The document outlines an 8-step project plan to validate and correct label information for an application with start dates ranging from March 29 to August 13, 2019 and target completion dates by August 23, 2019. As of the date of the document, steps 1 through 5 are complete, step 6 is ongoing, and steps 7 and 8 have yet to begin but are marked as ongoing. Overall project completion is currently at 70% of the targeted 86-day schedule.

Uploaded by

Ratakarn Buntee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
23 views2 pages

Print Label Plan

The document outlines an 8-step project plan to validate and correct label information for an application with start dates ranging from March 29 to August 13, 2019 and target completion dates by August 23, 2019. As of the date of the document, steps 1 through 5 are complete, step 6 is ongoing, and steps 7 and 8 have yet to begin but are marked as ongoing. Overall project completion is currently at 70% of the targeted 86-day schedule.

Uploaded by

Ratakarn Buntee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Start Target

Project Item
date date
No. Validate & Correct label information Application 29-Mar-19 23-Aug-19
1 - Discuss detail about requirement. 1-Apr-19 5-Apr-19
(Wk14)
2 - Study print label room work flow. 8-Apr-19 12-Apr-19
(Wk15)

3 - Design program work flow. 18-Apr-19 3-May-19


(Wk16-18)
4 - Design and create database. 6-May-19 24-May-19
(Wk19-20)

5 - Design and create user interface for each module. 27-May-19 14-Jun-19
(Wk33)

6 - Coding program. 24-Jun-19 26-Jul-19


(Wk34)
7 - Verify label data is correct with requester. 30-Jul-19 9-Aug-19
(Wk34)
8 - Debug program and trial run in production line. 13-Aug-19 23-Aug-19
(Wk35)

Total :=
Times % Target % Actual
Status
Develop by item by item

5 days 5% 5% Done

5 days 5% 5% Done

10 days 10% 10% Done

15 days 15% 15% Done

15 days 20% 20% Done

15 days 20% 15% ongoing

9 days 10% 0% ongoing

12 days 15% 0% ongoing

86 days 100% 70%