ballast system (Item No. 62).
The purpose of this non-return valve is to prevent backflow of cargo gases from
the tanks to the I.G. production plant.
In the case of excess pressure, the liquid in the seal is forced out on deck,
and the pressurized gas escapes to atmosphere.
In case of vacuum, the liquid is sucked into the deck I.G. line, and air from
outside is drawn into the tanks.
(The noise of gas or air going through the seal acts as an audible alarm signal).
3-11
Hamworthy Moss AS
Order no: 130959 Chapter: 4
Rev: 00 Date:
TABLE OF CONTENTS 20060912
Description: Page:
4.3.1 General. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 - 4
4.3.2 Main Control panel – Cargo Control Room
(Item No. 233) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 - 4
4.3.3 Local Panel - Engine Room (Item No. 234) . . . . . . . . 4 - 5
4.3.4 Sub Panel - Wheel House (Item No. 239)and
Sub Panel – Engine Control Room (Item No. 240). . . 4 - 5
4.3.5 Oxygen analysing system. . . . . . . . . . . . . . . . . . . . . . 4 - 5
4.3.6 The instrument air. . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 - 6
Hamworthy Moss AS
CHAPTER 4 - INSTRUMENTATION AND CONTROL SYSTEM
Rev: Date:
4. INSTRUMENTATION AND CONTROL SYSTEM
4.1 Indicating/Recording Instruments
Temperature Seawater main inlet flue gas scrubber (Item No. 175).
Temperature inert gas outlet flue gas scrubber (Item No. 179).
Inert gas pressure outlet cooling tower topping up generator (Item No. 220).
Inert gas pressure outlet flue gas scrubber (Item No. 167).
4-1
Hamworthy Moss AS
CHAPTER 4 - INSTRUMENTATION AND CONTROL SYSTEM
2 - pen recorder/indicator (item No. 217) for O2-content in inert gas and I.G.
deck pressure.
4.1.6 Transmitters
Pressure transmitters - I.G. in I.G. deck main line (Item No. PT-182).
Low amp. blower 1 or 2 failure, alarm and stop of plant (Item Nos. 180 and
181).
Inert gas temperature high, alarm and stop of plant (Item No. 188).
Flue gas temperature high, in flue gas scrubber, alarm and stop of plant (Item
No. 192).
High inert gas deck main pressure, alarm and vent to atmosphere (Item No.
182).
Very low inert gas deck main pressure alarm (item No. 182).
4-2
Hamworthy Moss AS
CHAPTER 4 - INSTRUMENTATION AND CONTROL SYSTEM
Low instrument air pressure - common, alarm and stop of plant (Item No. 183).
Low Seawater pressure to cooling tower topping up generator, alarm and stop
of plant (Item No. 184).
Low fuel oil pressure to burner topping up generator, alarm and stop of plant
(Item No. 185).
Low Seawater pressure to flue gas scrubber, alarm and stop of plant (Item No.
184).
Low Seawater cooling level in burner jacket, alarm and stop of plant (Item No.
191).
High Seawater level in flue gas scrubber, alarm and stop of plant (Item No.
193).
High Seawater level in cooling tower topping up generator, alarm and stop of
plant (Item No. 193).
Low Seawater level in deck water seal reservoir, alarm (Item No. 194).
is a glow plug transformer, which is connected to 220V and gives approx. 13V
to the glow plug fitted on the ignition burner.
is registering the burner flame, and on the contrary case take care of stopping
the plant and that alarm is given.
The flame control consists mainly of a scanner unit with photoelectric cell and
an amplifier, which amplifies the weak signals from the photo cell to impulses
that are able to operate a flame relay. See separate instruction for adjustment
of the amplifier, Chapter 11.
The programming controller takes care of all control and regulation functions.
4-3
Hamworthy Moss AS
CHAPTER 4 - INSTRUMENTATION AND CONTROL SYSTEM
When the inert gas plant is started (i.e. water circ. running) an interlock signal
will prevent the boiler soot blowers from being started.
In the following are listed all instruments and control panels within the system,
with the main items and the function of same.
The operation and use of the panels during plant operation are covered in
detail in following section 5.
The Main Control panel is located in Cargo Control Room, and the plant start
up is initiated from this panel. The panel contains the programmable controller.
On the front of the panel, the I.G. plant is visualized on touch screen. The alarm
handling system works as follows:
The control system is provided with N.C. alarm contacts, i.e. upon loss of elec-
tric power, the system will fail to safe. At normal running conditions the alarm-
banner is dark and no flashing bell can be seen. Any alarm condition is indicat-
ed on the touch screen (on any page) by a flashing bell in the upper right hand
corner of the screen and an audible alarm will be given by a horn.
The last occurred alarm is described in the alarm-banner, with a red text. By
acknowledging the alarm, the audible alarm will stop. Acknowledging the
alarm, on the touch screen, is done, by pressing the alarm banner. The text
then turns from red to blue. After having reset the alarm, and in case the alarm
cause is removed, the alarm description will disappear.
In case of more than one alarm having been activated, only the last registered
alarm will be shown in the alarm-banner. In order to accept the other alarms,
push the ALARM LIST button, and accept each alarm description separately.
By too high/low oxygen content, as well as most other alarm and shut down sit-
uations, the inert gas to atmosphere valve will open and the inert gas main
valve will close.
4-4
Hamworthy Moss AS
CHAPTER 4 - INSTRUMENTATION AND CONTROL SYSTEM
This panel is locally mounted on the generator and contains touch keys for
manual start of the Topping up Generator. On the front of the panel, the Top-
ping up plant is visualized on a touch screen.
The panel contains touch keys for alarm accept and alarm reset.
The items mounted can be seen on the drawing for Local Panel Topping Up
Generator.
The items mounted on the front can be seen on the drawing for Sub panel for
Wheelhouse and Engine Control Room.
The oxygen analyser panel (Item No. 232) is located in the vicinity of the gen-
erator.
Analyser sample flow is set by the flow control valve (Item No. 745).
The three-way valve (Item No. 358) selects between sample (instrument) air or
N2.
Sample gas is taken from generator outlet nozzles pressurized to the analyser.
4-5
Hamworthy Moss AS
CHAPTER 4 - INSTRUMENTATION AND CONTROL SYSTEM
Adjustable O2-Alarm
On the alarm page in the touch screen for the main control panel (Item No 233)
it is possible to adjust the O2-alarm set point. (HAC 204).
Press the touch key, a numeric pad pops up, set the alarm level and press
enter.
Supply to the pneumatically operated valves and control devices shall have a
pressure of 6-10 bar (g), and supplied dry and clean.
The pressure is reduced to max. 7 bar (g) by the reduction valve (Item No.
262).
4-6
Hamworthy Moss AS
Order no: 130959 Chapter: 5
Rev: 00 Date:
TABLE OF CONTENTS 20060912
Description: Page:
5.1 Short form, step by step, plant start and stop instructions . . . 5 - 1
5.2.1 General. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 4
5.2.2 Normal (auto) start - Flue gas. . . . . . . . . . . . . . . . . . . 5 - 4
5.2.3 Normal (auto) start - Inert gas generator . . . . . . . . . . 5 - 4
5.2.4 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 5
Hamworthy Moss AS
CHAPTER 5 - INSTRUCTION FOR PLANT START, OPER. AND STOP
Rev: Date:
5. INSTRUCTIONS FOR PLANT START, OPERATION AND STOP
5.1 Short form, step by step, plant start and stop instructions
By activation of key HELP on the touch screen a page containing touch keys
for operation procedures and trouble-shooting will show up.
5. Clean uptake valve for soot with touch key SELECT VALVE CLEAN.
6. Press START FLUE GAS touch key.
If flashing light, the plant is stand by waiting for start power available.
The start sequence is indicated with lamps on the mimic diagram on start
page on the touch screen.
5-1
Hamworthy Moss AS
CHAPTER 5 - INSTRUCTION FOR PLANT START, OPER. AND STOP
12. The deck pressure can be controlled by operation of touch key HIC2 SET
POINT in front of main control panel.
5.1.3 Gas freeing
The plant is prepared for purging the tanks with fresh air during gas freeing of
the cargo tanks.
3. The start sequence is indicated with lamps on the mimic diagram. Check
that all air is evacuated from cooling jacket outlet and sight glass before
the LED for “flame on” is energized.
4. Check and if necessary adjust combustion air capacity to obtain O2-con-
tent selected.
5. Check the temperature and pressures at normal running condition.
6. Check and if necessary adjust the flow through the O2-analysers' bubbler
unit.
7. The plant is now ready for production of inert gas to consumer. If push
button "SELECT CONS." is activated, the valve to deck will open.
5.1.5 Topping Up - Inert Gas Generator
1. Follow the procedures described in section 5.1.1 "Before start" and "Nor-
mal (auto) start" 1-3.
5-2
Hamworthy Moss AS
CHAPTER 5 - INSTRUCTION FOR PLANT START, OPER. AND STOP
2. Press SELECT TG MODE touch key. The plant will start automatically by
impulse from the inert gas deck line low pressure signal.
3. When the plant is ready for delivery of inert gas to consumer, the valve to
deck will open automatically.
5.1.6 Manual start - Inert Gas Generator
1. Carry out checks listed in section 5.1.1 "Before start".
2. Press LOCAL TG START touch key in main panel before MANUAL
START/STOP touch key located in front of local TG panel. By malopera-
tion or alarm the lamp will remain unenergized.
3. Check that all air is evacuated from cooling jacket at pipe outlet in sight
glass.
4. Start seawater pump and combustion air blower with the touch keys S.W.
PUMP and BLOWER.
5. Check and if necessary adjust the flow through the O2-analysers' bubbler
unit.
6. After a prepurging time of 50 seconds start fuel oil pump with touch key
F.O. PUMP and energize the ignition glow plug with the key GLOW.
7. Wait approx. 30 seconds and admit fuel oil and air to the ignition burner
with touch key IGNITION ON.
8. Wait another 5 seconds and admit fuel oil main burner with the key MAIN
BURNER.
9. When flame is established and indicated with LED, allow 5 seconds sta-
bilizing time before stopping ignition burner by depressing the keys
GLOW and IGNITION ON.
10. Check and if necessary adjust combustion air capacity to obtain selected
oxygen content in the inert gas.
11. Check the temperature and pressures at normal running condition.
12. Check and if necessary adjust the flow through the O2-analysers' bubbler
unit.
13. The plant is ready for production of inert gas to consumer.
5.1.7 Stop of plant
1. Close consumer valve by deenergizing touch key SELECT DECK.
2. The plant can be stopped with touch key STOP.
3. STOP OF PLANT IN F.G. MODE:
IT IS RECOMMENDED TO CLEAN THE BLOWER.
5-3
Hamworthy Moss AS
CHAPTER 5 - INSTRUCTION FOR PLANT START, OPER. AND STOP
4. The plant will continue running for a cooling down period except in air
venting mode.
5. Control panels shall be left with power on.
5.2 Description instructions for plant start and operation
5.2.1 General
The following start instructions are identical to those presented in the foregoing
sections 5.1.2 and 5.1.4, but give more detailed information of the automatic
sequence initiated.
Pressing touch key START FLUE GAS initiates automatically the following
start sequence:
The seawater inlet valve will open immediately. 10 secs. later the seawater
supply pump will start. 17 sec. delayed the blower will start and valves for
uptake will open.
After receiving running signal from blower, the capacity control valve will open
to modulating position.
The seawater inlet valve will open, and 10 secs. delayed the seawater pump
will start. 17 seconds delayed air blower will start and after receiving running
signal from blower the burner pressure control valve will open to modulating
position. After a pre-purging time of 50 seconds, the glow plug in the ignition
burner will be put on and the fuel oil pump will start. 30 seconds delayed from
activating the glow plug, fuel oil and air are supplied to the ignition burner and
ignited by the glow plug.
5 seconds after activation of ignition burner, fuel oil is supplied to the main
burner, and the glow plug will be deactivated. After 4 seconds oil to ignition
burner will be switched off, and 10 secs. later air to ignition burner will be
switched off.
5-4
Hamworthy Moss AS
CHAPTER 5 - INSTRUCTION FOR PLANT START, OPER. AND STOP
5.2.4 Operation
When the plant is running, the operator should check and make a record of all
values shown on the local mounted instruments.
Any abnormal value must be investigated and the fault corrected as soon as
possible.
Should the oxygen content alarm sound during normal operation, the inert gas
consumer valve will automatically close, and the atmosphere valve will open.
The operator must then adjust the air/diesel ratio, when running in generator
mode.
When the oxygen content is within its limits again, the selected inert gas con-
sumer valve(s) will open automatically.
5-5
Hamworthy Moss AS
Order no: 130959 Chapter: 6
Rev: 00 Date:
TABLE OF CONTENTS 20060912
Description: Page:
6.2 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 - 1
Description: Page:
The safety arrangements are an integral part of the inert gas system and it is
important for ship’s staff to give special attention to them during any inspection.
Inspection routines for some of the main components are dealt with in this sec-
tion.
Inspection may be made through the manholes. Checks should be made for
corrosion attacks, fouling and damage to:
• internal linings;
• demisters;
• packed beds.
6.4 Inert Gas Blowers
After use or when found to be necessary, the blowers must be rinsed with fresh
water.
NB!
HAMWORTHY AS AS SUPPLIER OF THIS PRODUCT REQUEST CUS-
TOMERS TO CARRY OUT THE FOLLOWING AS STANDARD ROUTINE:
1. IF SYSTEM GASES CONTAIN HIGH LEVELS OF SOOT/CARBON,
BLOWER SHALL BE CHECKED FOR INCREASED VIBRATION
ONCE EVERY HOUR.
2. INCREASED VIBRATION IS PROBABLE CAUSE OF BUILD UP OF
SOOT/CARBON ON IMPELLER AND/OR LARGE SECTIONS OF THE
6-1
Hamworthy Moss AS
CHAPTER 6 - MAINTENANCE AND TROUBLESHOOTING
First, the drain valves have to be opened, and the water is injected by opening
the valve for fresh water just when the blower(s) are switched off.
The blower impeller will run for some time because of its force due to mass,
thus a good cleaning of the internal parts is obtained.
When the impeller stops, the valve for fresh water has to be closed, afterwards
the drain valve has to be closed. The cleaning procedure might be repeated if
necessary. Inspection to be done through the hatches in blower housing.
It is recommended that after a full unloading of cargo with the inert gas
blower in operation, the impeller should be washed.
6.5 Adjustment and tolerances
6.5.1 Oil burner
The oil atomizer position, relative to the air deflecting cone, can be adjusted by
loosening the gland nut on the burner gun carrier tube, and move the oil gun
outward or inward.
The best position is easiest found if the adjustments are made with the burner
in operation, and by measuring the inert gas CO-content.
Start the I.G. generator and adjust slowly upward or downward the atomizer
and at the same time observe the colour from the sight glass. In the moment
the flame is very white and spots around the circumference of the flame turns
to be clear/blue, the best position is achieved. Further improvement is only
obtained with equipment for measuring of CO-content. The improvement is
only in range of some ppm CO.
The combustion air pressure to the main burner is indicated on pressure gauge
(Item No. 161).
6-2
Hamworthy Moss AS
CHAPTER 6 - MAINTENANCE AND TROUBLESHOOTING
The fuel oil pressure to the main burner is indicated on pressure gauge (Item
No. 165).
The pressure may be adjusted on the pressure regulating valve built in the fuel
oil pump, but should normally not be touched, once it is set correctly on initial
commissioning.
Gas temperature outlet cooling tower (Item No. 179) max 5°C above seawater
temperature for both plants.
Gas pressure outlet cooling tower topping up generator is equal to the combus-
tion air pressure, except the pressure loss through the burner and cooling tow-
er.
6.6 General
The plant particulars to be checked at regular intervals as listed below, and any
defects or irregularities found must be rectified as soon as possible.
6-3
Hamworthy Moss AS
CHAPTER 6 - MAINTENANCE AND TROUBLESHOOTING
All openings and slots in the nozzle must show clean cut, sharp edges.
The swirl chamber and the outlet orifice to be circular with no signs of
ovality.
NOTE!
NO STEEL OR METAL WIRE ETC. MUST BE USED TO OPEN DIRTY
OR CLOGGED OPENINGS IN THE NOZZLE.
6-4
Hamworthy Moss AS
CHAPTER 6 - MAINTENANCE AND TROUBLESHOOTING
Dip the filter into Acetone for 5 - 10 min. Wash the filter in water with a
little soap. Then clean the filter in fresh water until all soap (and acetone)
is removed. Please note that the filter is of PTFE material and must be
handled with care.
Ensure that the bubbler unit of the oxygen analyser is filled with fresh
water.
Do not operate the generator with oxygen content lower than 1% by vol-
ume.
If there is an absolute need for a gas with an oxygen content of less than
1 %, the plant may be operated at a lower value, but this may shorten the
plant life time.
6-5
Hamworthy Moss AS
CHAPTER 6 - MAINTENANCE AND TROUBLESHOOTING
This unit performs an important function and must be maintained in good con-
dition. Corroded inlet pipes and damage to float-controlled valves are not
uncommon. The overboard drain line and connection are also possible sources
of trouble.
To assure that the P/V Breaker can serve its function, all the I.G. branch line
shut off valves must be kept open
The seal must be filled with proper liquid (50% ethylene glycol / 50% fresh
water) to correct level. This can be done at atmospheric pressure in the deck
main line until the level can be seen in the level gauge, at the level indicating
arrow.
The non-return valve(s) should be opened for inspection to check for corrosion
and also to check the condition of the valve seat. The functioning of the valve
should be tested in operation.
6-6
Hamworthy Moss AS
CHAPTER 6 - MAINTENANCE AND TROUBLESHOOTING
The scrubber effluent line cannot normally be inspected internally except when
the ship is in dry dock. The shipside stub piece and the overboard discharge
valve should be inspected at each dry-docking period.
A method should be devised to test the correct functioning of all units and
alarms and it may be necessary to simulate certain conditions to carry out an
effective testing programme.
6-7
Hamworthy Moss AS
CHAPTER 6 - MAINTENANCE AND TROUBLESHOOTING
6-8
Hamworthy Moss AS
CHAPTER 6 - MAINTENANCE AND TROUBLESHOOTING
6-9
Hamworthy Moss AS
CHAPTER 6 - MAINTENANCE AND TROUBLESHOOTING
The s.w. flow through control valve (Item No. 50), mounted in the s.w. line to
cooling jacket, to be increased to achieve a temperature difference of approx.
13°C.
NOTE!
THE VALVE MUST BE LOCKED BY MEANS OF LOCKING SCREWS/NUTS
LOCATED ON THE GEAR UNIT.
The service & Maintenance and Operating personnel must be especially qual-
ified for the duties assigned to them. The scope of their responsibility, compe-
tence and supervisory duties must be closely controlled by an shift manager or
discipline supervisor. If the personnel do not have the required knowledge,
they must be trained and instructed. The supervisors must additionally ensure
that personnel fully understand the content of the Maintenance Instructions.
The Operator Company must ensure that all Maintenance and Inspection work
is performed by authorized and qualified personnel who have thoroughly stud-
ied the Maintenance Instructions.
Work on the IG System is only to be carried out when the System has been
shut down. The means of shutting down the System, described in the Instruc-
tion of start and stop, must always be followed.
The inert gas system is placed in safe area. However, no work or maintenance
creating electric sparks, metallic sparks, hot spots or any other source of gas
ignition must be carried out before the area have been declared safe by
responsible person. The manufacturer cannot be held responsible for acci-
dents occurring during maintenance.
6-10
Hamworthy Moss AS
CHAPTER 6 - MAINTENANCE AND TROUBLESHOOTING
Since flue gas still can leak from the boiler, the scrubber as well as the topping
up generator should be completely gas freed.
6-11
Hamworthy Moss AS
Order no: 130959 Chapter: 7
Rev: 00 Date:
TABLE OF CONTENTS 20060912
Description: Page:
7-1
Hamworthy Moss AS
CHAPTER 7 - EMERGENCY PROCEDURES
(iii) The tank bottom should be flushed with water and stripped. The piping
system including the cargo pumps, cross-overs and discharge lines
should also be flushed with water.
(iv) Washing should not commence until tests have been made at various
levels to establish that the vapour content in any part of the tank is below
10% of the lower flammable limit.
(v) Testing of the tank atmosphere should continue during the washing proc-
ess. If the vapour level rises to within 50% of the lower flammable limit,
washing should be discontinued until the vapour level has fallen to 20%
of the lower flammable limit.
(vi) If washing machines with individual capacities exceeding 60 m3/hr are to
be used, only such machine shall be used at any one time on the ship. If
portable machines are used, all hose connections should be made up
and bonding cables tested for continuity before the machines are intro-
duced into the tank and should not be broken until after the machines
have been removed from the tank.
(vii) The tank should be kept drained during washing. If build-up of wash water
occurs, washing should be stopped until the water has been cleared.
(viii) Only clean, cold seawater should be used. Recirculating systems should
not be used.
(ix) Chemical additives should not be used.
(x) All deck openings, except those necessary for washing and designed
venting arrangements, should be kept closed during the washing proc-
ess.
7.1.4 During cargo operations in port, more stringent regulations of the port Author-
ities shall take precedence over any of the foregoing emergency procedures.
7.1.5 The attention of the ship’s master should be drawn to regulation 11 (c) of sec-
tion 1 of the 1978 SOLAS Protocol in the event of the inert gas system having
become inoperative.
7.1.6 See also Safety Manual Ch. 13.11, IMO Publication Inert Gas System latest
ed.
7-2
Hamworthy Moss AS
Order no: 130959 Chapter: 8
Rev: 00 Date:
TABLE OF CONTENTS 20060912
Description: Page:
8.4 Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 - 2
8.11 Gas-Freeing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 - 4
The following is an extract from the I.M.O. Guide-lines for Inert Gas Systems –
1990 Edition.
8-1
Hamworthy Moss AS
CHAPTER 8 - APPLICATION TO CARGO TANK OPERATION
8.3.2 During the deballasting operation, the oxygen content of the gas and its pres-
sure in the inert gas main should be continuously recorded.
8.4 Loading
8-2
Hamworthy Moss AS
CHAPTER 8 - APPLICATION TO CARGO TANK OPERATION
if the tank is opened after cargo transfer, normal ship operations should not be
commenced until all the conditions have been checked and are in order.
8.6.5 During cargo transfer the oxygen content and pressure of the inert gas in the
inert gas main should be continuously recorded.
8.7 Ballasting of Cargo Tanks
The conditions for ballasting of cargo tanks are the same as those for loading
in 8.4. When, however, simultaneous discharge and ballasting is adopted, then
a close watch should be kept on the inert gas main pressure.
Cargo tanks should be washed in the inert condition and under a positive pres-
sure. Before each tank is washed, the oxygen level shall be determined at a
point 1 metre below the deck and at the middle region of the ullage space and
neither of these determinations shall exceed 8% by volume. Where tanks have
complete or partial wash bulkhead, the determination should be taken from
similar levels in each section of the tank. The oxygen content and pressure of
the inert gas being delivered during the washing process should be continu-
ously recorded.
• the oxygen level of the inert gas being delivered exceed 8% by volume; or
• the pressure of the atmosphere in the tanks is no longer positive;
When it is desired to gas free a tank after washing, the concentration of hydro-
carbon vapour should be reduced by purging the inerted cargo tank with inert
gas. Purge pipes/vents should be opened to atmosphere and inert gas intro-
duced into the tank until the hydrocarbon vapour concentration measured in
the efflux gas has been reduced to 2% by volume and until such time as deter-
mined by previous test on cargo tanks has elapsed to ensure that readings
8-3
Hamworthy Moss AS
CHAPTER 8 - APPLICATION TO CARGO TANK OPERATION
have stabilised and the flux gas is representative of the atmosphere within the
tank.
8.11 Gas-Freeing
8.11.1 Gas-freeing of cargo tanks should only be carried out when tank entry is nec-
essary (e.g. for essential repairs). It should not be started until it is established
that a flammable atmosphere in the tank will not be created as a result. Hydro-
carbon gases should be purged from the tank (see 8.10).
8.11.2 Gas-freeing may be effected by pneumatically, hydraulically, or steam driven
portable blowers, or by fixed equipment. In either case it is necessary to isolate
the appropriate tanks to avoid contamination from the inert gas main.
8.11.3 Gas-freeing should continue until the entire tank has an oxygen content of 21%
by volume and a reading of less than 1% of lower flammable limit is obtained
on a combustible gas indicator. Care must be taken to prevent the leakage of
air into inerted tanks, or of inert gas into tanks, which are, being gas freed.
8.12 Tank Entry
8.12.1 The entry of personnel into the cargo tank should be carried out only under the
close supervision of a responsible ship’s officer and in accordance with nation-
al rules and/or with the normal industrial practice laid down in the INTERNA-
TIONAL SAFETY GUIDE FOR OIL TANKERS AND TERMINALS. The
particular hazards encountered in tanks, which have been previously inerted
and then gas-freed are outlined in 9.2.8, 9.3.3 and section 10 of that guide.
• securing the inert gas branch line gas valves and/or blanks in position or, if
gas-freeing with the inert gas blower, isolating the scrubber from the flue
gases;
• closing of any drain lines entering the tank from the inert gas main;
• securing relevant cargo line valves or controls in the closed position;
• keeping the inert gas deck pressure in the remainder of the cargo tank sys-
tem at a low pressure such as 200 mm water gauge. This minimises the
possible leakage of inert or hydrocarbon gas from other tanks through pos-
sible bulkhead cracks, cargo lines, valves etc.;
• lowering clean sample lines well into the lower regions of the tank in at
least two locations. These locations should be away from both the inlet and
outlet openings used for gas freeing. After it has been ascertained that a
true bottom sample is being obtained, the following readings are required:
• 21% on a portable oxygen analyser; and
• less than 1% of lower flammable limit on a combustible gas indicator;
8-4
Hamworthy Moss AS
CHAPTER 8 - APPLICATION TO CARGO TANK OPERATION
• the use of breathing apparatus whenever there is any doubt about the tank
being gas-free, e.g. in tanks where it is not possible to sample remote loca-
tions. (The practice should be continued until all areas, including the bot-
tom structure, have been thoroughly checked);
• continuously ventilating and regularly sampling the tank atmosphere when-
ever personnel are in the tank;
• carefully observing normal regulations for tank entry.
8.13 Re-Inerting after Tank Entry
8.13.1 When all personnel have left the tank and the equipment has been removed,
the inert gas branch line blank, if fitted, should be removed, the hatch lids
closed and the gas pressure regulating valve re-opened and locked open to the
inert gas main where appropriate. This will avoid any risk of structural damage
when liquids are subsequently handled.
8.13.2 As soon as a gas-free tank is reconnected to the inert gas main it should be re-
inerted to prevent transfer of air to other tanks.
8.14 Special Notes concerning Product Carriers
8.14.1 Product carriers may carry petroleum products having a flash point exceeding
60°C – bitumens, lubricating oils, heavy fuel oils, high flashpoint jet fuels and
some diesel fuels, gas oils and special boiling point liquids without having to
keep the tanks in an inerted condition.
8.14.2 If cargoes with a flashpoint exceeding 60°C, whenever heated or otherwise,
are carried at temperatures near to or above their flashpoint (some bitumen cut
backs and fuel oils), a flammable atmosphere can occur (regulation 62.1
refers). When cargoes with a flash point exceeding 60°C are carried at a tem-
perature higher than 5°C below their flashpoint they should be carried in an
inerted condition.
8.14.3 When a non-volatile cargo is carried in a tank that has not been previously gas-
freed, then that tank shall be maintained in an inert condition.
8.14.4 Contamination of a product may affect its odour, acidity or flashpoint specifica-
tions and may occur in several ways; those relevant to ships with an inert has
main (or other gas line) interconnecting all cargo tanks are;
(i) Liquid contamination due to overfilling a tank.
(ii) Vapour contamination through the inert gas main. This is largely a prob-
lem of preventing vapour from low flashpoint cargoes, typically gasolines,
contaminating the various high flashpoint cargoes, e.g. aviation gasolines
and most hydrocarbon solvents. This problem can be overcome by;
• removing vapours of low flashpoint cargoes prior to loading; and
• preventing ingress of vapours of low flashpoint cargoes during loading
and during the loaded voyage.
8-5
Hamworthy Moss AS
CHAPTER 8 - APPLICATION TO CARGO TANK OPERATION
8.14.5 Experience suggests that petroleum cargoes do not suffer from contamination
by inert gas, but in this context it is important to ensure that the inert gas gen-
erator burner or flue gas system is operating efficiently and that the scrubber
is well maintained at all times.
8.14.6 All lubricating oils and jet fuels are acutely water-critical. Current practice
requires full line draining and mopping up of any water in tanks before loading.
Water contamination may occur on inerted ships due to water carried over from
the scrubber and/or deck water seals due to inadequacies in design or mainte-
nance of the drying arrangements.
8.14.7 All gas-freeing operations must be preceded by a purging operation, but gas-
freeing for purely quality reasons may be replaced by purging only. In addition
purging may be required when a non-volatile cargo is carried in a tank, which
has not been previously gas-freed.
(i) there are increased risks of air leaking into inert tanks and of inert gas
leaking into a tank being entered;
(ii) purging is not a prerequisite of gas-freeing when the hydrocarbon gas
content of a tank is below 2% by volume;
(iii) The operation of gas-freeing for product purity and where tank entry is not
contemplated does not require the atmosphere to have an oxygen con-
tent of 21% by volume.
8.15 Cargo-Ballast Operation Manual
INSTRUCTIONS TO BE INSERTED BY YARD/OWNER ACCORDING TO
SOLAS REGULATION, INCLUDING THE ITEMS SPECIFIED IN MSC/
CIRK.353.
8-6
Hamworthy Moss AS
CHAPTER 8 - APPLICATION TO CARGO TANK OPERATION
"4.1 This paragraph shall apply to oil tankers constructed on or after 1 October
1994.
4.2 Double hull and double bottom spaces shall be fitted with suitable con-
nections for the supply of air.
1. double hull spaces shall be fitted with suitable connections for the
supply of inert gas;
2. where hull spaces are connected to a permanently fitted inert gas
distribution system, means shall be provided to prevent hydrocar-
bon gases from the cargo tanks entering the double hull spaces
through the system;
3. where such spaces are not permanently connected to an inert gas
distribution system, appropriate means shall be provided to allow
connection to the inert gas main.
4.4.2 Where the atmosphere in double hull spaces cannot be reliably meas-
ured using flexible gas sampling hoses, such spaces shall be fitted with
permanent gas sampling lines. The configuration of such line systems
shall be adapted to the design of such spaces.
4.4.3 The materials of construction and the dimensions of gas sampling lines
shall be such as to prevent restriction. Where plastic materials are used,
they should be electrically conductive.”
8-7
Hamworthy Moss AS
CHAPTER 8 - APPLICATION TO CARGO TANK OPERATION
The gas freeing and ventilation arrangements must be capable of gas freeing:
8-8
Hamworthy Moss AS
CHAPTER 8 - APPLICATION TO CARGO TANK OPERATION
Most hydrocarbon gases from crude oil, hydrogen sulphide and inert gas are
heavier than air. With requirements for connections for inert gas supply to bal-
last tanks, inerting of ballast tank will probably be a normal procedure. A ven-
tilation arrangement extracting the heavier gasses from bottom utilizing
portable fans mounted on purge pipes and with fresh air supply from open
hatches in deck will probably be an effective gas-freeing method.
Inerting
The arrangements for inerting of double hull spaces may be through portable
connections to the inert gas system for cargo tanks or by fixed piping connec-
tions.
If fixed piping is used, the arrangement must include a separate deck water
seal and a non-return valve in order to prevent communications between
vapour spaces of cargo tanks and the double hull spaces. The practices for
inerting double hull spaces may either be to keep these spaces inerted at all
times when empty, or to inert them only if hydrocarbon gases are detected indi-
cating leakage between cargo tank(s) and the double hull spaces. If the former
practice is utilized, a fixed piping system is considered necessary.
As for gas freeing and ventilation the easiest method for inerting is to supply
inert gas to the space during de-ballasting. For that purpose an inert gas inlet
in the top of the space is needed. However, arrangements must additionally,
be provided to enable the space to be purged with inert gas. For this purpose
at least L-shaped tanks must be provided with inert gas supply outlets near bot-
tom far ends.
Alternative arrangements for inert gas purging will be the same as for ventila-
tion purposes detailed in paragraphs 4, 5, 6 and 7, replacing portable fan with
inert gas supply inlets.
Operational Procedures
8-9
Hamworthy Moss AS
CHAPTER 8 - APPLICATION TO CARGO TANK OPERATION
8-10
Hamworthy Moss AS
Ordre no: 130959 Chapter: 09
LIST OF DRAWINGS
Drawing no.: Rev: Description:
Revision No: 02
\\alke\jvsmast\rpt\cr\moss\parts_list.rpt Revision Date: 20-apr-2007 Page 1 of 11
Order No: 130959 FG10000-16 (8600-13590 Nm3/h)
Stk Packing
Item SO No Qty Article No Description Specification Remark Notes Supply Type No
1 M1014-001 Positioner with limit switch Fig. 793-011M 3-15psi Supply:1/4"BSP, A 2
Signal:1/8"BSP
1 M0110-002 I/P converter V18312-12221190 4-20mA/3-15 psi A 0
1 M0122-001 Pressure gauge, dia. 50mm Scale 0-30 psi/0-200 kPa Connect: 1/4" BSP A 0
1 M1815-001 Manual override kit with release valve A 2
8 120-100 1 N8235-003 Control valve assembly DN250 Fig. 14-133 Flange: DIN PN10 Blower No. 2 outlet B 2
1 M2482-001 Butterfly valve DN250 Fig. 14-133 Flange: DIN PN10 A 2
1 M1023-001 Pneumatic actuator For DN 250 Valve A 2
1 M1014-001 Positioner with limit switch Fig. 793-011M 3-15psi Supply:1/4"BSP, A 2
Signal:1/8"BSP
1 M0110-002 I/P converter V18312-12221190 4-20mA/3-15 psi A 0
1 M0122-001 Pressure gauge, dia. 50mm Scale 0-30 psi/0-200 kPa Connect: 1/4" BSP A 0
1 M1815-001 Manual override kit with release valve A 2
10 120-20 1 M6560-004 Shut off valve assembly DN300 Fig. 14-133 Flange: DIN PN10 Blower No. 1 inlet B 2
1 M2480-001 Butterfly valve DN300 Fig. 14-133 Flange: DIN PN10 A 2
1 M1021-001 Gear Fig. 455-WMK009 For DN200 - 300 mm A 2
1 M1015-001 Limit switch box w/2xV9 switch Fig. 792 LP A 2
11 120-30 1 M6560-004 Shut off valve assembly DN300 Fig. 14-133 Flange: DIN PN10 Blower No. 2 inlet B 2
1 M2480-001 Butterfly valve DN300 Fig. 14-133 Flange: DIN PN10 A 2
1 M1021-001 Gear Fig. 455-WMK009 For DN200 - 300 mm A 2
1 M1015-001 Limit switch box w/2xV9 switch Fig. 792 LP A 2
13 0-0 1 M3165-001 Shut off valve Deck isolating valve Deck isolating valve C 99
14 1 M1022-001 Limit switch 99
1 M1390-001 Shut off valve Sea water scrubber overboard 99
15 1 M1150-015 Shut off/non return valve Sea water DWS overboard 99
16 1 M1011-016 Shut off valve Sea water inlet from sea Sea water inlet from sea chest C 99
chest
18 1 M1011-018 Shut off/non return valve Sea water pump outlet Sea water pump outlet C 99
19 1 M1022-001 Limit switch 99
1 M7244-001 Shut off/non return valve Sea water aux. supply 99
20 2 M1011-020 Shut off valve Sea water inlet DWS pumps Sea water inlet DWS pumps C 99
Revision No: 02
\\alke\jvsmast\rpt\cr\moss\parts_list.rpt Revision Date: 20-apr-2007 Page 2 of 11
Order No: 130959 FG10000-16 (8600-13590 Nm3/h)
Stk Packing
Item SO No Qty Article No Description Specification Remark Notes Supply Type No
21 2 M1011-021 Shut off/non return valve Sea water outlet DWS pumps Sea water outlet DWS pumps C 99
24 140-20 2 N8658-001 Uptake valve assembly DN400 Flange: DIN PN10 Boiler uptake 1 and 2 B 12
1 M3168-004 Butterfly uptake valve DN400 Mod: VR-7890 Swing ThroughFlange: DIN PN10 A 2
1 M1096-001 Pneumatic actuator Fig. 79E-012 A 2
1 M1015-001 Limit switch box w/2xV9 switch Fig. 792 LP A 2
1 N1068-001 Solenoid valve 5/2 791/B 24V DC Connect: 1/4" BSP A 2
26 140-30 1 N8658-001 Uptake valve assembly DN400 Flange: DIN PN10 Boiler uptake common line B 12
1 M3168-004 Butterfly uptake valve DN400 Mod: VR-7890 Swing ThroughFlange: DIN PN10 A 2
1 M1096-001 Pneumatic actuator Fig. 79E-012 A 2
1 M1015-001 Limit switch box w/2xV9 switch Fig. 792 LP A 2
1 N1068-001 Solenoid valve 5/2 791/B 24V DC Connect: 1/4" BSP A 2
30 90-140 1 M0820-001 Shut off/non return valve 1" BGV-456022NR PN16 RG5 Connect: 1" BSP S. W. to deck water seal B 0
19C
34 180-10 1 M0827-001 Shut off valve 3/4" Brass. A: CIM 70/BS Connect: 3/4" BSP Drain of DWS A 0
39 160-10 2 M0820-001 Shut off/non return valve 1" BGV-456022NR PN16 RG5 Connect: 1" BSP Steam for cleaning uptake valve B 0
19C
40 80-10 1 M0830-001 Test cock valve Brass Connect: 1/4" BSP For PS 183 A 0
41 60-20 2 M0832-001 Test cock valve DN8 Type 7.6645 Connect: 1/4" BSP A 0
42 90-150 5 M0832-001 Test cock valve DN8 Type 7.6645 Connect: 1/4" BSP B 0
43 80-10 1 M0826-001 Shut off valve 1/2" Brass. A: CIM 70/BS Connect: 1/2" BSP Instrument air inlet A 0
47 120-80 1 N8440-001 Shut off valve assembly DN50 Fig. 14-133 (Spring open) Flange: DIN PN10 Vent to I.G. main B 2
1 M1302-001 Butterfly valve DN50 Fig. 14-133 Flange: DIN PN10 A 2
1 M6724-001 Pneumatic actuator Fig. 79E-006S Spring open A 2
48 50-90 2 N2863-001 Butterfly valve DN50 Fig. 14-133 Flange: DIN PN10 Drain condensate/F.W washing B 2
I.G. blowers
1 M1302-001 Butterfly valve DN50 Fig. 14-133 Flange: DIN PN10 2
1 M1106-001 Lever handle Fig. 412-015S DI/SS DN for manual operation 2
40-50
53 160-20 1 N8740-001 Ball valve DN25 assembly Closed, F180 Connect: 1" BSP Steam for cleaning uptake valves B 2
1 N8741-001 Ball valve DN25 F180 Full Bore Connect: 1" BSP A 2
1 N9365-001 Pneumatic actuator PRA-002 A 2
Revision No: 02
\\alke\jvsmast\rpt\cr\moss\parts_list.rpt Revision Date: 20-apr-2007 Page 3 of 11
Order No: 130959 FG10000-16 (8600-13590 Nm3/h)
Stk Packing
Item SO No Qty Article No Description Specification Remark Notes Supply Type No
1 N1068-001 Solenoid valve 5/2 791/B 24V DC Connect: 1/4" BSP A 2
54 0-0 2 M4569-001 Shut off valve Steam for heating of DWS Steam for heating of DWS C 99
64 180-20 1 M0062-001 Non return valve DN400 Material: COR-TEN / AISI 316Flange DIN PN10 For Inert Gas main line B 0
84 50-100 1 M6643-001 Flexible hose w/couplings 1/2" x 5m For blower flushing B 2
2 M0838-001 Hose claw coupling Connected to hose A 0
85 50-20 2 M0835-001 Male claw coupling Kag 12 R 1/2" A 0
86 2 M0818-001 Shut off/non return valve 1/2" BGV-456022NR PN16 RG5 Connect: 1/2" BSP I.G. blower flushing A 0
19C
100 1 M7831-003 Fan DN300 BK 25-1 Flange: DIN PN10 Blower No 1 B 2
101 1 M7831-003 Fan DN300 BK 25-1 Flange: DIN PN10 Blower No 2 B 2
103 1 M8767-001 El. motor M3BP 225 SMC2 65 kW 440V 60Hz IP55 El. motor blower No. 1 A 2
104 1 M8767-001 El. motor M3BP 225 SMC2 65 kW 440V 60Hz IP55 El. motor blower No. 2 A 2
105 50-50 6 M1167-001 Resilient mounting RA 350A w/stop B 2
106 50-60 6 M1167-001 Resilient mounting RA 350A w/stop B 2
107 50-70 2 M7676-001 Flexible bellow, DN300 Tuboflex T-49 yellow/NBR Flange: DIN PN10 Inlet I.G. Fan No. 1 and 2 B 2
108 50-80 2 M7676-001 Flexible bellow, DN300 Tuboflex T-49 yellow/NBR Flange: DIN PN10 Outlet I.G. Fan No. 1 and 2 B 2
110 0-0 1 M8484-001 Axial compensation C 99
111 1 M8484-001 Axial compensation C 99
112 1 M8484-001 Axial compensation C 99
114 60-20 1 M0239-001s Sight glass DN400 NS 6141/ISO 1751-A400-LW Connect: welding type, A 0
DN400
115 180-10 1 M0239-001s Sight glass DN400 NS 6141/ISO 1751-A400-LW Connect: welding type, A 0
DN400
116 60-20 1 M1214-001s Sea water spray nozzle Moss-2 1/2 -60-24, 60° Connect: 2 1/2" BSP A 2
117 8 M1348-001s Sea water spray nozzle Moss-2-90-15, 90° Connect.: 2" BSP A 2
122 0-0 1 M1011-122 Filter, sea water inlet C 99
125 2 M1011-125 Sea water pump Supply to DWS Supply to DWS C 99
Revision No: 02
\\alke\jvsmast\rpt\cr\moss\parts_list.rpt Revision Date: 20-apr-2007 Page 4 of 11
Order No: 130959 FG10000-16 (8600-13590 Nm3/h)
Stk Packing
Item SO No Qty Article No Description Specification Remark Notes Supply Type No
126 2 M1011-126 El. motor For DWS sea water pump For DWS sea water pump C 99
128 1 M1011-128 Sea water pump Supply to Scrubber Supply to Scrubber C 99
129 1 M1011-129 El. motor For Scrubber sea water pump For Scrubber sea water pump C 99
130 60-20 1 M1199-001 Wet filter for scrubber 1588x458x200 A 2
131 1 M1879-001 Demister for Scrubber 1588x458x150 A 2
132 180-10 1 M1334-001 Demister section for DWS 1588x434x150 A 2
141 80-10 1 N3295-002 Solenoid valve 3/2-way NC air SCE374A017MS 24V DC 1/4'' BSP Material: Brass Air supply to item 1 and 47 A 0
10bar
160 1 M0121-001 Pressure gauge, dia. 63mm Scale 0-10 bar / 0-1 MPa Connect: 1/4" BSP AISI Instrument air inlet A 0
316
161 60-10 0 M0120-001 Pressure gauge, dia. 100mm Scale -0,4+0,6 bar/-40+60 Connect: 1/4" BSP Exhaust gas A 0
kPa
60-20 1 M0120-001 Pressure gauge, dia. 100mm Scale -0,4+0,6 bar/-40+60 Connect: 1/4" BSP Exhaust gas A 0
kPa
163 90-10 1 M0120-001 Pressure gauge, dia. 100mm Scale -0,4+0,6 bar/-40+60 Connect: 1/4" BSP I.G. outlet blowers B 0
kPa
164 60-20 1 M0117-001 Pressure gauge, dia. 63mm Scale 0-4 bar / 0-400 kPa Connect: 1/4" BSP AISI Sea water main inlet scrubber A 0
316
167 90-20 1 M0120-001 Pressure gauge, dia. 100mm Scale -0,4+0,6 bar/-40+60 Connect: 1/4" BSP I.G. outlet scrubber B 0
kPa
169 90-30 1 M0117-001 Pressure gauge, dia. 63mm Scale 0-4 bar / 0-400 kPa Connect: 1/4" BSP AISI Sea water to D.W.S. B 0
316
175 60-20 1 M0124-001 Thermometer 0-100°C Straight type, L=63mm Connect: 1/2" BSP Sea water main inlet scrubber A 0
176 90-40 1 M0126-001 Hot gas thermometer 50-650°C Sensor length 300mm x 3/4"RConnect: 3/4" BSP Exhaust gas B 0
177 90-50 1 M0125-001 Thermometer 0-100°C Angle type 90, L=63mm Connect: 1/2" BSP I.G. outlet blower 1 B 0
178 90-160 1 M0125-001 Thermometer 0-100°C Angle type 90, L=63mm Connect: 1/2" BSP I.G. outlet blower 2 B 0
179 90-60 1 M0124-001 Thermometer 0-100°C Straight type, L=63mm Connect: 1/2" BSP I.G. outlet scrubber B 0
182 90-80 1 M0111-001 Pressure transmitter EEx ia II IG/air press -500/+2500 I.G.pressure in deck main line B 0
mmWG To be protecyed against weather
Setpoint 50/1450 mmWG
Revision No: 02
\\alke\jvsmast\rpt\cr\moss\parts_list.rpt Revision Date: 20-apr-2007 Page 5 of 11
Order No: 130959 FG10000-16 (8600-13590 Nm3/h)
Stk Packing
Item SO No Qty Article No Description Specification Remark Notes Supply Type No
90-70 1 M0085-001 Bracket for press. transmitter B 0
183 80-10 1 M0165-001 Pressure switch 3,45-8,34 bar 4140C K1E12 AAO-EE Connect: 1/8" BSP Low instrument air pressure A 0
Setpoint 5,0 bar
184 60-20 1 M0169-001 Pressure switch 0.1-2.1 bar P1H-B30-SS Connect: 1/4" NPT Low S.W. pressure inlet scrubber A 0
Setpoint 0,7 bar
187 90-90 1 M0167-001 Pressure switch -0.2/+0.2 bar D1T-M3-SS-Exi Connect: 1/4" BSP Low I.G. pressure in deck main B 0
To be protected against weather.
Setpoint 100 mmWG.
188 90-100 1 M0171-001 Temp. transmitter 0-100°C PT 100, 4-20mA, L=250 Connect: 1/2" BSP High I.G. temp. B 0
Setpoint 65 °C.
189 90-110 1 M0169-001 Pressure switch 0.1-2.1 bar P1H-B30-SS Connect: 1/4" NPT Low S.W. pressure to DWS B 0
Setpoint 0,7 bar.
192 60-20 1 M0164-001 Temperature switch 49-71*C 4140D K1EOOCE2-EE Connect: 1/2" BSP High I.G. temp. in scrubber A 0
Setpoint 55°C.
193 1 M0181-001 Level switch Type 003S Connect: 1" BSP High S.W. level scrubber A 0
194 180-10 1 M0182-002 Level switch Squing-2 Connect.: 1" BSP Low S.W. level in DWS A 0
206 0-0 1 M0234-002 Pressure regulator valve for Nitrogen gas bottle 2
207 1 M0233-002 Span gas bottle nitrogen Bottle 2
231 80-10 1 M1176-001 Pneumatic Panel B 12
232 100-10 1 N9374-001 Oxygen Analyzer panel Moss IGS Analyser 3500 B 0
233 70-10 1 M1606-001 Main control panel FG+TUG B 2
234 70-30 1 M1699-003 Local panel T.U.G A 2
237 70-70 1 M1053-001 Power distribution panel B 2
238 70-90 1 M1054-001 Intrinsic Safe Panel B 2
239 70-110 1 M1052-004 Sub panel in Wheel House Flush mounting B 2
240 70-120 1 M1698-004 Sub panel in EC Room Flush mounting B 2
241 110-10 1 M1632-001 Starter blower DOL- max. 100kW 185A Starter blower 1 B 2
242 110-20 1 M1632-001 Starter blower DOL- max. 100kW 185A Starter blower 2 B 2
Revision No: 02
\\alke\jvsmast\rpt\cr\moss\parts_list.rpt Revision Date: 20-apr-2007 Page 6 of 11
Order No: 130959 FG10000-16 (8600-13590 Nm3/h)
Stk Packing
Item SO No Qty Article No Description Specification Remark Notes Supply Type No
249 70-130 1 M0190-001 Alarm sirene Type: 172.24 24V DC B 0
250 180-10 1 M1289-001 Deck Water Seal DWS - Nom. size: 2
10000Nm3/h-16
252 170-10 0 M1274-001 P/V Breaker Nom. size: DN400 B 2
253 60-20 1 M1283-001 Scrubber Unit FG - Nom. size: 10 FG9490 2
000Nm3/h-16
254 120-50 1 M1131-001 Name plates for loose items Plastic, laminated 70x20mm, Øhull=3,5mm, B 2
C/C=60mm
120-70 1 M8001-001 Engraving av Tag plate Hamworthy Moss standard B 2
240-30 0 M1847-001 Engraving Company name plate B 2
256 130-10 1 N9095-001 Hydro Carbon/O2 analyzer-port Model RX-415 B 2
130-20 1 N9095-002 Sample hose 30m for RX-415 B 2
130-30 2 N9095-003 Sample bag for RX-415 2 litre B 2
260 140-50 1 M2394-001 Hatch DN350 w/steel frame NS 6141- A300 - LW For air vent B 2
140-40 1 M1077-001 Limit switch for air sealing XCK-J 161 B 2
262 80-10 1 M1833-001 Reduction valve w/filter 1/2" C15, G1/2", 535 132 021 0 A 0
264 90-120 1 M0255-001 Vacuum valve DN15 Connect: 1/2" BSP B 0
265 90-130 1 M0078-001 Flame Arrestor NS-2527 DN50 Flange: DIN PN10 B 10
900 190-10 1 M1080-001 Spare parts box Model 23-20, 200x350x200 B 2
908 190-20 1 M8020-001 Chart paper, fan fold PHC33 Spare for recorder Fuji PHC33 B 0
190-30 1 M8023-001 Ink cartridge PHC33 with ink absorption cloth incl Spare for recorder Fuji PHC33 B 0
912 190-40 1 M1129-001 Ball bearing 6312/C3 Spare part Non-Drive end B 2
913 190-50 1 M2423-001 Ball bearing 6313/C3 Spare part Drive end B 2
1005 220-10 1 N8777-001 Shut off valve assembly DN80 Fig. 14-133 Flange: DIN PN10 Sea water inlet scrubber A 2
1 M2474-001 Butterfly valve DN80 Fig. 14-133 Flange: DIN PN10 A 2
1 M1017-001 Pneumatic actuator Fig. 79E-006 A 2
1 M1015-001 Limit switch box w/2xV9 switch Fig. 792 LP A 2
1 N1068-001 Solenoid valve 5/2 791/B 24V DC Connect: 1/4" BSP A 2
1006 1 N8162-006 Control valve assembly DN80 Fig. 14-133 Flange: DIN PN10 Inert gas capacity A 2
1 M2474-001 Butterfly valve DN80 Fig. 14-133 Flange: DIN PN10 A 2
Revision No: 02
\\alke\jvsmast\rpt\cr\moss\parts_list.rpt Revision Date: 20-apr-2007 Page 7 of 11
Order No: 130959 FG10000-16 (8600-13590 Nm3/h)
Stk Packing
Item SO No Qty Article No Description Specification Remark Notes Supply Type No
1 M1017-001 Pneumatic actuator Fig. 79E-006 A 2
1 M1014-003 Positioner with limit switch Fig. 793-011M 15-3psi Supply:1/4"BSP, A 2
Signal:1/8"BSP
1 M0110-002 I/P converter V18312-12221190 4-20mA/3-15 psi A 0
1 M0122-001 Pressure gauge, dia. 50mm Scale 0-30 psi/0-200 kPa Connect: 1/4" BSP A 0
1 M6910-001 Manual override kit <- DN125 for F79E-003/006/012 with release valve A 2
1012 1 M0816-001 Control valve 1" BGV-456022 PN16 RG5 Connect: 1" BSP Combustion air to atmosphere A 0
1014 0-0 1 M1390-002 Shut off/non-return valve Sea water scrubber overboard 99
1017 1 M1011-018 Shut off/non return valve Sea water pump outlet 99
1028 1 M1011-016 Shut off valve Sea water inlet from sea 99
chest
1032 220-10 2 M0828-001 Shut off valve 1" Brass. A: CIM 70/BS Connect: 1" BSP For sight glass A 0
1035 1 M0826-001 Shut off valve 1/2" Brass. A: CIM 70/BS Connect: 1/2" BSP Secondary air to burner A 0
1040 1 M0830-001 Test cock valve Brass Connect: 1/4" BSP Gauges and switches A 0
1041 4 M0832-001 Test cock valve DN8 Type 7.6645 Connect: 1/4" BSP Gauges and switches A 0
1045 2 M0825-001 Shut off valve 3/8" Brass. A: CIM 70/BS Connect: 3/8" BSP Air for cleaning of sight glass A 0
1050 1 M1301-001 Control valve assembly DN50 Fig. 14-133 Flange: DIN PN10 Seawater inlet A 2
1 M1302-001 Butterfly valve DN50 Fig. 14-133 Flange: DIN PN10 A 2
1 M1103-001 Gear Type QE4 A 2
1 M1103-002 Long locking bolts for gear A 2
1052 1 M0338-001 Silencer/spark arrestor For 1" SM A 0
1062 1 M0824-001 Control valve PN100 TA-52475-308 Connect: 1/4" BSP Air to ignition burner A 0
1066 2 M0138-001 Non return valve Type RHD 8 L Connect: pipe Ø8 OD Air flush of oil gun A 0
comp.ends
1069 240-20 1 M0044-001 Non return valve DN100 Material: COR-TEN / AISI 316Flange DIN PN10 Common for F.G. and T.U.G. B 0
1073 220-10 1 M0245-002 Burner gun, no return Hamworthy Moss Conn. M18x1,5 A 0
1074 200-40 1 M0156-001 Ball valve DN15 2013M AISI 316L PN64 Connect: 1/2" BSP A 0
1081 1 M0149-001 Fuel oil filter DN25 2.04.5, Ident-Nr.0228422 Flange: DIN PN16 A 0
Revision No: 02
\\alke\jvsmast\rpt\cr\moss\parts_list.rpt Revision Date: 20-apr-2007 Page 8 of 11
Order No: 130959 FG10000-16 (8600-13590 Nm3/h)
Stk Packing
Item SO No Qty Article No Description Specification Remark Notes Supply Type No
1082 1 M1303-001 Fuel oil pump without motor E4 NA-1001 6P A 2
1083 1 M2372-001 El. motor M2AA 80 A A 2
1084 220-10 1 N9345-001 Flexible oil hose, 3/8" Dunlop Hiflex 122 (EN853 Connect: M18x1,5 L=1m Fuel oil to main burner A 2
1SN)
1085 1 N9341-001 Flexible oil hose, 1/4" Dunlop Hiflex 122 (EN853 Connect: M16x1,5 L=1m Fuel oil to ignition burner A 2
1SN)
1086 1 M1361-001 Oil nozzle, main burner 60° - 7,5 USG/H A 2
1087 1 M0106-002 Ignition burner Hamworthy Moss A 10
1088 1 M0105-002 Oil nozzle, ignition burner Type F80, 1 GPH - 80°R Connect: 9/16" 24 UNEF A 0
1089 1 M3586-001 Ignition glow plug 12V Type GH 408 Connection M14 x 1,25 A 0
1090 2 M0231-001 Sight Glass Hamworthy Moss A 10
1107 210-40 1 M5904-002 Blower DN100 L45/2P DIN PN 10 A 2
1109 1 N8794-001 El. motor M3AA 132 SC2 A 2
1110 1 M5905-001 Blower DN100 assembly LRB45/2P Flange: JIS 5K B 12
1114 220-10 1 M0239-001s Sight glass DN400 NS 6141/ISO 1751-A400-LW Connect: welding type, A 0
DN400
1117 6 M1366-001s Sea water spray nozzle Moss-1-90-4, 90° Connect.: 1" BSP A 2
1123 0-0 1 M1011-128 Sea water pump Supply to Scrubber 99
1124 1 M1011-129 El. motor For Scrubber sea water pump 99
1130 220-10 1 M1331-001 Wet filter for scrubber 692x206x200 A 2
1131 1 M1314-001 Demister for scrubber 692x554x150 A 2
1152 1 N3296-002 Solenoid valve 2/2-way NC air SCE272A017MSS3 24V DC 1/4'' BSP Material: Brass Air to ignition burner, 24V, 60 Hz A 0
15bar
1153 200-40 1 N8726-001 3-way ball valve DN15 F138 Connect: 1/2" BSP A 2
1 N8727-001 3 way Ball valve, DN 15 F138, DN15, Full Bore Connect: 1/2" BSP A 2
1 N9365-001 Pneumatic actuator PRA-002 A 2
1 N1068-001 Solenoid valve 5/2 791/B 24V DC Connect: 1/4" BSP A 2
Revision No: 02
\\alke\jvsmast\rpt\cr\moss\parts_list.rpt Revision Date: 20-apr-2007 Page 9 of 11
Order No: 130959 FG10000-16 (8600-13590 Nm3/h)
Stk Packing
Item SO No Qty Article No Description Specification Remark Notes Supply Type No
1156 220-10 1 N3296-002 Solenoid valve 2/2-way NC air SCE272A017MSS3 24V DC 1/4'' BSP Material: Brass Fuel oil to burner, 24 V, 60 Hz A 0
15bar
1157 1 N3296-002 Solenoid valve 2/2-way NC air SCE272A017MSS3 24V DC 1/4'' BSP Material: Brass Air flush of oil gun, 24 V, 60 Hz A 0
15bar
1158 1 N3297-003 Solenoid valve 2/2-way NC oil SCE272A046MS 24V DC 1/4'' BSP Material: Fuel oil to ignition burner, 24 V, A 0
AISI316L 60 Hz
1161 1 M0115-001 Pressure gauge, dia. 63mm Scale 0-1 bar / 0-100 kPa Connect: 1/4" BSP AISI Combustion air to burner A 0
316
1162 1 M0115-001 Pressure gauge, dia. 63mm Scale 0-1 bar / 0-100 kPa Connect: 1/4" BSP AISI Seawater to cooling jacket A 0
316
1164 1 M0117-001 Pressure gauge, dia. 63mm Scale 0-4 bar / 0-400 kPa Connect: 1/4" BSP AISI Seawater main inlet to scrubber A 0
316
1165 1 M0119-001 Pressure gauge, dia. 63mm Scale 0-40 bar / 0-4 MPa Connect: 1/4" BSP AISI Fuel oil to burner A 0
316
1175 1 M0124-001 Thermometer 0-100°C Straight type, L=63mm Connect: 1/2" BSP Seawater main inlet to scrubber A 0
1178 1 M0124-001 Thermometer 0-100°C Straight type, L=63mm Connect: 1/2" BSP Seawater outlet cooling jacket A 0
1179 1 M0124-001 Thermometer 0-100°C Straight type, L=63mm Connect: 1/2" BSP Inert Gas outlet scrubber A 0
1180 1 M0168-001 Pressure switch -1/+1,25 bar D2T-M18SS-Exi A 0
1184 1 M0169-001 Pressure switch 0.1-2.1 bar P1H-B30-SS Connect: 1/4" NPT A 0
1185 1 M0166-001 Pressure switch 6.89-23.44 bar 4140C K1E13 AAO-EE Connect: 1/4" BSP A 0
1191 1 M0181-001 Level switch Type 003S Connect: 1" BSP A 0
1193 1 M0181-001 Level switch Type 003S Connect: 1" BSP High sea water level Scrubber A 0
1200 2 M0086-001 Photocell complete Hamworthy Moss Burner flame scanner A 10
1202 200-40 1 M0339-001 Flow indicator 0-100kg/h Model 10A1197ASS Connect: 1/2" BSP A 0
1209 220-10 1 M0094-002 Ignition Transformer 234VA 115-220 9-13V 50/60HZ For glow plug A 2
1220 1 M0112-001 Pressure transmitter Type 8161-1221-1111 0-0,3 bar (g) A 0
1229 200-40 1 M1295-000 Fuel Oil Unit TG B 12
1241 230-10 1 M1725-001 Starter T.U.G Blower DOL- max. 9kW 14.5A B 2
Revision No: 02
\\alke\jvsmast\rpt\cr\moss\parts_list.rpt Revision Date: 20-apr-2007 Page 10 of 11
Order No: 130959 FG10000-16 (8600-13590 Nm3/h)
Stk Packing
Item SO No Qty Article No Description Specification Remark Notes Supply Type No
1243 230-20 1 M1681-001 Starter fuel oil pump Max. 5kW 12A B 2
1253 220-10 1 M1248-001 Burner / Scrubber unit GP - Nom. size: 500Nm3/h-7 Incl. pneumatic panel A 2
1901 260-10 1 M1361-001 Oil nozzle, main burner 60° - 7,5 USG/H Spare B 2
1902 260-20 1 M0105-002 Oil nozzle, ignition burner Type F80, 1 GPH - 80°R Connect: 9/16" 24 UNEF Spare B 0
1903 260-30 1 N9345-001 Flexible oil hose, 3/8" Dunlop Hiflex 122 (EN853 Connect: M18x1,5 L=1m Spare B 2
1SN)
1904 260-40 1 N9341-001 Flexible oil hose, 1/4" Dunlop Hiflex 122 (EN853 Connect: M16x1,5 L=1m Spare B 2
1SN)
1905 260-50 1 M0150-001 Insert for fuel oil filter Basket element - 250 mikron Spare B 0
1907 260-60 1 M3586-001 Ignition glow plug 12V Type GH 408 Connection M14 x 1,25 Spare B 0
1931 260-70 1 M1952-001 Ball bearing 6208-2Z/C3 Spare B 2
1932 260-80 1 M1952-001 Ball bearing 6208-2Z/C3 Spare B 2
1933 260-90 1 M1443-001 Ball bearing 6204-2Z/C3 Spare B 2
1934 260-100 1 M2597-001 Ball bearing 6203-2Z/C3 Spare B 2
Revision No: 02
\\alke\jvsmast\rpt\cr\moss\parts_list.rpt Revision Date: 20-apr-2007 Page 11 of 11
Hamworthy Moss AS
Ordre no: 130959 Chapter: 10
LIST OF DRAWINGS
Drawing no.: Rev: Description:
Type: SBS3500-IG-M-AX4-HM
Part no.: SBS3500– 00756.
Contents:
I PREFACE........................................................................................................................................... 3
I.1 ABOUT THE MANUAL .................................................................................................................... 3
I.2 ABOUT THE SYSTEM ..................................................................................................................... 3
I.3 COMPANY ADDRESSES .................................................................................................................. 4
I.4 INTRODUCTION TO SBS3500 ........................................................................................................... 5
I.5 SPECIFICATIONS ............................................................................................................................ 6
I.5.1 Analyzer Board..................................................................................................................... 6
I.5.2 Optional equipment .............................................................................................................. 6
I.6 TYPE APPROVAL ........................................................................................................................... 7
II INSTALLATION ............................................................................................................................... 9
II.1 CONTROL AT DELIVERY ................................................................................................................ 9
II.2 LOCATION AND INSTALLATION ..................................................................................................... 9
II.2.1 Safety Aspects..................................................................................................................... 10
II.2.2 Electrical connections ........................................................................................................ 11
II.2.3 Analyzer Board................................................................................................................... 13
II.2.4 Connection ......................................................................................................................... 13
II.2.5 Sample gas connection ....................................................................................................... 13
II.2.6 Calibration gas connection ................................................................................................ 13
II.2.7 Electrical connection.......................................................................................................... 13
II.3 COMMISSION OF SYSTEM ............................................................................................................. 14
II.3.1 Pre-checks:......................................................................................................................... 15
II.3.2 Start of system .................................................................................................................... 15
III OPERATION................................................................................................................................ 17
III.1 CALIBRATION OXYGEN SIGNAL .................................................................................................. 17
III.1.2 Manual calibration procedure ........................................................................................... 18
III.1.3 Automatic calibration (Optional) ....................................................................................... 19
III.1.4 Artificial calibration........................................................................................................... 19
III.2 CALIBRATION OPTIONAL AUX. INPUTS ....................................................................................... 20
III.3 SETTING OF OUTPUT SIGNAL ....................................................................................................... 21
III.4 SETTING OF OUTPUT RANGE ........................................................................................................ 21
III.5 SETTING OF ALARM LIMITS ......................................................................................................... 22
III.6 ROUTINE MAINTENANCE ............................................................................................................ 22
III.6.1 Sample and test selection ................................................................................................... 22
III.6.2 Bubble glass and flow control ............................................................................................ 22
III.6.3 Analyzer.............................................................................................................................. 23
IV TROUBLE-SHOOTING: ............................................................................................................ 25
VI APPENDIX ................................................................................................................................... 29
VI.1 HOOKUP INFORMATION POWER BOARD .................................................................................. 31
VI.2 PROGRAM STRUCTURE ............................................................................................................ 32
VI.3 OXYGEN ANALYZER BOARD ................................................................................................... 37
VI.4 PIPING & CONNECTION DIAGRAM ........................................................................................... 39
VI.5 OUTPUT SIGNAL CHARGE ........................................................................................................ 41
VI.6 QUICK GUIDE -CALIBRATION .................................................................................................. 43
1
SBS 3500 Inert Gas Monitoring
2
I Preface
The instructions have been made in general terms and does not take into consideration the
existing equipment and installation, as such the instruction manual is designed for the oxygen
analyzer.
The Manual does not describe all possible situations but only the most common and known
situations, and cannot replace the necessary instruction and education of the personnel.
Should situations not described in the Manual occur, which cannot be solved in accordance with
normal known practice and good workmanship, the operator should contact Hamworthy Moss
AS for instructions.
Hamworthy Moss reserves the right to minor alterations and improvements owing to
developments without being obliged to enter the corresponding changes in this Manual.
In all correspondence or when ordering spare parts, be careful to state equipment type
and fabrication no.
It should be pointed out that installation and operation of the SBS 3500 Oxygen Monitoring
System and associated equipment should be carried out by skilled, trained and certified
personnel, and that SBS Technology A/S does not take any responsibility of the operation of the
system and associated equipment whatsoever.
3
SBS 3500 Inert Gas Monitoring
• Selector valve with four (4) position ports, enabling selection between e.g. three (3) sample
point and one (1) calibration and test gases.
• Calibration gas selection with two (2) ports, enabling selection between two types of
calibration gases, e.g. ambient 20.9% clean instrument air (span) and 2.0% test gas (zero).
• Sampling system with manual flow control valve, filer, bubble glass and oxygen sensor.
• Oxygen analyzing.
Hamworthy Moss AS
Vaerftsgt. 13
P.O. Box 1053
1510 NO-1510 Moss
Norway
E-mail: [email protected]
4
I.4 Introduction to SBS3500
The SBS3500 Oxygen Monitoring System is used to monitor the oxygen content in Inert gases.
The compact design provides a wide range of configuration possibilities, outstanding
performance and reliable on-line monitoring.
The SBS3500 is more than just an analyzer. Oxygen monitoring is also sample selection,
sample conditioning, display and visualization.
The zirconium oxide oxygen analyzers have long been established as industry standards. The
SBS3500 is based on a new type of industrial sensors, which can be used in a wide measuring
range.
The sensor element is on one side exposed to the inert gas and on the other side to fresh air.
Difference in oxygen concentration on the two sides of the zirconia ceramic element will at high
temperature result in ionic flow through the sensor material. Because of the transportation of
ions a small electrical voltage originates. The detected signal on the opposing surfaces of the
zirconia sensor is a picture of the actual oxygen concentration in the sample gas and is used for
further processing in the analyzer.
Atmospheric
Inert Gas
Figure 1. Transmitter
5
SBS 3500 Inert Gas Monitoring
I.5 Specifications
6
I.6 Type Approval
7
SBS 3500 Inert Gas Monitoring
8
IIInstallation
1. The equipment should be installed in a clean area away from dust, oil mist and
moisture. The system elements should all be installed at viewing level in an area with
good access for operating and servicing the system.
2. It is recommended that the analyzing panel is located near to the sampling point in order
to have current and accurate readings. Long and large bore sample lines will increase
the responds time due to dead volume.
3. The location and installation of the system must be chosen so that the ambient
temperature at any time is below 55°C.
9
SBS 3500 Inert Gas Monitoring
Warning!
The SBS3500 analyzer is only suitable for installation in a safe non-hazardous area.
Warning!
The SBS3500 analyzer is not suitable for use with flammable sample gases.
Warning!
Do not attempt welding or carry out hot-work without prior approval.
Warning
The O2 probe is hot and can cause severe burning to personals if not handled with care
Power supply!
Ensure that main supplies are switched off when connecting to the analyzer equipment.
Read the instruction carefully to ensure correct connection of all power and signal leads.
Ensure that the correct AC voltage is connected to the analyzer. See rating marked on the
transformer inside the analyzer or on the analyzer name plate.
EMC
For compliance with the EMC product standard EN50270 the connection cables for the
main supply, relays, interface and analog output signals should be shielded or provide
equivalent protection. Special precautions have to be taken for “long” signal or control
lines of more than 30 M.
Circuit breaker!
The installation must include a means of isolating electrical power by a switch or circuit breaker
external to the analyzer and within reach of operator. It must be clearly marked.
Protective earth!
The analyzer must be connected to protective earth.
10
Connections!
All electrical connections and power supply fuse FUH-1, are accessed on the lower part of the
power board inside the analyzer. To gain access the top cover on the analyzer must be unbolted
using standard 6-8 mm screwdriver. To work on the analyzer or termination the interconnection
ribbon may be disconnection on the based board.
11
SBS 3500 Inert Gas Monitoring
Connection’s in BOLD are basic connections. All other connections are to be considered
optional.
12
II.2.3 Analyzer Board
The analyzer board is supplied with two (2) angle iron mounting brackets. The brackets are
made from ordinary mild steel and can bee directly welded or bolted to chosen location
structure as required. For dimensions and layout see appendix VI.4
The two mounting brackets must be mounted horizontal and parallel with a distance of 580 mm.
II.2.4 Connection
Assuming the above Boards is now installed in an appropriate location, we are now ready to
connect the system with sample gas, calibration gas and power.
The connection for sample gas is arranged on the left upper corner of the system board at the
sample manifold. Up to three (3) samples can be connected to the manifold. The three
Connection of sample connections are all arranged as 1/8” female connection’s, and marked from bottom 1, 2 and 3.
gas 1 and sample gas 2
The system is supplied with the manifold sample port 2 and 3 plugged.
13
SBS 3500 Inert Gas Monitoring
Power supply
Before connecting the power supply to terminal JS-1 terminal 1-2, check power supply rating
marked on the name plat on the side of the analyzer. The power supply rating for the analyzer
must correspond with power supply available and in accordance with the specifications for the
analyzer.
Relay outputs
The power board is arranged with four (4) relay outputs connected to JP1 terminals 1-8.
Relay 1, 2 and 3 are optionally functions for automatic calibration and relay 4 as a common
alarm relay. All relay functions are connected with normal open function
Relay 1 is connected to terminals 1-2 = solenoid valve for Zero gas (low cal.) Terminal for relay output
Relay 2 is connected to terminals 3-4 = Solenoid valve for Span gas (high cal.)
Relay 3 is connected to terminals 5-6 = Solenoid valve for Sample gas
Relay 4 is connected to terminals 7-8 = Common alarm analyzer
When the monitoring system is arranged for automatic calibration the power supply for the
solenoid valves are normally taken after the fuse elements inside the analyzer. The 0.5 AT fuse
inside the analyzer can be replace with up to 2.0 A fuse when solenoid valve are powered from
the analyzer.
14
II.3.1 Pre-checks:
• Check that the span and zero calibration gases are connected and that all connections
are secured and not leaking. A leaking connection will result in loss of calibration gas
and may result in poor calibration.
• Check that the sample gases are connected and that the connections are secured and not
leaking. Sample gas connections should be as close to the process as possible and
preferably made from 6 mm stainless piping in order to reduce the dead volume in the
sampling system. If the sample gas is heavily contaminated pre-filter should be
installed. The sample gas has to be taken from a suitable location representing the gas to
be tested.
• Switch on the power supply. During the heating up of the oxygen-probe the display will
indicate an increasing oxygen content and will after 1-2 minutes start to stabilize. After
10 minutes when the sensor temperature has reached its operation temperature the
oxygen readings are to be considered stable.
• Fill up the bubble glass with clean water. About ¾ filled or ¼ above the center line
marked inside the glass
• With the IG system blower running turn the selector valve to sample port to be selected,
1-3.
• Open the flow control valve slowly until bubbles a noted. Open the flow control valve
so much there is a steady stream of bubbles from both the by-pass and sample return
pipes, placed inside the bubble glass. The left pipe is for by-passing of sample gas and
secure a better flow rate. The right pipe is the return of sample gas from the probe(s).
Increased flow indicating by more bubbles from both pipes will reduce the sampling
delay time.
• The gas flow passing the probe(s) must be adjusted so that the temperature of the probe
will not be affected. Too high velocity will change the probe temperature and
consequently the readings.
• Turn the selector valve to test and the calibration selector valve to zero and calibrate the
zero gas reduction station to about 0.2 bar and until the flow is about the same as noted
for the sample gas by observing the bubble flow.
• Turn the calibration selector valve to span calibration gas and adjust the span gas
reduction station to about 0.2 bar and until the flow is about the same as noted for the
sample gas by observing the bubble flow.
• Re-calibration, or test of calibration can be performed when the probe temperature has
reach normal operating temperature and the indication has stabilized. Normally after 10
minutes after starting the system. Calibration is carried out as described in paragraph
III.1.
15
SBS 3500 Inert Gas Monitoring
16
III Operation
This chapter describes the calibration of the SBS3500 system and routine maintenance. After
completing the installation and before putting the system into operating the system shall be
calibrated using known calibration gas. For the optional 0/4-20 mA Aux. inputs 1-3 the
calibration is based on input range and scale required.
The analyzer is arranged for manual calibration and optional automatic calibration. In addition
the analyzer can be artificial calibration. However, artificial calibration should only be used for
quick check and can not replace certified calibration gas.
The zero and span calibration gas is introduced to the analyzer via pressure reduction stations
and the selector valve and sampling system via the normal flow direction.
Warning!
The pressure and flow rate of the zero and span gas used to calibrate the analyzer must not
exceed 8 bar and flow should be as normally used for sample gas. In order to prevent
excessive pressure inside the bubble glass the sample outlet from analyzer and bubble gas
must be vented directly to atmosphere.
17
SBS 3500 Inert Gas Monitoring
The zero calibration gas to be used shall be pure nitrogen with a known amount of oxygen,
typically 1-3%.
The certified oxygen content in the zero calibration gas shall be programmed into the analyzer,
see program structure or routing diagram function P0405 and change value accordingly.
Note: For artificial calibration the P0405 value shall be 0% oxygen.
Introduce zero calibration gas to the analyzer by moving selector valve to position test gas and
select Zero gas. Check zero calibration pressure on the pressure regulating valve Max. 0.05 MPa
Waite for the zero value reading to stabilize, e.g. 2% oxygen reading and then push the E and
Select calibration gas for
ARROW DOWN simultaneously for 5 sec. To save the new zero setting push E again. span or zero calibration
The span calibration gas to be used shall be good quality clean dry instrument air with oxygen
content of 20.9% is recommended.
The span oxygen content in the span calibration gas shall be programmed into the analyzer, see
program structure or routing diagram function P0406 and change value to 20.9% for normal
instrument air.
Note: For artificial calibration the P0406 value shall be 20.9 % oxygen. Manual calibration of the
low value (zero) when
zero gas is introduced.
Introduce the 20.9 % span calibration gas to the analyzer by moving selector valve to position
Span Gas. Check Span calibration pressure on the pressure regulating valve, max. 0.05MPa
Waite for the span value reading to stabilize, e.g. 20.9 % oxygen reading and then push the E
and ARROW UP simultaneously for 5 sec. To save the new zero setting push E again.
The calibration should be checked weekly or as needed according to the application. Manual calibration of the
High value (span) when
span gas is introduced.
18
III.1.3 Automatic calibration (Optional)
If the analyzer is arranged with the optional possibility to carry our automatic calibration the
selector board is equipped with three (3) solenoid valves.
First change P=414 to 0 = use known zero calibration gas e.g. 2% (Save by ENTER)
Next set P0405 to e.g. 2 % and P0406 to 20.9 % (SAVE by ENTER)
Start the calibration in menu P0300 by changing the value to 1 and save.
The calibration will now start with calibrating first LOW and then HIGH. If the calibration takes
a long time the it is because the oxygen signal takes too long time to stabilize. The time required
for stable signal is set in menu P0415. Default the value is 10 seconds. On the other hand if the
stabilizing time is too short the calibration will not be correct as the signal has hot had the
required time to stabilize.
If the IGS monitoring system is equipped with two (2) analyzers the calibration will have to take
place one at the time. Two analyzers cannot be calibrated at the same time.
During automatic calibration observe the zero and span gas flow is sufficient and bubbles
flows from both tubes in the bubble glass.
During artificial calibration the sensors have to be exposed to ambient air with an oxygen
content of 20.9 % otherwise the calibration will not be correct. Select test and span gas.
Start the calibration in
menu P0300 by
changing the value to 1
Start the calibration in menu P0300 by changing the value to 1 and save.
and save.
The calibration will now start with calibrating first LOW and then HIGH. If the calibration takes
a long time the it is because the oxygen signal takes too long time to stabilize. The time required
for stable signal is set in menu P0415. Default the value is 10 seconds.
19
SBS 3500 Inert Gas Monitoring
The min. values are set in: P0405, P0505, P0605 and P0705(P0505 & P0506
The max. values are set in: P0406, P0506, P0606 and P0706(P0505 & P0506
The 0-22 mA current analog input signal is in the AD-converter with a 12 bit resolution or 4096
steps.
Next connect a known HI-value current on the input, and press ENTER in the span cal. menu
P0508 to accept the high-end calibration value.
The Min. /Max.- values at the menu P0505 and P0506 are used for conversion of the raw data
into the required scale and range.
Next connect a known HI-value current on the input, and press ENTER in the span cal. menu
P0608 to accept the high-end calibration value.
The Min. /Max.- values at the menu P0605 and P0606 are used for conversion of the raw data
into the required scale and range.
Next connect a known HI-value current on the input, and press ENTER in the span cal. menu
P0708 to accept the high-end calibration value.
20
The Min. /Max.- values at the menu P0705 and P0706 are used for conversion of the raw data
into the required scale and range.
1. Connect a current meter with the range 0 to 20 mA between terminals JS3-1(+) and
JS3-2 (-)
2. Set the output range P0801 to 1 = enabling 4-20 mA output signal
3. Set output selection P0802 to 1=oxygen, 2=Aux 1., 3=Aux 2, 4=Aux 3
4. Set Min. value P0805 to 0.0 (Example for oxygen signal output)
5. Set Max. value P0806 to 20.9 (Example for oxygen signal output)
Apply zero calibration gas e.g. 2% oxygen content to the analyser at the correct pressure and
flow rate. When the readings has stabilised adjust the zero value P0807 for 5 mA output signal
based 2 % oxygen level, see signal charge under appendix.
Then apply span calibration gas in the form of clean instrument air (20.9%) to the analyser at
the correct pressure and flow rate. When the readings has stabilised adjust the span value P0808
for 20 mA output signal.
For further references see appendix Error! Reference source not found. and Program structure
The range can be changed in both the Min. and Max. area. Normally only the Max. setting is
changed.
The output signal shall correspond to external requirements for input signal and range.
21
SBS 3500 Inert Gas Monitoring
When one of the alarms are energized the display will indicate the alarm e.g. high Oxygen
content P0404. When pressing the enter key the oxygen content will be displayed.
The Alarm values are set by first entering the MENU and the entering the submenu where the
alarm values are to changed e.g. P0404 high oxygen level.
Before shipment the analyzer alarm was set as per standard default values, see menu
configuration sheet.
Periodical check the reduction stations and connection for leaks. Max. allowed pressure for the
reduction stations is 8 Bar and temperature 60 °C. Depressurize the reduction stations before
cleaning and service. Clean with neutral detergent. Prevent the reduction units from the
ultraviolet rays and adhesion of organic solvents.
22
It is recommend to drain the bubble glass monthly and re-fill with clean distilled water.
The bubble glass may need internal cleaning and O-rings replaces as required for leak free
operation. Clean with neutral detergent. Prevent the glass from ultraviolet rays and adhesion of
organic solvents. For spare parts see spare part list.
Check daily the level in the bubble glass and re-fill with clean distilled water as required.
III.6.3 Analyzer
The Analyzer is tested from factory.
The analyzer does not require any special maintenance. Dirt and oil on the surface of the
analyzer (s) to be removed carefully using neutral detergent and clean dry rag.
For calibration and change of settings see above and appendix VI, settings and quick Guide-
calibration.
23
SBS 3500 Inert Gas Monitoring
24
IVTrouble-shooting:
Trouble-shooting should always be carried out by trained and certified personnel. The SBS3500
Oxygen Monitoring System is connected to hazardous electric voltages, which can cause severe
personal injury or mechanical damage if not handled correctly and in accordance with normal
safety regulations.
Display only indicating The interface signal terminal JS-3 terminal 12-14 is open
dotted line: and the analyzer is configured for st.-by mode, see P0200.
----- (0=st-by mode - 1=ON all the time)
Close terminal 12-14 or change st-by mode to ON all the
time in program P0200 and save
Display only indication 0.0 No signal from probe. Check probe connection both at the
0.0 analyzer and probe end.
Bad probe. Change the probe with spare probe.
Bad connection: Repair or change connection cable
Flicking FAIL and then a Fail means failure or alarm. The FAIL follows by a
program no. e.g P0404 program no. indicating the alarms.
P0403 = Alarm low oxygen
F AI L P0404 = Alarm high oxygen
P0503 = Alarm low Aux.1 signal (P0603 and P0703)
P0504 = Alarm high Aux 1 signal (P0604 and P0704)
Alarms for low cal. and Runtime
P04 04 see P9803, P9804 & P9805
Alarms disable = P0402-P0502- P0602- P0702=0
Alarms enable = P0402-P0502- P0602- P0702=1
Incorrect indication of Oxygen The calibration may have been incorrect applied. Check
level. calibration and go back to workable range. Re-calibrate
11.6 the analyzer, see III.1
If normal manual calibration is not working try artificial
calibration first. See III.1
25
SBS 3500 Inert Gas Monitoring
Incorrect remote display and Check display range setting P0805 and P0806
recording Check and re-calibrate the output signal, see chapter III.3
Incorrect signal output, resulting Overloading of the output signal. The analyzer can power
in wrong display of oxygen level up to 200 ohm load without using signal repeater or
on remote instrumentation. signal amplifier.
Can not calibrate the analyzer The oxygen cell may be may out of order
despite calibration procedure is The sensor cable is damaged
followed correctly The analyzer is defect
26
V Spare Part list
27
SBS 3500 Inert Gas Monitoring
Optional equipment
24 00592 Signal converter (4-20 mA)
28
VIAppendix
29
SBS 3500 Inert Gas Monitoring
30
VI.1 Hookup Information Power Board
Protective earth
Neutral Live N
Power lead P
31
SBS 3500 Inert Gas Monitoring
1. MENU:
2. ENTER:
3. ARROW-UP:
4. ARROW-DOWN:
Use the ARROW-UP or ARROW-DOWN to switch between the various sensor input i.e. % Oxygen,
Temperature, AuxIP1 and AuxIP2.
In case of remote displays a minimum menu is used i.e. no menus for input and output.
Press MENU to leave the parameter unchanged, going to the last menu-item.
Use the ARROW-UP or ARROW-DOWN to change the displayed parameter.
When the parameters are OK, press ENTER to temporarily save the new value and exit the menu-item.
Each menu has a unique number starting with “P” i.e. P0001, P0002., see Routing Diagram.
When the system is in standby or not active the display will show “-----”
but pressing any of the four keys will enable access to the menu.
A five minutes timeout for “no action”/ “no changes” will exit the menu.
In case the menu has been entered and left open, a one minute timeout will automatically close the menu,
discarding any changes.
32
System Menu continued...
|_ P0300, Calibration
Note Default Menu Functions
0 |_ P0300 1=start, 0 =stop, (1 = for start of calibration)
33
SBS 3500 Inert Gas Monitoring
34
|_ P9800, Probe service, Password protected “8651”
Note Default Menu Functions
0 |_ P9801 1=Probe service module enable - 0=Probe service module disable
0 |_ P9802 1=Alarm P9803, P9804 & P9805 enable - 0=Alarm disable
0 |_ P9803 Alarm LO for oxygen cal. zero
4095 |_ P9804 Alarm HI for oxygen cal. span
R 10000 |_ P9805 Alarm Runtime in hours 0-65535
D 0 |_ P9806 Runtime in hours 0-65535, full-ON as full time, half ON as half
time
R 0 |_ P9807 First cal. Zero value for memory
R 4095 |_ P9808 First cal. Span value for memory
R 24 |_ P9809 Time between self cal in hors 0-65535 – 0=self cal. OFF
R 0 |_ P9810 1= New probe mounted, clear old probe data – cleared after new cal.
R 0 |_ P9811 1= Probe half power when Interface is OFF - 0=Full power
35
SBS 3500 Inert Gas Monitoring
36
VI.3 Oxygen Analyzer Board
37
SBS 3500 Inert Gas Monitoring
38
VI.4 Piping & Connection Diagram
39
SBS 3500 Inert Gas Monitoring
40
I/O chart SB S3500
25
20
VI.5 Output signal charge
15
10
Oxygen level in %
0
0 5 10 15 20 25
S igna l in m A
41
SBS 3500 Inert Gas Monitoring
42
SBS 3500 Inert Gas Monitoring
NOTE: NOTE:
During operation and calibration observe flow and adjust if required During artificial calibration senor to be exposed to ambient air (Span gas)
Saving of the new setting by pushing “E” During operation and calibration observe flow and adjust if required
43
Contact Hamworthy Moss AS for information’s about Inert Gas
Analyzers & Monitoring Systems
Tel +47 69 27 99 00
Fax +47 69 25 45 78
E-mail [email protected]
Web www.hamworthy.com
TABLE OF CONTENT
NO. DESCRIPTION
2 Test Report of IGG (Burner/Scrubber Unit), Deck Water Seal & P/V-Breaker