Code: Btpp/Turbine/007/Vacuum Raising Guidelines For Condenser Vacuum Raising Precondition
Code: Btpp/Turbine/007/Vacuum Raising Guidelines For Condenser Vacuum Raising Precondition
Code: Btpp/Turbine/007/Vacuum Raising Guidelines For Condenser Vacuum Raising Precondition
PRECONDITION:
PROCEDURE:
1. Open HT- AST to Turbine Seal Header atmospheric drain as well as motorized
drain (MAW10AA011) before seal steam admission valve. (MAW-10).
3. Crack Open AST to seals MOV (AS-9) and warm up AST to seals line.
4. Crack Open AST to ejectors isolation valve in HT/AST header and warm up
the AST to ejector line.
5. Ensure warm up of seal steam line (AST Temp near seal header>200o C)
6. Open AST to Ejectors and Gland Seal Root valves fully and Choke the
atmospheric drains. (After ensuring warming up of lines)
8. Start vacuum pulling by opening pilot ejector steam valve and then the air
valve. Ensure the proper closing of VB valve and charge its siphon.
Page 1 of 5
10.Start one Gland steam extractor fan. (Ensure their suction and discharge
gate valves are in open condition. Also ensure Gland Steam Condenser (GSC)
drain to Flash tank is through)
13.When condenser pressure is about 0.3 ata, Cut in the next ME and take out
the pilot ejector.
(While cutting out pilot ejector first close the air valve and then close the
Steam valve. Close the steam valve gradually without causing fast pressure
rise in the AST header.)
14.Ensure the condenser pressure is about 0.1 ata. and cut out one main
ejector.( Preferably, after Synchronizing)
15.The approximate duration to reach 0.1 ata after opening the starting ejector
steam valve is about one hour.
16.Confirm the reserve status of the non running Gland Steam Extractor Fan.
3. MS pressure below 20 Ksc and HRH pressure is about 1.0 ksc, with Re Heater
start up vents in open condition. HP BP opening should be minimum.
4. Close all drain to LP Flash Tank, HP Flash Tank, Turbine Flash Box-1 and
Turbine Flash Box-2(All MAL drains).
Page 2 of 5
5. Cut out Main ejectors from service by closing the air valve first and then the
steam valve.
6. When condenser pressure is about 0.5 ata, open the vacuum breaker.
7. When condenser pressure is about 0.9 ata, close seal steam valve MAW 10.
11.Close Steam valve to ejectors. Observe for any rise in condenser pressure.
12.Partially open the atmospheric drains of Steam to Ejector and Steam to seals
Page 3 of 5
9. Check the air flow in the ejector vents and if air flow is insufficient and water
is coming out of the vents, ensure the ejector drains are in open condition
and drain flow to Condenser is normal. If flow is insufficient, fill the siphons
(high level in ejector compartment #1) or open bypass of steam traps (high
level in ejector compartment #2).
10.Check the activity performed before vacuum drop and take necessary
corrective action.
11.Check gland sealing of the reserve CEP is proper.
12.Check gland sealing of all valves connected to the condenser.
13.Ensure LPBP is in closed condition.
14.If HP/LP Heaters are out of service, ensure closed condition of High Level
Drain Condensate.
320
260
20 200 300
Page 4 of 5
SCHEMES FOR STEAM TO EJECTOR & STEAM TO SEALS
Page 5 of 5