01 Phi Tacr 02
01 Phi Tacr 02
01 Phi Tacr 02
For the Ministry of Public Works and Transport, Lao PDR and
This consultant’s report does not necessarily reflect the views of ADB or the Governments concerned,
and ADB and the Governments cannot be held liable for its contents. All the views expressed herein may
not be incorporated into the proposed project’s design.
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE SECRETARY
PORT AREA, MANILA
FINAL REPORT
in
association
KATAHIRA & ENGINEERS with SCHEMA KONSULT, DCCD ENGINEERING
INTERNATIONAL INC. CORPORATION
Road Sector Institutional Development and Investment Program (RSIDIP):
Final Report
TABLE OF CONTENTS
Page
ABBREVIATIONS
ANNEXES
ABBREVIATIONS
SV Site Visit
TA Technical Assistance
TARAS Traffic Accident Reporting and Analysis System
TCT Transfer Certificate of Title
TD Tax Declaration
TNCs Term Network Contracts
TOR Terms of Reference
UP University of the Philippines
VOC Vehicle Operating Cost
WAN Wide Area Network
WB World Bank
1. INTRODUCTION
1.1 Background
1. The Government of the Philippines requested the Asian Development Bank
(ADB) during its 2007 Country Programming Mission for a Project Preparatory
Technical Assistance (PPTA) to provide funds for a Road Sector Improvement
Project (hereinafter referred to as RSIP). The PPTA was included in ADB’s
Country Operations Business Plan (2007-2008), and in ADB’s pipeline for non-
lending products and services for 2008.
2. The request was based on an outline concept paper for the RSIP, prepared
by the Department of Public Works and Highways (DPWH) in July 2007. The
concept paper envisaged a US$500M project, including a technical and financial
assistance package comprising preventive maintenance and/or rehabilitation of
selected national roads, as well as institutional capacity building components in
support of its mandate and development objectives.
3. The National Economic Development Authority (NEDA) favourably reviewed
the DPWH concept paper for the PPTA on 12 December 2007. ADB dispatched a
Mission which undertook the fact-finding activities on 10-14 March 2008.
4. The PPTA will have a total cost of US$800,000. The Government of the
Philippines requested ADB to provide US$660,000 equivalent counterpart
amount. In turn, ADB requested that the PPTA should be financed on a grant
basis by the Japan Special Fund, funded by the Government of Japan. The
Government of the Philippines financed the remaining US$140,000 by providing
the necessary office accommodation and services, remuneration, etc, mostly in
kind. The Philippine Government was advised that the approval of the PPTA
does not commit ADB to finance any ensuing project.
5. On 2 July 2008, ADB officially approved PPTA to the Government of the
Philippines. Katahira & Engineers International (KEI) was selected in 29 August
2008 for undertaking the PPTA Project. KEI is being assisted by the national
consulting firms SCHEMA Konsult and DCCD Engineering Corporation. The work
started last 29 September 2008 and scheduled to be completed in June 2009.
12. The contents of this Final Report can be divided in three main parts,
corresponding to the different areas to be covered by the PPTA:
Chapters 2-7: The framework and general preparations for the investments
in the maintenance project (conditions, planning, management, economy,
etc.).
Chapters 8-11: The proposed design and program of implementation of the
maintenance project, including its expected economic benefits.
Chapters 12-14: Possible environmental, social and other effects of the
maintenance project, as well as actions to be taken to prevent or
compensate for negative effects.
13. As mentioned in Paragraph 9 above, the above chapters in this report
concern the works towards Tranche 1, including the detailed design as well as
the economic evaluations and analysis of possible environmental or social
effects of project implementation. The framework for similar tasks regarding
Tranches 2 and 3, which may be undertaken by other consultants is compressed
in Chapter 15.
2. PROJECT DESIGN
for road roughness measurements. Their schedules were timed for the fastest
possible completions and deliveries with good enough results. After the
measurements were completed for each road, the results were sent the same
day by fax or phone connection to the Consultant’s office and used for the
detailed design. In turn, after the completion of the detailed design the total
construction cost for that road was calculated and provided for economic
evaluation. These four steps were overlapping for different roads and thereby
undertaken in parallel without any loss of time, like good factory processes.
7. It would nevertheless have been difficult for the Consultants to complete this
PPTA on time without the good help provided by DPWH, including most of its
different offices but perhaps in particular ADB-PMO and PMO-FS.
6. The fourth ADB road improvement project from March 1987 to (in practice)
January 1995 was prepared to include improvements or rehabilitation to 745 km
of National roads, mainly in Cebu, Negros and Mindanao. A pilot study to
improve the maintenance of national roads through the introduction of
maintenance by contract (MBC) was also included.
7. At the time of appraisal, the total time envisaged for the project was 5 years
and 3 months. This was subsequently extended four times, to a total of 5 years
and 10 months after the projected closing date. This long delay were due to
several causes, such as:
(1) The consulting services was started 14 months later than intended,
mainly due to a protest from one short listed firm, claiming that its
proposal had not been properly evaluated.
(2) Substantial time was spent in the tender and award process. The
average was 7 months between bid opening and notice to proceed, but
one contract took 18 months to process due to extended negotiations
and budget constraints.
(3) Several long construction delays, with time extensions up to 869 days.
Most construction delays were caused by: (i) termination of some
contracts and awarding of new contracts; (ii) changes of the scope of
work, such as the additional pavement strengthening and the
construction/repair of additional bridges found to be necessary; and
(iii) the generally slow work process of some of the contractors
(requiring replacements).
8. The long delays were accompanied by substantial cost overruns. The road
improvement works were initially divided into 12 contract packages with a total
value of PhP 1,437.5 million. Other contracts had to be added to replace slow
contractors, or due to changes in the project scopes, or as loans for extended
scope on some of the original contracts such as for additional pavement
strengthening, bridge works or drainage improvement. The total cost of the
project, thus, became about 40% more than originally intended.
9. During the progress of the project, the executing agency had problems in
obtaining the necessary disbursement of funds from Government. Some delays
could otherwise have been avoided. In turn, however, it should be recognized
that the period 1989-1991, when most of the construction activity took place,
coincided with the Gulf crisis. The inflation was high, the cost of construction
items such as cement increased by more than 20 percent per year, and there
were severe shortages. Some contractors were unable to get supplies.
10. The Fourth Road Improvement Project also had substantial benefits and is
classified in ADB’s Completion Report as partially successful. Apart from savings
in vehicle operating costs due to the road improvements, the public transport on
the project roads has increased and the economy in the surrounding areas has
improved significantly, particularly for the poorer income groups.
contract (MBC) approach. At the end of the pilot program, a goal was agreed
that 84% of the maintenance should be by Maintenance by Contract (MBC)
scheme. This has since been reduced to 50% by congressional mandate.
19. Like ADB’s Fourth Road Improvement Project, the Fifth Project could also
be shown to have substantial socio-economic benefits for the populated areas
around the improved roads. Through cost reductions for farm-to-market
transports, and improved access to markets for rural areas, the Project is
believed to have contributed to poverty reduction for approximately 980,000
people. The relatively high benefits due to this and some related benefits were
largely caused by significant increase in traffic volumes after the project
appraisal.
implementation. At the time of the Project Completion, the LAR activities were
still not yet complete, leaving some affected persons at a disadvantage.
25. The Validation Report for the Sixth Road Project lists the following “lessons”
for future ADB projects:
(i) LAR issues must be carefully evaluated, and ADB policies must be
clearly understood and included in the loan agreement.
(ii) For more efficient implementation, it is advisable to concentrate on a
specific geographic area, rather than pursue a scattered, large project.
(iii) Long delays between design and implementation often necessitates
major modifications of the design, causing further delays.
(iv) Project implementation arrangements would be more efficient if the
project management office was provided with enough authority to
undertake procurement, supplemental agreements, and variations.
(v) To avoid misuse of project vehicles, the possibility of renting or leasing
these vehicles should be studied as a means of ensuring proper use
and accountability.
(vi) Complete buy-in by the agencies concerned with institutional
development must precede commitments, to avoid waste of resources.
(vii) An overly optimistic implementation schedule at appraisal places an
additional burden on both the Executing Agency and ADB.
37. The program under PAHRDF includes a Human Resource and Leadership
Development plan, to support and empower staff skills and strengthen the
corporate culture.
4.1 Objectives
1. The basic objective of this analysis is to assess the financial management
system of DPWH with respect to the following:
(1) Existing accounting and auditing processes and procedures.
(2) Examine the implementation of document and fund flows.
(3) Tracking processes with due attention to integrity and completeness of
auditing.
(4) Effective implementation of foreign-assisted projects with Official
Development Assistance (ODA) financing.
use of the new National Government Internal Control System developed by COA
and DBM to be fully implemented by the second quarter of 2009. The Internal
Audit System manual, to be released during the first quarter of 2009, will be
used as a basis by the NRIMP-2 Specialist.
12. Financial Management (FM) has been identified as one of the key support
processes of NRIMP being implemented in DPWH. The component under this
program aims to provide: 1) assistance in strengthening the internal controls for
supporting documents associated with financial transactions at the Central
Office; 2) assistance in improving financial reporting; Parallel testing of the FM
Budget Module with subsequent adjustment of the software based on the COA’s
input; 3) installation and proper implementation of e-NGAS; 4) installation of
Modules and Outcomes Based Monitoring Framework; and 5) preparation of
bidding documents for communication network equipment maintenance.
management and internal control systems. The task will further support the
roll-out of the electronic version (e-NGAS). The Accounting module is fully
operational in the central office and pilot regional offices. DPWH implemented
the new Budget module in the last quarter of 2008 and will implement the seven
additional modules (listed in Paragraph 12 above) as they become available.
Outputs of this task will include roll-out of the different modules to regional
offices.
21. The Budget Module (“e-Budget”) was developed to maintain electronically
complete records of the Budget Execution Process. This has facilitated
improvement in processing and recording more accurate information and easy
access to budget information when needed. This RA will help ensure that DPWH
will have fully operational Accounting and Budget modules in the Central Office
and also in all 16 Regional Offices and District Engineering Offices through a
wide computer network. The e-Budget became fully operational in the Central
Office in 2008, and parallel testing of the system has been completed. Now it is
also being implemented in most Regional and District Offices of the Department.
Soon, all offices of the Department will have the benefit of e-Budget.
22. Reform Agenda on Internal Audit Capacity Building (IACB) aims to support
the Internal Audit Services of DPWH in upgrading internal audit procedures to
international standards and assisting in the conduct of semi-annual internal
audits across DPWH.
23. Reform Agenda on an Independent Procurement Evaluator (IPE) which is
presently being tendered, includes the procurement of a team with an individual
procurement specialist supported by local consultants who will undertake the
IPE role, working alongside the Project Management Office (PMO), Procurement
Bureaus and BAC’s.
24. Reform Agenda on an Independent Technical Audit (ITA) includes a firm
which would be tasked to undertake independent technical audits of project
activities periodically, at least annually, including audits of contracts as
implemented, cost control from estimation to completion, performance of firms,
quality and quantity of project outputs, achievement of project results, etc.
25. Reform Agenda on Organizational Effectiveness Advisors will conduct an
organizational analysis and develop restructuring plans in consultation with
senior DPWH management.
26. Reform Agenda on Road Partnership Support will include an advisor to
provide support and advice to the citizen group Road Watch, formed as an
alliance of transport-related NGOs to operate as an effective independent and
external monitor for the Road Sector in constructive communication with DPWH.
Grants will be provided for the operating costs of the organization.
27. The Philippine Public Expenditure Review (PER) on Transportation completed
in 2008 recommends that construction supervision be outsourced to relieve the
project supervision burden of DPWH in-house staff. Much of the construction
supervision, particularly for locally funded projects, should be considered for
outsourcing to private consultants. This step should be taken both for the
central and district offices. It will also require the development of management
capacity for planning, fund allocation, project execution, and financial
management alongside strong internal controls and result-evaluation
methodologies.
28. The same report also encourages the coordination between line agencies to
ensure efficient implementation of the huge infrastructure program from 2008
and forward. A formal memorandum of understanding between DPWH and DBM
indicates their performance obligations to be as follows: DPWH should commit to
allocate funds within its budget ceiling, undertake specific policy, institutional,
and process reforms to increase its absorptive capacity for more efficient use of
funds and provide for stronger accountability and governance (setting quarterly
performance targets, performance monitoring, financial management and audit,
support to Road Watch and the like). On the other hand, DBM will commit to
release allotments for the infrastructure program comprehensively upon the
General Appropriations Act (GAA) approval and issue comprehensive quarterly
cash allocations, from which DPWH can immediately disburse to support its
projects.
29. One recommendation stipulated that DPWH Financial Management and
associated information systems need to be tightened. Despite the significant
reforms initiated by DPWH under its RIMSS project, weaknesses remain in
financial management and information systems. The latest COA reports shows
cases of disallowances and other irregularities in significant, although
decreasing, numbers. In May 2007 DPWH issued an updated set of omnibus
delineation and delegation of authorities with an internal check-and-balance
provision. It also rolled out to the regions the accounting module of the new e-
NGAS prescribed by COA. DPWH and other line agencies should follow these
guidelines to improve the transparency and accountability of their budget
execution. Doing so would ensure that all implementing systems are
interconnected and can interface with the information and project monitoring
systems as well as ensure that physical accomplishments reflect the funds
disbursed.
30. Appropriate training for staff was mentioned as one of the pressing needs
of the Department. For IAS strengthening to be more effective, DPWH and
other implementing agencies should strengthen their IAS, with emphasis on risk
based and system audits in addition to the current compliance audits.
Immediate capability build-up and trainings are needed.
31. The procurement processes in DPWH and other line agencies should be
further shortened and streamlined by:
(i) fully implementing (to the district level) the new DPWH Procurement
Manual for locally-funded projects, recently approved by Government
Public Procurement Board, including timelines and standard bidding
documents (SBDs), however, the pending issue that this manual is
invalid for non-publication should first be resolved;
(ii) Installing and implementing the agency performance indicators (API)
for procurement developed and piloted for DPWH with World Bank
assistance in 2005;
(iii) Intensifying the training of procurement officials and staff;
(iv) Posting standard bidding documents on the website;
(v) Completing any right-of-way acquisition before bidding;
(vi) Computerizing eligibility screening and post-qualification of bidders, to
the district level; and
(vii) Applying stiff sanctions for breaches.
5.1 Objectives
1. The main objective of this analysis is to assess the status of road
maintenance financing as follows:
(1) Review the status of financing and maintenance of national road
network in the Philippines.
(2) Undertake critical analysis of medium term development plans and
investment programs, projections for investments and expenditures
required to maintain the national road network, as well as, other
pricing, cost-recovery policies and allocation policies that will sustain
the development of the national road network in the long run.
(3) Review the status of road sector policy dialogue and issues between
the Philippine Government and its development partners.
for Luzon roads that were neither screened nor prioritized by the master plan.
This compromised the relevance of the whole planning process.
8. Another issue is the non-optimal disbursement of funds due to various
constraints for the efficient implementation of infrastructure projects. In 2005,
DPWH was only able to disburse PhP25 billion of its PhP37 billion annual budget,
which is equivalent to 70% of its funds. This improved slightly in 2006 when 85
% were systematically disbursed. Efficient disbursement of budget becomes
necessary to ensure maximum impact of projects.
9. The financing of national roads comes from two main sources, namely: (i)
the government budget executed through the General Appropriations Act (GAA);
and (ii) the Special Road Support Fund (SRSF) sourced from the Motor Vehicle
User Charge (MVUC).
10. Republic Act No. 8794 (27 June 2000) mandates the imposition of motor
vehicle user charges (MVUC) for road maintenance, local roads development,
road safety and air pollution control. The user charges are collected by the Land
Transportation Office (LTO) from individual motor vehicles as one component of
its annual registration fee. The MVUC is subdivided into four special accounts by
a formula established under the law’s implementing rules and regulations (IRR).
11. Program allocations is administered by the Department of Finance and
managed by the newly established Road Board as provided under the same law
in accordance with the following pattern of distribution: 80% collected shall go
to the Special Road Support Fund (SRSF). Along with the Special Local Road
Fund and the Special Road Safety Fund, the SRSF shall be under the auspices of
DPWH; 5% for the Special Local Road Fund, administered by DPWH; 7.5% for
the Special Road Safety Fund, administered by DPWH; and 7.5% for the Special
Vehicle Pollution Control Fund, administered by DOTC.
12. Seventy (70) percent of the SRSF shall be utilized for the exclusive
maintenance of national primary roads, including the improvement of drainages.
The remaining 30% thereof shall be allocated and used for the maintenance of
national secondary roads throughout the country, also including drainage.
13. The Road Board administers revenues from road users to the Road Fund
and the allocation of funds to eligible programs. The Board allocates and
approves funds for road preservation programs, based on programs prepared
and submitted by DPWH. DPWH also conducts the procurement, financial
management and supervision for its projects.
14. While the SRSF was established in 2000 with funds from the MVUC now
regularly flowing through it, the releases have been controlled by Department of
Budget and Management (DBM) with no release until 2003. Subsequently, its
administration has been subjected to external pressures resulting in delays and
diversions in the release of funds. As a result, it has not been as effective as
expected in improving the road maintenance program.
15. Financing through the use of GAA or general government tax tends to fall
short of the required investment, especially for the maintenance of the road
network which prompted various road sector reforms in the Philippines.
Reforms were initiated in 1997 and further emphasized in the Better Roads
Philippines (BRP) Study in 1999.
16. BRP expressed the need for sustainable financing through road user cost
recovery and commercialization of road sector operations. It also proposed the
creation of a Road Management Authority wherein, at the institutional level, the
Road Fund and Road Board were established in 2001 and became fully
operational in 2004.
17. The Road Fund was dedicated for the establishment of new roads and for
catch up maintenance programs so as to bring the road levels within the country
back to acceptable levels.
18. The total revenue generated for road financing did not experience a net
increase during the period 2002 to 2004. This was due to the fact that while
annual financing from SRSF increased, the allotted resources under the GAA
were almost halved, resulting in no net increase in the total financial resources
for the road sector.
19. There was a considerable increase in budgetary allocation to the sector
between 2004 and 2006, however. This was mainly due to the rising revenues
from road users taken from the SRSF and projected to further increase in the
next five years. However, the 2006 figures comprised only about one third of
the estimated needs in that year, indicating the need for higher cost recovery.
Figure 5.2-1 reflects the trend of source of financing for the national roads
sector from 2001 to 2006.
45
40
35
30
25
20
15
10
5
0
2001 2002 2003 2004 2005 2006
20. With the recent resurgence in the economy, the capital budget and SRSF
for 2007 rose to PhP69 billion (1.8% of GDP) which is believed to be able to
restore the sector if the budget is well prioritized, spent efficiently and
sustained.
21. To ensure effective maintenance of roads and bridges, there is a need to
address the fragmented budget allocations, ensure need-based budget,
allocation of administrative costs compared to the overall budget, and risk
exposure when used for employment-generation programs. Table 5.2.2
tabulates the forecasted annual national road funding and its appropriation until
2012.
Table 5.2.2: Annual expected funding for national roads (in millions of pesos)
80
70
60 Percentage of National
50 Roads in Good and Fair
condition
40
Percentage of National
30 Roads paved
20
10 Percentage of Total Roads
paved
0
1982 2001 2006
Figure 5.3-1: Comparison of National Road Condition
Source: World Bank Infrastructure Database and DPWH, 2006
23. Road users primarily shoulder the economic costs of poorly maintained
roads. Increased funding for the preventive maintenance of roads would
translate into higher savings in vehicle operating costs (VOCs) to road users,
rather than allowing road deterioration to a point that requires reconstruction.
DPWH studies have shown that the economic benefit of improving bad and poor
roads to good condition as well as reconstructing paved roads would translate
into 15% to 53% savings in VOCs. Moreover, according to the World Bank’s
Public Expenditure Review of Transport Infrastructure, when a road is allowed to
deteriorate from good to poor condition, each dollar saved on road maintenance
increases VOCs by US$2 to US$3. From a long term viewpoint, savings coming
from VOC will benefit the entire economy through reduced costs of transporting
people and goods, thereby inducing greater production. Thus, to achieve cost-
effectiveness, it becomes imperative that resources be appropriated in a timely
manner to fund road maintenance and induce a sustainable road sector policy as
well.
24. The operations and maintenance of national roads and bridges, major flood
control structures, and related facilities of national importance is the
responsibility of the DWPH. The Regional and District offices undertake the
maintenance of the facilities generally by administration.
25. The present maintenance setup within the DPWH includes routine
maintenance and preventive maintenance. Routine maintenance consists of
carriageway maintenance and roadside maintenance, which basically involves
localized repair of pavement and shoulder defects, regular maintenance of road
drainage, side slopes, verges and furniture, which are done mainly by
administration. Preventive maintenance entails asphalt overlay, usually with
thickness of 50-100 mm. It also includes selective reblocking or replacement of
damaged slabs not exceeding four continuous blocks. These works are usually
done by bidding them out as contracts.
26. The allocation of funds for routine maintenance among the district level is
made on the basis of the Equivalent Maintenance Kilometre (EMK) formula. The
formula allocates funds based on the length of the road adjusted to consider its
width, surface type and traffic volume. Allocation of funds for preventive
maintenance is based on the results of HDM-4 output with parallel consultations
from District Offices. The Bureau of Maintenance (BOM) forwards the list of
projects to the Planning Service for funding by DBM. Several iterations are
usually done to come up with the final list due to funding constraints. On the
other hand, works for routine maintenance is funded through the GAA while
preventive maintenance is funded by both the GAA and the MVUC or SRSF.
27. According to a DPWH-World Bank study, the order of PhP4–6 billion raised
from the MVUC was utilized to cover road maintenance. Table 5.3.2 tabulates
the amount raised for routine and preventive maintenance between 2002 and
2006. However, this only funds 21 to 32% of the maintenance needs. In 2005,
a total amount of PhP2,099 Million from MVUC funds was allocated for
preventive maintenance. In 2006, this increased to PhP2,500 million. In
addition, under NRIMP-1 the DPWH implemented a preventive maintenance
program which covered 730 km from 2000 to 2006.
28. The thrust towards asset preservation is a sound and cost-effective policy
because of the very high economic returns from relatively inexpensive but
sustained maintenance on the existing roads. DPWH studies have shown that
preventive maintenance is more cost-effective and durable than routine
maintenance. However, funds for maintenance are disproportionately allocated
with roadside maintenance being allocated 25% in 2003, 33% in 2004, 35% in
2005 and 65% in 2006. These values are much higher than the required 10%
to 15% that should have been appropriated to roadside maintenance. On the
other hand, preventive maintenance received PhP 2.1 Billion in 2006 which only
covers 12.35% of the total length required for preventive maintenance. Also,
carriageway maintenance is appropriated a lower budget which only covers two-
thirds of the network.
29. Under-investment in the road preservation program is due to funding
constraints. Based on the assessment, only 30% of the total funding
requirement is actually supplied. Existing problems result from the lack of
proper procedures and transparency in the allocation and flow of funds. Thus,
the objective of maximizing allocated funds to serve its intended purpose is not
achieved.
30. The result of the consultation revealed that the control environment, in
some cases, instigates corruption. There are cases when labour allocation for
routine maintenance is released ahead of the budget for materials causing
problems in implementation, funded projects are not included in the list
submitted and approved by DBM, collusion between the officials of the district or
regional and the central office, misinformed reporting, overestimating
maintenance work requirements or understating road conditions, among others.
31. DPWH, compared to its related Agencies in other countries, has low
productivity when it comes to road administration. There are about 35,000
DPWH employees with 60% deployed to manage the national road network.
This translates to a ratio of one employee to cover 1.3 kilometres of national
roads. In comparison, Indonesia employs 2,726 employees translating to one
employee per 10 kilometres of national road. This is being tackled under
Philippines’ recent rationalization program which also aims to increase the
productivity of road administration.
32. Another issue is truck overloading which significantly contributes to the
premature wear and tear as well as extensive damage to roads and bridges.
Consequently, this affects the life cycle and maintenance needs of the road
network and also significantly increases vehicle operating costs. The 2004
JICA-DPWH axle load survey determined that 23.4% of loaded trucks exceeded
the prescribed Gross Vehicle Weight (GVW) limits while 15% of loaded trucks
exceeded the maximum permissible axle load of 13.5 tons. The 2006 Truck
Overloading Report cited that there is rampant truck overloading in the country.
It was then recommended in the report to strictly enforce 13.5 ton axle load
limit. By doing so, this would translate into a gain of PhP160 Million over 15
years for heavily travelled roads in good and fair condition. Other
recommendations included: strengthening measures to control overloading,
strictly apprehending violators, and reducing the maximum allowable GVW limits
so as to reduce the wear and tear on the roads without significantly increasing
road user costs.
33. DPWH has signified its intent to provide increasing priority in funding
towards preventive maintenance, rather than routine maintenance. There was
a 76% increase in road maintenance during 2007. From an amount of PhP 6.6
Billion solely from MVUC, it increased to PhP 11.6 Billion, including a PhP 4
Billion supplement from GAA funds. But the amount still falls short of the
required funding, covering only 60% of the resources needed.
39. The President of the Philippines organized the Road Board which is tasked
to implement the prudent and efficient management and utilization of the
special funds. The Board is composed of seven (7) members, with the
Secretary of the DPWH as ex-officio head, and the secretaries of the
Departments of Finance (DOF), Budget and Management (DBM), and
Transportation and Communications (DOTC), as ex-officio members. The
remaining three (3) members shall come from private transport and motorist
organizations, which have been in existence and active for the last five years
prior to this Act.
40. The MVUC Law has been passed creating the SRSF from vehicle registration
fees to be used for road maintenance. The Road Fund was to ensure continued
fund availability for maintenance works. However, this has been weakened by
its haphazard implementation. Although revenue collection has been reasonably
satisfactory, confidence in the Road Board has weakened due mainly to the
presence of political influence. Technical advice on the Road Board as well as
increased transparency initially improved the operations of the Board.
41. Thus, under NRIMP-2, one of its components shall address strategic sector
reform to strengthen the operations and mandate of the Road Board, to include
the review of road cost recovery and MVUCC-IRR, the expansion of road user
revenues as well as determine options for restructuring the management and
delivery of services in the road transport sector.
42. There is a need to institutionalize the planning and programming systems
and tools which were developed and tested under the World Bank and Asian
Development Bank-assisted Road Information Management Support System
(RIMSS), to help in rationalizing selection, priority setting, scheduling, and fund
allocation for road maintenance and construction projects, using objective
technical and economic criteria. These tools include: HDM-4 for preventive
maintenance and rehabilitation of national roads funded under the GAA and
MVUC; Routine Maintenance Management System (RMMS), to be operational by
the end of 2008, to serve as basis for routine maintenance; and Multi-Year
Programming and Scheduling (MYPS) System and MCA, to validate 2007 road
construction projects and generate priority multi-year road projects for funding
and implementation, beginning in 2008.
43. There is also a need to properly manage the rising funding for road and
bridge maintenance, so as to be more effectively programmed and efficient.
Fragmented to districts, budget allocations are not needs-based and are blunted
by administration costs. These allocations also support job creation programs.
Moreover, operational performance has been mixed, but maintenance programs
has improved with all major civil works having been outsourced to the private
sector for years. A number of contract performance problems have, thus, been
overcome, especially in avoiding disputes, and in prompt and policy-compliant
land acquisition. But some operational difficulties persist in cost over-runs, slow
contract administration, and weak quality and supervision.
44. A policy of cost recovery for operations and management is required
especially to ensure sustainability of infrastructure funding. Alternative financial
arrangement scheme includes mobilizing and increasing private participation in
the sector through build-operate-transfer (BOT) arrangement which would fall
under public-private partnerships (PPP).
45. The national government has turned its attention towards increasing private
sector financing in the delivery of infrastructure services in the country. To
support its growth agenda, and given the knowledge that it could not shoulder
the financial requirement through public funds alone, the government has
tapped private sector resources to complement infrastructure requirements. To
ease their entry and regulate the rights and obligations of operators, the
government introduced the BOT Law in 1994 which is considered a first in the
region. DPWH also echoes the desire to increase private sector participation.
46. Some PPP schemes that have already been utilized in the country include:
Design-build-finance-operate schemes, Concessions with user charges based on
cost recovery, and BOT schemes. The latter includes initial investment from
the private sector, which is then entitled to initially own and operate the asset
for a fixed period until it is transferred to the government.
47. PEGR implemented its Reform Agenda on strengthening the PPP program in
the National road sector through capacity building of both DPWH and NEDA.
There is an ongoing assessment of the impact of E.O. 686, i.e., transferring
back the Toll Regulatory Board (TRB) from DPWH to DOTC and clarifying its
mandate.
48. DPWH has also piloted Long-Term Performance Based Maintenance by
Contracts (LTPBMC). Previously, maintenance fund allocation using the EMK
formula did not capture needs and road conditions. As alternative to LTPBMC,
DPWH is now planning to test several contract options of international best
practices to adopt contractual arrangements for road maintenance. Such
options included: Contracts for Rehabilitation and Maintenance (CREMA),
highway asset management, Term Network Contracts (TNCs), road
management concession, and road micro-enterprise. The following details the
options:
(1) CREMA involves performance based maintenance contracts under
which all works, including some rehabilitation, is provided under a
lump sum, fixed price contract. Normal duration was five years.
Benefits were rapid improvements in road conditions, state of the art
techniques, equipment, materials and management, and reduced
maintenance costs.
(2) TNCs involve long-term performance-based maintenance contracts for
very extensive networks of 300–4,200 km. Benefits were innovations
in methods and management, lower maintenance costs, more stable
budget projections, and fewer contracts for road authorities to
manage.
(3) CREMA and TNCs improve on LTPBMCs as they use network
efficiencies, cover longer periods, transfer more of the risks to the
contractors, and require more innovations in management, materials,
equipment, and techniques.
49. The BRP study suggests the use of the Users-pay principle to rationalize
road infrastructure financing. BRP estimated that the cost of maintaining the
national road network is PhP13.4 billion a year, which is equivalent to about PhP
19 Billion in 2007 figures. To assist financing, BRP is proposing road user
charges through vehicle registration charges and fuel levy. Vehicle registration
charges should be based on the equivalent cost of damage caused by the
vehicle on the road while fuel levy would involve a three-phased increase to
PhP1 per liter. Insofar as toll roads are concerned, data from DPWH and TRB
show that existing user tolls are able to recover not only operation and
maintenance (O&M) costs but capital costs as well.
6.1 Background
1. DPWH is mandated to undertake the planning, design, construction, and
maintenance of infrastructure (i.e. roads and bridges, flood control, water
resources projects and other public works). DPWH processes are typically
information intensive (i.e. traffic data, contract data, costs, personnel and
management data) as well as labor intensive (i.e. collect, organize, store and
distribute accumulated information). Moreover, it also aims to address various
issues that arise specifically in project implementation, the need for
transparency in operations and management, and the use of information
technology, accountability and organizational culture.
2. ADB’s 2003 Country Assistance Program Evaluation for the Philippines found
that the core problem of the road sector was the weakness of DPWH specifically
on the maintenance and development of the national road network. Further
emphasis was placed on the need to conduct adequate preparatory studies, site
investigations, and engineering designs prior to project approval, as well as to
address institutional weaknesses of the executing agency.
3. The need for institutional strengthening through the development of a
Methodology and Framework for National Transport Planning was identified
under World Bank’s National Road Improvement and Management Program
(NRIMP). NRIMP is one of the first programs that concretely addressed
Institutional Capacity Building (ICB).
4. The Rationalization Plan, as mandated by Executive Order (EO) No. 366 dated
04 October 2004, aims to transform the Executive Branch into a more effective
and efficient government. It allows the government to eliminate redundancies
in its operations, utilize present resources, improve its systems and procedures
and use its savings to fund the Department’s priority programs and projects.
However, this has brought about mismatched priorities as well as aggravated
the lack of capacity of DPWH to implement its programs.
5. DPWH objectives include emphasis on customer needs (both internal and
external), focus on reengineering of all significant processes, identification and
prioritization of opportunities for improvement in cost, efficiency, effectiveness,
and controls and the use of technology as an enabler. The Department is
acknowledged to have one of the most modern communication networks within
the entire government bureaucracy. However, a number of issues have arisen
during the implementation of complex Information and Communications
Technology (ICT) systems and process wherein the institution seemed to be
taking in too much of what it is capable of handling.
6. Information and Communications Technologies (ICTs) have become an
integral component of capacity building at all levels. Thus, to enable various
reform agenda in the Department, it utilized and enhanced its information
systems and technology infrastructure so as to realize its objective of creating a
more open customer-driven culture and to create a coherent yet diverse
organization.
6.2 Objectives
7. The objective of this analysis is to evaluate and assess the status of DPWH
ICB efforts through:
a. Review of past, ongoing and planned efforts by other development
partners such as the World Bank (WB), Australian Agency for
International Development (AusAID), Japan Bank for International
Cooperation (JBIC), Japan International Cooperation Agency (JICA), and
others.
b. Identify and evaluate past and current ICB efforts being carried out by
the DPWH such as the Business Improvement and Implementation
Projects (BIIPS) under the Road Improvement and Management Support
System (RIMSS) and others.
c. Identify policy and institutional deficiencies and constraints in the ICB
efforts for road sector development, planning and management.
d. Assess various resources and skills of DPWH personnel, identify
management priorities, thrusts and directions for outsourcing and
privatization by DPWH.
e. Assess the potential of implementing various available ICB concept
papers and project proposals submitted by various Offices concerned
within DPWH
8. Through the above analysis, the Consultant aims to identify and recommend
ICB measures that would effectively strengthen the institution’s provision of
services in the road transport sector as well as augment and/or supplement
other BIIP and RIMMS activities, such as:
a. Identify and recommend ICB components and their relative priorities,
component requirements and the corresponding organizational
development.
b. Recommend optimum and realistic implementation phasing of proposed
ICB activities to be included in Tranches 1, 2 and 3.
c. Prepare necessary concept papers, application request and other related
documents.
6.3 Methodology
9. A comprehensive survey and review of documents prepared by various donor
agencies such as the World Bank (WB), Asian Development Bank (ADB),
JBIC/JICA, AUSAID as well as other development partners and related
institutions was conducted to determine planned, existing, completed and closed
projects for DPWH through website search, informant interview and library
visits. Moreover, key informant interview was undertaken which involved
representatives from various Department bureaus, donor agencies and through
public consultations with stakeholders.
10. After the initial data were collected, synthesized and analyzed, prioritization
of ICBs would be undertaken. This will be done through the utilization of a
decision making tool, the Analytic Hierarchy Process survey, which can combine
both qualitative and quantitative data. The said questionnaire would be
26. Under the PAHRDF, the program includes a Human resource and Leadership
Development wherein its first phase will culminate in early 2009 and its second
phase, under NRIMP-2, will start in the first quarter of 2009. The package
includes the development of a comprehensive HR and leadership Development
Plan to be formulated and developed to support and empower staff skills
development as well as to enable staff to align with the changing needs and
directions of an effective corporate culture. A key goal is to develop leadership
skills and potential among younger and mid-level professional staff in order to
attract and retain high calibre professionals. A second goal will be to streamline
and modernize recruitment, incentive and professional mobility to processes
across DPWH, including merit-based performance management corporate
standards and an internal communication strategy, in an interactive manner,
including through assistance, coaching and mentoring.
27. NRIMP-2 resulted in a stricter, more comprehensive set of anti-corruption
measures included in the project. To minimize all possibilities of unnecessary
human intervention, World Bank required the adoption of new sanctions
guidelines on fraud and corruption so as to combat a much wider scope of
activities linked to fraud, collusion and obstruction of investigations. This was
triggered by circumstances in 2003 when the Bank’s supervision identified signs
of bid-rigging in the procurement of two road contracts under NRIMP-1 and in
two further rounds of bidding in 2004 and 2006, and rejected award of the
contracts.
28. An investigation of the Department of Institutional Integrity (INT)
concluded in 2007 revealed that a cartel of contractors engaged in corrupt and
collusive practices in all three rounds of bidding. These findings were disclosed
to the Government of the Philippines in November 2007 for possible follow-up
under Philippine law. The investigative findings served as crucial factors in the
design of mitigating measures for NRIMP-2. Furthermore, INT initiated the
Bank's internal process to determine whether the practices detected in the
investigation merit the application of Bank Group sanctions.
29. NRIMP’s evaluation emphasized the need for transparency and
accountability in government transactions which prompted the creation of the
Procurement Transparency Group (PTG). The group was formed to evaluate,
comment on, record and monitor procurement activities of all government
agencies and offices. Its membership includes government agency
representatives from the Presidential Anti-Graft Commission, NEDA, Department
of Justice (DOJ), Department of Budget and Management (DBM) and the
Department of Interior and Local Government (DILG).
30. This encouraged strengthening the involvement of civil society through the
institutionalization of BL or Road Watch, an independent oversight and anti-
corruption group which is mandated to oversee road projects as well as to serve
as platform for citizen’s voices to be heard. Its tasks include: checking DPWH
fund spending, ensuring that value for money is being achieved, and reporting
on the actual results of improvement in road conditions with the end goal of
minimizing, if not eliminating, corruption and waste in the Department.
31. The ICB component under the REAPMP which is funded by JBIC is designed
to complement components of NRIMP-1 and 2 which have been initiated but not
fully implemented under NRIMP-1. REAPMP focused on three result areas,
institutions. The systems put in place under NRIMP-1 is said to facilitate DPWH
processes. However, various systems failures and problems have been noted,
specifically in the maintenance contracts, supply contracts, system
sustainability, systems obsolescence, hardware and system maintenance,
technical errors and system compatibility, among others. The costs incurred to
purchase original software and hardware is relatively high and its productivity
per cost is not justifiable given the system issues that arose thereafter. Also,
issues related to quality, reliability, usability of the data are questionable due to
the lack of performance benchmarks.
36. Moreover, there is lack of continuity within the system given the absence
of a maintenance agreement. The Monitoring and Information Service (MIS) is
trying to fill in this gap at present. However, system problems still exist such as
very slow system and unreliable networks and capability of hardware could not
accommodate the increase in applications. Improving the bandwidth is one of
the initial solutions to improve the system. The completion report for RIMSS
expounded on the difficulty to integrate and coordinate the large number of
contract packages implemented within RIMSS, prompting the hiring of services
of a coordinating consultant. This also contributed to further delay in data
gathering and retrieval.
37. The lack of performance benchmarks was also mentioned during the
strategic planning session which would help assess the performance of the
systems which was initially secured at great costs. It was hoped that the new
ICB component would not fall within a similar dilemma.
38. The RIMSS Completion report also discussed that, compared to other
components, there was low priority granted towards Human Resource
Management (HRM) and Organizational Strengthening programs in the
Department. Thus, it was once again reiterated that to ensure productivity
within the DPWH, human resources development, along with man-made capital
and natural resources, are essential and should be given due importance.
39. An examination of DPWH manpower personnel shows that the average age
of existing employees is 53 years old, almost of retirement age, and majority
had been in service for the past 16 to 30 years. Although a number of
individuals are quite receptive to change, the majority within this age group
would less likely be willing to adapt to the introduction of new processes and
would show resistance to the implementation of new systems.
40. In addition, Table 6.4.2.1 illustrates a high percentage of casual and
contractual personnel at various levels of DPWH which was further exacerbated
by the implementation of the Austerity Measure and the Rationalization Plan in
the Department. Moreover, these individuals are also not entitled to
government benefits and have temporary and irregular status. Issues that need
to be addressed are: frequent turnover of staff especially at the district level,
the lack of accountability and job ownership, mismatch between the function
and training provided, lower than required education level, seemingly low level
of productivity and work performance, among others.
the key result areas and planning parameters as well as to come up with
performance objectives per strategic priority.
46. The whole program included corporate planning, strategic planning and
operations planning. While the exercise involved upper and middle
management in the first phase, initiated in July 2008 and is about to be
completed by 08 December 2008, the second phase, tentatively set to be
implemented in 2009, is aimed to replicate the program but at the regional level
and a selected number of staff from the district level.
47. The results included performance objectives, Operations Plan of each
Bureau and to ensure the sustainability of the plans and projects, it was
determined that there was a need for the institutionalization of the strategic
planning process and operations planning process. Also, through a Special
Order, the Strategic Planning Committee (SPC) was formed headed by the
Assistant Secretary for Planning. Membership includes: selected service
directors, assistant bureau directors, selected division chiefs.
48. Post Evaluation Exercise will be conducted by PAHRDF every six months
after the culmination of the program to assess the outcome of the exercise.
Likewise, the SPC also signified their intent to undertake post-evaluation
activities.
49. The aims of the sub-component on organizational effectiveness are to
increase effectiveness as well as improve performance and management of
DPWH staff. The initial focus will be a corporate audit of the DPWH which will be
used as the basis for developing a corporate plan and a business plan. The
former will include the design and implementation of a new organization
structure and staffing plan to update the Rationalization Plan. This will also
include the structuring, financing and monitoring of an incentives program to
encourage excellence in performance.
50. Corporate modernization scheme is also underway which aims to conduct
strategic reassessment and organizational assessment of the mission and
mandate of the DPWH including the 2006 Rationalization Plan so as to evaluate
the need for an alternative corporate structure. The program aims to address
issues related to the organization, staffing, processing time for various bureau
and office functions. Through internal consultation, strategic reassessment
exercises and recommendations, the task will produce plans for an enhanced
organizational structure, streamlined management, and a comprehensive
human resource and leadership development plan. After the approval from
DBM and adoption by DPWH, the plan would be implemented as a second stage
under the mandate of the Rationalization Plan for DPWH. The last item,
integrity development aims to support the implementation of the Integrity
Strengthening Action Plan of DPWH.
51. ICB Efforts concurrently require a human resource development component
in the form of trainings. The Department has strengthened IT literacy of its
personnel through various ICT trainings and the conduct of refresher courses.
However, funding for training are limited given that the bulk of DPWH budget
goes to civil works and maintenance. This has further been curtailed by the
Rationalization Plan in 2006 which required that the annual training calendar
identified by the BRS requires approval from the national government before its
implementation. Due to approval delay, the 2008 training courses have not
been implemented since the start of the fiscal year. Other issues identified
were: lack of equipment and facilities, lack of experts, low remuneration for
speakers, high turnover of personnel being trained, mismatch between trainees
and actual scope of work, training multiplier effect is highly dependent on the
attitude of supervisors, lack of an evaluating and reviewing body, as well as
regularity in post-evaluation of trainings and workshops. The process of
identification of training needs, provision of trainings and utilization of
knowledge gained should be re-evaluated to rightfully reflect the DPWH’s thrust
and ensure wider impact.
52. As the importance of ICB entered the mainstream of development models
over recent years, there is a constant search for successful capacity building
templates which can be replicated over multiple locations. A recurring
frustration for international donors in their pursuit of effective aid spending has
been the lack of capacity of government to deliver the intended programs. It
was identified that the concept of ICB provision is rather vague within the DPWH
and the initial perception of ICB approaches are limited to training, consulting
services and equipment provision. Thus, there is a need to widen the
understanding and ensure a more open understanding of the concept. Training
is also necessary but to ensure adequate use of funds for trainings would bring
about huge impact on the organization, there is a need to re-evaluate the whole
process of identification and provision as well as post-evaluation of training
needs. Training courses should therefore be updated regularly.
53. A previous exercise administered by Southeast Asia Interdisciplinary
Development Institute (SAIDI) in 2005 identified the DPWH five (5) core values
which need to be strengthened. These are public service, integrity,
professionalism, excellence and team work. Further activities should bring forth
and concretize these core values.
54. The process of change management and business process reengineering
are difficult processes which pose the danger of misunderstanding and lack of
acceptance which dictates more substantial efforts in awareness building and
consensus. The implementation of new methods and technology should be
implemented within an overall framework of its relevance and potential
replicability to other areas as well as ensuring that the capacity of users are at
par with the system’s requirements. It involves assessing how the talents and
energies of staff can be enlisted and upgraded on a regular basis to improve
these institutions' operations.
55. The Consolidated Review Report on Relevant Transport Sector Work
completed for PEGR indicated that DPWH personnel in general have high
technical planning capabilities and skills which contrast with the local
government units directly dealing with the road network. A gap arises between
the technical-know-how of central personnel and staff at the regional/district
offices.
56. The value of skills improvement and technical capabilities, especially in the
short term, is undoubtedly important for capacity development, thus, should be
encouraged. However, its sustenance as well as the proper matching of
required trainings and actual personnel function are still recurrent issues.
Moreover, utilization and retention of already available capacities can only be
65. The previous sections present a review of past and current ICB initiatives in
the DPWH. Gaps and constraints have been identified and pointed to potential
areas of ICB that would put in place sound and adequate systems for the DPWH
to perform effectively its core functions.
66. ICB interventions that have been identified are basically based on the
following criteria.
(1) Those that continue existing activities.
(2) Those that will institutionalize established systems.
(3) Those that will ensure the successful implementation of established
systems and processes.
(4) New initiatives to address fully the ICB needs of the DPWH Strategic Plan.
67. The consultant worked closely with the Project Technical Working Group and
the ICB Component Group of NRIMP-2 in preparing an ICB package for this
project. The resulting package is described below, with project profiles shown in
Annex 1.
performance of the DPWH versus the target Medium Term Public Investment
Program (MTPIP).
70. The project is targeted for completion within two (2) years and has an
estimated cost of PhP 95.7 Million.
101. The total estimated cost of the project is PHP 48 Million spread over three
(3) years.
7.1 Introduction
7. Purpose and Objectives of the Philippine Road Sector Policy Road Map
(PRSPRM) is to give a general overview of potential policy directions from
issues, trends, and developments in the current state of the Philippine road
sector development. It will give insights into the prevailing investment priorities
of the Government of the Philippines (GoP) and the Asian Development Bank
(ADB), trends and issues being faced, and identify areas where investments can
be looked into, financial windows of assistance and opportunities for further
growth and cooperation explored in greater detail. It can also be an aid in
identifying potential areas where the allocation of technical assistance resources
for the preparation of new investment projects, grant funding, more in-depth
policy review, researches and pilot projects can be made. The PRPSPRM can also
strengthen and harmonize activities and the linkages among the various
stakeholders in the sector.
8. The PRSPRM has 9 sections: (1) Key issues in the sector: (2) Government’s
Sector Policy and Planning Framework, (3) Government’s institutional
arrangements and capacity in the sector, (4) ADB sector experience, (5) role of
other development partners in the sector, (6) Intended sector outcomes and key
outputs supported by the ADB, (7) Links to CPS Outcomes and other sector
themes, (8) Indicative areas for interventions, and (9) Monitoring mechanisms.
10. The Philippines has a total road network of 205,497 km as of 2007 broken
down as follows:
Table 7.3.1: PHILIPPINE HIGHWAY NETWORK
As of December 2007
Classification Length % Paved % Unpaved
National 29,369 km 70 30
Arterial 15,559 km 79 21
Secondary 13,810 km 60 40
Provincial 31,284 km 25 75
City* 7,052 km 77 23
Municipal* 15,803 km 34 66
Barangay* 121,989 km 7 93
TOTAL 205,497 km 23 77
*Note: As of 2002
Source: DPWH
12. While the average road density for the Philippine national roads appear
high at 0.67 km of road per square km of total land area (Table 7.3.2), many
areas have road densities much lower than the Philippine average. These
regions with low road densities and/or paved road ratios generally are also the
less economically developed regions or regions that have markedly undeveloped
provinces (Table 7.3.3). Overall paved ratio is low at a level of 0.23 which is
attributable to the large inventory of barangay or farm-to-market/village roads.
Source: DPWH
Table 7.3.3: Surface Type and Paved Ratio by Region (National Road),
As of 2007
NATIONAL ROADS
TOTAL
REGION CONCRETE ASPHALT GRAVEL EARTH
LENGTH
km % km % km % km %
CAR 554 30 105 5.7 1174 63.6 13 1 1,846
NCR 713 69 318 31 0 0 0 0 1,032
REGION I 881 55 568 35 139 9 21 1 1,610
REGION II 908 51 319 18 537 30 1 0 1,765
REGION III 987 49 785 39 260 13 0 0 2,032
REGION IV-A 948 39 1115 46 341 14 0 0 2,404
REGION IV-B 685 31 323 15 1176 54 1 0 2,185
REGION V 905 41 682 31 610 28 0 0 2,197
REGION VI 1,217 42 960 33 700 24 4 0 2,880
REGION VII 892 44 853 42 272 13 19 1 2,037
REGION VIII 1,637 69 292 12 427 18 16 1 2,373
REGION IX 544 45 292 24 382 31 0 0 1,218
REGION X 729 43 440 26 513 30 0 0 1,682
REGION XI 662 46 247 17 537 37 0 0 1,447
REGION XII 558 43 256 20 490 38 0 0 1,304
REGION XIII 558 41 72 5 729 54 0 0 1,358
PHILIPPINES 13,378 738 7,629 400 8,287 457 76 4 29,370
Source: DPWH
13. Table 7.3.4 presents the trend in growth of road length by road
classification. In general, from 1982 to 2007, the length of national roads had
been growing at an average of 0.63% per annum, provincial roads at 0.77% per
annum, city roads at 3.52% per annum, municipal roads at 1.62% per annum,
and barangay roads at 1.62% per annum. Overall, road length had grown at an
average rate of 1.25% per annum. Caution though on the quality of available
data as periodic adjustments and reclassification of data were noted.
Table 7.3.4
Growth of Roads In the Philippines (In km)
CY 1982-2007
NATIONAL PROVINCIAL CITY MUNICIPAL BARANGAY
YEAR TOTAL
ROAD * ROAD ROAD ROAD ROAD
1982 23,783 29,544 3,741 12,142 85,264 154,474
1983 24,137 29,725 3,718 12,240 85,847 155,667
1984 25,098 28,849 3,897 12,432 86,868 157,144
1985 26,259 28,425 3,987 12,825 90,214 161,710
1986 26,238 28,335 3,987 12,896 90,880 162,336
1987 26,082 28,964 3,955 12,875 85,940 157,816
1988 26,070 29,173 3,982 12,626 85,595 157,446
1989 26,095 29,144 3,949 12,707 87,149 159,044
1990 26,272 29,156 3,949 12,819 88,363 160,559
1991 26,422 29,156 3,949 12,819 88,363 160,709
1992 26,554 29,156 3,949 12,819 88,364 160,842
1993 26,594 29,156 3,949 12,819 88,364 160,882
1994 26,154 29,156 3,949 12,819 88,364 160,442
1995 26,720 29,117 3,949 12,819 88,364 160,969
1996 27,369 28,762 3,949 12,819 88,364 161,263
1997 27,650 28,530 3,949 12,819 88,364 161,312
1998 27,895 28,503 5,767 15,816 121,702 199,683
1999 29,247 27,224 5,767 15,816 121,702 199,756
2000 29,734 27,136 7,052 15,804 121,989 201,715
2001 29,878 27,076 7,052 15,804 121,989 201,799
2002 30,030 26,926 7,052 15,804 121,989 201,801
2003 28,649 26,926 7,052 15,804 121,989 200,420
2004 30,030 26,926 7,052 15,804 121,989 201,801
2005 28,952 26,926 7,052 15,804 121,989 200,723
2006 29,098 26,926 7,052 15,804 121,989 200,869
2007 29,370 31,285 7,052 15,804 121,989 205,500
* - Includes 120 km Expressways in Luzon (South Luzon - 42 km; North Luzon - 78 km)
operated by the Philippine National Construction Corporation (PNCC)
Note: The decrease of the length of road from 1985 to 1986 was due to the correction of
some national and barangay road sections nationwide with overlapping station and
double listed road section and non-inclusion of the physical length in lineal meters of
bridges; No updated provincial, municipal and barangay (farm to market and/or
village road) data for 2003-2006 and only 2007 provincial road data was updated.
Source: DPWH
14. As of 2007 the Philippines has a total of 7,743 national bridges with an
aggregate length of 314,453 l.m., of which 6,324 or 81.67% are concrete
(257,836 l.m.), 56 or 7.23% are steel (40.57 l.m.), 667 or 8.61% are bailey
(13,618 l.m.), and 192 or 2.48% are timber structures (2.42 l.m.) (Table
7.3.5).
Table 7.3.5
Summary of Existing National Bridges (Length and Number) By Type
As of 2007
TYPE OF BRIDGE
Total
REGION Concrete Steel Bailey Timber
Length (in lm) No. Length (in lm) No. Length (in lm) No. Length (in lm) No. Length (in lm) No.
Cordillera Administrative Region 5,882 187 3,015 33 1,756 83 17 2 10,669 305
National Capital Region 18,746 264 567 5 19,313 269
Region I 24,139 441 5,611 58 327 19 30,077 518
Region II 18,007 381 4,328 23 303 20 55 5 22,693 429
Region III 25,229 569 3,519 37 21 1 102 7 28,871 614
Region IV-A 15,206 562 958 27 529 34 14 2 16,707 625
Region IV-B 15,027 408 1,578 45 3,358 128 581 46 20,544 627
Region V 20,033 519 1,389 34 730 50 22,152 603
Region VI 22,922 573 3,886 68 1,881 69 88 3 28,777 713
Region VII 15,375 460 2,051 25 552 36 67 3 18,045 524
Region VIII 25,646 717 5,474 58 1,151 72 759 63 33,030 910
Region IX 9,279 224 1,338 26 51 4 20 1 10,688 255
Region X 11,798 303 2,570 49 299 13 6 1 14,673 366
Region XI 10,837 224 966 14 402 14 12,205 252
Region XII 9,402 239 829 19 454 24 10,685 282
Region XIII 10,311 253 2,491 39 1,804 100 720 59 15,325 451
Nationwide 257,836 6,324 40,570 560 13,618 667 2,429 192 314,453 7,743
Source: Road and Bridge Information Application (RBIA), DPWH
Source: DPWH
15. In the Philippines, motor vehicles are classified in four groups: cars,
utility, trailers, trucks and buses and motor tricycles. Table 7.3.6 presents
data on 2007 motor vehicle registration obtained from the Land Transportation
Office, It will be noted that registration of all types of vehicles have more or less
steadily increased in the past 23 years. The average growth is 3.5% per annum
for cars, 6.60% for utility vehicles, 5.20% for trailers, trucks and buses, and
11.20% for motor tricycles. In 2007, total registered vehicles was at 5,530,052
consisting of 751,092 cars or 13.58% of the total, 1,795,610 utility vehicles or
32.47%, 335,776 trailer trucks and buses or 6.07%, and 2,647,574 motor
tricycles or 47.80% of the total.
16. In terms of the total number of registered motor vehicles by region for the
year 2004 to 2007 (Table 7.3.7), the highest share of motor vehicles was
noted in Luzon, particularly in the National Capital Region (NCR), and the lowest
share was noted in Mindanao, particularly in Region XIII. Of the total member
of registered motor vehicles. In 2007, 28% was recorded in the NCR and only
1.0% in Region XIII.
17. In terms the type of motor vehicles by type of fuel used by motor vehicles
(Table 7.3.8), it will be noted that there are more vehicles using gas than
diesel and that buses and trucks predominantly use diesel.
Table 7.3.8
1985-2007 Motor Vehicle by type of Fuel Used
18. Despite major investments in the roads sector in the 1970s to 2008, with
technical and financial assistance from development institutions such as the:
International Bank for Reconstruction and Development (IBRD), Japan Bank for
International Cooperation (JBIC), Japan International Cooperation Agency
(JICA), and the Asian Development Bank (ADB), and other donor country
assistance programs; the demand for road development, improvement and
management remains high.
19. The Philippine road network suffers from the following principal
deficiencies:
b. For the national secondary roads about 60% is paved, 49% of the
existing paved sections need to be rehabilitated, while there are still
40% which are still unpaved.
c. About 23% of the total length of all roads is paved and 77 percent is
still unpaved.
e. Areas where roads are most sparse and unimproved are also the most
economically undeveloped.
20. Between 199and 2005, there has been a decline in the total public sector
infrastructure expenditures as a percentage of GDP in the Philippines resulting
to a significant underinvestment by the national government, government
owned and controlled companies, and local government units (LGUs) fell from
3.3% of GDP in 199to 1.8% in 2005, then rose to 2.3 percent in 2006 and to
2.6% in 2007. This is less than the 5% benchmark estimated by the World Bank
that will enable middle income countries in East Asia to meet their infrastructure
development requirements and growth aspirations.
23. Funding shortages are a primary cause of the problems of the road
network. The available MVUC special funds of about P 4 to 6 Billion in the last
four years cover only 21-32% of the maintenance needed and is contributing to
the progressive deterioration of roads. The low level of expenditures is
attributable to the low contribution by the Government, road users, and the
private sector in general; low relative priority accorded to the sector by the
country’s leadership.
24. For routine maintenance, a disproportionate share has been used to fund
employment-generating roadside maintenance programs – 25% in 2003, 33%
in 2004, 35% in 2005, and 40% in 2006. This is typically earmarked to
sweeping, beautification, planting, and other labor-intensive activities with up to
10 workers per km. The more important task of carriageway maintenance
suffers as a result.
26. There is a need for coordination between the sector line departments and
oversight agencies on the development of an overall sector master plan to
province and integrating framework for infrastructure, There is also a need for
an updated inter-modal transport plan that would harmonize and rationalize
road, rail, sea and air intermodal linkages in transport planning and operations.
Planning-budget linkages and disconnects or mismatches were noted among
said agencies which in the end run are resulting to inefficient allocation of
resources (i.e. investments in lower priority or non-viable projects of vested
interest parties), poor capacity (e.g. timely Government cash support and
budget cover), conflicts among agencies, and poor governance.
28. Continuing support for local urban and rural development and
environmental management issues also contributed to MDGs. Strategies and
programs geared at enhancing institutionalizing the 1991 Local Government
Code (LGC) notably to enhance decentralized service delivery in the regions,
provinces, municipalities, barangay (villages), and communities, especially for
roads related urban and rural development. National and local government
roles need to be fully rationalized. This compounds the lack of clarity in
resource control, accountability and responsibility for administration
arrangements, budget allocation, and functional assignments. Urban and rural
development was seen as having the potential to address poverty reduction,
social inclusion and service access, and environmental problems. While support
was relevant, multiple institutional layers; bureaucratic inefficiencies;
operational design issues, including land acquisition; and failure to implement
policy provisions relating to environmental management limited expansion of
the program. Tables 7.4.2 and 7.4.3, presents development of the country’s
progress relative to MDGs.
30. For the road sector the provision of the necessary economic support
requirements, adherence to new planning systems (e.g. MYPS, HDM-4, PMS,
BMS), improvement of systems (planning and selection of projects,
procurement, design, construction supervision, quality assurance, maintenance
and sustainability, financial management and internal control, etc.) with
efficiency and value for money in mind will enhance investor confidence and
investments in the country.
32. In early 2008, however, risks began to emerge to the sustainability of this
growth rate arising from a slowdown in the United States economy and other
external factors such as high commodity prices (e.g. oil).
33. The Philippines has crossed the threshold of per capita incomes (beyond
ADF norms of $925 in 1997 prices) but exhibits high poverty incidence. In
terms of unemployment and poverty, Poverty incidence declined from 33.0% of
the population in 2000 to 30.0% in 2003, but then increased again to 32.9% in
35. Notable successes in private finance through cooperative joint ventures for
construction of toll roads, post-construction securitization essentially all in the
form of equity contributions, and entry into international bond markets for road
financing. About 80% of private investment in toll roads and all private mass
rail transport investment were in cities (urban context). Private involvement in
long term maintenance contracts is a relatively new area to be expanded in the
near future.
39. The Philippine Government recognizes the fact that it lives in a global
economy, closely interconnected by trade and investments. Thus, government
is effecting and pursuing fundamental reforms and changes to bring in
investment that will create jobs and opportunities and eventually reduce
poverty.
40. Given the current fiscal constraints, investment priority is presently being
focused in areas where the Philippines has natural and human resource
advantage such as: IT-related industries, contact centers, tourism, fashion
garment, jewelry, medical services/healthcare/wellness, electronics,
automotive, agri-business/marine-culture, and shipbuilding, etc.
46. Pursuant to Executive Order No. 124, series of 1987, the DPWH is
mandated to undertake: (a) the planning of infrastructure, such as roads and
bridges, flood control, water resources projects and other public works, and (b)
the design, construction and maintenance of national roads and bridges, and
major flood control systems. These activities are undertaken in support of
national development objectives such as those envisioned under the 2005-
2010 Medium Term Development Plan (MTDP).
47. In 2004 and currently for 2008-2009 (on-going), the DPWH has
undertaken and is updating Department strategic planning process. It has
crafted its mission, vision, and goals as follows:
Vision:
Mission:
Goals:
50. The following 3 goals are currently being pursued in the 2005-2010 and
2011-2016 planning horizons:
(1) Improve the public’s access to activities, goods and services through the
preservation, improvement, and expansion of the national road network
in a cost-effective and environment-friendly manner, and enhance its
operation, safety, efficiency and inter-modal connections;
(2) Protect and enhance the communities and environment thru flood control
and mitigation measures and the provision of other facilities; and
51. For the Philippine road sector, the main goal of the DPWH is to improve
the public’s access to activities, goods and services through the preservation,
improvement, and expansion of the national road network in a cost-effective
and environment-friendly manner, and enhance its operation, safety, efficiency
and international connections. In pursuit of this goal, the following policies and
strategies have been formulated/adopted:
Strategies Objectives
1. Formulate long-range physical Prepare by Region and by District, master
master plans by region, to relate plans for 2025, and medium term programs
national roads with local roads, other for 2005-2010, covering national roads in
transport modes, and other relation to other infrastructure, with the
infrastructure of national and local concurrence of Regional Development
governments, considering land use Councils (RDCs).
plans and needs of agriculture,
Strategies Objectives
tourism and industries; prepare
corresponding medium-term (6-10
years) regional development
programs for national roads.
2. Under the long and medium term
plans and programs:
a. Pave all national roads with Increase ratio of paved length to total length
concrete or asphalt of national roads from 70% in 2004 to 95%
in 2010, with International Roughness Index
(IRI) of less than 4.
b. Replace/construct national bridges Increase ratio of permanent to total national
with permanent structures bridges, from 93% in 2004 to 100% in
throughout the country 2010.
c. Prioritize roads to support the 10-
point agenda of the Government:
c.1 Complete the nautical highways Complete paving and improve remaining
to transport the produce of unimproved road sections of the Western,
Mindanao to Luzon and Visayas Central, and Eastern Nautical Highways.
Rehabilitated or replace weak bridges along
the routes.
c.4 Improve access to major tourist Pave and improve roads leading to tourist
destinations complexes at Cebu-Bohol-Camigiun,
Palawan, Cordillera, Clark-Subic and Davao.
Strategies Objectives
b. Rehabilitation To meet rehabilitation needs (based on
PMS/BMS) by providing adequate funding.
52. To attain the development goals in line with the policies and strategies set
above, the medium-term program for transportation infrastructure aims to
undertake the priority sub-sector activities. The said activities will focus on the
following targets for the road sector:
d. The investments for national roads will shift in favor of regions with low
road densities and low paved road ratios.
53. Figure 7.5.7.1 presents the DPWH Medium Public Investment Plan for
DPWH for 2005-2010 for it to attain its objectives and targets in the roads
sector.
Figure 7.5.7.1
Source: DPWH
54. Table 7.5.7.1 presents the DPWH Maintenance Investment Program from
1987 to 2007 that shows that about 90% of the DPWH maintenance
investments coming from the GAA and Motor Vehicles Users’ Charge is being
annually programmed for roads and bridges.
Table 7.5.7.1
DPWH Maintenance Investment Program
1987-2009 (In Million Pesos)
Source: DPWH
55. Table 7.6.1 presents the main laws that govern the road sector in the
Philippines. Two main laws govern the Philippine road sector: the Philippine
Highway Act (RA 917, 1953) and the Land Transportation and Traffic Code (RA
4136 of 1964) with the former defining the 4 classes of roads (national,
provincial, city/municipal and barangay), while the latter sets the rules for road
use.
Table 7.6.1
Main Legal and Regulatory Provisions
Legal Provision Purpose
Commonwealth Act (146, 1936), and Provides the framework for grant of
amendments, the latest being franchises for public land transport for hire,
Executive Order 125-A, series of 1987 including rate setting based on application
and public hearings. Makes the Land
Transportation Franchising and Regulatory
Board (LTFRB) the quasi-judicial grantor.
Philippine Highway Act (RA 917, 1953) Provides for an effective highway
administration; classifies roads according to
administration and funding; Establishes a
Highway Fund, and provides for technical and
financial assistance to provinces, cities, and
municipalities.
Limited Access Highway Act (RA 2000, Sets the framework for the development of
1957) limited access roads under the administration
of the Department of Public Works and
Highways (DPWH).
Land Transportation and Traffic Code Governs the registration and operation of
(RA 4136, 1964) motor vehicles and licensing of owners and
drivers, and establishes traffic rules.
Charter of Toll Regulatory Board Regulates entry and pricing of limited access
(Presidential Decree 1112, 1977) roads.
Build-Operate-Transfer Law (RA 6957 Lays down the rules for private sector
as amended by RA 7718, 1994) financing and development of infrastructure
Right-of-Way Law (RA 8974, 2000) Sets rules for expediting right-of-way
acquisition and stipulates the role of Local
Government Units (LGUs) in relocation/re-
settlement; Allows for the immediate
possession of land being expropriated upon
payment of zonal value of the property and
pending court decision on the final purchase
price.
Motor Vehicle Users’ Charge (RA 8794, Provides for additional resources for
2000) maintenance, safety, and air pollution
control, and for establishing a Road Board for
the prudent and efficient management and
utilization of these resources.
Table 7.6.2
Road Sector Allocation of Responsibilities/Mandates
Agency Functions
Department of Public Works and Planning and construction of the national
Highways (DPWH) road network
Maintenance of the national road network
Setting technical standards for the
construction of all road and bridge classes
Establishing regulations for vehicle weights
and axle loads for all road classes
Selective upgrading and construction of
local roads for other agencies, such as the
Department of Agriculture and Department
of Agrarian Reform, and through
Congressional Funds
Assisting LGUs in the provision of roads
when such services are unavailable or
inadequate
Road Board Managing the Special Road Fund (SRF)
where collected monies from the Motor
Vehicle Users’ Charge (MVUC) are
deposited and designated for road
maintenance, safety, and air pollution
control
LGUs: Provinces, Cities, and Planning and construction of local roads
Municipalities (including barangay roads) within their
respective jurisdictions
Maintenance of local roads
Economic regulation of tricycles and
pedicabs for hire, in terms of market entry
and pricing.
Agency Functions
Toll Regulatory Board – Attached to Economic regulation of toll roads.
the DPWH
Specialized bodies such as the Public Provision of roads within certain areas,
Estates Authority (PEA), Bases usually export processing zones, following
Conversion and Development Authority technical standards and guidelines of the
DPWH
(BCDA), and Subic Bay Metropolitan
Maintenance of roads and other
Authority (SBMA) infrastructure within their defined
geographic areas
National Economic Development Formulation and coordination of policies in
Authority (NEDA) transport (roads, Maritime, air, etc.) in the
Medium Term Development Plan (MTDP)
Formulation of medium-term public
investment programs that include roads
Approval and oversight of infrastructure
projects exceeding PhP300 Million
Department of Budget and Synthesis and review of budget requests of
Management (DBM) agencies, submission of consolidated
budget to Congress, and execution of
approved appropriation
Release of the annual Internal Revenue
Allotment (IRA) of LGUs
Department of Agriculture (DA) and Incidental financing of rural roads that are
Department of Agrarian Reform (DAR) necessary components of their
departments’ agriculture and agrarian-
related programs
Source: World Bank Group, Philippines: Meeting Infrastructure Challenges, 2005
57. The main oversight government agencies are the NEDA and DBM, Advisory
and coordinative services in the formulation of sector policies and programs are
provided by the NEDA through its Infrastructure Committee (InfraCom) and
formulate the DPWH’s medium term investment program. Monitoring and
coordination of public sector investments (both foreign and domestic exceeding
PhP 300M) is done by the NEDA through its Investment Coordination Committee
(ICC). The ICC requires the endorsement of appropriate regional development
council/s before clearing local projects for implementation. The DBM drafts the
annual national budget for approval of Congress and sets the budgetary ceilings
through its Development Budget Coordinating Committee (DBCC). NEDA and
the Department of Finance (DoF) approve all foreign funding and official
development assistance (ODA) investment projects.
58. The Philippine Medium Term Plan (MTPDP) is crafted and revised every 6
years to synchronize with the term of the Philippine President. It contains the
broad strategies and policies on infrastructure development as well as key
objectives. Annex 3 presents the Infrastructure Development Process currently
implemented by DPWH.
59. In May 2007, the DPWH issued Department Order No. 30 series of 2007
prescribing the adoption and implementation of the OPIF of the Public
Expenditure Management being mainstreamed by the DBM. The OPIF is
basically: (a) an approach to expenditure management that directs resources
towards results and accounts for performance; (b) enables Government
agencies to focus efforts and resources on core functions and on delivering high
impact activities at reasonable costs and qualities.
60. The OPIF adopts an analytical approach based on logical framework linking
societal and sectoral goals, organization outcomes and major final outputs
(MFOs) in assessing agency performance. MFOs refer to goods and services the
DPWH is mandated to deliver to external clients through the implementation of
agency programs, activities and projects. Agencies are made accountable for
the base level of the OPIF logframe or set performance indicators for
accomplishment based on pre-determined targets and measures in the budget
program.
61. The following goals, outcomes, and MFOs have been prescribed for the
national roads sector:
b. Sectoral Goals: (a) Access to markets and production areas, and physical
integration of the country; and (b) safe environment though infrastructure
facilities.
d. Major Final Outputs: (a) National roads maintenance services; and (b)
National roads construction services.
e. Programs/Activities/Projects:
63. In 2008, the DPWH availed of grant assistance from the PAHRDF for the
conduct of “Capacity Building for Management Leadership Development on
Strategic and Operations Planning” which is currently on-going in its Phase 2
activities for: (1) leadership development training for District Engineers
nationwide and (2) development of Operations Plans at District Level. Phase 1
covered leadership training to top level executives; bureau and services
directors and assistant directors; major project management offices’ directors
and assistant directors, regional offices directors and assistant directors, and
Strategic Planning Technical Working Group members as well.
64. The Strategic Plan, when properly carried out will provide a viable means
for the DPWH to:
65. Tables 7.7.2.1 and 7.7.2.2, and Figure 7.7.2.1 present some of the
major highlights in terms of organizational vision, and updated strategic
planning (StratPlan) framework which the DPWH will be pursuing in 2009-2016.
It will be noted that StratPlan Framework had adopted and incorporated the
Organizational Performance Indicator Framework (OPIF) prescribed by the DBM
and expanded these to include Key Result Areas (KRAs) for the following major
concerns: (a) Program Delivery, (b) Internal Support, and (c) External Support.
Table 7.7.2.3 shows the general key result areas and concerns the DPWH
management will be giving priority in their plans and programs in 2009-2016.
Development oriented
Social relevance
People empowered
An organization with moral ascendancy
Bridging the gap between the rich and the poor
DPWH’s symbol is the bayanihan (community oneness)
Environment friendly
STRATEGIC PRIORITIES
KEY RESULT AREA
2009-2016
External Relations Public Relations Public Relations Management
Effective Partnership Alliances & Partnering w/ NGOs &
Community Beneficiaries
Partnering w/ LGUs
Partnering w/ NGAs
Program Delivery Planning & Funding Long & Medium Term Plans
Project Preparation & Pre
construction
Annual Infra Program
Post Evaluation
Design Design Standards
Quality Assurance in Design
Value Engineering
Construction Contract Management
Construction Management
Quality Assurance in Project
Implementation
Project Monitoring & Evaluation
Maintenance Contract Management
Maintenance Management
Quality Assurance in Project
Implementation
Monitoring & Control
Disaster Risk & Response
Internal Support Organization/HRM/ Human Resources Development
Integrity Development
Human Resources Management
Integrity Development
Organization/Management
Information Technology Research &
Management Development
STRATEGIC PRIORITIES
KEY RESULT AREA
2009-2016
Logistics Management
Disaster Risk & Response
Research & Standards Applied Research
Development
Hydrologic Data Collection &
Evaluation
Geotechnical Engineering
Construction Methods/Materials
Standards
Materials Quality Control&
Assurance
Technical Training
Accreditation
Business
Improvement and
Implementation
Projects (BIIPs)*
Note: * - BIIPs activities will be serving all other KRAs as internal support, subject to DPWH prioritization and
available resources
Final configuration of matrix may change as PAHDRF project activities are still presently on-going
NGO – Non Government Organizations,NGA - National Government Agencies, LGU – Local Government Units,
RA9184-Republic Act 9184 – Government Procurement Reform Act
Source: DPWH
66. One of DPWH’s major long term concerns focus on the continuing
improvement of the DPWH organization centered on:
68. The objective of the RIMSS project is to improve the quality and delivery
of DPWH services in the provision and management of the road system. The
RIMSS effort is currently to enhance existing DPWH road management
processes, as well as to improve existing fragmented information services by
69. The priority RIMSS tools are individually called Business Process
Improvement Implementation Projects (BIIPs). Initial implementation of the
BIIPs was as a sub-component of the ICB component of the World Bank NRIMP
and the ADB 6th Roads Project. Said project was started in July Program until
June, 2000. Its current activities are now funded by World Bank under the
NRIMP-1 from July 2001 to June 2010 and Asian Development Bank under its
6th Roads Project.
70. The business processes to be improved by the RIMSS cover three core
processes for highways and five support processes for all public works
operations (Figure 7.7.2.2):
a. Core Processes for Highways: (1) Plan, (2) Build (Design and
Construction), and (3) Operate. These processes are associated with
DPWH’s highway assets.
73. By the end of 2007, the ADB had approved $9.8 billion in public loans
and $148.8 million in technical assistance to the Philippines. Through its
private sector operations for the same period, ADS had approved $275 million
in loans and $37 million in equity investments.
74. A major recipient is the road network which is the most indispensable
part of the Philippines' transportation system. It plays an important role in the
attainment Government's national goals and strategies for development. ADB
has provided assistance to the road sector since 1970. Projects had been
undertaken in Luzon, Visayas, and Mindanao, reflecting the Bank's policy to
spread its assistance evenly among the major regions of the country. The
common objectives of these projects were to construct, rehabilitate, and
upgrade existing national and feeder roads to facilitate commodity flows and
accelerate the socio-economic development of their respective regions.
Source: DPWH
75. The 2008 CAPE assesses the performance of the ADS assistance
program since 2003 as an input for preparation of the new country partnership
and strategy
b. ADB country strategies and plans were overly broad-based with wide
sector and geographic coverage.
c. ADB's ongoing investment operations experienced implementation
delays; problems with land acquisition and resettlement; procurement
delays; shifting political support for urban, agriculture, and education
reforms; and a dearth of counterpart finance by 2002-2003 when
fiscal constraints were most severe.
78. With the PPTA already completed, the proposed “Rural Roads
Development Project Readiness TA Loan” could not be appraised because of
Government’s inability to commit budget cover and the lack of clarity on both
relending mechanisms and the Government-LGU cost-sharing formula.
80. According to the ADB’s Country Operations Business Plan (COBP) for
2009-2010, the Country Strategy and Program (CSP) 2005–2007 for the
Philippines covered only 3, rather than the usual 5 years in anticipation of
economic uncertainties in 2005. In 2007, the Asian Development Bank (ADB)
and the Government of the Philippines (GoP) agreed on an operational
program for 2007–2008, which extended the CSP by 1 year through the
country operations business plan (COBP) 2007–2008. In 2008, ADB and the
GoP agreed on an operational program for 2009–2010, which would extend the
CSP by 2 more years through a COBP 2009–2010. The CSP retains its
strategic focus on: (a) fiscal consolidation, an improved investment climate,
and accelerated attainment of the Millennium Development Goals (MDGs), as
confirmed by the country assistance program evaluation (CAPE) for the
Philippines; (b) the ADB study on the critical development constraints in the
country; and (c) Importantly, extending the CSP to 2010 will align the cycle of
the country partnership strategy with the Government’s planning cycle.
82. Against this background, the strategic focus and selectivity of the CSP
remains relevant and robust for 2009–2010. The COBP will maintain the
emphasis on alignment around government priorities, selectivity, and quality-
at-entry. It will continue ADB support for medium-term reforms via the
Development Policy Support Program, the Financial Market Regulation and
Intermediation Program, and the Local Government Financing and Budget
Reform Program. The country’s improved fiscal situation has allowed the
Government and ADB to pay greater attention to other binding development
constraints, namely, the need to accelerate the attainment of the MDGs and
83. The COBP 2009–2010 is closely aligned with the Strategy 2020 of ADB
(Strategy 2020: The Long-Term Strategic Framework of the Asian
Development Bank 2008–2020). Of the five core areas of operation in the
strategy, three—infrastructure, environment, and financial sector
development—are covered by the proposed lending program. The Philippines
is engaged in several regional cooperation initiatives, such as the Brunei
Darussalam–Indonesia–Malaysia–Philippines East ASEAN Growth Area (BIMP-
EAGA) and the Coral Triangle Initiative. Regional advisory technical assistance
(TA) projects in 2009–2010 will support regional cooperation and integration,
another core area.
85. Table 7.8.1 presents the summary of ADB country program directions
since 1998 that have bearing with the road and transport sector.
86. Table 7.9.1 presents the other development partners assistance and
corresponding sectors they are operating in currently being undertaken in the
Philippines. Historically, the World Bank, the new Japan International
Cooperation Agency (recently merged with the former Japan Bank for
International Cooperation - JBIC) and the ADB have provided the largest
amounts of external assistance to the Philippine road sector.
Table 7.8.1: Summary of ADB Country Programs Since 1998 Relevant to the Road Sector
Road and Transport Transport : (i) invest in Agriculture : (i) invest in rural Economic growth: (i) Governance: Reforms to (i)
Sector and Other transport with emphasis development including increase attention to rural improve resource
Sector/Thematic on national and rural removing infrastructure development; (i) support mobilization and budget
Related Strategies road expansion and bottlenecks; strengthening more balanced regional operations of LGUs to reduce
BIMP-EAGA Brunei, Indonesia, Malaysia, Philippines-East ASEAN Growth Area; BOO/BOT = build-own-operate/build-operate-transfer: COA =Commission on Audit; COS = country operational strategy;
CSP =country strategy and program; CSPU =country strategy and program update; DOH = Department of Health; EA = executing agency; GOCC = government-owned and -controlled corporation; lEI =
innovation and efficiency initiative; LARP =Land Acquisition and Resettlement Plan; LGU = local government unit; LWUA = Local Water Utilities Administration; MDG = Millennium Development Goal;
MTPDP = Medium-Term Philippine Development Plan; NGO = non-government organization; NPC =National Power Corporation; NPL =non-performing loan; SME =small-and medium-sized enterprise.
Source: Asian Development Bank Philippines CAPE: Increasing Strategic Focus for Better Results, June, 2008
87. The ADB and World Bank have generally focused on the improvement of
existing roads either through rehabilitation or the conduct of periodic
maintenance, while JICA/JBIC focused on the improvement of existing roads
and construction of new roads. Three sector loans from these 3 institutions
are currently envisaged to push through before the end of 2010 (World Bank
NRIMP Phase 2 is now on going) and the ADB and JICA project under
packaging and negotiation. Generally, these loans will have a loan requirement
of USD$220M to USD$300M. Components of this assistance will generally
cover asset preservation, road improvement, and institutional capacity building
in support of reforms.
89. ADB, given its unique position in the Philippines and responsibility in
Asia, should play a more active role in donor coordination, both at the regional
and at Philippine level. Cooperation will be deemed critical for overall
development and formulation of a harmonized and coordinated sector policies
and programs that address important road and road transport sector issues.
The transport sector will continue to be a major focus of external assistance in
the majority of countries in the foreseeable future. There is still a need to
extend cooperation and collaboration with other development partners to
optimize the benefits from external assistance for member countries and
ensure that core elements of transport road maps achieve their intended
outcomes.
90. ADB should take the lead in supporting local authorities to implement
strategic planning and sector studies with full opportunity for the various
interested stakeholders to comment on, among others, terms of reference and
participate in sector issue and reform analysis. Such studies can rapidly
produce a strategic agenda, identifying objectives and constraints, institutional
development needs, processes of sector management, appropriate policies, as
well as broad expenditure allocations within a realistic budgetary envelope.
This can be periodically repeated/updated every three to five years or if and
whenever necessary. This can form the basis for improved donor collaboration
at the country level. Support should also be provided to build the capacity of
local transport research institutes and promote effective transportation policy
development and planning, to help countries develop in-country analytical
skills for road transport policy developments and enhance their role in donor
coordination in the future.
7.10 Intended Sector Outcomes and Key Outputs Supported by the ADB
Table 7.10.2: Summary of ADB-Philippine Partnership Targets and Progress for 2005-2007
93. Table 7.10.3 presents an intended sector outcomes and key outputs
that can be supported by ADB under its current Country Strategy and Program
for the Philippines.
Table 7.10.3
Road Sector Outcomes and Key Outputs that can be supported by ADB
94. Table 7.11.1 presents the Sector Results Framework for the road sector
considering the CPS outcomes of improved fiscal outlook and improved
business climate; Improved/Increased financing and investments, both public
and private as well as bank and non-bank, to Government and Local
Government Units, and Private Sector (B-O-T/PPP, investors and transport
operators). Results based systems institutionalized and adopted by necessary
partners, and harmonized planning, budgeting, procurement, and maintenance
95. The World Bank in its 2005 paper “Philippines: Meeting Infrastructure
Challenges” recommended. It will be noted that these were focused on: (i)
Improving governance and accountability of spending at the Department of
Public Works and Highways; (ii) Implementing structural changes in the road
sector; (iii) Placing greater reliance on user charges to support sector needs;
(iv) Improving private sector participation; and (v) Improving management of
road use to protect lives and road assets. The corresponding projects and
activities are presented in Table 7.12.1.
97. This had generally borrowed and followed the analytical framework
adopted in the 2004 ADB paper, “A Transport Strategy for Sustainable
Development”. The paper notes that “There is no overarching strategy that fits
all development member country (DMC). For each country, the ADB will have
its roadmap summarizing the country strategy and indicate how ADB
assistance will help achieve the strategy”. Furthermore, it also noted that
“less emphasis” has been given to poverty...while more emphasis placed on
transport facilitating economic growth … within the overall context of poverty
reduction strategy.”
Sector
Subsector
CPS Outcomes Key Opportunities Milestone/Tracking
Outcome/Key Sector ADB Assistance
Relevant to the Sector and Constraints Indicators/ Interim Risks
Outputs
Indicators
Improved fiscal outlook Adopted and Increased budgets Approved Annual Program Lending External economic
and improved business Institutionalized and investments for Budgetary Allocations T.A. Advisory shocks (e.g.
climate Fiscal Policy road sector projects Percentage of Services slowdown, crisis, high
Recommendation Improved magnitude Approved Budget commodity prices,
Policy Advocacy
Outlook for greater and coverage of plans Allocation to Required etc.)
Donor Community
growth, investments, and/or development Annual Needs Slow , non or partial
Support
and capital needs Improved level application of
generation physical targets proposed changes
Government bodies
not meeting fiscal
requirements (e.g.
tax/revenue targets)
Proposed solutions
may not be the
proper solutions if not
properly evaluated
Improved/Increased Wider coverage of Increased budgets Reduced equity and Program Lending to Parties having trouble
financing and programs with private and investments for investment Private Sector and or unable to meet
investments, both sector support, bank road sector projects requirements for Local Governments start-up requirements
public and private as and non-bank Improved magnitude major projects Non-bank financial (e.g. right of way,
well as bank and non- financial assistance. and coverage of plans Grants and technical windows of financing and bank
bank, to Government Involvement of and/or development assistance support to assistance to guarantees
and Local Government Private sector in needs project operations Government, Public requirements
Units, and Private provision of services Sector, and Local
Private sector Local Government
Sector (B-O-T/PPP, Governments (e.g.
Improved coverage management and functions for rural
investors and transport technical and
by Local technological skills roads enhanced
operators) financial support for
Governments of their brought into sector (capability and
programs. capacity pre-construction
Private-public
improvements) activities) for B-O-T
partnerships born and
projects
forged
Sector
Subsector
CPS Outcomes Key Opportunities Milestone/Tracking
Outcome/Key Sector ADB Assistance
Relevant to the Sector and Constraints Indicators/ Interim Risks
Outputs
Indicators
Results based systems Unified and focused Efficient and km of roads Advocacy of good Non-acceptance by
institutionalized and approach to project effective delivery of constructed within practice procedures vested groups who
adopted by necessary development and goods and services plan and Harmonized donor may block or
partners sustainability within plans, specifications, cooperation and circumvent the
Harmonized planning, Improved attainment budgets, and km of roads coordination with system
budgeting, of plans and schedules) maintained at set Government Uniform application in
procurement, and programs quality bench-mark operations the organizations
maintenance of Improved resource (e.g. International Sustained Lending involved to truly
projects and allocation and Roughness Index Programs minimize leakage and
investments, e.g. funding system value equal or less bad decisions which
compliance to plan and Reduction than 4) , affects efficiency
intended purpose/s Road charges
approximating road
maintenance and
costs of externalities
such as pollution,
optimized fares and
tariffs for road
transport services
Poverty Reduction Socially relevant and Support to Poor and Km of roads Advocacy and pilot Projects may not be
Job Creation equitable Disadvantaged constructed and work for different economically viable
Social and Human development Groups maintained in project approaches, and represent a net
Development Pro-poor strategy Support to Areas identified social or e.g. roads cum drain to the economy
Projects may not be with peace and order pro-poor zone livelihood and/or in the medium to
economically viable problems Length of bridges integrated area long run
and represent a drain constructed in projects. Quality at entry
to the economy in the identified social or Funding support for filters need to be
medium to long run pro-poor zone special poverty made clear under
Special screening or enclave areas results based
filtering techniques at programs approach
investment Assistance in special
programming stage evaluation and
may be necessary. appraisal techniques
for impoverished
areas.
Note: B-O-T - Build-Operate-Transfer Projects; PPP – Public-Private Partnership; T.A. – Technical Assistance
Table 7.12.1
Road Sector Recommendations
1. Transport and the Lack of reasonable access to markets, social services and civil Advocacy and continued support for pro-poor road
Poor society remains a dominant problem for large numbers of the and transport policy (Projects and investment lending
poor in rural areas and for rapidly increasing numbers in cities. in target segment, and improved socio-economic and
In fact, "The lack of basic infrastructure-particularly roads, poverty benchmarks)
transportation and water-is seen as a defining characteristic of
poverty 1. Targeting transport investments to the poor or to
poor regions should be an integral element of a
Transport investments can facilitate poverty reduction in two sustainable growth strategy that includes
ways (i) by directly increasing the productivity of the poor investments in transport infrastructure and
through improved accessibility to schools, clinics, markets, services.
businesses, etc, and (ii) by increasing the productivity of
employment generating business and industry. 2. Targeted investments should ensure that the
overall transport investment plan is equitable as
The major role of trunk roads, secondary networks, and rural well as efficient.
access improvements, is in enabling increased agricultural
production, higher productivity, increased non-farm activity, 3. Emphasis needs to be placed on attracting
improved labor mobility and expanded participation in better affordable transport services since these are the
health and education services. It is well recognized that services that generate the benefits to the local
economic growth is the major force contributing to poverty communities
reduction
4. Poverty-focused transport projects should include
Emphasis needs to be placed on attracting affordable transport provisions for monitoring and evaluation impacts
services as it is the services that generate the benefits to the and outcomes. Continued attention to monitoring,
local communities. evaluation and empirical research is important in
order to provide invaluable guidance and feedback
Competition for and in the market is necessary if the benefits of for further improvements in the design of projects
transport are to be passed on to users rather than owners and to overcome access problems of the poor.
operators of vehicles and vehicle fleets. In many rapidly
growing urban areas a similar problem is commonly observed For transport services, there is a need for a proper
where deterioration of public transport services results from a regulatory framework to be in place to provide low
low fares policy, often below costs, and government authorities cost-efficient public services where the transport
are unable to support revenues. benefits are widely distributed (Regulations, laws, and
Orders issued and circularized and complied with;
resulting fares and tariffs optimized and desired
outcomes attained)
2. Supporting Research on economic growth repeatedly highlights the Continued fund support to programs for improvement,
Economic Growth importance of transport investment to supporting overall growth upgrading, and construction as well as expansion of
Transport's contribution to sustainable economic growth road sector projects (Lending and Investment and
depends on the extent to which economic activities can be Projects; Improvements of Travel Cost and Time,
linked efficiently and economic "distances" reduced. Percentage Attainment in Meeting Plans, and
Transport can facilitate expansion of domestic and international Generated traffic volume, etc.)
markets.
Since improving transport services needs to be undertaken in a
manner that will keep an economy competitive in an era of
increasing globalization, the performance of the sector needs to
be continuously raised.
'
The specific factors of importance will vary between countries
and regions within countries depending on local circumstances
and whether international or domestic markets predominate.
2.1 Operational The greatest evidence for the need to improve operational Road asset management principles are advocated,
Efficiency efficiency is the poor level of maintenance that characterizes the supported, and institutionalized (Compliance to
road network/s Planned Programs; % of Budgeted or implemented
compared to plans; Guidelines Adopted across
Inadequate maintenance is resulting in large losses of capital organizations)
assets that are lost prematurely due to the neglected and
deferred maintenance. Monitoring the support and compliance of Road Fund
in meeting demand and that Road Board/authorities
There is a common misperception that a lack of resources is the are properly and efficiently functioning as reflected in
reason for poor maintenance. The reality is that much more network quality (% Compliance, and International
money is spent on reconstruction of roads than would have been Roughness Index rating of networks)
necessary had maintenance been done in the first place.
Advisory and procurement services on development,
Large gains in efficiency are possible from institutional reforms utilization, and sustainability of modern management
that strengthen the capacities of local, regional and national systems; trainings; networking and exchange
governments to manage the framework for transport more (systems developed, rolled out, and utilization rate;
efficiently and enhance the capacities of transport organizations improved cost/time of doing business, improvement
to provide customer-responsive services. in processing time; costs or benefits of better
decisions)
Throughout the sector, a significant obstacle to improved
operational efficiency in public sector institutions has been
outdated administrative structures, often with large labor forces.
2.2 Relieving The main impact of transport on growth is through lowering Continued fund support to programs for improvement,
Bottlenecks to Trade costs and thereby improving the efficiency of production and upgrading, and construction as well as expansion of
increasing the prospects of trade whether domestic or sector projects (Lending and Investment and
international. Projects; Transport Cost and Time savings, Generated
traffic volume, etc.)
Dependability and reliability of services is often as important as
other factors of production. The physical, policy and procedural
impediments to better transport services and bottlenecks to
trade need to be addressed.
2.3 Accessibility to Upgraded trunk routes are required in various locations to open Advocated as part of pro-poor policy (Item 1 above)
Isolated Areas up depressed landlocked and/or isolated areas and permit them
to participate in the modern market economy
2.4 Urban Transport Cities and towns are playing an ever-increasing role as the locus Continued Advocacy of modern urban concepts,
of economic growth. ADB has estimated that 80% of the integrated intermodal transport systems, within the
region's new economic growth will be generated in its urban wide framework of overall land use as well as fund
economies, highlighting the importance of the urban agenda to support and private-public partnerships (Plans, Design
national economic growth. Plans, Project/Sub-projects, Investment support;
urbanization impacts on cost. Time, convenience and
Urban transport investments not only facilitate trade and safety)
commerce. but also structure the shape of cities and the
location of business activities. Modern urban transport systems
therefore-need to be seen as a facilitator of economic growth in
the same way as national transportation networks.
Many of the region's major cities are among those facing the
most serious problems in the world in regard to traffic
congestion, declining quality of public transport, and unplanned
growth in peripheral urban areas without adequate transport
services.
2.5 Private Sector In many countries most road-based bus services, para-transit Marketing and design of new innovative lending and non-
Participation services, and virtually all road freight services are delivered by lending windows for private sector participation as well as
the private sector. With respect to large facilities, concessioning partnering with Government for road and transport
of ports and airports to private operators have seen the greatest sector finance as equity and leverage to increase
successes and have often led to dramatically improved domestic currency resources from the domestic capital
productivity. markets (financial windows and modalities offered, rate of
capital generation/utilization, etc)
Build-operate-transfer (BOT) and concession approaches for
other transport modes including toll roads, railways and urban
mass transit systems have yielded more mixed results.
there have been few projects in these sectors profitable enough
to attract the private sector without some public sector
participation.
Since the 1997 Asian financial crisis several BOT projects have
been a particular burden since many were structured with
substantial foreign financing, which led to higher debt
repayment obligations in local currency after devaluation.
3. Addressing Conflicting interests, inside and outside the sector, constantly Review and enforcement of prevailing governance and
Governance require reconciliation, as new areas and new traffic develops and anti-corruption policies (investigations, cases filed);
new solutions are proposed. Continued support to government sector strategic
planning, at national and local levels, with emphasis
Decentralization of government responsibilities is a trend that is on wide consultation, genuine consensus building and
placing more responsibility for urban and rural transport effective assessments made on the impact of
systems closer to the people affected by these systems. investments actually made and quality of services
provided (workshops and workshop outputs, number
Existence of large, immobile transport institutions trained).
The single most important task of government is to provide Continued advocacy and support to decentralization
clear and effective guidance, through policies and identification of government responsibilities for urban and rural
of priority investments for the evolution of the sector. transport systems closer to the people affected by
these systems (performance of devolved and
The second most important task is the development of decentralized functions)
institutional arrangements and management systems that create
internal incentives for accountability, efficiency and innovation. Support the increased corporatization of public
agencies in the sector and the establishment of
sound commercial accounting systems, organized
Road Boards to manage their road assets and road investments. around lines of business, commercial practices
Representatives of the private sector, road user and civic groups including tariff setting, introducing public service
as well as public officials govern these Boards. The concept is to obligations to serving disadvantaged areas and
operate the road system as if it were a revenue earning utility contracting out non-core subsidiary services (Savings
and create a transparent link between expenditures on roads in costs of government operations, service delivery)
and the revenues gathered from road users. Road-user-charges,
Advocacy and support to improved approaches on
channeled into a road fund that is managed by the Road Board
road expenditure management through better
is the preferred means of financing road maintenance."
linkage between road user charges and actual
expenditures on the road system (extent of coverage
There is still a large agenda of needed institutional reforms in
of road requirements).
government-owned transport operating agencies and public
transport companies Support and champion increased emphasis by the
development community on improvement of
Procurement procedures for contracts financed by ADB follow governance through greater attention to contracting
international best practice, member countries do not always procurement, contracting procedures, value for
follow such practices in contracts financed by national budgets. money applied by road and transport agencies on
In the highways field, competitive tendering has become the non-ADB financed procurements (harmonized
normal practice for any significant construction activity. What approaches)
constitutes competitive procurement, however, is subject to
wide variation in terms of transparency and integrity of the Support strengthening of service procurement and
process and the extent of true competition. contract enforcement skills of road sector agencies’
staff on measures to address corruption and
Similar considerations apply to the operations of enforcement transparency, mechanisms for handling complaints,
agencies, where corruption remains a major obstacle to internal control and auditing arrangements
improvement of law enforcement, traffic management, vehicle (Trainings, and Number of staff trained)
inspection, driver licensing, vehicle emissions, and route Cooperate and coordinate with other major donor
franchising. agencies, government, and stakeholder groups on
harmonized measures to address governance and
corruption (harmonized approaches established).
4. Financing for Address the need to improve the contribution of the transport Advocate and champion policy measures and
Sustainable sector as well as recovery of costs from road users. operational mechanisms to increase road user
Transport contributions to fully meet the costs for needed
If properly managed, improvements in cost recovery could
maintenance, rehabilitation, and network
resolve the maintenance problem and turn the development of
improvements as well as external costs involved in
road networks from a heavy burden on national budgets to a
road use - air pollution, noise, congestion, accidents
financially sustainable process.
and division of communities. (Extent of coverage by
Improved cost recovery could also provide incentives for road fund)
reduction of the negative impacts of motor vehicle use and the Cooperate and coordinate with other major donor
overall impact could make a significant contribution towards agencies, government, and stakeholder groups on
making the overall growth process more efficient and more harmonized measures to address governance and
equitable. corruption.(harmonized processes institutionalized)
The fuel levies would reflect the short-run marginal costs of use
of roads and should include an allowance for externalities
including road safety, local environmental effects and the global
warming risks of carbon dioxide emissions, which are almost
directly proportional to fuel use.
The license fees would raise the substantial additional sums
required to cover total expenditures, and would also reflect
differences in vehicles' marginal costs that cannot be captured
by fuel charges. Placing the revenues from these sources in a
road fund as could add to the attractiveness and sustainability of
the reform.
The deteriorating traffic conditions throughout most of the standards for providing for cyclists, pedestrians, and
region indicate that much more effort needs to be directed freight carts in new road infrastructure design
towards improvement of urban transport and its management. (meetings, dialogues, workshops, public information).
6. Vehicle Emissions Air pollution from vehicular sources need to be addressed as Advocacy and adoption of an urban air quality action
motor vehicles emit large quantities of carbon monoxide, plan. The development of comprehensive strategies
hydrocarbons, nitrogen oxides, and other toxic substances such needs to incorporate (i) stricter emissions standards
as fine particles and lead. Each of these, along with secondary for new vehicles, (ii) adoption of cleaner fuels including
by-products such as ozone, can cause serious public health and use of alternative fuels, (iii) programs for inspection
environment problems. The localized health consequences of air and maintenance of in-use vehicles, and (iv)
pollution are severe. comprehensive transportation planning, traffic
management and demand management measures to
Equally ominous is the rise in the transport sector's share of promote sustainable transport. These measures need
total carbon dioxide emissions, which are directly linked to to be supplemented with specific initiatives regarding
global-warming . The growth in motorization in Asia will result air quality monitoring, and improved vehicle
in substantial increases in emissions and deteriorating air technology standards (System/Process institutionalized
quality if mitigating actions are not taken. and maintained)
7. Regional Increasing trade and cooperation among countries in the Asia Advocacy and to the establishment Support Brunei
Cooperation and Pacific region has made a significant contribution to their Darussalam-Indonesia-Malaysia-Philippines East
development. As economies grow the opportunities also increase ASEAN Growth Area (BIMP-EAGA) Region as well as
but to take advantage of these opportunities presented often United Nations plan on an Asian Highway (meetings,
requires improved transport infrastructure and services. dialogues, conferences, public information)
Unexploited opportunities for cooperation are to be found
particularly in the relations between land-locked and sea-locked
countries and their neighbors
8. Transport Safety and Improvement of safety is an emerging issue that urgently Support institutionalization of policy guidelines, system
Security requires attention in the region's transport sector, and is for road safety and status of recommended priority
particularly acute in the road sector. interventions in the fields of engineering, education,
law enforcement and emergency medical services
It is estimated that in the Asia-Pacific region annual fatalities
(System institutionalized).
from road traffic accidents number about 500,000 and the
number of injuries exceed 20 million. The fatalities represent
Advocate and educate stakeholders on incorporating
about 45% of the world road total, despite the fact that the
road safety components in road sector operations
region has only 16% of the world's vehicle population.
(Trainings, Public Information)
Continuing rapid motorization coupled with high accident rates
suggests that these alarming totals will rise considerably further
in coming years unless action is taken to address them.
Another safety issue that is emerging concerns the carriage of
dangerous goods and hazardous material by and land. There is a
need for formal training in the carrying hazardous materials and
cargoes and licensing of truck drivers.
Emergency services for both land and sea modes require training
to respond to contingencies and incidents.
Improvements in signaling and communications is primarily
safety driven.
Improvements in transport security are now recognized as a
necessary and growing part of transport sector analysis and are
expected to become a growing element of future lending
operations. Passenger and bag screening measures being
established at international and domestic terminals as well as
urban mass transit and public bus transport. These measures will
be a burden for many countries, and countries not having
compliant systems and can be disadvantaged in terms of delays
in clearance of their exports by importing countries and have
further impacts on their attractiveness as investment locations
9. Multimodal Transport increases in throughput are now increasingly constrained by Advocate and pilot adoption of a multimodal "supply
and Trade Logistics shortage of space on the landside, severe congestion on access chain approach to analyze transport system
roads or, in a few cases, road networks that are unable to performance in support of trade and economic growth,
support extensive movement of 40-foot containers. Distribution It considers how system performance and efficiency is
by waterway, where available, or by rail, sometimes to inland affected by infrastructure bottlenecks as well as by
container depots, has helped to ease the problem, but in some regulatory and procedural requirements imposed by
cases the railway does not reach the port or has very limited modal agencies, other governmental bodies (e.g.
capacity. customs), and private sector players such as freight
forwarders and haulers (trainings, computer software
Efficiency in documentation clearance directly will play an
demonstrations, procurement).
increasingly important role and impacts on efficiency of
transport systems and infrastructure.
Coordinate and cooperate with other donors on
Improving multimodal transport and logistics will require better programs on Improving multimodal transport and
methods of public private cooperation in planning and logistics, possibility of public private cooperation in
implementation of diverse activities under different planning and implementation of diverse activities
responsibilities. under different responsibilities (harmonized
approaches based on best approaches and advocacy)
Solving these multimodal logistic obstacles to container and
goods transport-whether by upgrading road or rail, improving
transfer points, changing customs, inspection, and
transshipment policy and procedures, or, Ultimately, by shifting
more traffic to ports outside the main cities-will be an important
issue in the medium term as the volumes of trade increase.
10. Transport and the Special mobility needs of the disabled and elderly are often Advocacy of retrofit of existing facilities and-design of
Disabled neglected in transport planning and design. new facilities should consider barrier free access for
the aged and disabled (trainings and public
Both retrofit of existing facilities and-design of new facilities
information).
should consider barrier free access for the aged and disabled.
Issues include wheelchair access to public transport vehicles:
bus, rail, airplane (especially at small airports) taxi and mini
buses, as well as terminal access at bus, rail, metro and airport
locations. Curb ramps on pathways for wheelchairs, Braille
markings and handrails are all important components of a
strategy to accommodate mobility requirements.
11. New Technologies Information technology (IT) is one area that warrants attention Coordinate and cooperate with other donor
for contribution to improving performance of the transport and communities on complementary and collaborative work
road sector and economizing on the need for infrastructure on institutional capacity building work in road sector
expansion. agency such as the DPWH and its RIMSS (institutional
capacity building programs, harmonized system
Advances in this area have relevance for all modes. Improved
applications, state of the art technologies deployed
communications systems (mobile telephones, global positioning
where funds allow these)
system. and Internet) can reduce the empty running of trucks
Package and implement an institutional capacity
and their immobilization in traffic jams, can facilitate tracking 'r
building program component under a possible Road
and security of containers, and expand the effective capacity of
Sector Improvement Package. TA resources may be
restricted channels and corridors.
required to package and coordinate the scope of work
Smart cards for use of public transport can reduce fraud, enable requirements (Implementation and Investment Plan,
adoption of fare structures that are better integrated between Project Proposal, ADB Appraisal and negotiation).
the legs of a journey, and facilitate targeted subsidization of
disadvantaged categories of the population.
Improved management information systems cum geographic
information systems, assembling and analyzing data on the
past and current state of all sections of an infrastructure
network, , and the maintenance interventions undertaken, can
contribute substantially to better maintenance budgeting and
allocation.
IT can enhance road and rail safety by better accident reporting
and improved signaling and communications.
Electronic tolling of vehicles. in various forms. can be expected
gradually 10 spread among sites where capacity constraints are
most serious, initiating a fairer system of charging for
infrastructure use.
Technical Work Group and by the Inter-Agency Steering Committee for the
project. The selected 8 road sections and the comparison of Consultant’s
findings and the previous HDM-4 results are shown in Table 8.1.1.
7. Although the selection was intended to be considered as ”final” and will be
used as such for the design, it is based on approximate HDM-4 results and
visual (although thorough) inspections. The final costs for the work on each
section, and the total cost for all road projects were estimated based on the
design results. To insure about the risk for large deviations, two other road
sections have also been inspected and were kept as ”spare”.
8. Out of the 28 long list of road sections for asset preservation, 11 were
originally shortlisted under Tranche 1 (including one section from Dumaguete
North Road) but later reduced to 8, after combining two road sections for
Butuan-Cagayan de Oro City-Iligan Road and two road sections for Bauang-
Baguio road and deleting the section from Dumaguete North Road. That would
leave 18 remaining road sections in the long list. Out of those 18 road sections,
however, 5 were excluded due to the resulting low rates of return. Another 3
sections that appeared to be suitable for asset preservation (which remains to
be certified, however), were set aside in case more funds would be made
available for Phase/Tranche 1. Thus, only 10 road sections for asset
preservation were left as candidates for Tranches 2 and 3, where they would
have to compete with other 22 road sections requiring improvement or
rehabilitation.
9. Table 8.1.2 shows the long list of road sections for asset preservation
distributed to Tranche 1 for priority projects and the remaining to Tranches 2
and 3. On the other hand, Table 8.1.3 shows the longlist of road sections
proposed for improvement or rehabilitation.
10. However, in the later part of negotiation with ADB, after cost estimates
were distributed by Tranche, three (3) additional roads were accommodated for
Tranche 1 under the ”Design-and-Build” scheme in view of the availability of
excess programmed funds for Tranche 1 due to reduction of scope of civil works,
since a significant length of sections (distributed among the 8 roads) were later
found out to be already improved by the Regional and District Engineering
Offices of the DPWH. The additional three (3) road sections for asset
preservation under Tranche 1 are: 1) Dumaguete North Road (Manjuyod-La
Libertad Section); 2) Dumaguete North Road (La Libertad-Vallehermoso
Section); and 3) Butuan-Cagayan de Oro City-Iligan Road (Agusan del Norte
Section), which was later separated from the whole Butuan-Cagayan de Oro
City-Iligan Road project. Therefore, the remaining roads for asset preservation
as candidates for Tranches 2 and 3 were again reduced to 7 roads. The total 11
road sections under Tranche 1 was divided into three (3) contract packages.
11. The map showing the location of road projects under Tranche 1 is
presented in Figure 8.1-1.
Table 8.1.2
PROPOSED ASSET PRESERVATION PROJECTS
HDM-4 Recommendation
Total Length
Projects Region Province NPV/C Costs (PM) Ranking Remarks
(km) Asphalt Overlay Reconstruction Good
(km) (km) (km)
TRANCHE 1
2 Olongapo-Bugallon Road III Zambales 140.96 91.42 8.34 41.20 7.51 946.21 13 CP-2
5 Iloilo-Capiz (Old Route) VI Iloilo 11.82 8.80 2.11 0.90 29.83 126.86 2 CP-4
Butuan-Cagayan del Oro City-Iligan Road X Misamis Oriental 21.19 17.11 3.47 0.61 51.95 375.89 1 CP-5
6
Butuan-Cagayan del Oro City-Iligan Road * Design
XIII Agusan del Norte 16.16 9.84 5.55 0.77 12.26 212.17 10
(Agusan del Norte 1st Leg. District) and Built
7 Bukidnon-Cotabato Road XIII Cotabato 47.61 34.90 - 12.71 8.72 193.87 12 CP-6
8 Dipolog-Oroquieta City road IX Zamboanga del Norte 49.15 17.75 - 31.40 8.88 100.43 11 CP-7
Dumaguete North Road VII Negros Oriental 50.71 16.31 25.56 8.84 15.16 509.30 7
CP-8
9 Dumaguete North Road VII Negros Oriental 6.25 2.94 3.31 - 13.83 73.73 9 (Design
and Built)
Dumaguete North Road (Jct. Kabankalan-
VII Negros Oriental 57.63 13.44 4.23 39.96 7.37 20
Negros)
TRANCHES 2 & 3
1 Bigaa-Plaridel via Bulacan & Malolos Rd III Bulacan 22.08 10.00 3.11 8.97 14.98 123.08 8
2 Siquijor Circumferential Road VII Siquijor 71.80 51.32 13.88 6.60 5.99 503.26 21
3 Sindangan-Liloy Road IX Zamboanga del Norte 28.00 17.70 6.51 3.79 5.67 204.28 15
5 Dipolog-Sindangan-Liloy Road IX Zamboanga del Norte 82.05 70.83 7.84 3.38 3.02 478.09 19
6 Famy-Infanta-Dinahican Port Road IV-A Quezon 37.05 12.11 13.04 11.90 2.60 252.01 21
7 Manila-Batangas (Malvar-Lipa Road) IV-A Batangas 25.24 8.91 5.81 10.52 29.79 343.38 3
8 Iloilo-Capiz (Old Route) VI Iloilo 30.74 21.05 1.98 7.71 27.03 185.02 4
9 Palico-Balayan-Batangas Road IV-A Batangas 53.32 18.39 7.79 27.14 21.62 275.63 5
10 Toledo-Pinamungahan Road VII Cebu 26.74 24.61 1.91 0.22 2.41 160.60 22
11 Gapan-Fort Magsaysay Road III Nueva Ecija 24.43 8.88 11.42 4.13 1.21 274.40 24
12 Ormoc-Baybay-Southern Leyte Bdry. Road VIII Leyte 23.21 7.31 3.17 12.73 1.12 100.37 25
13 Palompon-Isabel-Merida-Ormoc Road VIII Leyte 77.76 24.15 0.76 52.85 0.96 137.32 26
14 Liloy-Ipil IX Zamboanga Del Norte 30.73 18.68 7.84 4.21 0.94 204.29 27
15 Ormoc-Baybay-Southern Leyte Bdry. Road VIII Leyte 67.16 31.50 - 35.66 0.85 159.29 28
Table 8.1.3
LONGLIST OF PROPOSED ROAD IMPROVEMENT PROJECT
Length
Projects Province
(km)
8 San Nicolas - Natividad San Quintin - Umingan - Guimba Road Pangasinan / Nueva Ecija 23.50
21 Mindanao East - West Lateral (Sta. Filomena - Ticlaan Section) Iligan / Bukidnon 75.00
TOTAL 1,328.65
Figure 8.2.1.2
Figure 8.2.1.3
Figure 8.2.1.4
Figure 8.2.1.5
elevations ranging from 3 to 36m except the last 1.85km where it is abutted by
hill and in rolling terrain.
Scope of Civil Works
Asset Preservation:
80 mm thick AC Overlay; Length = 14.86 kms, Width = 6.70 m
Improvement of Shoulder, pavement markings, repair of distressed PCCP and
miscellaneous works as needed
Figure 8.2.1.6
27. The 58.23 km road project is located in Central Visayas Island, Region VIII,
in the Province of Negros Oriental under the 1st District Engineering Office
(Figure 8.2.1.7). The road starts at km 50.742 of the district engineering
boundary in the town of Manjuyod, traversing in a northerly direction passing
about four (4) towns and ends at km 108.967 in La Libertad municipality before
approaching Pisong Bridge. The terrain of the project area is relatively flat to
gently rolling along the coastal of Tanon Strait. The existing 2-lane pavement
comprises of 27.50 km PCCP with 6.10-6.70m width and 30.73 km ACP having
6.10 m width. The DPWH’s 1st Engineering District has about 8.49 km on-
going/scheduled road sections for improvement and which is considered an
exception. The conceptual design of the project road will consist of 25.68 km
AC overlay, 20.16 km reconstruction and an exception of 12.39 km.
Scope of Civil Works (Per Conceptual Design)
Asset Preservation:
50-100 mm thick AC Overlay; Length = 25.68 km, Width = 6.70 m
Improvement of Shoulder, pavement markings, repair of distressed ACP/PCCP
and miscellaneous works as needed
Reconstruction:
230 mm PCCP, 200 mm Aggregate Subbase; Length = 20.16 km, width 6.70m
Figure 8.2.1.7
Figure 8.2.1.8
Figure 8.2.3.1
Lot 3.3: Butuan-Cagayan del Oro City-Iligan Road (Agusan del Norte)
Butuan-Cagayan de Oro City-Iligan Road (Agusan del Norte) (Butuan City,
CARAGA Region) Km 1232.91 – Km 1265.00 (Length = 32.09 kms including
bridges, with exceptions).
33. The 32.09 kms project road is situated in the island of Mindanao, Region
XIII (CARAGA region) (Figure 8.2.3.3). It starts at km 1232.91 in Butuan city
junction with the Pan-Philippine Highway, now known as the Philippine-Japan
Friendship Highway passing the towns of Buenavista and Nasipit, then ends at
km 1265.00 in Aclan, Carmen. The first road section of about 15.54 kms with
varying travel width from 6.10m to 12.60m, is envisaged as a 4-lane concrete
pavement undivided dual carriageway in the city proper of Butuan. There are
on-going road construction in this first section under the Butuan City
Engineering District and therefore considered the first section as exception in
the project. The remaining concrete surfacing in the outskirt of Butuan up to
Carmen municipality under Agusan del Norte District Engineering Office is a 2-
lane, 6.10m width carriageway and considered for AC overlay. The alignment
traverses a westerly direction in a relatively flat terrain. The project road will
consist of 16.42 km AC overlay and exception of 15.66 km.
Figure 8.2.3.2
Figure 8.2.3.3
Figure 8.2.3.4
Table 8.4.1
ADB TA 7093-PHI - PREPARING THE PHILIPPINES ROAD SECTOR IMPROVEMENT PROJECT
ASSET PRESERVATION UNDER TRANCHE I
#REF!
LENGTH
CP NO. NAME OF ROAD PROVINCE REGION WORK DESCRIPTION
KM.
(1) (2) (3) (4) (5) (6)
30.9 km AC Overlay
LOT 1.1 - BAUANG - BAGUIO ROAD 30.978 LA UNION/ BENGUET I and CAR 80 m reconstruction
8.17 km exception
CP - I
54.24 km for 50 mm thick AC Overlay
LOT 1.2 - OLONGAPO - BUGALLON
65.549 ZAMBALES 3 2.94 km for 100 mm thick AC Overlay
ROAD
8.37 km for 125 mm thick AC Overlay
40. The unit rates (refer to Table 8.5.1) are based on the material cost for the
first quarter of 2009. The methods adopted and the bases how these unit costs
were arrived at are discussed below:
TABLE 8.5.1 UPDATED UNIT RATES FOR THE EIGHT PROJECTS OF ASSET PRESERVATION
(Total Unit Cost)
CP‐1 CP‐2 CP‐3A CP‐3B CP‐4 CP‐5 CP‐6 CP‐7
PAY
DESCRIPTION UNIT
ITEM Bauang-Baguio Olongapo- Palo-Carigara- Daang Maharlika Iloilo-Capiz Butuan-Cagayan de Bukidnon- Dipolog-Oroquieta
Road Bugallon Road Ormoc Road Road (Old Route) Oro City Road Cotabato Road City Road
101(3)a REMOVAL OF EXISTNG AC PAVEMENT sq.m. ‐ 45.85 ‐ 47.46 48.30 46.05 ‐ 46.61
101(3)b REMOVAL OF EXISTNG PCC PAVEMENT sq.m. 410.07 ‐ 413.23 ‐ ‐ ‐ ‐ ‐
CRACK AND SEAT OF EXISTING PCCP
101(3)c sq.m. 716.98 687.43 733.63 735.97 737.83 703.75 741.83 695.10
(with asphalt leveling course)
105 SUBGRADE PREPARATION sq.m. 28.19 27.38 28.38 28.38 28.91 27.51 28.78 27.85
200 AGGREGATE SUBBASE COURSE cu.m. 635.12 606.84 641.28 ‐ 654.18 ‐ ‐ ‐
202 CRUSHED AGGREGATE BASE COURSE cu.m. 1,109.09 817.14 954.14 957.66 973.63 830.63 ‐ ‐
300(2) AGGREGATE SURFACE COURSE cu.m. ‐ 836.83 ‐ ‐ 994.68 850.68 1,179.27 862.56
301(1) BITUMINOUS PRIME COAT, CUT‐BACK ASPHALT MC‐70 tonne ‐ 61,680.02 68,291.43 68,291.43 66,932.87 64,772.38 66,062.92 ‐
302(2) BITUMINOUS TACK COAT, EMULSIFIED ASPHALT SS‐1 tonne 60,891.04 59,590.02 66,159.17 66,159.17 64,784.42 62,671.01 63,918.19 58,604.81
BITUMINOUS CONCRETE SURFACE WEARING COURSE,
310(1)a sq.m. 640.99 603.83 673.82 678.11 667.69 633.63 677.53 602.61
HOT LAID (50mm thick)
BITUMINOUS CONCRETE SURFACE WEARING COURSE,
310(1)b sq.m. 1,023.21 963.81 ‐ 1,082.59 1,065.85 1,011.50 ‐ 961.83
HOT LAID (80mm thick)
BITUMINOUS CONCRETE SURFACE WEARING COURSE,
310(1)c sq.m. ‐ ‐ ‐ ‐ 1,368.08 ‐ 1,387.57 ‐
HOT LAID (100mm thick)
BITUMINOUS CONCRETE SURFACE (LEVELING) COURSE,
310(2) sq.m. ‐ ‐ ‐ ‐ 568.05 ‐ ‐ ‐
HOT LAID (50mm thick)
311(1)b PCC PAVEMENT (PLAIN), 200mm thick sq.m. 1,096.58 ‐ 1,033.15 ‐ ‐ ‐ ‐ ‐
SPL 312 SEALING OF CRACKS AND JOINTS ON EXISTING PCCP l.m. 109.10 110.70 114.34 114.34 114.58 110.09 113.15 106.72
SPL 313 PATCHING OF POTHOLES sq.m. 1,283.01 1,227.02 1,344.19 1,352.49 1,334.63 1,270.39 1,352.71 1,211.08
REFLECTORIZED THERMOPLASTIC PAVEMENT MARKING
612(1) sq.m. 864.06 903.09 859.42 859.42 874.86 858.85 869.80 866.57
(White)
REFLECTORIZED THERMOPLASTIC PAVEMENT MARKING
612(2) sq.m. 871.26 910.29 866.62 866.62 882.06 866.05 877.00 873.77
(Yellow)
715(8)1 GEOTEXTILE PAVING FABRIC WITH GLASS sq.m. 655.40 670.82 653.13 653.13 655.58 656.76 654.60 ‐
REINFORCEMENT
Concrete re-blocking and AC overlay. The work will consist of breaking and
removing the damaged blocks, then placing a new PCC pavement before AC
overlay. The scope of this work may consist of the following:
(1) Breaking the affected concrete blocks into pieces.
(2) Removing the broken pieces and disposing the debris.
(3) Replacing the existing sub-base if they failed to meet required tests.
(4) Subgrade preparation if sub-base passed the required tests.
(5) Paving with new concrete for the removed portion with provision of
steel bar ties between the new and the old pavements.
(6) Application of Tack Coat.
(7) Paving of AC for the whole section scheduled for AC overlay.
Using paving fabric and AC overlay - for a stretch of existing concrete
pavement with longitudinal and transverse cracks but no base failures,
47. From the above schemes considered, the following options depending on
the existing condition of pavement, are recommended:
Scheme A2 - PCCP Reconstruction with AC Overlay when the pavement upon
investigation shows severe deterioration, severe cracking and settlement.
Reconstruction for asset preservation is limited only to 20% in cost of the
total project cost.
Scheme A3 - AC Overlay with Paving Fabric AC Overlay. To be used when
longitudinal and transverse cracks are appearing but no base failure. AC
Overlay with Paving Fabric – As mentioned in the pavement design is one of
the measures in controlling reflective cracking. It mitigates surface reflective
cracking problems at the same time the fiber acts as waterproofing
membrane in sealing crack areas against possible water intrusion which will
weaken the road foundation. Installation is faster and that overlay can be
done even in lean hours in the night to avoid traffic problems.
Scheme A3-1 - Crack and Seat and AC overlay – Cracking and seating is
another way of preventing reflective cracking in the hot mix asphalt concrete
9.1 Introduction
1. In accordance with the Terms of Reference (TOR) of the Technical Assistance
(TA), the Consultants study team selected and designed eight (8) national road
sections for specific periodic maintenance works and three (3) national roads for
”design-and-build’ scheme based on maximum economic return and minimum
negative environmental and social impacts. The road sections were selected
from the long list provided by the DPWH. Periodic maintenance, as defined in
the concept paper prepared by DPWH, involves asphalt overlay and re-blocking
of cracked concrete pavement.
3. It was concluded that the most cost-effective approach for asset preservation
was to optimize the use of existing pavement structures by adding layer (AC
overlay) to increase its structural strength and to remedy functional deficiency.
This approach requires the evaluation of the existing pavement and determining
(a) the section for reconstruction and (b) the overlay section.
4. As part of the Philippine Government’s assistance to the TA, the Planning
Services extended their full assistance in gathering related documents and the
respective District Engineering offices furnished the Consultants substantial data
of the existing roads which was reflected in the contract drawing.
5. The Consultants hired the services of Renardet S.A Consulting Engineers for
the roughness survey at 100 meters interval on both direction of the travelway
which was completed on March 12, 2009. The roughness index has been used
in the economic evaluation of each road. Pavement investigation at 500 meters
interval involving measurement of pavement layer thicknesses, determination of
subgrade CBR and taking core samples of ACP/PCCP for strength test was
carried out by three (3) independent geotechnical companies to complement
available information already provided by the DPWH. The investigation was
completed on March 7, 2009 and the results were used in the pavement
analysis. The traffic data obtained from DPWH’s Planning Services have been
used to estimate the amount of traffic and the cumulative number of equivalent
standard axles that will pass through the road over the 10 years design life.
6. All the data collected was tabulated and analyzed for each project road to
depict the variation in conditions along the project roads. Homogenous sections
within which the various parameters are relatively uniform have been identified
and defined the specific pavement treatment.
7. A separate report for roughness survey, pavement investigation and
pavement design will be submitted to the Bureau of Design (BOD), DPWH and
the ADB.
11. The detailed design methodology and pavement design for the eight (8)
road sections which forms part of the pavement design report mentioned in
paragraph 7 will be submitted separately.
12. In brief, below is the outline in determining the design thickness of rigid
and flexible pavement structures for reconstruction.
SN ol = a o1 * D o1 = SN f – SN eff
D o1 = (SN f – SN eff )/ a o1
Where:
SN ol = Required overlay structural number
a o1 = Structural coefficient for the AC overlay
D o1 = Required overlay thickness, inches
SN f = Structural number required to carry future traffic
Effective structural number of the existing
SN eff =
pavement
D o1 = A(D f – D eff )
Where:
14. The A factor, which is a function of the PCCP thickness deficiency, is given
by the following equation.
A = 2.2233 + 0.0099 (D f – D eff )² - 0.1534 (D f – D eff )
15. The effective thickness of the existing slab (D eff ) is computed from the
following equation:
Where:
D = existing PCC slab thickness, inches
F jc = joints and cracks adjustment factor
F dur = durability adjustment factor
F fat = fatigue damage adjustment factor
(3) The thickness of AC overlay over combined Flexible and Rigid Pavement
to increase structural capacity to carry future traffic demand is
determined by the following equation:
D o1 = A(D f – D eff )
Where:
D o1 = required thickness of AC overlay, inches
A= factor to convert PCC thickness deficiency to AC
overlay thickness
Df = slab thickness to carry future traffic, inches
D eff = effective thickness of existing slab, inches
16. The A factor, which is a function of the PCCP thickness deficiency, is given
by the following equation.
17. The effective thickness of the existing slab (D eff ) is computed from the
following equation:
Where:
D p = existing PCC slab thickness, inches
Da = existing AC slab thickness, inches
F jc = joints and cracks adjustment factor
F dur = durability adjustment factor
F ac = quality adjustment factor
Table 9.4.1
ADB TA 7093-PHI - PREPARING THE PHILIPPINES ROAD SECTOR IMPROVEMENT PROJECT
ASSET PRESERVATION UNDER TRANCHE I
#REF!
LENGTH
CP NO. NAME OF ROAD PROVINCE REGION WORK DESCRIPTION
KM.
(1) (2) (3) (4) (5) (6)
30.9 km AC Overlay
LOT 1.1 - BAUANG - BAGUIO ROAD 30.978 LA UNION/ BENGUET I and CAR 80 m reconstruction
8.17 km exception
CP - I
54.24 km for 50 mm thick AC Overlay
LOT 1.2 - OLONGAPO - BUGALLON
65.549 ZAMBALES 3 2.94 km for 100 mm thick AC Overlay
ROAD
8.37 km for 125 mm thick AC Overlay
Figure 9.5-1
Figure 9.5-2
Table 9.6.1
ADB TA-7093-PHI - PREPARING ROAD SECTOR IMPROVEMENT PROJECT, ASSET PRESERVATION UNDER TRANCHE 1
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
ACTIVITY
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Loan Processing
EA's recruitment of supervision consultants AP-1
Supervision Consultants Services
Procurement of Tranche 1 Civil works
Implementation of CW Tranche 1
Tranche 2 Processing
Tranche 3 Processing
Package 1 - LUZON
Package 2 - VISAYAS
Package 3 - MINDANAO
4. Combining the Dipolog-Oroquieta Road with the other Road Sections within
the Mindanao Group of Island (Butuan-Cagayan de Oro City-Iligan Road and
Bukidnon-Cotabato Road) in one contract package would be impractical
considering their remoteness from each other, thus, might incur difficulty in
closely monitoring the Works.
12. This Section consist of provisions that are specific to each prequalification
and supplement the information or requirements included in Section I,
Instructions to Applicants.
13. This Section contains the evaluation factors, methods and criteria to be used
to determine how Applicants shall be prequalified and later invited to bid.
14. This Section contains the forms for the Application Submission Sheet and all
the forms required to be submitted with the Application.
17. A minimum of 60 days shall be given to the Applicant to study and prepare
complete and responsive Applications.
19. For Road Sections whose bidding will be conducted thru International
Competitive Bidding, the Sample Bidding Documents for Procurement of Works
are used following ADB Guidelines and adopting the single stage-one envelope
procedure (without prequalification). The bidding rules and procedures of ADB will
govern the bidding process as well as the relevant procedures for open
competitive bidding as specified in the latest amended IRR of R.A. 9184, to the
extent it is consistent with ADB’s procurement procedures.
20. For Road Sections to be procured using either NCB or ICB with Design and
Build Scheme, corresponding Sample Bidding Documents as cited under items 8
and 9 above is used with some modification to conform with Annex “G”
(Guidelines for the Procurement and Implementation of Contracts for Design
and Build Infrastructure Projects) of the latest Implementing Rules and
Regulations of Republic Act No. 9184 to the extent it is consistent with ADB’s
procurement procedures.
4. The inputs to the HDM-4 system include the properties of the existing road
network, with the varying surface types, conditions, lengths, AADTs,
construction and maintenance unit costs, vehicle operating costs, right-of-way
acquisition costs; and the cost of mitigation measures for all identified
probable adverse environmental impacts of road improvement/construction.
5. Basically, the HDM-4 model is fit for assessing the traffic benefits for all the
“traffic” subproject roads. However, “developmental” road projects are not
subjected to HDM-4 runs in view of the different approach and methodology
considered in assessing normal and generated traffic benefits accruing from
the improvement/construction of these roads. Manual calculation is therefore
undertaken in this case. However, considering that the project roads are
already existing and are mainly considered for asset preservation, therefore,
no developmental benefits are expected to accrue.
6. The HDM-4 model was utilized mainly for economic evaluation of the
different maintenance work alternatives for the roads proposed for asset
preservation under Tranche 1. However, for the preliminary evaluation of
roads proposed for the succeeding phases of the project under Tranches 2 and
3, considering the limited time available, the more simplified spreadsheet
model known as “ECOVAL”, the earlier developed economic evaluation tool
during the conduct of road feasibility studies in DPWH, was used.
a. Traffic Projection
7. The study team established the base year traffic by road project, the
source of data of which mainly came from the DPWH central database.
However, the available traffic data from DPWH is as of 2008, this was then
projected to 2009 base year estimates by applying the established traffic
growth rates. The equivalent standard axle load (ESAL) factors utilized are
likewise those established by the DPWH as a result of loadometer surveys
undertaken in 2008.
PRIVATE TRANSPORT
2000-2006 7.4 3.0 4.3 3.0 3.0 4.5 4.2 3.0 4.0 2.6 2.0 3.5 3.5 2.2 2.0 2.0
2006-2012 7.5 5.5 5.7 3.2 3.2 6.2 4.4 3.0 4.0 4.0 2.5 3.5 3.5 1.5 2.0 2.0
2018-2024 4.8 4.5 4.0 2.5 2.5 3.5 2.0 2.5 2.5 2.0 1.5 2.0 2.0 2.5 3.0 3.0
PUBLIC TRANSPORT
2000-2006 7.0 6.6 7.0 6.4 6.4 5.5 6.0 4.5 6.4 4.5 4.5 6.3 6.3 6.0 4.2 4.0
2006-2012 7.0 8.0 7.0 7.2 7.2 5.0 5.0 4.0 7.2 5.0 5.0 5.9 5.9 4.5 4.5 4.5
2012-2018 6.5 7.5 6.0 6.3 6.3 4.5 4.5 3.5 6.3 4.5 4.5 4.5 4.5 3.5 4.5 4.5
2018-2024 6.1 5.3 5.0 5.3 5.3 4.0 4.0 3.0 5.3 4.0 4.0 4.0 4.0 4.0 4.0 4.0
FREIGHT TRANSPORT
2000-2006 4.3 5.7 6.3 4.3 4.3 5.2 5.1 3.6 4.3 3.5 4.0 3.7 3.7 4.5 3.6 4.1
2006-2012 5.4 6.6 6.5 4.8 4.8 5.6 4.8 4.7 4.8 4.0 4.5 3.5 3.5 3.4 3.6 4.5
2012-2018 4.9 6.0 5.9 4.3 4.3 5.0 4.3 4.5 4.3 3.5 3.5 2.7 2.7 2.6 5.0 5.0
2018-2024 3.8 4.2 4.2 3.7 3.7 3.9 3.6 3.7 3.7 3.1 3.1 2.5 2.5 3.0 4.4 4.0
NOTE: 1) NCR = National Capital Region; CAR = Cordillera Administrative Region; ARMM = Autonomous Region of Muslim Mindanao
2) The resulting Traffic Growth Factors arrived at through the formula were adjusted based on the
actual traffic growth trends in different regions.
3) The user is encouraged to interpolate between time periods given to arrive at Traffic Growth Rates for individual years.
Road Sector Institutional Development and Investment Program (RSIDIP):
11-3
Final Report
Road Sector Institutional Development and Investment Program (RSIDIP):
Final Report
c. Cost-Benefit Analysis
10. The purpose of an economic appraisal of road projects is to determine
how much to invest and what economic returns to expect. The size of the
investment is determined by the costs of construction and annual road
maintenance. The economic returns are mainly in the form of savings in road
user costs due to the provision of a better road facility.
11. The economic evaluation process in HDM-4 is based on generated annual
cost streams for road construction, road maintenance and road user costs.
The cost streams will usually begin in a specified base year, onwards
throughout the entire analysis period usually chosen to equal the design life of
new road pavements.
12. The cost of new road construction is calculated from the sum of site
preparation, earthworks, pavement construction, bridge and drainage
structures, and overheads. The annual cost of road maintenance works
depends on the maintenance policy or specified standard and the predicted
pavement condition. The applied maintenance may range from routine
maintenance to full reconstruction. Routine maintenance includes activities
which are required regardless of the overall condition of the road or the traffic
level, i.e., grass cutting, road sign repairs, drainage clearance, etc. and
maintaining localized failures. HDM-4 calculates the quantities of the various
work activities which are multiplied by the specified unit cost of each activity,
in either economic or financial terms to derive the maintenance costs.
13. Road user cost may be defined as costs incurred by vehicle operators and
by the traveling public, which are specified in HDM-4 as economic rather than
financial costs. Road user costs consist of vehicle operating costs, time costs
and accident costs.
14. The economic analysis was performed on “with” and “without” project
scenarios. The difference in vehicle operation costs between these scenarios
is the expected benefits accruing from the road investment. Basically HDM-4
model normally quantifies the road user cost savings to normal traffic. Normal
traffic is referred to as the traffic demand, which results from the natural
growth in population and economic activities within the influence area of each
project road. Other types of quantifiable benefits, which are separately
inputted to the model after separate manual calculations, include generated
traffic benefits as a result of the opportunity for faster, cheaper, more
comfortable and reliable transport between the areas served; diverted traffic
benefits or the savings realized by the traffic that is presently using other
roads or other modes of transport upon diversion to the improved project
road; and development benefits which may be in the form of net value added
in agriculture or induced production increases. However, for the analysis of
the project roads under Tranche 1, only the road user cost savings to normal
traffic was calculated.
19. The first Tranche of the project involves the evaluation and detailed
design of selected project roads for asset preservation or periodic
maintenance.
21. The said engineering survey was undertaken for the purpose of providing
updated and more accurate engineering data as basis for the detailed
engineering design to be undertaken for Tranche 1 road projects. Particularly,
the various input data necessary for updating include, among others, the
required pavement thickness, the road roughness (IRI) values and the current
road surface types and conditions. Upon completion of this survey, economic
evaluation using HDM-4 model was undertaken.
12.1 Introduction
1. Initial Environmental Examination (IEE) has been conducted for all 11
subprojects of Tranche 1. According to ADB guidelines, the Project can be
categorized as environment category “B” for environmental assessment.
According to Philippine Environmental Guidelines, the subprojects can be
categorized as either Group II or III. Hence, IEE report is prepared to meet the
requirements of both the ADB and the government. The IEE is prepared as a
stand alone document and enclosed with the draft final report. The summary
initial environmental examination is also prepared for the Project and presented
as ‘Annex C’ of the IEE report.
12.2 Methodology
2. The following procedure has been adopted to examine the detailed baseline
environment and assess the possible environmental impact on the physical,
ecological and socio-economic resources that could result due to the
implementation of the Project:
• Field visits to all the road projects by the environmental specialists;
• Preparofation environmental database of all subprojects through detailed
review and analysis of available spatial maps for all environmental
parameters;
• Review of proposed civil works such as overlay, reconstruction and
maintenance for each road project;
• Review and analysis of reports and field data collected from the previous
road projects;
• Discussion with various stakeholders;
• Assessment of the present environmental scenario and identification of the
impacts of the proposed project;
• Addressing critical problems, considering technical, financial and
institutional factors; and
• Preparation of an environmental management and monitoring plan, and
mitigation measures.
3. An environmental data base consisting of the following information has been
prepared for each road project.
• Terrain – minimum and maximum elevations, steep slope areas, sensitive
side slopes susceptible to landslide and rock fall.
• Climate – mean annual temperature and mean annual rainfall.
• Soils – soil group, texture, drainage, and sand fraction (a function of soil
erodibility).
• Geology – geology, geomorphology and hydrogeology.
• Streams – total streams, watershed, names of major rivers
12.7 Conclusions
11. Based on the results of the IEE, the Project will not generate significant
environmental impacts provided the mitigation measures detailed in the IEE are
implemented appropriately. Based on the requirements of the Government of
Philippines and ADB, there are no further environmental studies required for the
proposed Tranche 1 road projects.
10. The project area covers the Provinces of Zambales and Pangasinan.
11. Zambales is located in the Central Luzon region. Its capital is Iba.
Zambales borders Pangasinan to the north, Tarlac and Pampanga to the east,
and Bataan to the south. The province lies between the South China Sea and
the Zambales Mountains. With a land area of 3,700 km, Zambales is the second
largest among the seven provinces of Central Luzon. It has a population density
of 170 people per square kilometer, one of the lowest in the country. The
province is noted for its mangoes, which are abundant from January to April.
12. The Aetas of Mount Pinatubo were the earliest inhabitants of what is now
the province of Zambales. They were later displaced by the Sambal, an
Austronesian people after whom the province is named. Many Sambal still
believe in superstitions and mysteries that have been handed down through the
generations. The Sambal, the Tagalogs, the Ilocanos, and the Kapampangans
today constitute the four largest ethnic groups in Zambales; these identities
may and do, however, overlap with one another due to intermarriage and other
factors. Most of the people of southern Zambales are migrants from different
parts of the country owing to the influx of job opportunities brought on by the
U.S Subic Naval Base (San Antonio and Subic) during the American regime of
the country. Many people found jobs and permanently settled there. The
presence of the Americans greatly influenced the inhabitants, from their tastes
in food, clothing, and style.
13. Zambales is a rich source of nickel and chromite. Zambales hosts 173
kilometers of beaches, with coral reefs, dive spots, surfing areas, hotels and
day-use beach huts. The province is approximately a 3 to 4 hour drive from
Manila, though this can vary greatly with traffic. The "Fiesta Poon Bato," (literal
translation is Feast of the Sacred Stone) held in January, is a religious festival
that attracts over half a million people each year. The festival venerates Ina
Poon Bato (literal translation is Mother of the Sacred Stone) also known as
Nuestra Senora de la Paz y Buen Viaje (Our Lady of Peace and Good Voyage),
the oldest known image of the Virgin Mother in Asia. The Barrio of Poon Bato
located in the Botolan, that is host to the image and the fiesta, was completely
destroyed during the 1991 Mt. Pinatubo eruption. The icon was saved and
moved, along with the barrio inhabitants, to nearby Loob Bunga Resettlement
Area. The "Mango Festival" is held in the provincial capital of Iba every April,
and the "Domorokdok" (Sambal word for Dance) Festival is held each May in
Botolan. These include street dancing, agricultural shows, competitions like
sand castle building and "bikini open" beauty pageants.
14. Pangasinan is located on the west central area of the island of Luzon along
the Lingayen Gulf. The provincial capital is Lingayen. The total land area of
Pangasinan is 5,368.82 square kilometers. According to the latest census, it has
a population of 2,645,395 people in 477,819 households. The total population is
projected to rise to 3,039,500 in 2010. The province is 170 kilometers north of
Manila, 50 kilometers south of Baguio City, 115 kilometers north of Subic
International Airport and Seaport, and 80 kilometers north of Clark International
Airport.
15. Pangasinan is famous for the Hundred Islands National Park. This is a
marine park located off the coast of Alaminos City in the Lingayen Gulf and is
composed of some 123 islands, most of which are quite small and uninhabited.
The 1200 megawatt Sual Coal-Fired Power Plant, and the 345 megawatt San
Roque Multi-Purpose Dam are located in Pangasinan. Pangasinan has extensive
areas devoted to salt making and aquaculture along the coasts of Lingayen Gulf
and South China Sea. Pangasinan is a major producer of rice, mangoes, and
bamboo crafts. Pangasinan occupies a strategic geo-political position in the
central plain of Luzon, known as the rice granary of the Philippines. Pangasinan
has been described as a gateway to northern Luzon and as the heartland of the
Philippines.
16. The province is a major fish supplier in Luzon, and a major producer of salt
in the Philippines. It has extensive fishponds, mostly for raising bangus or
"milkfish," along the coasts of Lingayen Gulf and South China Sea. Pangasinan's
aquaculture includes oyster and sea urchin farms. The major crops in
Pangasinan are rice, mangoes, corn, and sugar cane. Pangasinan has a land
area of 536,819 hectares, and 44 percent of the total land area of Pangasinan is
devoted to agricultural production. The 1200 megawatt Sual Coal-Fired Power
Plant, 345 megawatt San Roque Multi-Purpose Dam, the Northern Cement
Corporation, are located in Pangasinan. It has export earnings of around $5.5
million and has 593 banking and financing institutions. It has a labor force of
about 1.52 million, and 87 percent of the labor force is gainfully employed.
17. The project area of the project road covers the whole Province of Leyte.
Leyte is located in the Eastern Visayas region with a total land area of 5,901.5
sq. km. Its capital is Tacloban City and occupies the northern three-quarters of
the island of Leyte. Leyte is located west of Samar, north of Southern Leyte and
south of Biliran. To the west of Leyte across the Camotes Sea is the province of
Cebu.
18. The total population of the province as of census year 2007 is 1,544,251.
The people of Leyte are divided into two main groups, primarily by language. In
the west and south are the Cebuanos, while in the north and east are the
Waray-Waray. The Cebuanos have ties with Cebu, the most populous province
in the Visayas; the Warays are more tied to Leyte and Samar.
19. Leyte is subdivided into 40 municipalities and three cities, two of which are
administratively independent of the province. The municipalities are clustered
into 6 congressional districts. Ormoc City is an independent component city,
while the capital Tacloban was declared a highly-urbanized city in 2008. Both
cities govern themselves independently of the province and their residents do
not vote for elective provincial officials. Baybay attained cityhood in 2007 but
reverted to its municipal status when the Supreme Court declared its city
charter unconstitutional in 2008; however, Baybay would regain its city status
following the reversal of the Supreme Court decision dated December 22, 2009.
20. The economy of Leyte depends on agriculture. Rice is farmed in the lower
flatter areas specifically those around Tacloban, while coconut farming, for
coconut oil is the main cash crop of the more mountainous areas. Fishing is
also a major source of livelihood among residents. The province is the site of
the largest geothermal plant in Asia, making it one of the resource-rich
provinces of the Philippines.
23. Iloilo province is located in the Western Visayas region. Iloilo occupies
the southeast portion of Panay Island and is bordered by Antique to the west
and Capiz and the Jintotolo Channel to the north. Just off Iloilo's southeast coast
is the island of Guimaras, once part of Iloilo but now a province in its own right.
Across the Panay Gulf and Guimaras Strait is Negros Occidental. Iloilo's capital
is Iloilo City. The Province of Iloilo is the largest marshland in Western Visayas
after the Sanderbans. The province is divided into two distinct geographic
regions; the highlands of the Madia-as on the western border and the lowland
plains which account for a larger portion of the province. Small islands east of
its northernmost tip also dot the Visayan Sea - of these, Pan de Azucar and
Sicogon are well-known. Iloilo is subdivided into 42 municipalities, 1 component
city, and 1 highly urbanized city of Iloilo.
24. As of census year 2007, the province has a total population of 1,691,878.
People from Iloilo are called Ilonggos. There are two local languages spoken in
the province: Hiligaynon sometimes called Ilonggo, and Kinaray-a. Hiligaynon
and variants of it are spoken in Iloilo city and a few towns of the province.
Spanish is strictly a local language, at least in a historical way, but the number
of natural Spanish speakers have declined strongly after WWII, and due to this,
there are today many Ilonggos who do not consider it a local language.
25. Spanish architecture can be seen in old buildings in downtown Iloilo.
Chinese Merchants and Indonesians were trading with the Ilonggos long before
the Spaniards came. The ruling Spanish government encouraged these foreign
merchants to trade in Iloilo but they were not given privileges like ownership of
land. The Mestizo a class eventually was born from the intermarriages of the
locals and Chinese merchants, Spanish with the local Melayu people. They later
emerged as the ruling class of the Ilonggos.
26. Capiz province is located in the Western Visayas region. Its capital is
Roxas City and is located at the northeastern portion of Panay Island, bordering
Aklan and Antique to the west, and Iloilo to the south. Capiz faces the Sibuyan
Sea to the north. It is known for its mother-of-pearl shells that have the same
name and are used for decoration, making lampshades, trays, window doors,
etc. Capiz is known for a popular local myth of Aswang, a generic name for
ghouls, monsters and witches.
27. Dubbed as the “Seafood Capital of the Philippines”, Capiz boasts of its 80-
kilometer coastline and wide expanse of swampy lands easily converted into
fishponds. It holds one of the richest fishing grounds and a major contributor in
the aquamarine industry of the Philippines. Four big telecommunication
companies offer telegraph, telex and telephone services. There are 33 banking
institutions and 116 intermediaries operating in the province.
28. Farming and fishing are the primary sources of income of the people. The
combined natural bounty of land and sea sustain a vibrant food industry.
Primary agricultural raw products are rice, corn, coconut, sugarcane, banana
and cut flower. Apart from a surplus of agricultural products, Capiz is also a
major supplier of prawn and milk fish of the country. Other agro-industrial
harvests include blue marlin, squid, oysters, shrimp, seaweed, squid and angel
wings. Rich fish ponds attract investors to venture into prawn culture, prawn
feed manufacture, seaweed farming and the distribution and processing of other
marine products. A robust workforce of 445,246 operates with a literacy rate
of 90.5%. The agricultural sector ensures the province as one of the wealthiest
in the Western Visayas Region although progress is impeded by corruption.
29. Its relatively unexplored caves are said to have high deposits of mineral
resources such as limestone, gold and metal.
50. The province's total land area is 829,378 hectares (8,293.78 square
kilometers). It accounts for 59% of Northern Mindanao. Thirty-eight percent
(38%) is alienable and disposable. The rest is classified timberland. It also
accounts for 80 percent (80%) or 34 million metric tons of the region’s
nonmetallic mineral deposits which include high grade white and red clay, gold,
chromite, copper, serpentine, manganese, quartz and limestone deposits can
also be found in the province.
51. Based on the National Statistics Office (NSO) Census last 2000, Bukidnon
has a total population of 1,060,415. Males slightly edge the females with
546,234, accounting for about 52% of the province’s total population while
females, with 514,181, account about 48%. It is expected that by 2010, the
province of Bukidnon will have a total population of 1,344,301.
53. Del Monte Philippines, Inc. (DMPI), Lapanday Diversified Products Corp. and
Mt. Kitanglad Agri-Development Corporation are engaged in pineapple
production. Dole Philippines (Skyland) and Mt. Kitanglad Agri-Ventures, Inc. are
into banana production. DMPI is also engaged in cattle fattening. Bukidnon
Sugar Milling Corporation (BUSCO) and Crystal Sugar Milling are into sugar
milling and refining. Phil-Agro Industrial Corporation is in starch production.
Menzi Agricultural Development is in cacao production. Agaropyta Phils. Inc.,
Bukidnon Greens Inc., FP Obrero Farms and ARDEM, Inc. are in cutflower
production. Food manufacturing giants, San Miguel Foods Corp. (SMFI_PFC),
Monterey Farms Corp., Swift Foods, Inc. have intensified their contract breeding
and growing operations in the province. Valencia Rubbertex, Inc., an 80-20
Japanese-Filipino joint venture produces rubber boots and rubber shoes for
Japan.
54. Bukidnon has already assumed its role as producer and supplier of fresh
fruits and vegetables. These produce are either sold in domestic markets or
exported to Japan and other neighboring countries. Fresh pineapples, banana,
sugarcane and cutflower grown over the years are among its exports. New agri-
business industries are still growing. Even export of rubber boots and shoes, an
infant industry in the province is increasing tremendously. A wide variety of
resource-based handicrafts is extensively produced from rattan, bamboo and
wood. San Fernando is known for its rattan furniture. Bamboo baskets, wood
wares and carvings, mats and other handmade products are ideal souvenir
items.
57. The first Visayan settlers reached the town of Pikit in 1913, and since then,
Christian migrants have moved and lived in Cotabato, cohabitating the province
with the local indigenous groups. 71% of Cotabato’s population are migrants
from Luzon and the Visayas, while the remaining 18% belong to the indigenous
communities Manobo, T'boli, and Maguindanao. The major languages spoken
are Hiligaynon or Ilonggo (43%), Cebuano (31%), Maguindanao (16%), and
Ilocano (10%), but a local spanish based creole, chavacano, is spoken.
58. Over the last nine years, North Cotabato has graduated from being a
basket case to one of the Philippines most vibrant economies. In 1998,
Cotabato was listed as the 5th poorest province in the country. Early in 2006,
the National Statistics Coordination Board ranked it 39th among the countries
more progressive provinces based on the results of its most recent survey on
poverty incidence.
59. The province, since 2004, has become Region XII’s favorite investment
area. The province registered a total of P397.49 million worth of investments in
2004, ranking second (2nd) only to General Santos City. This meant a 113%
leap in investments, the biggest in the region as of February 2005 according to
DTI-12. The Cotabato Province Investment Promotion Center (CPIPC) has
recorded total investments made in the province from 2000 to 2004 at P901
million. Leading investments is the continuously expanding banana industry
with DOLE-Stanfilco standing as the biggest player, having a total investment of
P200 Million. Lapanday Global Fruits in Dallag, Arakan has a P50 million
investment, while new player AJMR promises to put in P3 billion.
60. This influx of investments has consequently opened more job opportunities
for our workers in the province. Dole-Stanfilco opened 6,346 jobs for residents
of Makilala, Magpet, and Kidapawan City, while Lapanday has provided
employment to 167 local residents. Some 3,000 jobs will meanwhile be
generated by AJMR’s operation. New jobs generated by these investments from
200 to 2004 reached 68,595 new, and making Cotabato the leading province in
job generation in the region, according to DOLE-12.
Road
Population Type of Asset
Municipality/City Income class Length in
as of 2007 Preservation
Kilometers
Road
Population Type of Asset
Municipality/City Income class Length in
as of 2007 Preservation
Kilometers
CAGAYAN DE ORO 553,966 1st Class Highly Urbanized
CITY (Capital)
P50,000,000 or more.
2 lone District
OPOL 47,187 4th class Partially Urban
2nd District P20,000,000 or more but less
than P30,000,000
2. Iloilo –Capiz Road ( Old Route), Region VI, Province of Iloilo 37.24 Asphalt overlay
3. Bauang- Baguio Road, Region CAR, Province of Benguet 39.15 Asphalt overlay
Road
Population Type of Asset
Municipality/City Income class Length in
as of 2007 Preservation
Kilometers
Road
Population Type of Asset
Municipality/City Income class Length in
as of 2007 Preservation
Kilometers
62. Based on the surveys, focus interviews and observation, the Poverty,
Gender and Ethnic analysis (ADB’s “Social Analysis for Transport Projects” 2008)
was referred to, to gain insight into the characteristics of households living in
the periphery of the identified road network as part of Tranche 1 of DPWH’s road
preservation project. The purpose of which was to find out their respective
relationship to the proposed project during the implementation of the said
project.
63. The proposed road activity will use the overlay technique to preserve the
integrity of the identified road networks as indicated by the design engineers of
the project. This activity they indicated would last only for a maximum of
twelve (12) hours and will be implemented by the District Engineers’ Road
Maintenance Division. In this context, the consequential impacts on poverty,
social and ethnicity of these activities would be minimal, thus, maintaining
generally a degree of status quo on the life-ways of all sectors of the populace
within the road areas of operation and implementation. Although, this may be
the case, the sectoral stakeholders’ analysis is done to identify the possible
minimal impacts and recommend appropriate mitigating measures. Due to this
situation, there will be no occurrence of HIV/AIDS, human trafficking and etc. as
there will be no migrant workers.
64. Likewise, the Indigenous peoples living within the road networks enjoy all
the privileges as provided by the Indigenous Peoples Rights Act (IPRA) of
1997 and monitored by the Regional National Commission of Indigenous
People. Although a minimal impact may occur, appropriate mitigating measures
are recommended (see matrix). Thus at no instance will these peoples be
disadvantage.
65. The situation of the road networks from ocular observation are generally as
follows:
66. Butuan-Cagayan de Oro-Iligan Road (urban poor/
women/disadvantaged groups). The stakeholders along the road
network starting from the town of Tagoloan entering Bugo towards the
first Barangay of Cagayan De Oro are mostly commercial. It is a four-
lane highway and is heavily travelled from those coming from Butuan
and Bukidnon. The convergence of traffic has made the road filled with
sporadic encroachments of transient vendors and informal settlers. After
the bridge, traversing the CDO river traffic is reduced to minimal and
residents in the area are generally engaged in big commercial business.
(see matrix for the stakeholders’ analysis).
67. The Iloilo–Capiz road (old route). - (rural poor/women/
disadvantaged groups). The stakeholders along this road network are
generally farmers with areas of commercial activities along the town
centers. Most people going to Roxas tend to use the route, as it is
shorter. The residents generally use the road as farm to market road.
Incidental encroachments occur in the populated areas of the town. No
incidence of households to be displaced. (see matrix for the stakeholders’
analysis).
14.1 Introduction
1. This Resettlement Framework (RF) is prepared for road sections under
Tranches 2 and 3. As mentioned in the Interim Report, Tranches 2 and 3
include road sections that, in addition to those for asset preservation in Tranche
1, also require more extensive rehabilitation and perhaps improvement. For this
Project, ADB’s policy is to negotiate one Tranche at a time; i.e., the GOP and
ADB shall only start negotiating the budget for Tranche 2 once the road projects
in Tranche 1 comes close to completion. As such the final name and number of
road sections to be included is not finalized yet.
5. Most of the road sections under the present PPTA are geographically
dispersed over the islands of Luzon, Visayas, and Mindanao making it difficult to
implement and administer. Add to this is the fact that, since it is natural for
long road alignments to cross several administrative boundaries, delineation of
institutional responsibilities would be tough.
2003 D.O. 327 “Guidelines for Land Acquisition and Resettlement Action
Plans (LAPRAPs) for Infrastructure Projects”
LAPRAP document shall describe the project,
expected impacts and mitigating measures, socio-
14.4 Bridging the Gaps between GOP Policy and ADB’s IRP
11. It is important to note that although the abovementioned legal documents
are able to address major resettlement concerns, some limitations are still
apparent with respect to compliance with the basic principles of ADB’s
Involuntary Resettlement Policy (IRP). The following paragraphs describe these
limitations.
12. Based on existing rules and regulations, each government agency has its
own mandate upon which policies are drawn out in order to achieve its goals.
These policies are mostly in the form of Department Orders and Memorandum
Circulars. With regards to exercising the power or eminent domain either
through negotiated sale or expropriation proceedings, DPWH is limited to
acquire land if the purpose is to develop infrastructure projects such as roads
and bridges, water supply, flood control, and other undertakings within its
mandate. As such, the Department has no legal personality to acquire land,
nor provide basic facilities and services for resettlement purposes, or for any
other purposes outside its mandate. In fact, Section 1.5 of D.O. No. 327
explicitly states that the concerned Local Government Units (LGUs), the Housing
and Urban Development Coordinating Council (HUDCC), National Housing
Authority (NHA), and other concerned agencies are mainly responsible for the
development of resettlement sites.
13. Since these NGAs are also servicing other line and attached agencies,
allocation of housing units to qualified beneficiaries become very cumbersome
and often results into delayed resettlement of APs. As long as there is no clear-
cut procedure in form of an inter-agency MOA between DPWH and these NGAs
or better yet an Executive Order from the President, relocation of displaced
communities will remain as a section in the RP report.
14. Section 1.6 of D.O. No. 327 states that where relocation is necessary,
“the receiving LGU (under whose political jurisdiction the relocation site will be
located) may seek assistance from the DPWH for the provision of access roads
to the relocation site, and other government agencies for the provision of basic
facilities and services”. This implies that the primary role of the Executing
Agency, which is DPWH, is just to provide the access road, while provision of
other basic social services such as water and power supply, health centers, and
access to schools, public market, and places of worship are passed on to other
government agencies. This may, to some extent be achievable in major cities
and first to second class municipalities with high Internal Revenue Allotments
(IRAs). For lower class recipient LGUs, it becomes a burden since the
competition for basic social services becomes stiffer as a result of the influx of
families to be resettled.
16. The rental subsidy equivalent to the “prevailing average monthly rental
for a similar structure of equal type and dimension to the house lost”, as
mentioned in Chapter III Section 4 of the LARRIPP is also deemed insufficient
for the affected family to find a structure of equal type and dimension because
the prevailing practice of lessors for the past few years is to require at least one
(1) month deposit and one (1) month advance. Others even require two (2) to
three (3) months advance payment. For this reason, a rental subsidy equivalent
to three (3) times the average monthly rental for a similar structure type and
dimension is recommended.
17. DPWH’s LARR Policy of 1999 is silent on the integration of resettlers into
host communities. Even the 3rd Edition (2007) of the Department’s LARRIPP did
not describe in detail procedures to be undertaken in order to organize or ready
the host communities, although it was mentioned in passing that “efforts must
be made to prepare the receiving community” in page 22, Chapter IV, referring
to cases when IPs have to be resettled outside the affected ancestral domain.
20. In these cases, resettlers as well as host populations are unfairly put in
situations they wouldn’t be in had there been efforts made to prepare both
parties for eventualities as a result of their integration into one community. To
avoid or at least minimize these type of conflicts, the following are
recommended:
22. For parcellary surveys that are contracted out, this can be corrected by
DPWH by drawing up a detailed Terms of Reference (TOR) together with a
clause in the contract that any additional budget adjustment exceeding
contingencies set, as a result of discrepancy between the submitted parcellary
survey and actual field validation shall be shouldered by the contractor. For
those conducted by DPWH, administrative sanctions and cases, as prescribed in
pertinent Department Orders must be strictly implemented.
14.5 Entitlements
23. In accordance with the DPWH resettlement policy embodied in DPWH’s
LARRIPP, 3rd Ed., Series of 2007, the application of legal doctrines with regards
to compensation to APs are outlined in Table 14.5.1 - Entitlement Matrix.
LAND More than 20% Project Affected PAF will be entitled to:
(Classified as of the total land- Family (PAF) with Cash compensation for loss
Agricultural, holding loss or Transfer of land and at 100%
Residential, where less than Certificate of Title replacement cost for
Commercial, or 20% lost but the (TCT) or Tax structures, at the informed
Institutional) remaining land Declaration (TD, request of PAFs
holding become which can be
Land valuation shall be, in
economically legalized to full
accordance with Section 5 of RA
unviable title)
8974, computed based on:
Holders of Certificates of
Land Ownership Award
(CLOA) granted under the
Comprehensive Agrarian
Reform Act shall be
compensated for land at
zonal value
Cash compensation for
damaged crops at market
value at the time of taking
Rehabilitation assistance in
the form of skills training
and simple financial
management equivalent to
the amount of P15,000.00
per family, if the present
means of livelihood is no
longer viable and the PAF
will have to engage in a
new income activity
PAF without TCT Cash compensation for
damaged crops at market
value at the time of taking
Agricultural lessors are
entitled to disturbance
compensation equivalent to
five (5) times the average
of the gross harvest for the
past three (3) years but not
less than P15,000.00
Less than 20% PAF with TCT or PAF will be entitled to:
of the total Tax Declaration Cash compensation for loss
landholding lost (TD, which can of land and structures at
or where the be legalized to 100% replacement cost at
remaining land full title). the informed request of
holding is still PAFs.
viable for use.
Valuation of compensation for
land shall be the same as
described above for PAFs
holding Transfer Certificate of
Title (TCT) or Tax Declaration
(TD, which can be legalized to
full title).
Holders of free or
homestead patents and
CLOA under CA 141, Public
Lands Act will be
compensated on land
improvements only.
Holders of Certificates of
Land Ownership Award
(CLOA) granted under the
Comprehensive Agrarian
Reform Act shall be
compensated for land at
zonal value.
Cash compensation for
damaged crops at market
value at the time of taking.
PAF without TCT Cash compensation for
damaged crops at market
value at the time of taking.
Agricultural lessors are
entitled to disturbance
compensation equivalent to
five (5) times the average
of the gross harvest for the
past three (3) years but not
less than P15,000.00
STRUCTURES More than 20% PAF with TCT or PAF will be entitled to:
(Classified as of the total Tax Declaration • Cash compensation for entire
Residential/ landholding loss (TD, which can structure at 100% of
Commercial/ or where less be legalized to replacement cost which is
Industrial) than 20% lost full title) defined as the “amount
but the necessary to replace the
remaining improvements/structures
structures no based on the current
longer function market prices for materials,
as intended or equipment, labor,
no longer viable contractor’s profit and
for continued overhead, and all other
use attendant costs associated
with the acquisition” (IRR,
R.A.8974).
25. The DPWH, in its latest LARRIP Policy recognizes that the “identities and
cultures of Indigenous Peoples are inextricably linked to their physical
environment and the natural resources on which they depend”. That is why in
the said Policy it provided comprehensive guidelines so as to ensure that
projects they implement “do no further harm to IPs and leave them worse off
with the projects than without”.
27. Shown in Table 14.5.1 is a summary of the recognized impacts along with
the corresponding safeguard instruments for IPs and ICCs, as prescribed by
DPWH in its LARRIPP Policy:
Table 14.5.1: Impacts and Social Safeguard Instruments for IPs and ICCs, Based on the DPWH LARRIPP
Table 14.5.1: Impacts and Social Safeguard Instruments for IPs and ICCs, Based on the DPWH LARRIPP
(v) Social impact assessment and validation that the entitlement matrix
have covered all resettlement entitlements;
(vii) Inclusion of itemized budget for all resettlement activities in the total
project cost for each road section;
(ii) ensure that funds are available so that the RP can be implemented in
a timely manner; and
(i) Assist the DPWH and NCIP staff in identifying who among the APs are
IPs or belong to ICCs;
(ii) Assist the DPWH staff engaged in the LARRIPP activities in the public
information campaign, public participation, and consultation;
(iv) Receive complaints and grievances from PAFs and other stakeholders,
as referred by the MRIC and act accordingly;
38. This procedure is initiated once the letters from PAFs, expressing their
grievances are received by the MLIC/DEO. The deadline for submitting letters of
grievances shall be set 30 days after the date of public disclosure; with a
maximum extension of another 15 days, if request was made by more than ten
percent (10%) of the PAFs.
39. A Grievance Action Form (GAF), as prescribed in the said LAPRAP Tracking
Manual shall be used during the detailed design stage to cover the various
aspects of property acquisition based on validation of the RP. The GAF shall, at
the very least, contain the following:
Notification of APs
Compensation
Relocation to Replacement
Land
Income Restoration
Commencement of Civil
Works
Internal Monitoring
1
Monitoring procedures for MOAs and IPAPs of IPs/ICCs living inside ancestral domains will be guided by the
monitoring, evaluation, and reporting arrangements set forth in the MOA.
(ii) Coordination with the NCIP regarding the monitoring and evaluation
of the situation of affected IPs/ICCs, whether inside or outside
ancestral domains;
(iv) Ensuring that RPs and IPAPs are implemented as designed and
planned;
(v) Verifying that funds for implementing the RPs, MOAs, and IPAPs are
promptly provided by the IO/PMO and in sufficient amounts;
(vi) Recording all grievances and their resolution and ensuring that all
complaints are promptly addressed;
(vii) Monitoring, in coordination with the relevant branch of the NCIP the
implementation of IPAPs, covering affected IPs/ICCs living outside
ancestral domains.
(ii) Coordinating with the NCIP with regards to the monitoring and
evaluation of the situation of affected IPs/ICCs, whether they are
living inside (covered by MOA) or outside ancestral domains (covered
by the IPAP);
(iii) Verifying and assessing the results of the information campaign for
APs’ rights and entitlements, including consultations with affected
IPs/ICCs living outside ancestral domains;
(iv) Verifying that the compensation process has been carried out in
accordance with procedures communicated with the APs and IPs
during consultations;
(v) Assessing whether resettlement and IPAP objectives have been met,
particularly with regards to livelihood and restoration and/or
enhancement of living standards;
44. Other details on stages, frequency, schedule, reporting, and indicators used
for internal and external monitoring of sub-projects can be found in Sections D
to H of the LARRIPP.
8. As appears from the “Province” column in the above Table, most projects
on the list are in the Visayas Region, with no less than 13, versus 4 in Luzon
and only 1 in Mindanao. This imbalance is expected to even out, however,
when the road projects to be undertaken by the World Bank and JBIC are also
included.
9. It should be noted that all results presented in this Chapter will remain
approximate for some years yet. A detailed design of roads for Tranche 2 will
be undertaken in parallel with the civil works in Tranche 1, etc., resulting in
more precise cost estimates and then probably also more precise rankings
between the candidate roads.
RATIONALE:
Project post-evaluation is necessary to complete the development cycle
of a project. It is intended to answer the question on how a project has
achieved its desired impacts. Part of the 6th ADB Road Project involved
the conduct of benefit monitoring and evaluation of selected road
projects. JBIC provided Manuals in the conduct of Ex-Post Evaluation of
JBIC-funded projects. However, the two funding institutions have
different approaches in post evaluation. What is needed is to produce a
unified approach to post-evaluation and to embody it in a set of Manuals
and Guidelines.
OBJECTIVE:
The overall objective of the consultancy services is to develop DPWH
Manual for Impact/Post-Evaluation of Completed Projects adoptable
either to foreign or locally funded projects.
SCOPE:
1. Review the existing criteria in the Selection of Projects subject to
impact/post-evaluation and make revisions if deemed necessary.
2. Review the available JBIC Handbook in the conduct of Ex-Post
Evaluation of completed JBIC funded projects and section of 6th ADB
Final Report on Benefit Monitoring & Evaluation for possible
merging/revision in the preparation of Independent Manual. The said
manual should include the following:
- Procedures of Post-evaluation;
- Clear definitions of commonly used terms, e.g. post-evaluation,
impact evaluation, benefit monitoring and evaluation, ex-ante
evaluation, and ex-post evaluation;
- Tools of evaluation; and
- Feedback of evaluation findings.
TIMEFRAME: 48 months
ESTIMATED COST: PHP 95.7 MILLION
RATIONALE:
The DPWH has no integrated information system on the life-cycle of a
project, from feasibility study to post-evaluation. Such a system is
important to tract progress as well as any problems encountered in each
phase and the actions taken on the problems. The system is an
important tool in project management.
OBJECTIVE:
The overall objective of the project is to improve the tracking process of
a project including feasibility study, design, environmental compliance,
procurement of Right-of-Way, construction, project hand-over,
maintenance and post evaluation.
SCOPE:
Phase I
(1) Development of an effective project management techniques that
would include the delivery of projects on time and within budget;
RATIONALE:
Many of the manuals, guidelines and specifications which are currently in
use are already out of date. Considerable advances have been made
internationally in the understanding of materials, pavements and road
structures as a whole. Applied research to adapt international
technology to local conditions would be needed to update existing
manuals and specifications. A related concern pertains to the lack of
local expertise in the area of surface treatments of bituminous
pavements.
The DPWH implements between 14,000 and 22,000 infrastructure
projects per year. Most of these projects are being implemented by the
district and sub-district engineering offices nationwide which are not fully
capable to conduct testing of materials. This situation could be
addressed by the development of a Quality Assurance System (QAS) and
the upgrading of the DPWH laboratories nationwide.
OBJECTIVES :
(1) To conduct research on improving pavement performance;
(2) To improve material testing capability and capacity; and
(3) To develop and install quality assurance system.
SCOPE:
(1) Prepare and implement a sustainable research designed to enhance
and expand the existing specifications for concrete/asphalt mix
design;
(2) Conduct training programs on asphalt surface dressings;
(3) Develop a Quality Assurance System and install it in the DEOs; and
(4) Upgrade the DPWH laboratories nationwide.
TIMEFRAME : 8 YEARS
ESTIMATED COST : The cost is estimated at PhP 760.9 Million broken down as
follows:
Research program - PhP 200.0 M
Training in surface dressing - 53.4 M
Quality Assurance Development - 101.0 M
Upgrading of laboratories - 406.5 M
RATIONALE:
The DPWH has taken several initiatives to strengthen its in-house
capability in environmental management and right-of-way management
through technical assistance from Highway Management Project to the
NRIMP, Phases 1 and 2, all World Bank-assisted projects. It is necessary
to continue these initiatives and ensure their application in the ROs and
DEOs of the department.
OBJECTIVE:
To sustain the gains of the initiatives on environmental and social
safeguards and right-of-way management through: (1) the enhancement
of the EIA Regional Offices in environmental management; and (2) the
improvement in ROW management through GIS applications to ROW
functional areas, among others.
SCOPE:
Environmental Management:
1. Continue the initiatives on accreditation of ESSO to ISO 140001 to its
regional counterparts;
2. Procure EIA instruments such as air, noise and water samplers and
train ESSO and its counterparts on the usage of these instruments;
ROW Management:
1. Review and study the results of the GIS applications under NRIMP-2
and make improvements;
RATIONALE :
It is the government’s policy to consider gender issues in infrastructure
development. In particular, the greater role of women in the decision-
making process is being recognized. However, the nature and scope of
women participation have not been well studied. There is also the
absence of gender action plan that would mainstream the policy in
infrastructure development.
OBJECTIVE:
The general objective is to formulate gender-sensitive policies and
strategies and to prepare a six-year gender action plan highlighting
prioritized programs, projects and initiatives ensuring gender-equality in
infrastructure.
SCOPE:
1. Undertake environmental scanning and identify gender issues and
concerns in the involvement of women, youth, senior citizens and
disabled persons in infrastructure development;
2. Develop a comprehensive and sustainable gender-based information
system (data-base) that could be interfaced with the current
Personnel Information System;
3. Conduct social gender analysis such as trend analysis, capacity of
women to participate in decision-making process, and access of
women to health and other services;
4. Prepare standard gender-sensitive design parameters of various
infra-projects;
5. Formulate gender-responsive policies, strategies and initiatives in
infra project formulation and implementation;
6. Establish monitoring and evaluation indicators and guidelines;
7. Organize women’s group in the department;
8. Conduct training on trainers to enhance knowledge on gender and
development and roll-out trainings to all Regional and District
Offices;
9. Undertake gender-sensitive pilot projects and implementation of
gender-designed projects (Luzon, Visayas and Mindanao); and
10. Prepare a six- year term gender action plan for DPWH.
TIMEFRAME : 3 years
RATIONALE:
Effective governance is dependent upon a good communication network.
Seventy DEOs are not currently connected to the Wide Area Network of
the department.
OBJECTIVE :
To connect 30 additional District Offices to Wide Area Network (WAN) of
the Department (43 DEOs have already been connected).
SCOPE:
1. Construction of network room or data center;
TIMEFRAME : 3 years
RATIONALE :
There is a need for the DPWH to expand its enterprise-wide platform of
database servers, application servers, administrative servers, and client
workstations. The installation of IT facilities should take advantage of
the expansion of the communication network under a separate project.
OBJECTIVE :
The objective of the project is to procure and install IT computer and
software for DEOs.
SCOPE:
TIMEFRAME : 3 YEARS
RATIONALE :
Compared to other components, low priority had been accorded towards
Human Resource Management (HRM) and Organizational Strengthening
programs in the DPWH. It is essential that HRD be given due importance
to ensure high productivity within the department.
OBJECTIVE :
To develop a comprehensive approach to the management of the
Department’s most valued assets - the workforce who individually and
collectively contributes to the achievement of the goals and objectives of
the organization.
SCOPE :
a) Leadership Development -
Implementation of appropriate interventions for DPWH key officials,
including division chiefs, for organizational effectiveness.
Phase I
Establishment of a new standardized performance appraisal
system with associated training; and
Phase II
Establishment of a new selection and hiring process, including
criteria, with associated training;
TIMEFRAME : 3 years
RATIONALE:
The TARAS was developed as part of the ADB-assisted 6th Road Project.
It was implemented and was deployed to the ROs. While a Memorandum
of Agreement (MOA) was signed between the DPWH and the PNP,
continuous training of PNP personnel is still needed to effectively
implement the system. There is also the need to integrate the road
accident data systems of other agencies like the MMDA into the TARAS.
Its deployment to the DOs is also long overdue.
OBJECTIVE:
1. To improve the current accident data system by reviewing the
existing policies, procedures, and practices for collecting and
reporting road accident data in DPWH and the Philippine National
Police (PNP); and
SCOPE:
1. Expanded deployment of TARAS to the DPWH District Engineering
Offices (DEOs). Currently, only the Regional Offices (ROs) are
authorized to have TARAS Users.
2. Improvement of TARAS:
(a) Upgrade data entry of accident data from the present manual
encoding to direct input from an electronic device to prevent
backlog and delays;
(c) Integrate other road accident data systems of other agencies, e.g.
Metro Manila Reporting and Analysis System of the Metro Manila
Development Authority and Department of Health with DPWH
TARAS for a unified accident data system in the Philippines.
TIMEFRAME : 3 years
RATIONALE:
The RSA system has been established within the department. It has
been used to evaluate the worthiness of several ADB/IBRD-assisted road
projects. More training is however needed. It is also essential to
develop a sustainable Accident Prevention Program using the RSA
system. Such a program should include the conduct of RSA on road
sections not identified as black spots.
OBJECTIVE:
To ensure a higher level of safety for all new highway schemes, newly
completed road projects and existing roads by giving safety a primary
consideration in each design and construction stage of the project.
SCOPE:
1. Development of a sustainable Accident Prevention Program using RSA
procedures for the national road network;
TIMEFRAME : 6 years
RATIONALE:
The institutionalization of the Road Watch or “Bantay Lansagan” is being
done under the NRIMP through the PEGR. It is pursued in partnership
with various Non-Government Units (NGOs) and people organizations
across the nation so as to encourage community vigilance and serve as a
platform for citizen’s voice. Continuing assistance to the initiative is still
needed in the next few years to ensure its sustainability.
OBJECTIVE:
The general objective of the project is to provide continuous support to
sustain “Bantay Lansangan” to effectively ensure its operations as a
partner in good governance outside the sphere of government funding
and vested interests. Still in its infancy BL still needs outside support to
carry on its mission and to uphold its advocacy in promoting changes and
reforms in Philippine road sector policies.
SCOPE:
1. Fund support to continue participatory results, monitoring and
evaluation through public expenditure reviews in each budgetary
cycle, planning and procurement;
4. Fund support for the preparation and publication of the Road Sector
Status Report Card; and
ANNEX 2
ANNEX 3
1. In the DPWH, the development of an infrastructure project (e.g. road, bridge, flood
control or water supply) follows a project development process consisting of four
phases, as shown in the chart.
I. Project Identification
5. If the project passes the feasibility criteria, it is considered for inclusion in the
DPWH medium-term infrastructure program and budget, provided that it is
among the highest ranked candidate projects that meet the Multi-Criteria
Analysis (MCA) score. MCA considers the following parameters:
7. The project must fit into the country lending program of the concerned
International Financing Institution (IFI), which is prepared in consultation with
NEDA, together with the DPWH and other implementing agencies, taking into
account the priorities in the MTPIP. In case a long list of projects is proposed to
the IFI for financing, the IFI reviews the list and advises the Government of the
Philippines (GOP) of its recommended short list which can be funded under its
loan ceiling.
8. The ICC screening is done at three levels – NEDA technical staff, ICC
Technical Board, and ICC Cabinet level. The ICC evaluates the merits of the
project in relation to set criteria (conformance to national priorities, EIRR,
inclusion in the medium term program and budget, etc.) and, if it finds that the
project meets all the requirements, approves it. The project is then elevated to
the NEDA Board for confirmation.
9. Once the project is approved by the ICC, the GOP submits it to the IFI for
appraisal and eventual loan financing. The IFI conducts an appraisal of the
project to review and confirm its feasibility and readiness for implementation.
The IFI discusses with the GOP/DPWH the description of the project, its cost,
financing to be made by the IFI and GOP, schedule, implementation
arrangements (right-of-way clearance, bidding and contracting procedures,
special project office, etc.) and conditions to be met before final negotiations
(relocation of informal settlers, etc.). These are embodied in Minutes of
Discussions/ Memorandum of Understanding signed by the IFI and GOP
representatives, and in an Aide Memoire/Project Appraisal Document. These
documents form the basis for the draft loan negotiation documents.
10. The DPWH obtains from the DBM a Forward Obligational Authority (FOA) to
cover the multi-year funding requirements of the project, including both the
proposed loan proceeds and GOP counterpart, as a prerequisite to loan
negotiations and for contracting purposes.
e) Loan Negotiations
11. Loan negotiations for the project with the IFI are undertaken by a GOP
panel usually chaired by the DOF, and composed of the DPWH, DBM, and BSP.
The negotiations discuss and agree on the scope and description of the project,
the project cost, the cost to be financed from the loan and the GOP counterpart,
the schedule of implementation, the arrangements for implementation, including
right of way acquisition and compensation and relocation of project affected
persons, bidding and contracting procedures for detailed engineering and
construction supervision and for civil works, project management, actions
requiring concurrence or approval of the IFI, terms of financing and repayment,
loan disbursement procedures, and other relevant terms.
12. After the loan is approved by the IFI, the loan agreement is signed by the
GOP and the IFI officials.
f) Fund Appropriation
13. Based on its medium term infrastructure program and budget and loan
negotiations, the DPWH includes the project in its proposed annual budget,
submitted to the DBM, for incorporation in the National Expenditure Program
(NEP) submitted by the President to the Congress for appropriation of funds
under the General Appropriation Act (GAA) for the following year. The proposed
appropriations for the project in the NEP cover both the loan proceeds and the
GOP counterpart which are scheduled to be disbursed during the budget year.
g) Detailed Engineering
14. This consists of the various technical surveys and investigations, such as
topographic surveys, soil borings, and hydrologic surveys, and design operations
needed to define the detailed physical characteristics of the project, according to
accepted engineering standards to an extent suitable for bidding purposes and
with a degree of detail that will enable estimates of quantities and costs to be
made within plus or minus 10% of the final figures. Detailed engineering also
includes the preparation of bid documents, including plans, specifications,
instructions to bidders, draft contract terms and conditions, bill of quantities,
cost estimates and price analyses. Consultants are generally hired to do the
detailed engineering in accordance with the procurement guidelines of the IFI as
stated in the loan agreement.
a) Fund Releases
17. The ROW for the project should be acquired and cleared ahead of actual
construction, and preferably before the bidding, in order not to impede the
work.
18. Where needed, the DPWH undertakes a parcellary survey to establish the
technical descriptions of the lots to be acquired and estimates of the buildings
and other improvements on the lots.
19. The Resettlement Action Plan done during the feasibility study is also refined
based on the detailed engineering design and parcellary survey.
20. The acquisition and clearance of the ROW follow the provisions of R.A. 8974
and the guidelines for land acquisition and resettlement agreed with the IFI.
These include proper compensation for the project affected persons and
relocation of informal settlers to a suitable resettlement site according to R.A.
7279 (Urban Development and Housing Act). This is done in coordination with
concerned agencies, e.g. LGUs, MMDA, NHA, etc.
22. The contract is executed between the DPWH and the winning bidder using
the contract form, terms and conditions given before the bidding as part of the
Instructions to Bidders. The contract terms and conditions generally follow the
internationally-accepted FIDIC form.
23. These include, among other things, the obligation of the contractor to carry
out the work according to the approved plans and specifications within the
prescribed durations, and the obligation of the DPWH to promptly pay the
contractor for actual work accomplished according to the plans and
specifications at the prices set in the contract. Provisions for performance bond
and liquated damages are also included.
d) Construction
26. Project completion is the transition from the development to the operational
stage. The PMO, with the assistance of its consultants, is responsible for
preparing the Project Completion Report and as-built plans for submission to the
DPWH management and to the IFI.
27. The DPWH makes the final payment to the contractor only after the PMO
certifies that the entire contract works are satisfactorily completed, including
correction of defects. The contractor’s Performance Bond is then released, but
this is replaced by a Warranty Bond to ensure that the contractor will properly
maintain and repair any defects on the completed project during the mandatory
period, usually one year. After the warranty period and upon correction of any
defects, the DPWH issues the Certificate of Acceptance.
28. If the project is a national road or bridge, a major flood control structure, or
a similar facility of national importance, the completed facility remains under the
responsibility of the DPWH during the operation and maintenance phase. The
District Offices normally undertake actual maintenance of the facilities by
contract or by administration. Funds for this purpose are included in the Current
Operating Expenses of the annual DPWH budget. Maintenance receives the
highest priority in fund allocation to preserve the facilities in good condition, and
thus efficiently function throughout their economic life.
b) Impact Evaluation
30. It includes an assessment of the actual benefits and cost arising from the
completed project, as against those assumed or projected during the project
study, covering the technical, economic, social, and environmental impact. This
may deal on congestion (for a road), reduces flooding (for flood control), greater
production and business, higher incomes and improved living conditions,
enhanced environment, etc. The lessons learned from this impact evaluation will
be used to revise or finetune the parameters, assumptions, and conditions in the
preparation and implementation of the future projects to improve the results
therefrom.
Source: DPWH
Reflectorized thermoolastic pavement markins sq.m. 774.96675 3.969.30 2.A37 -977 .52 3,969.30 2.837.977 .52 3,959.30 2.837.9L7 .52
TOTAL COST = 9,9s4,523.43 13,487,346.43 15,839,548.93
UNIT cosT/sQ.M. = 2,972.69 4,026.07 4,724.22
fabric a course on
0ired Unit Direct Unit Direct Unit
Description Unit Quantity Amount Amount Amount
Cost Cost Cost
fuohalt levelinc course sq.m. 20ro 882.68 1.774.L76.75 882.58 7,774,77 6.7 5 882.68 r,774,776.75
Geotextile Davim fabric with class reinforcement sq.m. 20ro 489.35 983,593.50 489.35 983,593.50 489.35 983,593.50
Bituminous tack coat. emulsified asohalt ss-1 tonnes 2.5728 77,024.04 198,167.4s 77.O24.U 198.157.45 77,024.04 198,167.45
Bituminous concrete surface wearinl course sq.m. 2010 3,548,353.50 2.878.73 5.565.647.30 3,520.88 7,076,968.80
Reflectorized thermoplastic pavement marking sq.m. 12L.5 3,959.30 442,269.95 3,959.30 482.269.95 3,969.30 442,269.95
TOTAL COST = 6,986,561.15 9,103,854.95 10,515,175.45
UNIT COST/SQ.M. = 3,475.X 4,529.24 5,23t.43
84 AC
Direct Unit Direct Unit Direct Unit
Description U nit Quantity Amount Amount Amount
Cost Cost Cost
Bituminous tack coat, emulsified asohalt ss-1 ronnes 7.246/' 77,O24.U 99.083.73 77.O24.U 99,083.73 77,O24.U 99.O43.73
Bituminous concrete surface wearint course sq.m. 2010 1,765.35 3,548,353.50 2,414.73 s.565.647.30 3,520.88 7.075_968.80
Reflectorized thermoplastic pavement marking sq.m. r27.5 3.969.30 442,269.95 3,969.30 442,269.95 3,969.30 442,269.95
TOTAT COST = 4,729,707.7a 6,247,OOO.98 7,654322.48
uNrT cosT/sq.M. = 2,O54.54 3,707.96 3,810.11
tOT 1.1 BAUANG.EAGUIO ROAD
A. CONCRETE PAVEMEM
Length = 500 mts
Width = 6.7 mts
5{, mm. AC Overlay 80 mm, AC Overlay
A2 PCCP Reconstruction with ACOverlav
Total Unit Total Unit
Description Unit Qua ntity Amount Amount
Cost Cost
Removal of existing pcc pavement sq.m. 3350 4to.o7 1.373.734.50 4ro.o7 1.373.734.50
Sub!rade preparation sq,m. 3350 28.19 ,436.50 28.r9 94,436.50
PCC Davement (plain), 200mm thick so,m, 3350 1,096.58 3.673.543.00 1,096.58 3.673.543.00
Sealinq of ioints of DccD l.m. 2251 109.10 245,584.10 109.10 245,584.10
Eituminous tack coat, emulsified asphalt ss-1 tonnes 2.7472 60.891.04 169,715.51 60,891.04 169.715.51
Bituminous concrete surface wearinq course sq,m. 3350 640.99 2,147,316.50 7,O23.21 3,427,753.50
Refl ectorized thermoDlastic Davement marking (vellow) sq.m. 47.06r 877.26 47,OO2.37 471.26 47,OO2.37
Reflectorized thermoDlastic Davement markins {white) so.m. 202.5 864.05 L74.972.75 864.06 774,972.75
TOTAL COST = [email protected] 9,2@,747.62
UNIT cosT/sQ.M. = 2,36/..27 2,746.49
AC with Fabric
Total Unit Total Unit
D€scription U nit Quantity Amount Amount
Cost Cost
S€alina of cracks and ioints on existinc Dccp l.m. 2251 109.10 245,584..tO 109.10 245,584.10
Geotextlle oavinr fabric with plass reinforcement sq.m. 655.40 439,118.@ 655.40 439,118.00
Bituminous tack coat, emulsified asDhalt ss-1 tonnes 2.7872 60,891.04 169,715.51 @,891.04 169,715.51
Bituminous concrete surface wearing course sq.m. 33s0 640.90 2,747,376.50 LO23.2L 3427,753.50
Reflectorized thermoolastic aavement markinc (vellow) sq.m. 47.067 477.26 47,OO2.37 477.26 4t,0o2.37
Reflectorized thermoDlastic pavement markinc (white) sq.m, 202.5 864.06 774.972.15 864.05 774,972.75
TOTAL COST = 3,2t7,708.62 4494,745.62
UNIT COsT/Sq.M. = 960.51 L,342.73
84 AC on ACP
Total Unit Total Unit
Description Unit Qua ntity Amount Amount
Cost Cost
Bituminous tack coat. emulsified asohalt ss-1 tonneS L.zAU 59.590.02 76,656.@ 59.590.02 75,556.60
Bituminous concrete surface wearing course sq.m. 2070 603.83 1,213,698.30 963.81 1,937,258.10
Refl ectorized thermoplastic oav€ment markinc (vellow) sq.m. 910.29 20,935.67 910.29 20,936.67
Reflectorized thermoDlastic pavement markinc (white) sq.m. 121.5 903.09 709,725.44 903.09 709,725.44
TOTAf- COST = 7,427,077.o7 2,144,576.41
UNIT COST/SQ.M. = 706.97 1,056.95
C. SHq'DER5
Length = 100 mts
Width = 2.1 mts
SchemeA5 Ac on PCCP
Total Unit TotalUnit
Description Unit Qua ntity Amount Amount
Cost Cost
Sealinp of cracks and ioints on existinc Dccp l.m. 2926 7LO.70 323,904.20 170.70 323,908.20
Bituminous tack coat. emulsified asDhalt ss-1 tonnes 2.t44 59,590.02 727.76t.@ 59.590.02 127.767.00
Bituminous concrete surface wearinc courcc sq.m. 3350 603.83 2,022,430.50 963.81 3.228.763.50
Reflectorized thermoplastic pavement markina {yellow) so.m. 38.43 970.29 34,942.44 910.29 34,9a2.44
Reflectorized thermoplastic pavement markim (whlte) 50.m. 202.5 903.09 742.475.73 903.09 742,475.73
TOTAT cosT = 2,692,357.87 3,898,290.87
UNIT CoST/SQ.M. = 803.69
B. AC PAVEMENT
length = 300 rnts
Width = 6.7 mts
50 mm. AC Orerlay 80 mm. Ac Overlay lm mm, AC Overlry
Scheme Bl Reconstruction ofexidinrAC Davement
quantity Dired Unit Direct Unlt Oirect Un it
Descrlption Unit Amount Amount Amount
Cost Con Cost
Removal of existing ac pavement sq.m. 2010 34.43 69.204.30 34.43 69,204.30 34.43 59.204.30
Subgrade preparation tonneS 2010 19.00 38,190.00 19.00 38,190.00 19.00 38,190.00
Bituminous Drime coat. cut-back asDhah mc-70 tonnes 2.7537 57.005.21 756,975.25 57,OOs.2r 156,975.25 57.005.21 756,975.25
Bhuminous concrete surface wearing course sq,m. 2010 544.80 1,095,048.00 865.15 1,738,951.50 7,O79.76 2,170,3t7.60
Reflectorized thermoDlastic oavement marknc sq.m. 121.5 3,969.30 442,269.95 3,969.30 482,269.95 3,969.30 442,269.95
TOTAL COST = 1,841,587.50 2,485,591.@ 2,9t6,957.tO
UNIT COST/SQ.M. = 916.26 7,236.67 7,45t.22
Sctem€ 82 Reconstructlon ofAc Pavement on PCCP
Direct Unit Dired Unit Dired Un it
Descrlption Unit Quantity Amount Amount Amount
Cost Cost Cost
Removal of exidinc ac Davement sq.m. 2010 34.43 69,2M.30 34.43 69,204.30 34.43 59,2(X.30
Seallnc of cracks and ioints on existint pccp t.m. 77 54 59.59 104,520.86 59.59 104,520.86 59.59 104.520.86
Bituminous tack coat. emulsified asohah ss-1 tonneS 1.2864 5O053.17 72,106.80 56,053.17 72,106.80 56,053.17 72,106.80
Bituminous concrete surface wearint course sq.m. 2010 544.80 1,095,048.00 865.15 1,73&9s1.50 j'O79.76 2.770.3t7.60
Reflectorized thermopladic pavement marking 50.m. 121.5 ? q6q ?o 482,269.95 3,969.30 482,269.95 3,969.30 442,269.95
TOTAL COST = L,423,149.97 2,467,O53.47 2,898,419.51
UNIT cosT/sQ.M. = 907.U r,227.39 7,442.OO
ta No AC
Dired Unit Direct Unit Direct Unit
Description U nit Quantity Amount Amount Amount
Cost Cost Cost
Removal of existinq occ oa\€ment sq.m. 3350 250.39 872,306.50 2&.39 872,306.50 [email protected] 872,306.50
Subarade preparation sq.m. 3350 19.00 63,650.00 19.00 63,550.00 19.00 53,650.00
PCC Davement (Dlain). 230mm thick sq.m. 998.69 3,345,611.50 998.59 3,345,611.50 998.69 3,345,611.50
Sealinc ofcracks and ioints on exidinc pccp l.m. 2251 59.59 134.137.09 59.59 134.137.09 59.59 134.137.09
Reflectorized thermoolastic oavement markinc sq.m. 2V2.5 3,969.30 803,783.25 3,969.30 803,783.2s 3.969.30 803,783.25
TOTAT COST = 5,279,444.34 5,219,488.34 5,219,488.34
UNIT COST/SQ.M. = 1,558.06 1,558.06 1,558.06
Sch€fie A!l-2 crack and seat with reflection crack control and Ac
Direct Unit Direct Unit Direct Unit
Description U nit Quantity Amount Amount Amount
Cost Cost Cost
Crack and seat of existinc pccD (with asphah leveling coursel sq.m, 707.74 470,165.80 707.74 470,165.80 70t.74 470.165.80
Bituminous tack coat, emulsified asphalt ss-1 tonnes 2.7872 50.810.45 141.618.89 50.810.45 141,618.89 50,810.45 141.618.89
Geotextile Davinc fabric wlth dass reinforcement sq.m. 489.35 327.86/..50 489.35 327,86/.50 489.35 327,464..50
Bituminous concrete surface wearinc course sq.m. 805.95 2,699,932.50 1.283.01 4.298.083.50 1,602.08 5.356.968.00
Reflectorized thermoolastic oavement markins sq.m. 326.40975 3,285.08 r,072,242.74 3,285.08 1,072,242.14 3,285.08 7,072,242.!4
TOTAL COST = 4,77L,453.43 6,310,014.83 7 374,499.33
uNrT cosT/sQ.M. = 1,406.53 1,883.s9 2"202.66
Sche{ne A5 AC on PCCP
Direct Unit Direct Unit Direct Unit
Description Unit Qua ntity Amount Amount Amount
Cost Cost Cost
sealins ofcracks and ioints on existins pccp l.m. 2926 62.34 742,405.U 62.34 !82,406.U 62.34 182,406.U
Bituminous tack coat, emulsified asphalt ss-1 tonnes 2.744 50,810.45 108.937.60 50,810.45 108.937.60 50,810.45 108.937.60
Bituminous concrete surface wearinq course sq,m. 805.95 2,699,932.s0 1,283.01 4,298,083.50 1,602.08 5,366,968.00
Reflectorized thermoolastic pavement markins sq.m, 202.5 3.285.08 665,224.70 3,2E5.0E 665.228.70 3.265.08 665.224.70
TOTAL COST = 3,656,505.64 5,254,656.& 6,323,547.74
uNrT cosT/sQ.M. = 1,091.49 1,568.55 7,447.62
B. AC PAVEME'{T
Length = 300 mts
width = 6.7 mts
5{, mm, AC Overlay 80 mm. AC Overlay 100 mm. AC Overlay
AC
Direct Unit Direct Unit Direct Unit
Description Unit Quantity Amount Amount Amount
Cost Cost Cost
Removal of existinc ac pavement 50.m. 2010 34.43 69.204.30 34.43 69.2U.30 34.43 69,2M.30
Subgrade preparation tonnes 2010 20.31 40.823.10 20.37 40,823.rO 20.31 40,823.10
Bituminous prime coat. cut-back asphalt mc-70 IOnneS 50.713.94 139.650.98 50,713.94 139,650.98 50,773.94 139,650.98
Bituminous concrete surface wearinq course sq.m. 2010 805.95 1,519,959.50 1.283.01 2,S78,850.10 1,602.08 3,220,180.80
Refl ectorized thermoplastic pavement marking sq.m. 121.5 3.285.08 399.L37.22 3.285.08 399.737.22 3.285.08 399.737.22
TOTAL COST = 2,268,775.70 3,227,665.70 3,868,996.40
uNrT cosT/sQ. M. = 7,728.74 1,605.80 r,924.47
Scheme 82 Reconstruction of AC
Direct Unit Direct Unit Direct Unlt
Description U nit Quantity Amount Amount Amount
Cost Cost Cost
Removal of existinc ac pavement sq.m. 2010 34.43 69,204.30 34.43 69.204.30 34.43 59,204.30
sealinq of cracks and ioints on existinc occD l.m. 7754 62.34 109,344.36 62.34 109.3,t4.35 52.34 109,3114.36
Bituminous tack coat. emulsified asDhalt ss-1 tonnes L.2a6/. 50,810.45 65,362.56 50.810.45 55,362.55 s0.810.45 65,362.56
Bituminous concrete surface wearins course so.m. 2010 805.95 1.619.959.50 1,283.01 2,578,850.10 L,@2.O4 3,220.180.80
Reflectorized thermoplastic pavement marking sq.m. 121.5 3.285.08 399.137.22 3.285.08 399.!37.22 3,285.08 399.737.22
TOTAT COST = 2,263,007.94 3,22t,494.54 3,463,229.24
UNIT COST/SQ.M. = 7,725.47 r,602.93 7,922.OO
84 AC on ACP
Direct Unit Direct Unit Direct Unit
Description U nit Quantity Amount Amount Amount
Cost Cost Cost
Bituminous tack coat. emulsified asDhalt ss-1 ronnes 7.246/ 50,810.45 65,362.56 50,810.45 65,362.56 s0,810.45 65.362.56
Bituminous concrete surface wearinc course so. m. 2010 805.95 1,619,959.50 1,283.01 2,578,850.10 1,602.08 3,220,180.80
Reflectorized thermoolastic Davement markins sq.m. 121.5 3.285.08 399.137.22 3,285.08 399,737.22 3,285.08 399,137.22
TOTAL COST = 2,O8r'.,459.28 3,043,349.88 3,684,680.s8
UNIT COST/SQ.M. = r,o37.04 1,514.10 7,433.77
tor 2.1b DAANG MAHARUKA ROAD (ULOAN-NAVAT HIGHWAYI
A COfiCNflE PAVEMENT
Length = 5O0 mts
Wadth = 6.7 mts
5(, mm. Ac oiretlay E{, mm. AC Orerlay
A3 AC Ov€rlav with Pavinc Fabric
quantity TotalUnit TotalUnit
Description Unit Amount Amount
Cost Cost
SealinR of cracks and ioints on existins pccp t.m. 2926 774.34 334,558.84 714.34 334.558.84
Geotextile Davim fabric with rlass reinforcement sq.m. 653.13 437.597.70 653.13 437,597.!O
Bituminous tack coat, emulsified asphalt ss-1 tonnes 2.7872 66.159.17 184,398.84 66.159.17 184,398.84
Bituminous concrete surface wearing course 5(I.m. 3350 578.11 2,27L,668.50 1,082.59 3,626,676.50
Reflectorized thermoDlastic Davement markinc (vellow) sq.m. 866.62 73,865.92 866.62 13,865.92
Reflectori2ed thermoDlastic pavement markine (white) sq.m. 202.5 859.42 174.O32.55 459.42 774.032.55
TOTAL COST = 3476,721.75 4,77 7,129.75
UNIT cosT/sQ.M. = L,019.74 7,424.22
I crack and Seat and AC
Total Unit Total Unit
Description Unit Qua ntity Amount Amount
Cost C.'st
Crack and seat of existinc pccp (with as9halt leveling cou6e) sq.m. 674 735.97 493.099.90 735.97 493.099.90
Bituminous tack coat. emulsified asDhalt ss-l tonnes 2.7872 55.159.17 t8r'39a.u 56.159.17 78/.,394.U
Bituminous concrete surface wearins course sq.m. 3350 fla.Ll 2,277,6ffi.50 1,082.59 3,626,676.50
Reflectorized thermoDlastic Davement markins (vellow) sq.m. IE 866.62 tt aaq qt 865.62 73,465.92
Reflectorized thermoplastic gavement markinc (white) sq.m. 202.5 859.42 174.032.55 859.42 774.032.55
TOTAL COST = 3,L37,065.77 4,492,073.77
UNIT COST/Sa.M. = 936.44 t,340.92
B. SHOUI.DER
Length = 100 mts
Width = 2 mts
51 Gravel Shoulder with ,ACP
Total Unit
Description U nit Qua ntity Amount
Cost
subgrade Preparation sq.m. 200 2.l.36 5,676.00
Arrrecate Base Course (150mm thk.) cu.m. 957.66 28.729.40
Prime Coat tonnes 0.31 8,297.43 27.t70.34
Bituminous concret€ surface wearing course (50mm thk.) sq.m. 674.71 135,622.00
TOTAL COST = 191,198.14
uNrT cosT/sq.M. = 955.99
Scheme 52 ACP Overlaid with ACP
Total Unit
Description Unit qua ntity Amount
C-ost
Eituminous tack coat. emulsified asDhalt ss-1 tonnes 0.14 66,159.17 9,262.28
Bituminous concrete surface wearing course (50mm thk.) sq.m. 204 678.11 135,622.00
TOTAL COST = t44,A84..2A
UNIT COST/SA.M. = 724.42
Length = 500 mts
Width = 6.7 tnts
50 mm. AC Overlay 80 mm. AC orrerlay 100 mm. AC Ovorlsy
Al Concrete re-blockins and AC Overlav
Dired Unlt Direct Un it Direct Unit
Descrlption Unit Qua ntity Amount Amount Amount
Cost Cost Cod
Removal of existlng Dcc Davement sq.m. 670 260.39 774.461.30 260.39 774.46L.30 260.39 174,467.30
Subcrade Dreparation sq.m, 670 20.37 73.607.70 20.37 13.607.70 20.31 73.607.70
PCC Davement {Dlaln). 230mm thick 50, m. 670 1,025.20 686,884.00 7,O25.20 686,884.00 7,O25.20 686,884.00
Bituminous tack coat. emulslfied asohalt ss-1 tonnes 2.744 50,810.45 108,937.60 50,810.45 108,937.60 s0.810.45 108.937.60
Bituminous concrete surface wearint course sq.m. 3350 805.95 2,699 ,932.50 1,283.01 4,298,083.50 1,502.08 5,366,968.00
Sealinc ofcracks and ioints on existinc DccD t.m. 2926 62.34 182,406.84 62.34 782,406.U 62.34 182,405.84
Reflectorized thermoDlastic Davement markinr sq.m. 202.5 3,285.08 665,224.70 3,28S.08 665,228.70 3,285.08 66.5.228.70
TOTAL COST = 4,531,458.64 6,129,609.U 7 ,794,494 .14
UNIT COST/SQ.M. = t,3s2.67 L,429.73 2,148.80
A2 PCCP Reconstruction. No AC
Direct Unit Direct Unit Direct Unit
Description Unit Quantity Amount Amount Amount
Cost Cost Cost
Removal of existinc Dcc oavement sq.m. 3350 250.39 872,306.50 260.39 872,306.50 260.39 872,305.50
Subgrade preparation sq.m. 3350 20.31 58,038.50 20.31 68,038.50 20.31 68,038.50
PCC Davement (olainl. 230mm thick sq. m. 3350 1,O25.2O 3,434,420.OO I,O25.20 3,43/,420.0O 7,O25.20 3.434.420.@
Sealinc ofcracks and ioints on existinc pccp l.m. 2257 62.34 L40,327.34 62.34 t40.327.34 62.34 140327.34
Reflectorized thermoplastic Davement markint sq.m. 202.5 3.285.08 665,224.70 3,285.08 665,228.70 3,285.08 665,224.70
TOTAT COST = 5,rao32r.M 5,180,321.04 s,180,321.04
uNrT cosT/sQ.M. = 7,546.36 1,546.36 1,546.35
B4 AC on ACP
Direct lJnit Direct Unit Direct Unit
Descrlption U nit quantity Amount Amount Amount
Cost Cost Cod
Bituminous tack coat, emulsified asDhalt ss-1 tonnes 1.2864 50.810.45 65,362.55 50,810.45 65,362.56 50,810.45 65,362.55
Bituminous concrete surface wearing course sq.m. 2010 805.95 1,619,959.50 1,283.01 2,578,850.10 1,602.08 3,220,180.80
Reflectorized thermoplastic pavement markinc sq.m. 127.5 3,285.08 399.137.22 3,28s.08 39.137.22 3,285.08 399.137.22
TOTAT COST = 2,044,459.24 3,043,349.88 3,584,680.58
UNIT COST/Sa,M. = 7,037.O4 1,514.10 7,433.17
Length = 5@ mts
Width = 6.7 mts
50 mm. AC Overlay 80 mm, AC Ovcrlay 100 mm. AC Orerlay
A2 PCCP Reconstruction with Ac overlav
Total Unit Total Unit Total Unit
Description U nit Qua ntity Amount Amount Amount
Cost Cost Cost
Removal of existing Dcc Davement sq.m. JJ5U 4t3.23 73U,320.50 473.23 1,384,320.s0 4t3.23 7,3U,320.50
Subgrade preparation sq.m. 3350 28.38 95,073.00 28.38 95,073.00 28.38 95,073.00
Attrerate subbase course, 200mm thick so.m. 670 &t.24 429.657.& 647.28 429,6s7.il 6/.1.24 429,657.&
PCC oavement (olain), 200mm thick so.m. 3350 1,033.15 3.451.052.50 3,461,052.50 1,033.15 3,451,052.50
Sealim of ioints of pccp t.m. 2257 L14.34 257.379.U 114.34 257,379.34 7t4.34 257,379.34
Bituminous tack coat, emulsified asphalt ss-1 ronnes 2.7872 66.759.t7 184.398.84 56.159.17 184,398.84 65,159.17 184,398.84
Bituminous concrete surface wearing course so.m. 3350 673.82 2.257.297.OO
Reflectorlzed thermoplastic pavement marking (yellow) so.m. t2 865.52 10.399.44 866.62 10,399.214 866.62 10.399.44
Reflectorlzed thermoplastic pavement marking (white) so,m, 202.5 459.42 774.O32.55 859.42 174,O32.55 4s9.42 t74,O32.55
TOTAL COST = 4,253,670.77 5,996,3t3.77 5,996,373.77
UNIT cOST/Sq.M. = 2,463.76 7,749.94 L7A9.94
SchemeA5 AC on PCCP
Total Unit
Description Unit Q.uantity Amount
Cost
Sealing ofcracks and ioints on existinc pccp l.m. 2926 Lt4.4 334,558.84
Bituminous tack coat, emulsified asphalt ss-1 tonnes 2.144 66,159.17 t47,U5.26
Bituminous concrete surface wearing course sq.m. 3350 673.42 2,257,297.@
Reflectorized thermoplastic pavement marking (yellow) sq.m. 72 6bb.bz 10,399./t4
Reflectorlzed thermoplastic pavement marking (white) sq.m. 202.5 859.42 174,032.55
TOTALCOST= 2,918,133.09
UNIT COST/SQ.M. = 871.08
Length= 300 mts
Width = 6.7 mts
50 mm. AC Overlay
Scheme 84 AC Overlav on existinc AcP
Total Unit
Description Unit Quantity Amount
Cost
Bituminous tack coat, emulsified asphalt ss-1 tonnes 7.246,. 56,159.17 8s,107.16
Bituminous concrete surface wearing course sq.m, 2010 673.82 1,354374.2O
Reflectorized thermoplastic pavement markine (vellow) sq.m, ll 866.62 t7,265.06
Reflectorized thermoplastic Davement markins (white) sq.m. ttt.t 859.42 104,419.53
TOTAL COST = 1,5s5,170.9s
UNIT COST/SQ.M. = 773.72
C. SHOUIDER
SchcmeA/[ AC with
quantity Dired Unit Direct Unit Direct LJnit
Description Unit Amount Amount Amount
Cost Cost Cod
Sealinc ofcracks and ioints on existinr occD l.m. 62.48 182,816.48 62.44 182.816.48 62.44 182,815.48
fuohah levelinl course sq,m. 670 320.34 274,524.45 320.34 2t4.624.45 320.34 274.624.45
Geotextile pavins fabric with glass reinforcement sq.m. 670 489.35 327.464.50 489.35 327,464.50 489.35 327,854.50
Bituminous tack coat, emulsified asphalt ss-1 IOnnes 2.7472 52.907.54 747.463.90 s2.907.54 147.463.90 52.907.54 747.463.90
Bituminous concrete surhce wearint course sq.m. 3350 &0.67 2,746,244.50 1,108.20 3,7 12,47 0.OO 7,271.57 4,259,558.50
Refledorized thermoplastic pavement marking sq.m. 202.5 3.078.30 623.355.75 3,078.30 623.355.75 3,078.30 623,355.75
TOTA| COST = 3,642,369.54 5,208,595.08 5,755,683.58
UNIT cosT/sQ"M. = \o47.27 1,554.80 1,718.11
AC on PCCP
Direct Unit Direct Unit Direct Unit
Description Unit Quantity Amount Amount Amount
Cost Cost Cost
Sealinc ofcracks and ioints on existinc pccp l.m. 62.48 182,816.48 62.48 182,816.48 52.48 182,816.48
Bituminoustack coat, emulsified asphalt ss-l tonnes 2.744 52.907.54 7I3.433.77 52,907,54 7r3,433.77 52.907.s4 113,433.77
Bituminous concrete surface wearins courso sq.m. 3350 6/,0.67 2.t46jU.5O 1,108.20 3,7t2,470.OO 1,271.s1 4,259,558.50
Refl ectorized thermoplastic pavement marklnl sq.m. 202.5 3,078.30 623,355.75 3,078.30 623.355.7s 3,078.30 623.355.75
ToTAL COST = 3,065,850.50 4,632,O76.N 5,179,154.50
UNIT COST/SQ,M. = L342.77 7,546.O2
B. AC PAVEMENT
length = 300 mts
Width = 6.7 mts
50 mm. AC Overlay 80 mm. AC Overlay 100 mm. AC Overlsy
Schem€ 81 Reconstruction ofexistinr AC Dav€ment
Direct Unit Direct Unit Direct Unit
Description U nit Quantity Amount Amount Amount
Cod Cost Cost
Removal of existinc ac oavement sq.m. 2010 34.43 69,204.30 34.43 59.204.30 34.43 69,204.30
5ub(rade prepardtion ronneS 2010 20.31 40,823.10 20.3L 40,823.10 20.31 40.823.10
Bituminous orime coat, cut-back asohah mc-70 tonnes 57.005.21 t56,975.25 57.OO5.2l L56,975.25 57,005.21 1s6,975.25
Bituminous concrete surface wearinr course sq.m. 2010 uo.67 t,247,746.70 1,108.20 2,227,4A2.OO 7,271.57 2,555,73s.10
Reflectorized thermoolastic Davement markinc sq.m. 727.5 3,078.30 374.O73-45 3.078.30 374.O73.45 3,078.30 374,013.45
TOTAL COST = L,928,762.80 2,868,498.10 3,796,757.20
UNIT COST/SQ.M. = 959.58 !,427.71 L,590.42
A COI{CRETE PAVEMENT
LenSth = 500 mts
width = 6.7 mts
50 mm. AC Oreday 80 mm. AC Ove?lay 100 mm. AC otreday
AC Overlav with Pavinr Fabric
quantity Total Unit Total Unit Totalunit
Description Unit Amount Amount Amount
Cost Cost Cost
sealinr of cracks and ioints on existinc Dccp I.m. 2926 774.54 335,261.08 114.58 335,261.08 114.58 335,261.08
Geotextile paving fabric with glass reinforcement sq.m. 670 655.58 439_238.60 655.58 439,234.& 65s.58 439,234.@
Bltuminous tack coat, emulsified asphalt ss-1 tonnes 2.7872 9.7u.42 180.557.14 u.7u.42 180,567.14 u.7u.42 180,567.14
Bituminous concrete surface wearinr course sq.m. 3350 667.69 2.236.757.50 1,065.85 3.570.597.s0 1,358.08 4,583,068.00
Refl ectorized thermoplastic pavement marking (yellow) sq.m. 30 882.05 26,467.4O 882.06 26,451.W 882.05 25,467.4O
Reflectorized thermoplastic pavement marking (white) sq.m. 202.5 874.a6 177.L59.rs 874.86 r77,759.75 874.85 177,159.ls
TOTAL COST = 3,395,449.27 4,729,245.27 5,74L,755.77
uNrT cosT/sq.M. = 1,013.57 7,471.73 L,713-96
Att-1
quantity Total Unit Iotal Unit Total Unit
Description Unit Amount Amount Amount
Cost Cost Cost
Crack and seat of exlstinq occD (with a3ohalt levelinr coursel sq.m. 670 737.43 494,346.r0 737.83 49,v6.to 737.A3 494.346.10
Bitumlnous tack coat. emulsified asohalt ss-1 tonnes 2.7472 4,78/..42 180.557.14 il,7w.42 180.567.14 u.7u.42 180.557.14
Bitumlnous concrete surfac€ wearinc course sq.m. 3350 667.69 2,236,761.50 1,065.85 3.570.597.s0 1,358.08 4.583.068.00
Reflectorlzed thermoplastic pavement markina (yellow) 5q.m. 30 882.06 26,46t.W 882.06 25.461.80 882.06 26,467.4O
Reflectorized thermoplastlc pavement markinc (white) sq.m. 202.5 874.46 177.159.15 874.85 874.46 r77,7s9.15
TOTAL COST = 3,115,295.69 4,449,131.69 sA6L,602.r9
UNIT cosT/SQ.M. = 929.94 t,328.70 1,630.33
A5
Total Unit Total Unit Total Unit
Description Unit Quantity Amount Amount Amount
Cost Cost Cost
sealinr of cracks and iolnts on existint pccp l.m. 2926 114.58 335,261.08 114.58 335,261.08 114.58 335,251.08
Bituminous tack coat. emulsified asDhalt ss-1 tonnes 2.t44 u.7u.42 138.897.80 4.7u.42 138.897.80 4,7u.42 138,897.80
Bitumlnous concrete surface wearinq course sq.m. 3350 567.69 2,236,76t.50 1.065.85 3.570.597.50 1,368.08 4,583,068.00
Rcflectorlzed thermoplastlc pavement marking (yellow) sq,m. 30 882.05 25,461.80 882.05 26.467.AO 882.05 26,451.80
Refl actorlzed thermoplastlc pavement marking (white) sq,m. 202.s 874.86 177.759.t5 874.86 177.759.75 874.86 177,159.15
TOTAL COST = 2,9t4,541.33 4,24A377.33 5,2@,U7.43
UNIT COST/SQ.M. = 870.01 1,[email protected] 1,s70.40
rrorro{APrz RoAD
B. AC PAVEMEI{T
Length = 300 mts
Width = 6.7 mts
50 mm, AC Overlay 8{t mm. AC Ove.lay l(x, mm. AC Ovejlay
81 Reconstruction of existinr AC Davement
Total Unit Total Unit TotalUnit
Description Unit Quantity Amount Amount Amount
Cost Cost Cost
Removal of existinr ac Davement sq.m. 2010 48.30 97,083.00 48.30 97.083.00 48.30 97.083.00
subcrade preDaration sq,m. 2070 28.97 58,109.10 28.91 58,109.10 28.91 58,109.10
Aqqreeate subbase course. 200mm thick cu,m. 402 554.18 262p40 36 554.18 252,980.36 554.18 262,94O36
crushed affrerate base course, 20omm thick cu.m. 402 973.63 397,399.26 973.63 391,399.26 973.63 391,399.26
Bituminous prime coat, cut-back asphalt mc-70 tonnes 2.7537 66,932.87 184.313.04 65,932.47 184,313.04 66,932.87 78r'..3t3.U
Bituminous concrete surface wearint course sq.m. 2010 667.69 1,342,056.90 1,065.85 2,r4L358.5O r,358.08 2,749.8r',O.4O
Reflectorized thermoplastic pavement marking (yellow) so.m. 882.06 26,46t.80 882.05 26161.80 882.06 26,461.80
Refleclorized thermoplastic pavement marking (whlte) so.m. tzL.5 874.86 to6,295.49 874.85 106,295.49 474.86 106,295.49
TOTAL COST = 2,468,598.95 3,269,000.55 3,476,442.45
UNIT cosT/sQ.M. = 7,224.27 r,626.37 L,924.60
of Ac Pavem€nt on PCCP
TotalUnit Total Unit TotalUnit
Description Unit Quantity Amount Amount Amount
Cost Cost Cost
Removal ofexistinc ac Davement sq.m. 2010 48.30 97,083.00 48.30 97.083.00 48.30 97.083.00
Seallm of cracks and ioints on exlstlnc pccp t.m. 7754 114.58 200,973.32 114.58 200,973.32 114.58 200,973.32
Bituminous tack coat. emulsified asohalt ss-1 tonnes 7.246/. u.7u.42 83,338.68 9,7u.42 83.338.68 9.7u.42 83,338.68
Bitumlnous concrete surfa@ wearim course so.m. 2010 667.69 1.342.056.90 1,065.85 2,142354.5O 1,358.08 2.749.84O.4O
Refl€ctorized thermoplastic pavement marking (yellow) so.m. 882.06 2646t.8O 882.06 25467.4O 882.06 26,461.80
Reflectorized thermoplastic pavement marking (white) so.m. lrl ( 874.86 705,295.49 874.86 to6,295.49 474.46 106,295.49
TOTAL COST = 1,855,209.19 2,655,510.79 3,253,993.09
uNrT cosT/sQ.M. = 923.49 7,327.65 1,623.88
Scheme84 Ac on ACP
TotalUnit Totel Unit TotalUnit
Description Unit Quantity Amount Amount Amount
Cost Cost Cost
Bituminous tack coat, emulsified asphalt ss-l ronneS 7.2464 4.7u.42 83.338.68 u,7u.42 83,338.68 9,7u.42 83,338.68
Bituminous concrete surface wearint coutse sq.m. 2010 667.69 1,342,056.90 1,055.85 2,142354.5O 1,368.08 2.749.8/,0.40
Reflectorized thermoplastic pavement marklng (yellow) 50.m. 30 882.06 26,467.AO 882.06 26,461.4O 882.06 26,467.4O
Reflectorized thermoplastic pavement marking (whlte) so.m. 121.5 874.86 L06,295.49 874.86 106,295.49 874.86 706,29s.49
TOTAI COST = 1,558,152.87 2354,454.47 2,965,936.77
uNrT cosT/sa"M. = 775.20 7,773.36 1,475.59
ltottro{lPtz RoaD
C. SHOI.'TD€R
Leryth = IOO mts
Width = 1.8 mts
GravelShoulder
Total Unlt
Descriptlon Unit Quantity Amount
Cost
Subgrade Preparation sq.m. 180 28.91 5,203.80
Atrretate Surface corirse cu.m. 27 994.68 26,856.36
TOTATCOST= 32,060.16
UNll COST/SO"M. = 178.11
rOT 3.2 IUTUAN-CAGAYAN DE ORO-ILIGAN CITY ROAo (Mlsamls Orl.ntrll
A COt{Ci3Tl PAVEMENT
Leneth = 500 mts
Width = 6.7 t; 5{l mm. AC Overlay m mm. AC Orerlay 10O mm. AC olrerlay
rlockinc and AC Overlav
Direct Unit Direct Unit Direct Unit
Description U nit Qu.ntity Amount Amount Amount
Cost Cost Cost
rxlstlnc pavement PCC Pavement so.m. 670 2@.?9 174,461.30 [email protected] 774.46t.30 2ffi.39 774.461.30
subirtda Dl!paration sq.m. 670 19.O0 72,730.OO 19.O0 12,730.00 19.00 72,730.0O
PCC P.v.m.nt 230 mm thk sq.m. 674 1,182.13 792.027.tO 1,182.13 792.027.L0 1,182.13 792.027.\O
l|ck cort tonnes 2,L44 s3,431.81 114.557.80 53431.81 114.557.80 53.431.81 114.557.80
Bltumlnout concrete surface sq.m. 3350 559.02 1,872.777.OO 887.90 2,974,465.00 1,108.20 3.772.470.OO
s llnl of lolnts Lm. 2926 180,973.10 61.85 180,973.10 61.85 180,973.10
trtlc raflectorized pavement marking sq.m. 202.5 I e1? t1 772.!75.O3 3,813.2I 772.L75.03 3,813.21 772,775.O3
TOTAT COST = 3,919,641.33 5,021,389.33 s,759,394.33
UNIT cosT/SQ.M. = Lr7O.M 7,494.92 1,779.22
SchemeAs AC on PCCP
TotalUnit Total Unit TotalUnit
Description Unit Quantity Amount Amount Amount
Cost Cost Cost
sealinc of ioints and cracks t.m. 2926 110.09 322.r23.U 110.09 322.723.34
Tack coat tonnes 2.tM 62.67 |.07 134.356.65 62.677.OL 134.366.65
Bituminous concrete surface sq.m. 3350 533.53 2.722,[email protected] 1,011.50 3.388.525.00
Ihermoplastic reflectorized oavement markinc (vellow) sq.m. 180 866.05 155,889.00 866.05 1ss.889.00
Thermoolastic reflectorized Davement markinc (white) sq.m. 202.5 858.85 773.977.73 858.85 173.977.73
TOTAL COST = 2,908,956.61 4,L74,421.7t
uNrT cosT/sq.M. = 868.35 7,246.22
I B. AC PAVEMENT
Length =
width =
300
6.7
mts
mts
5o mm. Ac overlay 80 mm, AC Overlay 1@ mm. AC Overlay
rn of existinq AC
Scheme 83 Ac on
Total Unlt Total Unit TotalUnit
Description U nit Quantity Amount Amount Amount
Cost Cost Cost
Tack coat tonnes L.286/. 62,677.07 80.619.99 62.677.Or 80.619.99
Bituminous concrete surface so.m. 2010 633.63 1,273,596.30 1,011.50 2.033.115.00
Thermoplestic reflectorized pavement marking (yellow) sq.m. 106 t56.05 91,801.30 865.05 91,801.30
Th"rmoolastic reflectorized oavement markins (white) sq.m. t27.5 858.85 104,350.28 858.85 104,350.28
TOTAL COST = 1,550,367.85 2,309,885.s6
UNIT COST/SQ.M, = 77r33 L,r49.20
C SHOUIDENS
Length = 100 mts
Width = 2.5 mts
s2
Total Unit TotalUnit Total Unit
Description Unit quantity Amount Amount Amount
Cost Cost Cost
Bituminous tack coat. emulsified asDhah ss-1 ronneS 0.18 66,159.17 11,908.55
Bituminous concrete surface wearint course sq,m. 250 533.63 158,407.50
TOTAL COST = 170,316.1s
UNIT cOsT/SQ.M. = 681.26
tOT 3.2 BUTUAN-CAGAYAN DE ORO-lLlGAN CITY ROAD lMlsamls Orlentall
A. CONCRETE PAVEME'{T
Length= 500 mts
Width = 6.7 mts
50 mm. AC Ovcrlay 80 mm. AC Orarlay
crack and Seat and AC Overlav
Total Unit Total Unit
Description U nit Qua ntity Amount Amount
Cost Cost
crack and seat with asohalt levellinc course sq-m. 670 703.75 471.572.50 703.75 47t,512.50
Tack coat ronneS 2.7472 62,67t.O1 774.676.s 52,677.O1 774.676.&
Bituminous concrete su rface 5q,m, 3350 533.53 2,722,[email protected] 1,011.50 3,388,525.00
ThermoDlastic reflectorized oavement markinc (vellow) sq.m. 180 856.05 155,889.00 866.05 155,889.00
ThermoDlastic reflectorized oavement markinc (white) sq.m. 202.5 858.85 773.917.73 858.85 t73,9L7.t3
TOTAL COST = 3,098,65s.76 4,36/,52O.26
UNIT CoST/SQ.M. = 924.97 1"302.U
Fabric
Total Unit Tota I Unit
Description Unit Qua ntity Amount Amount
Cost Cost
sealinc of ioints Lm. 2926 110.09 322,723.34 110.09 322.123.34
Geotextile paving fabric with reinforcement sq.m. 670 656.76 440,O29.20 656.76 440,O29.20
Tack coat tonnes 2.7472 62,67r.O7 774,676.9 62,67L.Or 774,676.64
Bituminous concrete surface sq.m. 3350 633.63 2,L22,6ffi.50 1,011.50 3,388,525.00
ThermoDlastic reflectorized Davement markinr (vellow) sq.m. 180 866.05 155.889.00 865.05 155,889,00
fhermoplastic reflectorized pavement marking (white) sq.m. 202.5 858.8s 773,917.13 858.85 773,9r7.13
ToTAL COST = 3,389,295.80 4,655,160.30
UNII coST/SQ.M. = 1,Olt.73 1,389.60
Total Unit
Amount
Cost
110.09 322,123,U
62,6?r.07 134,366,65
1,011,50 3,388,525.00
866.0s 155,889.0O
858.85 t73.9L7.13
ToTAL COST = 2,908,956,61 4,L74,A2t,rl
UNIT CosT/sQ.M. = 868.35 1,246,22
EUTUAN{AGAYAN DE ORGIUGAN CITY ROAD
B. AC PAVEME'{T
Length = 300 mts
Width = 6.7 mts
50 mm. AC Orrerlay 80 mm. AC Orerlay
81 Reconstruction of existinc AC oavement
quantity Total Unit TotalUnit
Description Unlt Amount Amount
Cost Cost
Removal of existinr asphalt Davement sq.m. 20!0 46.05 94550.50 46.05 92.560.50
Subgrade preparation ronneS 20'0 27.57 55,295.10 55,295.10
Crushed Accreatate Base Course, 20Omm thick cu.m. 402 &t0.63 333,913.26 830.63 333,9L3.26
Prime coat tonnes 2.7537 9,77234 ]74363.70 s,77234 t78,363.70
Tack Coat ronnes 2.7537 62,67L.01 772,s77.76 62,677.0L t72,577.16
Bituminous concrete surface sq.m. 2010 633.63 7,273,596.30 1,011.50 2,033,115.00
Thermoolastic reflectorized Davement markinc (vellow) sq.m. 106 865.05 91,801.30 866.05 91,801.30
Thermoolastic reflectorized Davement markinc (white) sq.m. 72t.5 858.85 104.350.28 858.85 104.350.28
TOTAL COST = 2,302,457.@ 3,061,976.30
uNrT cosT/sQ.M. = 1,145.50
AC Pavement on PCCP
TotalUnit TotalUnit
Description Unlt Quantity Amount Amount
Cost Cost
Removal of existlnB asphalt pavement so,m. 2010 46.05 92,560.50 46.05 92,550.50
Sealinq of ioints and cracks l.m. 775/. 110.09 193,097.86 110.09 193,097.86
Tack coat tonnes t.2a6r'. 62,67r.O7 80,619.99 62,677.0L 80,619.99
Bitumlnous concrete surface course 5q,m. 20lo 633.63 7,273,596.30 1,O11.50 2,033.11s.O0
ThermoDlastic reflectorized Davement markinc (vellow) 50,m. 106 866.05 91,801.30 866.05 91,801.30
ThermoDlastic refl ectorized Davement markim (whitel 5q,m. 127.5 858.85 [email protected] 858.85 104,350.28
TOTAL COST = 7,436,026.22 2,595,544.92
UNIT cosT/SQ,M. = 913.45 L,29t.32
B3 ACP
AC and C.ourse
Direct Unit Dlrect Unit Direct Unft
Des6rlption U nit Quantity Amount Amount Amount
Cost Cost Cost
Sealinr ofcracks and ioints on existinr DccD Lm. 2926 61.85 180,973.10 61.85 180.973.10 51.85 180.973.10
Asphalt l6vellng course so.m. 670 84L.79 563,999.30 841.79 553,999.30 841.79 563,999.30
Geot€xtllc pavlnS fabric with glass relnforcement sq.m. 670 489.35 327.a&-50 489.35 327.84.50 489.35 327,464.50
Bitumlnous tack coat, emulsllled asphah ss-1 tonnes 2.7872 57,tO7.7l 159,153.89 57.701.71 159,153.89 57.L07.7L 159,153.89
Bitumlnous concEte surface wearing cours€ sq.m. 3350 847.79 2,819,996.50 1,340.35 4,49o,205.OO t.673.77 5,607,129.50
Reflectoriz€d th€rmoplastic Davcm€nt markln! sq.m. 202.5 3,873.2r 772,L75.03 3,473.2r 772.775.O3 3.813.21 772,775.O3
TOTAL CosT = 4,824,L62.37 6,494,371.41 7,61X,295.31
uNtT coST/SQ.M. = 7,44O.O5 1,938.62 2,2? 2.O3
cou rse on AC
Direct Unit Direct Unit Dired Unit
Description unit qua ntity Amount Amount Amount
Cost Cost Cost
AsDhah levelinr course 50,m. 2070 8/.l.79 1.691.997.90 44t.79 1,69t,997.90 u7.79 1.691.997.90
Geotextile Davim fabric with dass reinforcement sq.m. 2010 489.35 983,s93.50 489.35 983,593.50 489.35 983,593.50
Bituminous tack coat. emulsitied asDhaft ss-l tonnes 2.5728 57.101.71 146.911.28 57.101.71 146.911.28 37.707.11 745,97r.24
Bituminous concrete surface wearint course sq.m. 2010 8r'l.79 1,691,997.90 1,340.36 2,694,723.60 L.673.77 3.364.277.70
Reflectorized thermoplastic pavement marking so. m. 72L.5 3,473.27 463,305.O2 3,873.27 463,305.02 3,813.21 463.305.02
TOTAI COST = 4,977,805.59 5,979,931.29 6,650,085.39
UNIT cosT/sQ.M. = 2,4'16.52 2,975.09 3,308.50
A. CONCRETE PAVEMENT
Length = 500 mts
Width = 6.7 mts
50 mm. AC Overlay lfi! mm. AC Oveday
Sdreme A3 Ac overlav with Pavinc Fabric
Total Unit TotalUnit
Description Unit Quantity Amount Amount
Cost Cost
Sealinc of cracks and ioints on existinc pccD t.m. 2926 113.15 331,075.90 rl5.l5 331.075.90
Geotextile Davine fabric with qlass reinforcement 50.m. 670 654.@ 438,582.00 59t.60 438.582.00
Bituminous tack coat. emulsified asDhalt ss-1 tonnes 2.7472 63,918.19 fi4.152.74 63.918.19 l7A,!52.7a
Bituminous concrete surface wearing course sq.m. 3350 677.s3 2,269,72s.50 7347.57 4.648.359.s0
Reflectorized thermoplastic pavement marking {yellow) sq.m. -to 877.00 74,032.OO 477.00 14,032.00
Refl ectorized thermoDlastic Davement markim (white) sq.m. 202.5 869.80 776,734.50 869.80 776.734.sO
TOTAI- COST = 3,407,703.68 5,786,337.58
UNIT cosT/sQ.M. = 1,077.22 1,727.26
1 Seat and AC
Total Unit Total Unit
Description Unit Quantity Amount Amount
Cost Cost
Crack and seat ofexistinc DccD (with asphalt levelinq course) sq.m. 670 747.46 497.04.6.20 741.86 497,046.20
Bituminous tack coat, emulsified asohalt ss-1 tonnes 2.7472 53,918.19 174.752.74 53.918.19 774.752.74
Bituminous concrete surface wearinc course 5q. m. 3350 677.53 2.269.725.50 L3a7.57 4.648.359.50
Refl ectorized thermoplastic pavement marking (yellow) sq.m. 16 a77.OO 14.032.00 877.00 14,032.00
Reflectorized thermoolastic oavement markine (white) 50.m. 202.5 869.80 176.134.50 869.80 176,134.50
TOTAL COST = 3,135,090.98 s,573,724.94
UNIT CoST/SQ.M. = 935.85 1,645.89
on PCCP
Total Unit Total Unit
Description Unit Quantity Amount Amount
Cost Cost
Sealinc of cracks and ioints on existins pccD l.m. 2926 113.15 331,076.90 -t15.-t) 331.076.90
Bituminous tack coat, emulsified asDhalt ss-1 tonne5 2.744 63,918.19 737,040.60 63,918.19 t37.0/,O.&
Bifuminous concrete surface wearing course sq.m. 3350 677.53 2,269,72s.50 7347.57 4,648,359.50
Reflectorized thermoolastic oavement markinq lvellowl 5q.m. 16 877.OO 14.032.00 a77.OO 14.032.00
Refl ectorized thermoolastic Davement markinc (whitel sq.m. 202.5 859.80 776,t34.50 869.80 176,134.50
TOTAL COST = 2,928,009.50 5,306,643.50
UNIT COST/SQ.M. = 874.03 t,58/.07
BUKIDNON{OTABATO ROAD
B. AC PAVEMET{T
Total Unit
Amount
Cost
53.918.19 82.224.36
L347.57 2,749,O15.70
477.OO 74,O32.OO
869.80 105.680.70
TOTAL COST = 7,563,772.36 2,990,952.76
UNIT COST/SQ"M. = 77a.OO 1,488.04
C SHOUTDER
Length = 100 mts
Width = 3 mts
A CONCREIE PAVEMENT
Length = 500 mts
Width = 6.7 mts
50 mm. AC Orerlay 80 mm. AC Ov€rlay 100 mm. AC Overlrt
Sdrrme Al Concrete re-blockinc and AC Overlav
Oirect Unit Direct U n it Direct Unit
Description Un it quantity Amount Amount Amount
Cost Ldst Cost
Removal of existins Dcc oavement sq,m. 674 260.39 714,46L.30 260.39 77 4.46L.30 260.39 774,461.30
Subcrade oreparation sq,m. 670 25.31 t6.957.70 25.31 76,957.70 25.31 t6.957.70
PCC oavement (olainl. 230mm thick sq,m. 670 1,023.04 58s.436.80 7,O23.M 685.436.80 1,023.04 685,436.80
Bituminous tack coat, emulsified asDhah ss-1 tonnes 2.144 55,895.89 119.840.79 55,895.89 t79.8r',0.79 ss.895.89 119.840.79
Bituminous concrete su rface wearint course sq.m. 544.80 1.825,080.00 865.15 2,898,252.50 t,079.76 3,617,196.00
Sealinr ofcracks and iolnts on existinr occD l.m. 2926 b-t-65 180,973.10 b1.65 180.973.10 61.85 180,973.10
Reflectorized thermoplastic pavement marking sQ.m, 3.813.21 772.775.O3 3,813.21 772,175.O3 3.813.21 772.t75.O3
TOTAT COST = 3,77 4,924.7 7 4,E/.4,@7.21 5,567,0d,O.71
UNIT COST/SQ"M. = 1,t26.84 t,447.79 1,661.80
TotalUnit
Amount
Cost
58,604.81 75349.23
961.83 1,933,278.30
473.77 1o,485.24
866.57 los,2a8.25
TOTAL COST = r,4o2,4O8.82 2,r24447.O2
uNlT cosT/sq.M. = 697.72 1,056.94
c. SH(X'LDEN
Length = 100 mts
Width = 7.4 mts
22,012.76
t57.23
F
o
o
u) (J
Xo
=lu
lrH
=N
lu
F
l-l
ADB TA 7093 - PHI: PREPARING THE PHILIPPINES ROAD SECTOR IMPROVEMENT PROJECT
ASSET PRESERVATION UNDER TRANCHE 1
CONTRACT PACKAGE 1
LOT 1.1 . BAUANG - BAGUIO ROAD
PROVTNCES OF LA UNTON & BENGUET ( REGION t& CAR )
SUMMARY OF COSTS
(For lmplementatlon, L = 30.978 km.)
(1) 12) (3J (s) (6) t4 (8) (e) 00) (11) 02) (13) (14) (15) lt6) 07)
Araa4 P.ovid€, o!€E!. !!d U!i44t lwo Pi.k'up rrE9!Q9eq!!_19l6!v cab, s6tu cr .aaoo 119.e1q:I! ! 59s,60130 r0 00 1000 2!.9q zrs l2o3s 517,766 67 1.236,887 05 2,679 967.U 637,340 65 4132493 20r 3537r
V6hicl6lor th. Enaineers (2 unib)
A 1.3(a) P.ovid€ a!!! !,leinEin s!ru6v Insiruil6n!./ Equipmsnt lor !h.3g]!Eac. to 1r.oo 419? 1c 4L!!9 oo 1o.oo 1q 00 20 o! a63iooo ao.sal.?a e5.3!!!! 283 157 2S 3S 533:S! 56 71210
fF Enq'no.' { Sch.dglqql
a 1,91b)
4.1.4
o,@,.'on or [email protected] P.,.o.nsl(sqt'.d916
o,opre$ PholoqraphB
!) -.' 12.OO
12.00
56 5a3 S3 678,5260Q
5Zt!!
1q-09
!Q 10 00
rooo
10.00
20 oo
2000
r35,705 2o
11t!!!!
jL1eL11
3.343.36
233,412 94
19,93136
2 9??49
21 254 gA
799.683S7
4t.271.82
r09 432 67
9,344 56 77 A7l
7s 994 9r
6 489 28
TOTAL OF PART A 9 326,874 oO 1 S65,374 80 1,343,069 a6 5,S0S 947 53 2 340 236 65 12 r35.3rS
qP!'l css44q119"rori *o 1941. t: 45r1494.05 451,394.05 19.S 20 00 90j7€.3i 6\012..7! r5s 451 9! 6 397 23 526056S{ :1? aa1 4l 6!2p45 60
Envomenral and 505,009 00 ro 00 q!q90 o0 72,720 00 173!7?9:09 jJ8 720
9P1,2 SociAl Saleguards Lsq _ llqqqp.00 t9 Q0 20 00 t 9 384 06 587 089 5,4 OO
o,qd 9t!l!9! !l 1cp99!9 13.!q 00 20 0a 31900.00 ?,!9? 99 6 192 0! 3 46!.29 124217e 2,903 04 24 r92 oO 24,192 00
s74 a94 05 194.97981 335 363.55 26,244 4e '| 126,774.2C 157,230 91 1 110 257 50
€AFTHWORK
488.0C 305.11 14q qqt! 1000 10.q 20.0c 29,n9 a3 21 4!913 st,?19!! 125,099 41 53.656 56 ?00 r 13 72
Subcr.de Pr€p.i.u9n _!q m. 4,019 0C 20 91 31e9L!! 10.00 lq.sq 20 0c 12,1lzjrs 28.99!?1 7t 198 q2 33 310 9€ 1131287 53 2A 19
JPL I03 C,*i and Soet tEr.inq PCC Pa!€monq !q.!1 7,000 0c 593 47 3 734,285J3 r000 1000 20 0c 746 457 09 537,137.14 l?44,594 1S 3,263 4961! 516.91160 1,238 071 63 : r1a,a79 61 716 93
TOTAI OF PAFT C 3.967,4708€ 793 494 r€ 571315.81 1 364,809 9€ 3,460 193 92 1,330 039 15 5 332 240 a6
!oo aggrolete suoo@ cour3e 99! 9a 0c 47254 46310!l 1o oo 1000 20 oc 9?9?13 6,66q 74 15.93!q 29 Sag.aq 16 6s7 14 15 734 98 62.24155 635 12
201 &q'.e9!, B&. co_uL.q 540 0c ?q!9q!q3 2a oc J2,366.33 37,7O3 4 i37 919!! 90!!21 42
TOTAL OF PART D 308.r42 3C 61 628.4€ 44,372.49 106,000 95 167 769 37 150.2r 7 48 9615640
INOIRECT
DIFECTCOST COSTCOMPONET
IT€I/| qUANTITY UI UNIT
DESCFIPNON UNIT
NO,
uNrcost ocM TOTAL rosT cosT
suBFACe COUASE
301(1) t9t1!rq 3.OQ 14q€q0 08 1000 10,0q 20 00 ?al3?n2 20,255.05 4S367.07 137,970 1! 25,899 94 24,17104 r89 0121 1! 63 015 72
!0?(?) r9!!a e7.qq 45 305.4,4 4.394969.16 10.00 ?9!e €7€,933 23 632,831.9! ! s11 765.1Q 4 316,?16 3€ 450,773 93 739,,141 03 i.)06431 32
310(1). !!!l 238.81?,Q9 475.S3 113.896 06s 81 1q,0q ?0.00 22.779,2131e 3! 180,246 q 23243,63t T4 25,593_59312
111(1)b
sPL3ra
!94
l4.
31s9 . 39!.i 54 22
1.9!4J!Z q!
lu sq 79,82 a,{ 321,541 7S 9341?14 150,16279 1 096 53
?114e 0o 2es,ze934 642 742 47 1 620,615 29 494,37409
!sI'. 95!.!? 2,463.4516,{
3,7r4.59454 r0 00
572f19.!! {12,394 64 2 517,205 53 660,69!.53 r.233 0l
eL31a 20 00 742,91a 91 534,901 51 1,2f1820.52 3 405,535 21 113 365 6r 4 992 41s 9! 71324
TOTAL OF PAFT E 127 ,392 724 1 1 25,474,544 02 r8 344 55r.70 43,e23 095.72 116 574,132 91 26121 750 A1 24,515,832 65 171 215 615 83
MISCELLANEOUS STBUCTUAES
605(r)! l!am..g S.f.! . 12p oo j!1?6.t3 659,02154 l0 00 1q 9q 20.00 133,304 31 9633910 234143 41 332,720 41 442 641 27 123,843 27 199 rq!95 7 ,024 73
60q{uL 83 00 2.19{!! r73 453 94 i 0:00 20 00 35,77079 61s2!]! q6,325 37 117 7232l !qq99 62 2.s9q 1,1
60s(21 &eulalory Sig.! 9oo 5195r.73 3lJZ!!9 r 0qq 7,rs !q 5 150!4 17,670.79
60s(3) nlormalory Sqn3 15oO rs 98q!? 239.437 52 ro q0 2Sq9 17,967 52 34 536 Q? 82 504 !1 1r4,041.01 167 668 21 40,592 4a 2r,489 45
9120) Lei*rorized Tnemopl6lic Pavom.nl Mqtr^o. (mit ) 19!, 7,3r30! r0 0q 10 00 20 00 940.3!9.93 6f10?445 2992.52714 r-q€4p76 r r .i rr€,376.3? 454 o€
612121 691eaorizcansa9p1991919v6-d9nf !34!1r..Ci![o;) lp09 00 644.2€ I,166 a6a 90 20 00 233,373 7a 163029.r2 7/11 1OB 56 465,644 22 36r,475 ol
TOTAL OF PAFT H 5,S91,497 27 1,394,37945 1 006833.21 2,145 212 66 4 244,433 77 3 031 687 22 2 030,9S8 94
sPlgoo Vobih:ation !.d Omobiloaton [1b ol Civl Wd* C@t) L00 1,406,397.51 1.406!92!! r0 0o 10 00 20.00 281.229!q 292.,2114 443 800.74 '| 25f,543 fA 308131.27 324.513 29 1 Jgo 19-16 r 890,198 25
PFIOVISIONALSUM
SPL looo Pros.'on.r Sum q 11]?,667.9S 2149 933 79 !?!5 614 03 73712O 1Q
PERCEI{TAGE 19 17,!
ADB TA 7093 - PHI: PREPARING THE PHILIPPINES ROAD SECTOR IMPROVEMENT PROJECT
ASSET PRESERVATION UNDER TRANCHE 1
CONTRACT PACKAGE 1
LOT 1.2 - OLONGAPO - BUGALLON ROAD
pRovtNcE oF ZAMBALES (REGTONS il )
SUMMARY OF COSTS
(For lmplementatlon, L = 65.549 km.)
PART C EARTHWORKS
PART J
PART K
PART L
ADA TA 7093 - PHI: PREPARING TllE PHIUPPINES ROAO SECTOR IMPROVE EIIT pROJECT
ASSET PRESERVATION UNDER TRANCHE I
CONTRACT PACKAGE 1
LOT 1.2 - OLONGAPO. BUGALLOI. ROAD
PROVINCE OFZAMBALES, REGION III
cosT
376 534
47,1O3.r'l
,(),632 46
12,421
3.ra,7li 2.58
2,702 511
2A24,t,q32
olREcl coaT NDtiECt
tIfl IAFK
coST cotPoiET
Io. DEaCFtPnOt{ u{lt ocr TOTAL TOTAL
TOTAL
cosT
UIIIT
cost
ul t cost TOTAL FOREtOIt LOCA! TAXES
(1) t2l (3) {.) (6) (6) (7) (8) (e) (10) (13) (14) (15) (16)
{11) 021 07)
MISCELLANEOUS STRUCTURES
to .nd DdioO{Eddr fi r ot Ch,ll Wort Co.0 1.C 4.120 4.t20348.96 t0.0 to.ot) &4.O77. s6161aia t72117 al 5 as, e'2 7a
'l
TOTAL OF PAFT J 4,120,3€€.96 3,735,660.31 961,619.71 e72,411.41 5,537.442 76
ip_a rm i e66or-u
17,323,807,61 6,046,062.73 9,164,2€4.1( 2,079,454.t( 17p2A,AC7.ai
PEFCETTAOE ta,
ADB TA 7093 - PHI: PREPARING THE PHILIPPINES ROAD SECTOR IMPROVEMENT PROJECT
ASSET PRESERVATION UNDER TRANCHE 1
CONTRACT PACKAGE II
LOT 2.1 PALO . CARIGARA. ORMOC ROAD AND DAANG MAHABLIKA ( LILOAN - NAVAL HIGHWAY )
PROVTNCE OF LEYTE ( REGTON V t )
SUMMARY OF COSTS
(For lmpl€m€ntatlon, L = 36.120 km.)
0) (2) {3) (4) (5) {6) (7) (8) (e) 00) ( ) 02) (13) 04) 05) 06) (17)
SUFFACE@URSE
30t {t) n'rc6 Pnm. Cor MC - t0 Cul-brck Alohd !s.8i ?.o€ a eir,sss a3 20,@ 9€9t q.6! a,s9€,955 3€ 452.211 96
3U212) n,mus T.ck Co!t. Ehulal.d &jlqLql{ 51q 49,225.57 2654,160.?7 10 00 20.00 531.0!q.r9 962,71309 2.q19,932!! 503,133 77 445.923.33 3,572.59496 66,159.r7
3r9(!)! himN concr€r€ sudlc. (w.{inc)c9!,!., !9r!441!@q !!&!l 196-7!!g t000 19 90 2q 00 I9,939.919!9 34.240,201 83 21 7a5,30AAC 133,931.95r 34 6B A2
!1111tI dand Cement Cdcr€r. P.v€hont, Plton z@nm lhk l5t L1 L492352 43 ?0.so 393,470.49 1,545,369 23 690,435 20 1 702,16611 6,03i/,4r.qq
sPL312 lmo ol cracrs ed Jor.E (EiErhs PcclL 52,629 0( q9.!! qq5-4!.€9 3129,75172 6,0r,'.72393
sPLai3 :hinq!!rc$d.. L09q1l :1! 2,101,947 AC 652,323 36 4,O32F7914
tonib Pevino F.bic whh Gl!.. R.lnlbrc.m.nr 5,000 0( 532 93 10 oo m.00 532,925.11 393 ?06 03 916,631 t9 2,451,74174 504,249S0 624,22514 3,53r,256J6 71625
MISCEILANEOOS STFUCTOFES
'ninq siqc
tr i!l r!! !{
5,213.5 93 da3.1o 1s,76s.6i 13 513 41 32,242.43 16,q9!4 62,041 20 126.12!.1] z9qe e!
1q!
5,9!!!1 zr.33!.rl 20.0o 15,/166.11 ?q.6!!l!
?r.{ l5lq9!! 10.m Jq ?et 69 ll5,363.41 159,59531 234,39531 56,73137 21,462 96
.cldiz.<lTh€rm9latc Prv.n.nr Muring., {whil6) !9!. _5r7rt6r0C
q3e 14! ?,671,14.11 10.m 20 oc t4?73 o1 r,264,345.54 2,360.40467 193s e?q:q! 9!91?
bcrdt d Thdnroellrtic P.v.n.nt M.rtinc., fi.llow) 10.00 20 ot 44 362 6C 3i 94r 07 36,9592: 59,027.51
l
101t31! R€nov.! ol Ei.linr AC Prv.mMt 1,533.00 1qq6f. 1 1q,6q1!q 5,901.27 21,40736 t2,99000
rosrii l S!bsr.d. Pop!trldon 37,asaool 199,e75.96 156 195 16 212,09510 30,374.55 312,904.43 1.qq3-9111!. ?3 33
cr&k od s.ar (Eri!0.! Pcc P.v.mmU 5,r)oo.ool 2,131,grc m a4f.!9191 330,031@ q96,46r 76
0) t2) (3) (4) (5) (5) (7) (8) (s) (t0) 01) (12) 03) 04) (15) 07)
!xr2,2aG.51
MISCELLANEOU9 STFUCTURES
.!6 8lqn.
14aeos6
2,95174
4q9la8l 13,3it1 9C l$t!!a!
{.r eu.q r,74! 6r 1.,592.9_9 2,643.10
3,€!!.3j 94.q22.33 3,@?.q!
\,4,! !Q7:94r.rl 21,4710!
F.nrbrr..d lh.rnroobirc it{tim..
Prwrn.nr lwhlgt 3:r5,3t0.53 625,106,76 r,!49,9! 933,393101 7at,/(}9.35 ?-41f]2.!!
&!q!IE!dra"oobrdclry9q9d!!!d!!r!, (Y€Io!v) 291 2f to19.92 64,547.59 53,39? a! ?52!!35.09
TOT L FOA PAnt C, O, E I H {LOT 2r b) t30220.101.9€ t 42t247.12 29 315 450.6,1 t75.0rt al7 03
MOBIUZATION ANO OEMOBILIZATION
gobllE dd md Dsnobiuz.rlon l1r. ol ctulrwod c@rl t.0c 20.0c 535 700.1 2,3719Os.29 610,579 a3 ,599.90459
t-0.@
6€5,226.0( 22tt,of7.19
1,403,874,31 3.oar.a55-01
-runr33d 133a,.!t!:e2 11.403.874.31
SUMMARY OF COSTS
(For lmplementatlon, L = 27.010 km,)
GRAND TOTAL
AOB TA 7093. PHII PREPARING THE PHILIPPINES ROAD SECTOR IMPROVEMENT PROJECT
ASS€T PRESERVATIOTI UNOER TRANCHE 1
CONTRACT PACKAGE II
LOT 2.2 tLOtLO. CAPTZ ROAO (OLD ROUTE)
PROVTNCE OF tLOtLO ( REGTON Vt )
DIFECTCOST NDINEC
COSTCOMPONET
ITEII UNIT
DESCFIPT!ON UNIT
NO,
UNITCOST octrl TOTAL cosT cosT
(1) (2) (3) (4) (5) (61 (7) (3) (e) (10) (r r) (12) (r 3) (r s) 117)
lo. t'o E.9!!99!9q8944 Bl 't2.oo 10.00 10.00 20 00 44,000 o0 34,5600C 42,560 0c 000 2B3 452 30 322 560 o0
4.1.1{9)
49. . t?.99
r2.00
15,000.0c
r r 7,964 a!
r0 00
r,4r 5 626 67 1o 00
r0 oo 20 00 .3q,qq0 00 25,92000 61,920 oC 212 AA9 60 ?9,0304C ?4r,920 00 20,160 00
10.00 20 00 ?Q3.8s0 24 496.929q 1 606,552 37 229.312.21 I 90? 642 24
EAFTHWORK
10r(3)b R.ddar oi E!a!!e4q!ar.d./,t 1,122 491 04 20.00 2Z!.41/.41 161 540 53 943,62129 122,1e2 9A
105{r) s!bsr!@!!!!q!!9n 12r.10s 00 ?1.91 ?!&4 ff2 34 109! 3lt.oB122 ?,2O1,774.f3 259,2r9 39 r,029,3r99? 3-!!q.3r4.03 2A 9l
O.cr.nd Sear (ENtnq PCC P.v.mc^! s,009!9 395 2U 22
-
TOTAL OF PAAT C s3r 93r 97 2,226 241 92 5 55r,892 33 770,11425 2,376 025 13 I694031 70
200 &Loga!€ rslqbele CouEo 2 0oo 00 4qql! 10.00 10.00 20.00 1q4,697.04 140181 87 334 676!? 345.597 69 3,1 t4t.4s 654 18
201 Aggr.q.l€ 8al9 Co!E. . -.!p19 00 2rq!1353.09 10.00 1 231,269 62 1 213 640 32 T2A 459 2e
{1} t2) (3) (4) (5) (6) 17l (€) {9) (10) or) (12) (13) (15) '16) (r7)
39q 9,948,215 57 r00o 20.oo J,997,643 11 1,433,303 0,{ 3.435,9a6 1€ 5,556.i37 42 4,705.733 0o 3,r5229131
301(1) 2,444 260 79 r0.!9 10,09 20 0o 43_!05?:1q 35r,39755 2,396.450 74 { cls94 !:19.710.50 66,932 a7
qz!! 44.202 7A 3,229580.59 10.00 !q!q 545,916.1? !!!pse6r 1,110,9751! 3,176,262 3A 621,457 05 542 836 gU 4,94!:55j,32 64,744 42
3rg{1Ie HglL.id l oDm t'i !l 2!!094 49O 47 10.00 1o0o 20.oo 4,q19,694.09 3,2t70 r82 63 4,249440.72 20 554.994.65 !,502,419 3r 4,925 265 35
3r0(1lb e/,5Ee!! 77,376699.45 10.00 10.00 20.00 15,475.339j!! 26,617,534 6r 7r 315,744 39 r 5,6?1 92q9q llL! 21o t2 103 99.4,284.06 r,065 85
31O(l)c !-lor Ltid (looqm q'i4l !!.!t- 35,!!ZF!? 9! 10 00 r q,00 20.00 Lqq9-5ts!q 5,06!l!!lq! 12,107 958.12 32 330,776.47 7 066,963 49 LqLr94 17 305,510.73 1 368 06
45.2€ 294 215 19 20,99 42-qq6!9 101210.03 ?!?.3oo 2e 72 925.32 395 425 21
59!.91!.9! 4?q995 6? 1,!24301.49 4 450,810.63 1,r29,692 73 1,492 622.6? r 334 63
SPL31 10.00 i0.00 20 oo 539.640.61 p4,22124 917,86r.06 2 446,917.80 513,144 39 6260Q2.73 717 21
263 55A 52
MISCELLANEOUS STEUCTURES
e.!! 5 236 72 4f,130 44 10 00 rq.Qq 2A 00 9,42609 qzqQ.7! 16,21247 2?47713 3t 123.55 8,742.63 63 343 31 7,03815
605(3) n.lorv s.q.s 7.99 15.ese.70 111,997.34 22,3995€ r q.r2z !9
6r2(1) crorEg! l!9!49rlC!!!!! 6nr M.lking., (wlir.) q,t2?.o9 699 91 611,339 37 1 324,570.!q !!z0qq9{14
don2.d Th6moph.tjc Pawn€nl Mekine., fi.lla) 656 30 10.00 20 0c L/r4,347.79 355,540.41 653.943 38 a!9.010-!1 321,29194 aa2 0€
SPL 800 i:ario oo Oernouitr li* or CMI wqk Cot) 1.00 l,!!I.075 e1 1,737,075.91 10.00 10.00 20 0c 347,415 18 25013493 597,554 r1 r pJ3.4?9 r3 392,249 34 408,947 85
OAYWORK
PROVISIOMLSUM
SUMMARY OF COSTS
(For lmplemontatlon, L = 45.842 km.)
DIFECTCOST cosTcot{PoNET
ITEM UNIT
oEscRtPTloll UNIT OUANNTY
uNtTcost TOTAL
TAXES
cosT cosT
(1) t2) (3) (4) (5) (6) l7) (3) (e) (10) (11) o3) (14) (1s) ( 17)
4.r.1G) l! 1oo 1 377,649.4q 10 00 t0 00 20 0c 375,52994 270,341.43 645,911 43 1,492 670 70 252 356 09 373,53414 r 5?3 560 93 2 523.560 93
23 o0 11 304 35 260,00! 00 ro 00 20 0c 5?1000 00 14810S80 157 463.04 4.!qc1q
23 00 26,141.5e 602,176.42 10 00 t0 00 20 0c 120.435 2€ 86,713 40 2or,t!!.q! 290 188 07 421.199 Z9 97,638 33 809 325 10 35.143 05
TOTAL OF PAFT A 2,s26,832 90 r 819 319.69 4 346,152 58 6,324.227 23 L774 452 53 2 a7T,537 3l
qe!'l !8. 1S9 qs! 866 36 9!s4q5.36 10 00 10.00 20 0c !11117 ?l 12:1,217 94 9 e22 7A 1.002 45r 22 138,037.35 1r5C 31127 1,1!0,!1! 2J
L! 975 000.0c 75 000.00 3qr.ooo.0c 200,337 20
13,000.0! 2,se2 0! ?1.192.90
EARTHWORK
t€hov.l ol ErstrqAc P.wmnl 134,se3 0! 1p5jr5r r 61 10.9q 1,654,919 99 528 2794 I 912.266 es
101(3)b i€movalol Er6lrg PCC P.v6m€nl 313!! 341,66144 416,19131 1995 233 95 254 355 50 935,20103 3 145 aao 4!
192p) SuDlu. Common Erc.vBDon qu.qr. 50,672 00 142 29 z,?19.39!.34 10 00 10 00 ,! s9 t l+z,oitjt 1 034,291 24 2,440,362 41 10147?.19 2,454,141.03 969C/ra25
104(]) :hb8nlmort I'om Ro.4!etE evalion r6,391Q0 217.47 3-673,350 32 10 gq r0 Q9 20 00 523,9€2.45 1 253,632 51 3.qq3.!zt II 1,139,400 30 4 936 962 83 292 28
Qq(1) !Jbg,ad€ P,.p91!!9L 279.903 00 21.51 6020.260.05 20.09 1,2q4.0!2 0r 866,917 45 2.070.969 46 9,060 562 o€ 2 366,944 aq 909r 229 51 23 91
sPL 108 :,acl ano Se.!lErlt19 PCc o.v6m6rt) 3,000 00 548.98 I 646,934 24 10 00 ro 00 20 00 32e 386€! ?17.158 43 96,545 33 1,443 897 79 221 221 13 542,354 4 2,2 t3 479 62 737 A3
TOTAL OF PART C 25,77s,06122 5 155 012 24 3 711,606 32 4,466,62106 21,762191 9C 2 719615.47 r0,054,952 92 34,641 682 2€
asg'€ra!. qu!!!!9 qgyre. 2A 513 00 446 f4 lai73.ae2 06 10.00 20.00 !q$.502 36 4.174.2tj14 gssz,6so.lz 5 231 4asr!! apzi,s26 65 rs,65,6$ 3i
-oi Aqgr€i.r. 8sa Cous 104,292.45 ?9-9!q 4s 15,01411 !!fz! c9
z4qq9 l3!095!ss6 6e
30r(1) 3oc 19r301.24 2000 ?9qqQ.74 51,394 a3 25.635 30
?ozl?L 432!2f9 1_0,oq _2,3 4,6!1!l ]llr\17 e2
3ro(1). _!!t !1. .11.S9! 0j 4!q 79 1790,632.57 1o 00 t0 o0 20 00 633,85r.09 1 991,977 61 5,33546415 r 168 693 90 1278,45213 T 7426141A
3r0(1)b 251,672.00 7930! r99 567,458.15 2000 40 301 797 8€ 263,245 513 4
3Lgit)a 3E !!. 4r,105 o0 1,017!?
q?Lla
!.! 10.oq 2a 0a 5 034.364 27 1:11?!@ q! q4j9,9?9 0! I421,036 93 !!!5e 103 89 r,3640€
.{t!!' _ _qsQ q! 3 757,389 61 10 o0 20 00 I 295,942 03 3,044.353 A5
3i1(r)c 69.m. 1a2,563.0C 9,1,al 135 12L9?a.07 10 00 10.00 2A OA 27,024,394.81 r9 457,564.27 r5,171,656 0a 22145,441.24 $ 731,Aa5 A0 rar 50q 933 rs r,273 65
sPL312
sPL 313
!! 6,052 oC
3,000.04
85 26
993.02
!15,96!.s8
2.97907,r.10
10.00
10.00
r0.00
10.0!
20 00
20 o0
103,192.72
59!-q1!q?
f4,294.76
428,986.67
177,49t.47
1,024,80149
424.924 T0
2.67q,.4Sq.38
140,645.61
677,615.64
127,AAA.74 6s14! qq
4,003.475 59
114 58
r,334 63
5aC 64 20.00 24o,532.15 550,717 r1 375,q0L6! 2 r51 633 95 7t7 21
rri3,386 270.r0 a2,6tt ,254 02 19.521 622.49 r42.204,876.91 365,441,27124 82,260,r06.91 r1€,934,85237 555 591 147 ot
MISCELLANEOUS STBUCTUFES
6050)
6q![]q 2920A ?.167 9q 632 450 43 10.0q ?9!e 91.t30.4€ ?17 7qq!! 4tq??o 91 2 912 A5
605(2) ?ggldory Siq.s 5,971 72 7413f9.57 20.00 r52!31!!1 r 10 070.66 262 946.57 ?! tt?? 509.66103 i39 512 36 8 025 99
117.0! 1s,99e.4 643p55?Q !307,434 A2 317123 16 2,515,92027 21 503 59
012(11 0i6qq'j 4I!6moplastc P.wm6nt M{[r]$. (wrre) !!un 12,qlqo! 4.253 232 54 r0.00 20.00 2 839 1r2.00 5 272!64 t 74 2.5t5 011 36 11,092 344 54 874.86
612\2) rnecio.i2edThemod&ii.Pawm.nlM.rkino!, fi.llowl 6563C l.!14 7?9 63 10 00 to00 ?0.0! !q2.!199! 4412107 521 065 99 e95.q13 s! 599,450 82 47Q ?32.23 aa2 06
400 obili2.rion and Dohobiliz.iion (i % ol civil wo c6tl 4,66€,42992 4,66S,d2992 10.00 1000 933,765S3 672,3rr 51 1,606 077.49 993 647 47 1.353 0s3 da 6,2ta got ai
GFAiIO TOTAI 508 793 2,r9 56 117 t11243 22 r r7 B39 203 29 67s 95. e45 9!
PEFCENTAGE 17.
ADB TA 7093 - PHI: PREPARING THE PHILIPPINES ROAD SECTOR IMPROVEMENT PROJECT
ASSET PRESERVATION UNDER TRANCHE 1
CONTRACT PACKAGE II
LOT2,4 DUMAGUETE NORTH ROAD
PROVINCE OF NEGROS ORIENTAL, lST DISTRICT, REGION VII
(La Llbertad 0 Vallehermoso)
DESIGN AND BUILT
SUMMARY OF COSTS
(For lmplementatlon, L = 39.756 km.)
OIRECTCOST COSTCOMPONET
ITEII
DESCRIPNON UNIT OUANNTY IOIAI
NO.
UNIICOST TOTAL ocM TOTAL cosT cosT
FOFAG LOCAL IAXES
16l+{10}
(1) (21 (3) (5) {6) t7) (3) (el oo) (1rJ (r2) (13) (17)
a r/"l ?rov@. comb nod Fio! otic. .ni Lato;iot lor di6 Edia;6. on F;; 23 0! 10 0o 10 o0 2000 t54,240 0o
'rovid. Livinl ou.^./! lor $6 Engjn69, oq R9!q!]q!9!9 I q0!
23 Qq .00 r0 o0 ?0 0q q9.aq! s! rl3,63O 0O 55.64160
Jr€raG/Mlintan Combh.d F.ld Offic. L.bor.ro"y.rd E9 23 aa r0 00 ro 00 20 00 542 656 a9 390,7r2 96 933,369 85 129 430 4C 437,598 52 3 646 654.29 153 550.19
-ivinA q!.li!ru]gr lr. €ngin€q. Lsch€lol. A) -
529,490 00 20 00 ?6,246 56 zrr egr 6e
9!!:1 dructon 5af6v and H€altr 1.0! 857,340.86 457 340 36 10.00 10 00 ?s 0! 171.46511 l?3r457.08 ?94.925 26 t0 506 8s 1,AA3 4A/.29 138,27193 1,rtlr 266 12 1 152 2j6.1?
Ionm€.tal and Social S.l.Ouards 10c 20 00 175 000 o! 126,000 00 301,000 00 204 367 2A 326 492 8o I41,120 00
r4,000.00 20 00 B 467.24 2, 19299
1 750,340.a6 350 06417 252,O49 AA 602,11126 r 442 40r.35 242,294 97
/!lor Exetng ,1qlqy9r91! 156 354 0C 3!.91 5,619,34€.06 20.00 6,435 539 45 3,205 4r2 06
4tlql Exi{,!g Pcc P.ved6nt ?] q' - !1!.!9 1,167,678 09 10 00 io 0q 2000 233 535 62 r68 i45 64 401,681 26 98r 96r it 12714135 450 250 83 r 55, .359 35 421 l9
'to2t2l 37,7!9:q! 142 29 r,046,321 24 l.!!3.34 !9 191 4
!O9nr tm Fo.dw.y Exdvalol ?1111 4.1q1l!q?Z l arsg r0 00 320 31r ?5 !s !?t !! La3r.a24 57 292 2A
ld6 Pr.p.r.tio'l 242,217 0a 2151 20 00 r,2r4.005 09 ?.033,090 r7 3 000,435 9€ 3 r 5!.!29,91 ?9,91
ltL 103 sd S{r (Etj!!nq PCC P.v.n.nl) 3?9.13q9! 237,154.53 555,545 3a 1l43!!1ll 221 221.13
?s9 lal. subbB.6 cour; 32,199 0C 1a,672,62i 3e r0 0o 2000 3.r 1,5?! q! 1991,333 11 r4,530 955 5C L9q5 725.81 7 665,637 7€ 21 06" oo8 {9
201 late Bage Co!!!9 q9.992!! 10 00 10 00 20oo 1q 9q9l! 19,036 49 23,976 07 36 432.32 !q9r 1 17 21,329 96
1a,742,323 2A 2,256 494 54 5,415 359 la 14 617 349.32 a02163704 1 ,AA7 417 72 21 r5i,632 38
ITEX
OIRECT COST
IARX I]
cosT coltPoNEr
DESCRIPNON UNIT TOIAI UNIT
NO.
UNITCOST TOTAL oct TOTAL
FOREIGI{ LOCAL TAXES
cosT cosT
(1) t2) (3) (4) (5) (6) t7) (3) (s) (10) (11) 02) (13) (rs) (16) (17)
{14)
SURFACE COUFSE
!q t!?1!4 13524,351.75 te qs t0 00 ?9.90 2 704 a7o 35 4$q2,37r 00 7.536 721.q3 6311707.53 4,2!q?9q6! 14176,724t6
!9!r! 9!@?,€ r090 . t4.342 76 34!263 25 6q q?.!!
?l 4a.2O2.fL l Q-oq l0 00 1,060 rt59 30 763,530.79 113?!,949 99 5,2i4 756 99 r 020,302.62 891,224 a3 7 t2f,236 49
ur 496.79 l aas 10 00 ?0.00 221127 A'f $ 15,932,021:3! qqp59.828 8l 100,841 920 32 22 084 675.63 ?4. !69.1!9J! 118-696.866 05 667.69
47.5!4!! r$,q! 17.q15.602 67 10 o0 ro 0o 2O-0! lEq3 r 20 53 5,ru5,446 78 13,008,567 32 34,653 437 8{ lfa5p34 5s 4,334.747 55 50 824,r69 99 r 065 s5
3t I{l)a
t c.m.nr cq!q9!ae.!tujr. Plnn,z3oqrn t'r 160,033 0C
627 9a 3.767349.61 10 00 10.00 20.00 . 51?.!!!Jq 3,044.353 A6 600 974 69 r 414,043 09 5,064 371.64 q,8.9q
947.A1 !J1.1?]E4!4 !!,?15.504 16 21,444,763.43 !!r.194,2ff.r9 176,703.013 9! 34,439 212.22 32 {4o.qlq91 2!3 9?1 791 99 1 273 Aa
s ol Crlck! lnd Joi.t . (Exa.ijnc PCCP) I rn. 89-2q 293,533.15 10.00 200c 53,706 63 42,264.77 100,975 4C 241,738 60 80,0r3.69 72,756.21 39,r 503.55 114 53
n3 o!r9q9l!3 993.02 ?!l!!1Ltu t0 00 2A 0C .4?!,995.61 1,024,401.4S 2,670.49639 677 615 64 4,003 475 59 r,?31q3
xil. F.vinq Fabnc wirh GIE$ 8€i.lorc.m€nl 533.64 600,921
1 94 lo.oo 320. 234,532 75 1,463.1!0 6! 37s,501ql 2,15i €38 95 717 21
MISCELLANEOUS SIFUCTURES
qot0r Y!'a'!.s qhlq !!. s ita.n-1 701/4,6! 20.q 100,s4:Lg! 72,392 35 '1f2.91f.29 250,422 73 33r.964 51 675 66r 97 7,03A 15
6q5{1)b )h€vron Sien. 204.00 2,167 39 19.00 10.00 20.q! 90,r5S.5l ?13,4r s 53 295,417 63 2,912.45
5 9f1.72 !1ej9a.d2 10:0q 20 0c 79113 29 166,992 45 27r!7999! 356.314 90 140,274.41 4.025 99
6qsGI 34.00 15,e.991q 2q!q ?9q7e4 e0 193 532 33 462,327 23 $4,994 23 2?7,979:18 I 406 3or 73 21,503 59
612(1) 650.94 7.107 543.10 !0.0q r0.0q 20.oc 1421.5i6.62 1 o-2149Le2 2 445 008.59 4540,7919! 2,794,24466 2 217,564.34 9,55:591 69 37446
61212) 1,Z9qe! 656.30 1,U4 768 65 10.00 20.0c 234,953.73 169 166.6! 744,394.33 464,912 03 365,0!?.64 1,574,449.06 842 0€
TOTAL OF PAAT H 11,129,416.31 2,225,849.26 1602,611.47 3,828,460 73 6,659,493 72 5.191,915 96 3 095,897.37 i4,95 707.05
lob'l'z.Don.nd bcmob izadd trlb o-;iwo Cos0 l 3 7Ss 936.63 757,147 3a sasiaBi 3 Af32r- 1,!6Qp!?l! 5,044.29443
PENCEITAGE 17.
ADB TA 7093 - PHI: PREPARING THE PHILIPPINES ROAD SECTOR IMPROVEMENT PROJECT
ASSET PRESERVATION UNDER TRANCHE 1
CONTRACT PACKAGE III
LOT 3.1 DIPOLOG - OROOUIETA CITY ROAD
PROVTNCE OF ZAMBOANGA DEL NORTE ( REGTON tX )
SUMMARY OF COSTS
(For lmplementatlon, L = 20.682 km.)
.nd +p!!!4993
ie, L!bot.!9ry!!!!Y!ns
(Sch€dula B t C)
26,181
45,697.03
45 312 21
PccP.y9!!.!!L ,
574 754.1 504,73062
3 106,054 57
Mohlll2r ,on li D.mHlhrt].. 6 a 6l CMr wdr cdl r,o5a,o15.t9 1o.00 112,3E:9! 353957.5C 24eE2t.t9
r ,056.01 5,9! g€9,3o3.6r 242,A0r.fO 21e,2r2.\a
2721Xt2.15
r21,501,355.51
PENCE {TACE
ADB TA 7093 - PHI: PREPARING THE PHILIPPINES ROAD SECTOR IMPROVEMENT PROJECT
ASSET PRESERVATION UNDER TRANCHE 1
CONTRACT PACKAGE III
LOT 3.2 BUTUAN . CAGAYAN DE ORO CITY - ILIGAN ROAD
PROVINCE OF MTSAMTS ORTENTAL ( REGTON X )
SUMMARY OF COSTS
(For lmplementatlon, L = 19.693 km)
(1) t2) (3) (5) (6) (7) (3) (10) (11) (13)
02) {1s) (16) (17)
4,1,1{!L ti,mbn6d nold gqlc dd Labdatdi li' tl6 Enqin6d 9I-F?n!41 q 13.0c 260,000 90 j9 gq 10.00 20 00 9L4S 99 o o0 41,932 a0 26,440.00
A.1 1(b) jvi4 Auan.ro |ot tho Enfn@r on Rant l Ba. !19, t30c 10.00 r9.00 20 0c 24,040.00 230 630.4C 20,160.00
4,1.1&L Mdnt h Conbnod Fiold Off€, L.loqEry &d 1r1 914.q1 l,rtl{339 94 10 0o ro 0o 20 0c 290,977 99 ?09,504.15 73,34e40 234,644.65 r.e9!.?4ro! !50.{13.24
{t
G lor tr. E.snooE (SchoduloA)
.qqpnont Fuhrtu,.dFr([email protected] apdios
)nbi.6d FGld Olfrc.. L.bor.Lory sd -'vho
t, 1.00 529490.04 lq0q 10.00 29 0q t05.!e6 q0 7624655 402,395 62 212 343.53 7r 1,634.56
41.2{31 '.1€ &d M.i.t io 4wD Pick-up Typ.,qq !1. cr.w c&&ryE! 9E3100e.c 10 o0 t0 00 ?q!! 1e6_q01.06 523 297 3a 1,250 099.23 2 886,063 75 676,!q4! 4,3!1.ro!: ! ist8sb 33
. Engi^d. {2 un'EI
Al3l5l ,l.jnt i. s!to6y In*u,nsntt EqliFnent bl $o a..irr.nc€ &' r3 00 2r,657j! 2S1 a5o OC 10.00 1q,00 40 543 20 96853. !fu.157ts 34,533 a2 56 7t2 rC 378,403.20 29,107 94
d Fcnt l b!!.. 1 !9!19{ul99t
!o. l3 00 5ao6zaa 10 00 !!0,97564 i.as7.60 't2t,f46.16 r !rL4r!!!!! !3to42 rs
62,764 33 10 0Q 20.0c r 2.553 67 e.o$ q1 21592.31 2C 526.22
TOTAI OF PAFT A 9,560,595 98 1 91211920 1 ,376,725.52 3,284 S45 02 5 440 045 71 4 631,371 76 2 373,023.53
OTHEB GENEBALAEOUIREMENTS
aon.vudi;; s.t6ty q4!!!!L 100 497,4t124 497,511 24 10 oo 20.0c 99 502 25 71,ui.62 1t.t{!,!/ 6559.49 531,75L!! !Q-23861 n68 655 r1 66S 65511
SPL.? and Socill Srf.olards 505,000.!q 1o 00 10 00 20.00 101 000 o0 1?11099 461,324.00 67472944
=nvnonm6ntal
?r9i9ct Billb..d 100 14,000 0c 18,090.0c 10 o0 10 00 ?.5e2.!! 6.192 00 aaGi.2c 12,A21f6 2,903 04 241e2Q9 2\191AA
TOTAI OF PAFI-T B 244 102 25 146,953 62 351,055 a7 151 072 29
Lo!Q9 omoval ol Exiltino AC P.vrm6ni q?z!,!! 34.26 2al153g 63 10 o0 10 o0 56706.13 4!!?! !1 q4.!34.s4 237,709 49 3r p00 6r r r r,555 06 . e!plat6 46 05
r050I c!9!cd! el!p!!g!![ 14.96t.00 !94 ll24,947.25 1o gQ 161,992.4C 96pq13! 119,325.29 1.511 929.11 27 5l
10 00 860.803 50
tr, (2) (3) (4) (5) (6) (7) (3) {e) 00) o1) lt2l (15) {i7)
SUEFACE COURSE
9q0 8,246.q0 ql?.9! 5-41 9,328.91 10.00 to.0o 7s1,563,36 1745,iigr4 2,449 432.45 1 640 620.27 850 69
391(U lMC.70 Cul.b&k tuPh.l 1.00 1q,1s?l! 43193.73 -19,9q 1o.oo 6,939.90 16,578.64 47.286.63 I224 A2 a 254 93 64 JT2 38 64,77238
302(?) Emullili.d A!ph.lt, SS-l 46!530.?2 20 00 467,322.03 1 491,793.89 4,260,405 23 3401q1 10
3iS(1)q 39,038.00 471.45 Jq194 576.1a 20 00 3,680,915-4 6 331,r74.18 1Zq0!?19 ?! 3,706 319 91 24 715.74O 27 633 63
160,05900 10.00 2! qe 11193!91!! 21,264 2e3 27 26 29\9?9:3?
96!.3? 3!.3?3,565.5. 10.00 17,664,713.13 3r 340,!77 36
1?L!! 4,213.95103 342.-79q?1
93,142 00 16!?.92s 5e 1000 20.00 1,526,535.i,1 ?,6?!p4!!! !,15qq1q 23 L3t!.19?.9! 1!0 09
3rO0O.O0 2,635,7015e 20 oa 567,t10 32 1q€j41, 975 481 3,1 2.543,631 6!q,qq!q as!,l c?!! L2j0 !s
SPL ctera Boiitorconcq qq.qr, 65i3600 t3 01 a5 25t 241 f5 10 00 5 076 r85 1212644196 6832,632.12 4,274.930.73 47 .37? ,726 71 716 37
246 727 ,209 a3 57 3215 44181 41,283,71810 94.634.159 9t 261,805,71710 59 511,243 fE 6rr,Ol1.408 09 385,36r 364.9{
MISCELLANEOI.]S STRUCTUEES
6qq{[ 99.!! 5 205 37 510,175.24 10?,0!5 05 13.iq!.?q 175,5!0?8 3331334.61 6!5 67! 53
64,90 15,972.26 j,921,124.6e 10 00 r0.00 20 oc 147,200.36 351,645 29 715 649 54 t72 6A9 62 1,3731469 93 2146672
6,0250C 539.0? 3 850114.08 10.00 10.00 ?q sq /70,022.42 554,416.43 '| 324,439.24 2,429p11.22 1,554 S48.17 1 190 427 93 5,174,553 32 85885
2.898 426 79 10.00 20 0c 529.635 36 997,054.41 1 92L69),gq I,177 944 A5 3,495.445 60 46605
TOTAL OF PART H 8,280 940.80 1,656,188.16 1 ro2 455 47 2 848,5:13 63 4 991,836 2r 3,7A7 33t 17 2,3s0 367 0,4 1r i29,544 43
r00 2,990,aa7 60 r0.00 10.00 20.0c !9q.969.s2 2r30,6ro 05 1,026 679.5? 2,7ot,Ni ae 638,4210 30 94 7849 lpl9!o27 1f
2,990,347 60 2,702,4O4.54 677,1A2 29
12,604,242.54 1,5r2,513 9r
PERCENTAOE
ADB TA 7o9il - PHI: PREPARING THE PHILIPPINES ROAD SECTOR IMPROVEMENT PROJECT
ASSET PRESERVATION UNDER TRANCHE 1
CONTRACT PACKAGE III
LOT 3.3 BUTUAN . CAGAYAN DE ORO CITY. ILIGAN ROAD
PROVTNCE OF AGUSAN DEL NORTE ( REGTON Xill )
OESIGN AND BUILT
SUMMARY OF COSTS
(For lmplementatlon, L= 16.421 km.)
uodal€d 27 F.bw mr 0
AOB TA 7093 - PHI: PREPARING THE PHILIPPINES AOAD SECTOR IMPROVEMENT PFOJECT
ASSST PRESERVATION UNDER TRATICHE 1
CONTRACT PACKAGE III
LOT 3.3 BUIUAII. CAGAYAN OE OFO CITY. ILIGAN ROAD
PROVII{CE OF AGUSAN DEL NORTE I REGION XIII)
(r) t2) (3) (5) (6) (7) (3) (s) (10) (11) (12) :16) (17)
A 1.1(.) tdia€ coDbin.d Fi.ld otiile !!q L.bdltory to, $. Errfier q F.nd! 1?!9 20 090 00 ?10.!q!.9! 10.00 48,000.00 32,q500c 0gQ 243,452 a9
rwidouvi^9 ouan9lqb4lqElgl9or on F6^t4!4!9 12 0q 15,000 00 13!,!@ q! 1q,00 10 00 25,920.00 61 920 00 s!s 212,349 60 29 030 4C 20.16q!!
l1lic) )p6r.l./V..r.'n Conbin.d Fiold Otico, Labor.lory dd !? s9 111,914 61 r,3.1?lz5 33 10 00 10 00 ?6859507 193.334 45 46r 9q!s1 1 520,626 19 ?1€,qes 0€ r €04 954 a5
'Mntqgarc'! lor the E.gheeB {scnedul€A)
4.1.1(q) urni6r Eqlrpmenr, FurnrMes/F nJ'.. ed apd'u$ 9?9lC!qe 52q490 00 r0 00 761246 5! 1!?t!156 402 344.62 tr2,343 s3 96 e95 41 711 634 5a
r tl6comb'n€d Fi.ld OFce Labor.lory..q Liu.q
rudl.6 ror tho Enqinc.E {scnsdul.. I49L
4.r.1{c) 1.0€ rt77,6,1050 1 37t 640 aO 10 oo 20 0c 375.5?990 270,36153 1,492,570 70 252 356 09 378,534 r4 2!5231560 93
,f.r.1{r) l?.!! r6r,9qo oo 1qlq 2- oc 32,?0q,0! 5!!9!400 r0r 539 20 r3,032 O!
41 r(hi 12.9! ?6,181.56 1! 00 10 00 62.8353C 45,241.1A 104,07753 14?t9 5a 35,r4405
Ar 2(.1 24"aC 119t!!.29 9F9Ur1?s.60 717 a,ta- L29qsi2 5a 2,367 310.0! r 313,603 60 2AO,S19 26
Ar3(.) 12 0C 4,462 5A ?8ll!!!! !-oa 10 00 20.00 56 310.0! 40,543.20 96.S53 20 23.3,157.2e 3A $3 82 !q71? to a7B.403 20 31,533 6C
i29! 53,067s4 696.8r0 67 10 oq ?qq9 13936r.1q to!J40.74 23e,4231 ?,94!o 821,309 51 112 361 62 916j r 3 s4 ft.o4iia
4 1.4 t2 0c 4,828.33 57,940.00 r0 00 1O Oq 20.00 11 588 0! cl!! 39 19,9313€ 27 254.q 4t,271.q? 7l,a?136 6.44923
TOTAL OF PART A 9 264,724 10 1 453 744 a2 1,334,695.27 3,144,44109 5,796 290.32 4,334 227 59 2,330 647 2A 12 457,r65 19
ro!!q!qi!!l salgry 6! l!94r' l! 10! a55,r27.01 !!9,rzz.os 10 00 l ooo tt1L24!1 qs.qB2 30 15CBO7 71 s34 769.?q 73,564 l7 613.034./5 6r3,034 4
9P1.2 ntrmn€nlrl Md Seisl Sal€durd8 1.0c 505.000 00 50i!!q.gQ 10 00 10 00 10100000 72,120 0A 173,724 0A 13s.919!9 461 328 oO 674 720 00
SPL.3 rcFct 8'!lboard r0c r8,000 00 18,qoq.q! 10 00 10 00 20 0c 3,qqq.00 2.592 00 6,192 00 gNq,4 12 421.76 2,903 04 z1.r e?.00 24,t92 0A
979,127.05 195 825.41 r40,994 30 336.a19 71 149 095.15 1,004 937.99 157,913 61 1 315.946 75
EAATHWOFK
101(3). H6nda or E! !^g ruL F.l€N!! 7,4419! 297 1r 2211250.U i0.00 20 00 442?E9,9 3r8.420.05 760.67012 2,?4p92!9 3r r,973 7C r,094,38910
1021?I g!!Plu. codmon Eravauo! j.000 0c 13!?lgle 10.00 26,643.19 19,16i'.46 45,A2f 16 112 349.1q r3,460 q 52173610 119 95
104(r). Enbdrmlnl lrom Ro.dw.y Er@vaton !!,!r', !a!! q! 205 a3 20s_!?q9! 19 00 41,15!:ll 29,634.92 70f919! r70 633!? €0,46312 i19p2j,e2 27663
105(1) Suhg,.d. Pr€ea,quon .q.q- 65 992 0C 1,350,558 65 r000 10 00 ?9.00 2701114 ,164.592 25 1 13?t99!! iaa,lso 3e 670,610 83 I ar5.r5r r0 21 51
sPL 10! [email protected] S€.r {Ex'.0.q PCC P.v€n.!]l 523 63 1,s79!q2932 10 00 !9q 314175.q! ?26,206.62 540,342 4€ 1311942.?!) 216,?97 a] !16,44210 74375
TOTAL OF PAFT C 5,47r.732 83 1 094 346 57 737,929 53 1,442,276 09 5 425 427 52 747 894 0€ 2,414,64127
2oo asrres4gj@tse cou'.. !q?9qn. n'q] 45453 1-577,!?1!9 1o 0o 31a 504.$ 227,163 59 !1?i9C5' 1270,623 4 724,369 r€ 67asgo.so 2,r20 r93 55
1,577.524 96 315 504.9S 227,163 59 542 664.5! 724,36914 671.390 A0 2 i20 r93 55
DIFECTCOST COSTCOMPONET
ITEM UNIT
DESCRIPTION UIITT OUANTfi
NO,
UNITCOST octl TOTAL
FOFEIGN LOCAL TAXES
cosT cosT
(1) t2l (3) (41 (5) (6) 11) (3) (e) (10) 01) (12) (r4) (17)
SUBFACE COUFSE
q!L 7,31900 632,95 _4,632,531.65 10.99 20.0c e29,q!!!3 jgzB9r 76 3 220,564 & 2 779,2s?93 !e31 62i 42 450.69
30?l?L a!!9 _!94! 16 610 22 2.235 259.!0 10.00 447,650 0Q 322 304 05 769958.14 2,19!4t9]! 551,096 53 4J7 lA5 Aa 3.00s 208 53 64q71 01
3lq1la Ho! Laid (somm qick) !a!l 2_r5-!! 47t 15 1.2791994 47 10 0q tq4q ?s! 255,998.81 144 319 2C 440 318 10 1,274,149.94 277,7O3 !1 301522.04 1,720 312 5t 633 63
3101!)L Laid (e,olrlm tiq) isrr. 108€6e!! 752 6l 82,010.694 43 100q 1s!q ?9 !! 16.402, r 38.€l 1,S09 540 0C 28,21167aAA 95 340,645.43 20 781,45S 3l 22,516 398 33 110 222 373 32 1,01I 50
1!t0F J91 28 591,2a0 35 ?0.0c ir8,256 07 85 1,t4 32 479,156 9€ 94,0r0 21 221513.62 794 680 30
311F)c 17 200.00 1890 71 15,9?!??9.99 1q.00 1000 20.m 3 064,045 08 2.206113 q! 5.270 158.91 r5 671 523.55 2 918,730 0? 7,308 r45 24 20 590 3Aa 3C 1.r9712
sPL 312 ].I!- 2 440 9! 4191 leerqq{o! 10q9 3q97?.8! 26 fAO 42 3q153 22 205,161 01 L!99 5i 61 692 66 264 617 24 1!Q 0e
sPt3i4 9!.!- 3 000 q! 533 ol 1,5s9p9911 r0.00 31-e,9!?.?? 234 261 2C !q0.068.43 1 46!,91q: : 309_935 53 2,i49 r04 57 71637
215f4,346.17
MLSCELLANEOUS STAUC-TUFES
605illq
'F" 5,205.A7 244,675 88 10 0Q 000 20.00 48 935 1q 35,233.33 34.168 59 121,263.9? 162,526.29 4505417 iza sal rr 6,99669
?.L51.87 221,6424 10 00 20.0c 44 32451 3r.916.57 76.24514 146 212.0G 146,89413 44le179 297,887 9€ 2.49212
6 rory sqn. d4
45 00
4100
5,q4!!Z . ?9?-39s.14 r0 00
654,462.69
10 00 a0.q! 59 4qZ q3
r30.972 54
3!-496.q4 9r.964 66 131!6q2.23 1fe-]19!j 359.303 81 le!413
13f12.26 94,300.29
5rr{tI {E.d Tianoplaltrc P.@nt M.d.q.. (wri!.j 99,m €39!? 2,492,218.47 523 443 69 119.47e.4 99!!e23 15
61?\2)
'nz€d
ft,.mopl..tc P.v€4.nt Ma4^9.. (!.!A!L M. 1,239.!! 79q.qq3 35 1o 00 159 6ff A1 271,U5 59 245.9qq!1
TOTA! OF PAFT H a o79,127.3A 1 015 425 4a 1 747,219 82 3,422 269.24 2.711 535 23
sPL 8Oq od Oehobh2.l.on (1ir 9t CrvrlWod,.o4 100 1200.003.16 1 200!0!al q 10 00 10 00 24o,OOO63 172,800 46 41r,8oi 09 r,305,68r 95 319 669.S9 377,779 J! rfr28o425 1 612,804 25
'uon -
TOTAL OF PAFIT J
DAYWOFK
PFOVISIONALSUM
SUMMARY OF COSTS
(For lmplementatlon, L = 38.110 km,)
(1) t2) {3) (5) (6) (7) (3) (s) {10) o1) 02) (15) (r6) (r7)
A1114 P@id. cohbi;€d?lqd or&!]dl-abo..ri,.r, tolqqqslneel on nenrat e. 130C .2qq09.m 260,00000 1000 10 oo I 20 0c 52,000r@ 69,4,40 0! 00c 307 507.20 11t!? 30 26,860 0C
A i.11!L l10c 15,@!! rel@!! Lq00 I o.oo T 39,000@ ?6.oqqq 6l,080 oo 00c 230_899 40 262,080.00 2qiqoroc
.L1.{!t looo I 230,,r2!:q 22!!!!
,;l
_- t!2.696 91 442,334 29 rcr342 4C 26 1334,453 37
qub a)
1e)456
I
A.1,114L 529,a90@ 529,490.0! 1000 1o5,S9S OO 75,246= 402,39562 96€9541 21L534.s6 711634.54
.;; A";;;i;;i s"h Dr L:. 1!a rpt7.6!9l! L877,q49 50 loori 1o otl szq,q9!9 210,331 53 sis,sr r a3 i s92,670 7q 252!35€ 09 2,!?q!6!]93
A.t ]ll P.ovido.nd Mdnlain Qmnunic.lion F..i|iy lc{ $'!1E49i..€.
Drosd. sup!!!!r!!rc@!l;.bro sroo! It FDrd
13,7!!? 170,000@ 1000 | 3..q90!q 24,$A.q 105,772 AC r7 57!!!
Q@g.@ombry !C a!- 19-0! 2!,tgtl! 40,35q.!! 1! 00 ro oo I 20 oo 64.072 t2 49,01192 16!.019 3j 238.236 39 5t186 68 457,444 62 35134.05
Lri.n Ou.ne6 lor th. Englner I Sch€dul. € L F I -laoJ56 1
el9!!e, opo.altaad M.int.ln 4WD Pick.ue Tve. Ddblo Crd Cab, Sdicg 26 oO a5 3.95?.129.!! r00o 739,!!!.92 52s,913 69 r 256 349 S€ 2f 1r,28.a! r,3?4J94 SO 4,9031529,63
r'.h(lelo' h. Enqh..'. (2 urd.l I
A.1.qFL ?Iotld. q!4 !!!!!raii Sury€y ng!!!L.nre/ Equ pm€.Itoi tf'. q!!i9!qlEq!L 2r,q52.69 28L9!!!! 10,00 loooT 56 319!9 !qs49.?c 2A3)57.2q 56.tl2 1o 31q,409 20 2s rc,.47
h. Enqln€d on R.nlt od6lschodur€ G ,
o'ova'o^ ot suto.y Per.orrg!ts9!!!!lq H) l
.a 1 3{b)
orogr... Photoqrapht
19.00 5!.9q9!9
4.3?! !9
7?3,s4r.4
62,753 33 ,"-l 1499.q7
24e.036.t 3'o5?6€
29,526 22
!eJ!c.6,
1.1?!?3
TOTAL OF PAFI A 1 367,291 9e 3,266,306.5€ 5 455 205 39
EARTHWOFIK
3oo 9u.4- 23 205 0C !zzr! 24,717 .9962A lo00 ,o* 20 0c | i.aas.599.2: 3.t6!.4l qq a 513,3r0 71 r 3 6!a952 82 7.4!]!?3r3e 33,26r 3oii.97 1rl92l
9!11!l 2!! ,_ 49,15 !! e3,3!Z!? l! 00 ,0@I ?q,00 ]!.0!rl! 33,817 9? 96.567 24 r8,663 16 132125.84 66 062 92
!9?A lo'l!q !12,00 rzElll! 1q@ l'o55'3o3,4 l6f,o1a.32 !E!g!er 73 a95,527 61 63913 r9
- 100E !qn ??!ie3 o. 501.12 1 39,s36,353!1 !!9 looo L?qqo 27,907?12.q4 127669.03524 299s.625 75 3r,3r3,211 r6 r37,536 472115
lQ- s!.t! 9303,6,{0:!1 m00 1,761,f?311 1.264,144 !!3O,r 72 35 ! ?59,944 12 ?r19o,393 29 C!
SPL313 1qn l to6.43 3,o1e,€e.q! rs!! looo T 60s,4a7.93 2 690!272 A1 675.09060 1;t5211
'sPa3r4 wirh Glas F.rnrdq.n.r.! 532 30 2v1,475.57
184,196.739 22
"1 .32,2ea.11 343,25?4 915,547 60
167,rK10 32
s.ir71 516 r1
GFAND'TOIAI-
Annex 6
CONSTRUCTION SCHEDULE
TA 7093 - PHI : PREPARING THE PHILIPPINES
ROAD SECTOR IMPROVEMENT PROJECT. ASSET PRESERVATION UNDER TRANCHE 1
CONTRACT PACKAGE I, LOT I..I . SAUANG - BAGUIO ROAO
E|ll<IINOINE&
o{
o62 - o062
-
g.EAASE AND BASE @IJRSE
v(.
1.2fr5
PROIrcTION STRL'CTUR€s
MISCELTAN€OIJS SIR(JC'URES
/u,
I
o.a
/k^
I
-
TOTAL CGI
PERCEIII 1.505 17.471 17la 0.s03
scr{EuJtr
{(r1 1,4F
t ir11 aaa 3'OOO
7l,atl
87.
t4.10
f;,oo
irtrrtHlY l Arc(|aT 3112 3 556 3 166
-l 37.409 ro
-l --ttoro
I I
37 074 37 1 701
--rtz
ctul rrvE scl{EDir.E I
{IPI t.L l.{a t3.t ta rrrs ra.c I taa.ttT
I
ztozx ,
TA 7093 - PHI : PREPARING THE PHILIPPINES
ROAO SECTOR IMPROVEMENT PROJECT, ASSET PRESERVATION UNDER TRANCHE 1
CONTRACT PACKAGE I. LOT .I.2 - OLONGAPO - BUGALLON ROAD
I ti L It ta
ENGIIIGINEER
,{
4*
tqs23,a{a 50 326
o232
0161_
lora co6r
rcI'TIILY SCI{€DULE PERCEiIT : 0754 0 536 8515 I335 I802 4 015
curuLltlrE sctcttuLE (!4, o.76a 1a$ lt.oao ara. dt.l?l to.aaa e€.taa
a ta ri rt l. ta
0 20tt 6
o6 0.025 0 025 o025 0@5 0 025 0 o2a
0.13? o1a2
0 352 t*
2 545
o.2
ogzl
T16i
TOTA Cq3l
iiK|l{tHLY ScHEqrLE PERCEIIT 1.014 I670 I670 840 6318 6.314
l*/-, E.orl
32 rZS | 32725 I rz sor 17 907
| 3 089 3.579
0tu.
oza
42.256
11.310 ./,,,o
2.AA
rl'.,
OA
-11" .]
lt.tEa ,aa.l6 rt.tta
3.4er 78 3 ar.zoe*oi reea
--.*'-l - rta;l I
rcI'TH.Y SCXET'UIE 3.t51
**l
3 451 3:159 32 752 43.752 33 752
cu** t*
""ta""*
^rcq|T
tlp)
I
ararl
=€6, I
--rer.1
I aolls ttaaa r4?.418 ctrto I
=.*" I I I
IA 7093 - PHI : PREPARING THE PHILIPPINES
ROAD SECTOR IIPROVE'IENT PROJECT, ASSET PRESERVATION UNDER TRANCHE 1
CONTRACT PACKAGE ll, LOT 2.3 - Dumagu€to North Road (Negros Orlgntal, l3t Dbtrlct) Sta. 5{l+742€ta. 108+967
OESIGN AND BUILD
I l| It
4-
te
/-n
oy'
4.,o
E
I 75
XTfll|.Y tCHEq'lE I rCrcc'ar 119 6.(B 6,1@ 6014 6Zil 6237 6231 6-237 5 029 0
'190 l"ou.]
CIruLAIIIIE SCTCq'LE lo, 2.6f a,tt firoi !0rto 'fi|llr
j"s==-1 tt5/B Jg 6ral €.gt it.-l
- fOtItlY tct€ot LE- a36? T;;;
l-::::-
r15.012 45 01? 42,6 r*.t 43.447 438,7
-
43311
''2aat
!1.642 3||64 1667 |
------ o.n IT|!,E !q{@t/ll I rFl rara2 $.nI| 2t!.74 !i,o F.rt!3- lt 6ao !l6a.ta 6A aaa.tla s.!aa r@sl
-
TA 7093. PHI : PREPARING THE PHILIPPINES
ROAD SECTOR IIIPROVEUENT PROJECT, ASSET PRESERVATION UNDER TRANCHE t
CONTRACT PACkAGE ll, LOT 2.4- Dumagu€te Nortr Roed (NegroE Orisntal,'l8t Dlstrlct) Sta. Sta.108+967- Sta.150+523
OESIGN AND BUILD
t,l tt 1'
---
,K
,d,"
"/
4,"
0 !q- fF
rqrt cosr 15739i.329r0
ro ll{.Y lctfDrr€ E; 0 753 -,-t "a*
6 383 5g 6216 6216 6216 6216 6216 5S o5t8 o 676
cllflul^ttvE lct €DULE {1) o.at7 l.5m 3,&t a,xn to.dlt a!.047 tlt.2.0 !6.47! 6r..o4 at tto to.L2 t2azt 6.324 tqt.u,o
HTXIY SallEartE"-- 4.609 4 34' 5.Sr 36 63e 36 600 L 1t2 35.6f8 35 578 E;; 35 674 36 6?a 33.664 2 976 3679
- ai,rn,! tlr/E lo€lrLE fla f-.ro- l"ro ,zn1tn l!0.t4 tfi!'. lf ,ts llaie 3l&tal !6a.lta lae.?a f4ii- 5lF,aat t !.rl t'|t.9t
TA 7093 - PHI : PREPARING THE PHILIPPINES
ROAD SECTOR IMPROVEIIIENT PROJECT, ASSET PRESERVATION UNDER TRANCHE 1
CONTRACT PACKAGE III, LOT 3.1 . DIFOLOG. OROqUIETA CITY ROAD
Ao*
'u.4
.lNl
o.zm an
o?a2 o.322
TOt t coSr
rci[HLY SCHEIIXXI PERGEfi 17 771 18415
n
rctfiHlY SCtiEgrJtE t ^flo."t
24.666 725
14','F
clnjlallvE lclcolJlE I trPl a17t
TA 7093. PHI : PREPARING THE PHILIPPINES
ROAD SECTOR IilIPROVEMENT PROJECT, ASSET PRESERVATION UNDER TRANCHE 1
CONTRACT PACKAGE lll, LOT 3.2 - BUTUAN - CAGAYAN DE ORO CITY - ILIGAN ROAD (t{lsamls Orlontal)
rl It
4,|G[,8IGER
0 341 0.221 0221 oz2f ozl o.zl o.227 o.27 o27
0134
,/
10 431 4".,
HSC€LIAI€T'S SIRTEILRES
,4,
=r/rgI I I |
TA 7093 - PHI : PREPARING THE PHILIPPINES
.I
ROAD SECTOR IIIPROVEMENT PROJECT, ASSET PRESERVATION UNDER TRANCHE
CONTRACT PACKAGE lll, LOT 3.3 - BUTUAN - CDO - ILIGAN ROAD (Agusan del Nort€)
DESIGN ANO BUILO
PCRCAiY $)
"n
066
st6t
o716
5,4,O.23 2761
|{*
rolar cogt
t{c}l{IHLY SCHEIX,I.E PERCEIIT 2 529 12.779 13.111 12 721
CI,IITITTI'E SCHEOULE
('!r) 7,181 17],,,. o,ata 71,!at
rcfaTl{tY ltct€qt-E tffot,lll I a:as I ztto | 112. 4 609 25 521 2s s2r 21302 24.932 2a t* 23 6,t3 23 64 3.016
-- r!o... I- I - rrlrE-l
I
cuxut-AnrE scHEDt .E Ir{") T rr. laE I ro.,raa laI', i- r.o€. I 4,3t5 t'tt.2aa r...!6 tao.iaa
TA 7@3 - PHI : PREPARING THE PHILIPPINES
ROAO SECTOR IMPROVEIIENT PROJECT, ASSET PRESERVATION UNDER TRANCHE I
CONTRACT PACKAGE III, LOT 3.4. BUKIDNON . COTABATO ROAD
El,lclr{GlN€ER
0 510
6
MISCEI.LIN&IJS STRJCruR€5
6
voauz lroN/D€mo6[E^ltot{
om
.4,
6,37r,51Ot1
Nissan Sentra
Honda City 704,732 480,472
Toyata Corolla
2. Passenger Car Honda CR-V M/T 4x2 1,409,744 980,826 757 ,301
Nissan Cefiro
Mitsubishi (Pajero)
Adventure GLS Sport
3. Passenger Utility Hayag Motors (48C2)
530,309 368,270 368,270
Mitsubishi 1300 FB MT
L 300 Exceed DX
Nissan SP215NSB
Hino FFIJ
lsuzu FSR
1,594,000 987,469
lsuzu Ef NKR 4BEl
7. Rigid Truck 982,188
tsuzu F I K
1,583,219 981,642
Hino FP3H
Mitsubishi Canter FE 639
8. Rigid Truck 972,632 690,319 690,319
tsuzu Dumptrucr I
1 1. Truck Trailer,
1,274,692 471,475 871,475
4 Axles Hino SH 273 T/T (recon)
2-Axle Medium
8,441 7,674
Truck (1 1)
7. Rigid Truck 13,624
z-Axle Heavy
15,664 14,240
Iruck (1 1 )
3-Axle Heaw
8. Rigid Truck 13,810 12,554 12,554
Truck (12)
Public Utility
Bus, Truck
Pass€nger Car
Goods Utility
Taxe6 - E.O. 691 ptovide' zerc rate of taxes ol oil imr,,fts stading June 2008
Table 2d: Maintenance Labor Costs
(financial and economic, PhP), July 2008 Prlceg
Total 68.97
Table 2e: Crew Cost3 (financial and economic, PhP), July 2008 Prices
Motor-tricycl6 1 0 62.5
Cosls syslem from Highway Planning Manual 1982 (page 33) (for individual vehicles but based on an average of 10 vehicle feet units) multiplied by 4 (infalion at about 7% per year)
(no increase from 2004 t0 2005) See abo Table 20 below.
Represenlative General Operaiion Record Security Water & Office Rental Communi- Yard or Agents & Maint. of Total per
Accountanl Typists Janilors
Vehicle Type Manager Manegsrs Keeper Guards Electricity (PhP 70/sq m) calions Garage Licenses Buildings Year
Passenger Car 9,759 7 tto 2'14 4,441 3,631 2,74'l 13,811 0 0 0 0 49,574
Public Utility 0 0 0 0 0 0 o 0 0 0 0 0 0
Goods Utility 0 0 0 0 o o o 0 0 0 o 0
Small Bus 0 0 0 0 0 0 0 0 0 0 0 0 0
Large Bus 6,769 6,154 4,333 3,621 2,OOO 2,354 2,43'l 641 0 2,856 0 982 4,6 t5 36,756
Gross Nalional Producl (GNP) 2004 in curent prices (PhP million) 7,245,323
1)
1 Ac@unts ,. GNP & <
NSCB, National Actounts by Ex@nditurc
2) NSO at website www.cansus.gov.ph
Table 2h: Passenger Tim6 Cost per Percon (PhP), July 2008 Prices
l\rotor-lricycle
Bus
PCSE, n< 1.0 1.2 1.0 1.4 1.5 1.4 1.6 1.8 1.8 1.8 1.8
No. of Axles 2 2 2 4 5 4
Tire Type bias radial radial bias bias bias bias bias bias bias bias bias
Base No. of Recaos 2.O 1.3 2.O 2.O 2.O 1.3 a-, 1.7 1.7 1.7 1.7 1.7
Annual Vehid+ Kilometers 25,000 17,500 60,m0 25,0m 70,000 80,000 50,000 50,000 60,000 60,000 40,000 40,000
Annual Working Hours 1,200 500 2,400 1 ,500 1 ,800 2,200 1,500 1,500 1,800 1 ,800 't,500 1,500
ESALF. 0 0 0 0.01 0.01 1.2 1.7 10.0 '12.5 7.6 5.0 5.5
New Vehicle Price. excl. Tires. PhP 58,938 747,643 360,741 619,035 647,505 1 ,650,438 900,443 ffi4,776 1 ,233,712 1,501,987 695,716 703,259
New Tire Price, PhP 505 2,414 1,882 3,402 6,385 ,t ? o70 13,624 12,5U 12,850 15,186 12,554 12,984
Fuel. PhP D€r liter 51.1 44.2 39.7 39.7 39.7 39.7 39.7 39.7 39.7 39.7 39.7 39.7
Lubricating Oil, PhP per Liter 179 275 275 zta 176 176 176 176 176 176 176 176
Crew Wages, PhP per Hour oz.cu 0 56.65 64.15 140 140 227 .27 227 .27 227 .27 227.27 227 .27 227 .27
Annual Overheads, PhP 0 49,574 0 0 0 36,756 60,685 60,685 60,685 60,685 60,685 60,685
Passengor Working Time, PhP/Hour 105 419 105 105 105 105 0 0 0 0 0
8. Bulidnoncotabdo R(
'ad
47.81 t1.290 0.160 22r
6.1 1@8+000 - 1608+600 North Cotabdto 0.d) AC Faaf 3.5 AC Falr 3.5 3016 8.626 2.509 31.4
6.2 1m6+600 - 1m8+Em 1st EngineerirE Oi€ 0.20 AC B.d 6.7 AC Bed 3015 5.66 l.Sll 31.7
6.3 1m€+600 - 1612+22 3.,t8 AC Fear 2.4 AC Fir 2.4 3016 44.473 2.& &.5
6.4 1412+2n - 1614+M 1.72 PCCP 5.4 PCCP Fair 3016 1.616 0.r94 14.1
6.5 1 61 4+CrD - 1 615+900 1.$ PCCP Good 6.2 PCCP Good 6.2 3016 Ex6mption
6.6 1615+900 - 1617+000 1.10 PCCP Faar 6.0 PCCP 6.0 3016 3.@8 0.583 24.O
4.7 1 61 7+000 - I 619+000 2.6 PCCP Good 8.0 PCCP Good 6.0 3016 Exemption
6.8 1 61 9+m0 - 1 6mam0 1.m PCCP PCCP Feir 7.2 3016 7.79 1.6rcl2 379
16:0+@0 - 1620+944 094 PCCP Good 6.6 PCCP Good 2.4 3015 Exemdirr
162+1W .t
6.10 16m+944 - t6 AC Good 2.4 AC G€.d 2.4 3016 Eremption
611 1622+1m - 1651+00O 28.90 PCCP Fair 5.4 PCCP 5.4 3016 24.171 0.173 r7.8
6.12 1 651 +000 - 1 631+0m 3.00 PCCP Good 4.7 PCCP Good 4.7 3016 Exemption
6.13 1 654+m0 - 1 &55+61 0 1.61 PCCP Falr 4.6 PCCP 4.6 3016 -1.795 4226 11.0
2030 27.61 1661.69 1,634.08 27.6'l 1123.93 1096.32 0.74 1534.87 153/..14 33.13 1661.69 1628.55
2031 0.48 1729.29 1,728.81 0.48 '1154.85 249.OO 1584.91 1335.91 0.58 1729.29 1724.7'l
2032 1661.69 1661.69
2033 1729.29 1729.29
2016 0.0c 1r6.94 116.94 0.00 53.17 53.47 0.00 85.15 0.00 I 16.94 116.94
2017 0.00 't21.41 121.41 0.00 55.45 55./t6 0.00 110.30 110.30 0.@ 124.11 121.11
m18 0.00 133.40 133.40 0.00 57.94 57.94 0.00 116.94 116.94 0.00 133.40 133.40
2019 0.00 141.93 141.9s 0.00 60.16 60.16 0.00 121.11 124.41 0.00 1,11.93 141.93
m20 0.00 149.37 149.37 0.00 61.83 61.83 0.00 133.,10 133.40 0.00 1,19.37 't19.37
m21 0.00 156.65 156.65 0.00 63.29 63.29 0.00 141.93 '1,t1.93 0.00 156.65 '|
56.65
202 -215.23 157.32 102.55 -215.23 61.82 307.(X 0.00 149.37 49.37
't -291.27 157.32 451.59
2023 0.00 179.97 179.97 0.00 69.40 69.40 0.00 156.65 156.65 o.o0 '179.97 't79.97
2021 0.00 191.59 '191 .59 0.00 72.10 72.'tO -367.84 157.32 525.16 0.00 191.59 191.59
m25 0.00 204.36 2U.6 0.00 75.05 0.00 179.97 179.97 0.00 204.36 20.1.36
202s 0.00 218.45 218.15 0.00 78.27 78.27 0.00 191.59 191.59 0.00 218.45 214.45
2027 0.00 2U.15 2U.15 0.00 81.85 81.85 0.00 204.. 2U.# 0.00 2U.15 2U.'t5
2024 0.00 251.60 251.60 0.00 85.78 85.78 0.00 21a.$ 218.45 0.00 251.60 251.60
20?9 0.00 271.'t6 271.16 0.00 90. t2 w.12 0.00 2U.15 234.15 0.00 271.16 271.16
2030 0.00 292.74 292.74 0.00 .42 94.82 0.00 251.60 251.60 0.00 292.74 292.74
2031 0.m 316.50 3t6.50 0.00 99.90 99.90 0.00 271.16 271.16 0.00 3r5.50 316.5{)
2032 0.00 292.74 292.74
m33 0.00 3 t6.50 316.50
2018 0.00 197.62 '197.62 0.00 85.13 85.13 0.00 't'17.31 117.31 0.00 197.62 197.62
2019 0.00 220.6 220.68 0.00 92.U 92.54 0.00 161_85 161.85 0.00 220.@ 20.68
2020 0.00 211.A2 211.a2 0.00 98.71 94.74 0.00 197.62 't97.62 0.00 21't.82 241.42
2021 0.00 258.41 258.41 0.00 102.81 102.81 0.00 220.68 220.6 0.00 258.41 258.41
202 0.00 ffi.u 266.34 0.00 103.33 103.33 0.00 241.42 211.42 0.00 266.34 266.31
2023 -877.13 253.16 I r30.29 -877.13 95.12 972.25 0.00 258.41 254.41 -1052.56 253.'t 6 1305.72
2021 0.00 303.41 303.41 0.00 112.'t7 112.17 0.00 266.34 266.34 0.00 303.4'l 303.41
2025 0.00 318.31 318.31 0.00 114.83 114.83 .1.315.70 253.16 't 568.86 0.00 3'18.3'l 318.31
2026 0,00 333.72 333.72 0.00 117.45 117 .45 0.00 303.41 303.41 0.00 333.72 339.72
m27 0.00 3,f9.52 349.52 0.00 119.96 '| 19.96 0.00 318.3'l 3't 8.31 o.o0 3/.9.52 349.52
m2a -303.90 9.12 668.32 -303.90 121.92 125.42 0.00 333.72 333.72 -364.68 36,4.42 729.10
2029 0.00 392.82 392.42 0.00 124.27 '128.27 0.00 349.52 349.52 0.00 392.82 392.82
2030 0.00 413.82 413.82 0.00 '131.71 131.7'l -455.85 364.42 420.27 0.00 413.42 113.42
2031 0.00 435.91 435.91 0.00 135.23 135.23 0.00 392.82 392.82 0.00 il35.9l 435.91
2032 0.00 4't3.82 413.82
2033 0.00 /135.91 435.91
A. Introduction
1. The environmental assessment and review procedures are formulated to serve as a
guide in the procedure of assessing the existing environmental condition of the
proposed road projects, in the identification of the potential impacts during the pre-
construction, construction and operation phases of the project, and in the preparation
of the environmental management and monitoring plan. Guidelines on the review of
the assessment reports is similarly designed to evaluate the completeness of the
document, if issues and concerns are well addressed and its compliance with the
prescribed presentation of required information.
2. The EARF will be applied for the proposed improvement of selected roads under
Tranches 2 and 3 of the Road Sector Improvement Project (RSIP). The EARF was
developed based on the procedures stipulated in the Government’s Department of
Environment and Natural Resources (DENR) and ADB Environmental Guidelines and
Policy of 2003.
6. Typical roads will be improved from poor/bad condition of the asphalt or concrete
pavement to PCCP/ACP reconstruction and AC overlay with replacement of some
bridges. Based on preliminary engineering inventory of the proposed subproject sites,
none will have major alignment deviations. Construction materials such as sand,
gravel, and quarry/borrow material will be sourced from the surrounding areas and
brought to the site.
7. Post-construction impacts of the road upgrade that have been identified are
associated with improved access such as:
• increased traffic volumes;
• possible increases in agricultural activity in the areas; and,
• increased temporary (tourism) and permanent population densities.
8. In addition, social impacts associated with outside influences on rural communities
such as:
• the erosion of traditional cultural values and practices;
• rural to urban migration and possible increases in crime such as drug trafficking.
9. The increase in impervious surfaces due to the sealing of the road combined with
increased traffic densities could also have an impact on water quality, although this is
more likely to be offset by improvements in drainage systems surrounding the road.
1. Environmental Assessment
10. In the country, the Philippine Environmental Impact Statement System (PEISS)
established through Presidential Decree (PD) 1586 in 1978 sets a systematic EIA
System and the Environmental Management Bureau (EMB) of the Department of
Environment and Natural Resources (DENR) is mandated as the lead agency in the
implementation of the System.
11. The DENR’s Department Administrative Order 2003-30 along with its Revised
Procedural Manual of August 2007 contains more detailed guidelines and procedures in
the implementation of the Philippine EIS System. The basic DENR policy governing the
implementation of the Philippine EIS system is articulated in Section 1.0, Article I of
DAO 2003-30: “Consistent with the principles of sustainable development, it is the
policy of the DENR to implement a system-oriented and integrated approach to the EIS
system to ensure a rational balance between socio-economic development and
environmental protection for the benefit of present and future generations.”
12. Consistent with the ADB’s Environmental Guidelines and Policy of 2003, the EIA
study shall determine the environmental impacts of the project and shall provide
recommendations/guidance at various stages of the project cycle. DENR Administrative
Order 2003-30 serves as guide in the determination of what group the project belongs
and the corresponding level of assessment required. Projects are classified into three
(3) major groups presented as follows:
13. Group I (ECPs): ECPs in either ECAs or NECAs – Environmentally Critical
Projects in either Environmentally Critical Areas or Non-Environmentally Critical
Areas. These projects require the proponent to submit ‘Environmental Impact
A. List of ECPs
- As declared by Proclamation No. 2146 (1981)
12. Coral reefs characterized by one or any combination of the following conditions:
With 50% and above live coralline cover; Spawning and nursery grounds for
fish; Act as natural breakwater of coastlines
16. A typical Environmental Impact Assessment (EIA) Report has the following
substantive contents:
i) Project Description, including its location, scale and duration, rationale,
alternatives, phases and components, resource requirements, manpower
complement, estimate of waste generation from the most critical project
activities and environmental aspects, project cost
ii) Baseline Environmental Description (of the land, water, air and people),
focused on the sectors and resources most significantly affected by the
proposed action
iii) Impact Assessment, focused on significant environmental impacts (in relation
to pre-construction, construction/development, operation and decommissioning
stages), taking into account cumulative, unavoidable and residual impacts;
iv) Environmental Management Plan, specifying the impacts mitigation plan,
areas of public information, education and communication, social development
program proposal, environmental monitoring plans (with multi-sectoral public
participation for EIS-based projects) and the corresponding institutional and
financial requirements/ arrangements.
2. Environmental Review
17. Section 4 of P.D. 1586 states that “No person, partnership or corporation shall
undertake or operate any such declared environmentally critical project or area without
first securing an ECC issued by the President or his duly authorized representative, which
is DENR”.
18. To secure said ECC, the required EIA Report will be prepared by the Proponent or
Consultant Based on Section 3.0 of P.D. 1586, all EIA Reports should be submitted to
the National Environmental Protection Council or NEPC (now DENR, through Executive
Order No. 192) for review and evaluation. The review of the EIA Reports by the
Environmental Impact Assessment (EIA) Section of the DENR-EMB is guided by three
(3) general criteria: (1) that environmental considerations are integrated into the
overall project planning, (2) that the assessment is technically sound and proposed
environmental mitigation measures are effective, and (3) that the EIA process is based
on a timely, informed and meaningful public participation of potentially-affected
communities.
19. Review of EIA Reports normally entails an EMB procedural screening for
compliance to minimum requirements specified during Scoping, followed by a
substantive review of either composed third party experts commissioned by EMB as the
EIA Review Committee for PEIS/EIS-based applications, or DENR/EMB internal
specialists, the Technical Committee, for IEE-based applications. EMB evaluates the
EIARC recommendations and the public’s inputs during public consultations/hearings in
the process of recommending a decision on the application. The EIARC Chair signs
EIARC recommendations including issues outside the mandate of the EMB. The entire
EIA review and evaluation process is summarized in the Review Process Report (RPR)
of the EMB, which includes a draft decision document.
Roads, new Length with no >= 20km >= 2 km but <20km < 2 km
construction and critical slope
widening
(including RO- or
or or
RO facilities) Length with
critical slope >=10km >=2km but <10km
24. For existing road project proposed for asset preservation or improvement, a Project
Description Report (PDR) is necessary in the application/processing of Certificate of
Non-Coverage (CNC) which is required by most lending institutions. In the case of
ADB, an Initial Environmental Examination (IEE) is necessary.
26. The Revised Procedural Manual for DAO 2003-30 provides flowcharts both for IEE-
Based ECC applications and CNC for projects where ECC is not required. CNC is
likewise not necessary for existing roads. The proponent, on the other hand, may opt
to secure CNC. Format of the IEE Report and the Project Description Report (PDR) are
also presented below:
NOTES
1.0 Informal Scoping 1.0 The Proponent may opt to request EMB
(option of the CO/RO to scope the IEER. In the scoping
Proponent) meeting, the Proponent and EMB jointly fill
out the Scoping Checklist. The
accomplished form may be signed by both
parties to serve as the official TOR of the
IEER.
2.0 EIA Study and Report 2.0 THIS STEP IS WHOLLY WITHIN THE
Preparation PROPONENT’S CONTROL. Proponent
undertakes the IEE Study. DENR-EMB
personnel may clarify procedural and
technical matters on the EIA process but is
not allowed to take part in the EIA study or
in the preparation of the report.. To
facilitate preparation of the IEE, the EMB
provides an IEE Checklist for new road
projects. The IEE Report Outline on the
other hand is presented below. The Revised
Procedural Manual for DAO 2003-30 also
provide templates for the Impacts
Management Plan, Environmental
Monitoring Plan and pro-forma Sworn
Statements of Accountability of Proponent
and Preparers.
EIA Report Review and
3.0 Evaluation 3.1 Proponent submits to EMB one (1) copy
of the IEER or IEEC, together with the
filled out Procedural Screening Checklist
3.1 Procedural Screening
(may use Annex 2-7a as template) for
the IEER submission.
IEER IEEC
Steps 4.0 to 6.0 5 Hard +
5 Hard + 1 CD
START OF 1 CD
5 5
Option
PC Option
of EMB
of EMB
IEER IEEC
10 5
EIAMD RO
EIAMD RO Division
Endorsing Division
Chief
Authority Chief
ESTIMATED WORKDAYS TO
SIGN-OFF and ISSUE DECISION
6.0 DOCUMENT
IEER IEEC
10 5
Deciding EMB RO EMB RO
Authority Director Director
NOTE #1: If no decision is made within
the specified timeframe, the ECC
application is deemed automatically
approved and the approving authority
shall issue the ECC within five (5)
working days after the prescribed
processing timeframe has lapsed.
NOTE #2: Prior to the release of the
ECC, Proponent shall submit to the EMB
one (1) hard copy and 2 e-files of the
FINAL IEE REPORT, integrating all AIs.
(Not applicable for IEE Checklists)
NOTE #3: The Proponent signs the
Sworn Statement of Full Responsibility on
ECC Conditions prior to the official release
of the ECC.
NOTES
ESTIMATED 3
WORKDAYS for EMB
3.0
CO or EMB RO TO
5.0 Transmittal of
ENDORSE DECISION
CNC Document
DOCUMENT
ESTIMATED 4
WORKDAYS for EMB CO
4.0
or EMB RO TO SIGN-OFF
and ISSUE DECISION
DOCUMENT
CO: EMB CO
Deciding Director
Authority RO: EMB RO
Director
NOTE: REFER TO ANNEX 2-7a (EIS SCOPING AND PROCEDURAL SCREENING CHECKLIST) AS BASIS
FOR DETERMINING SIMILAR OR EQUIVALENT SPECIFIC CONTENTS/ REQUIREMENTS OF EACH
SECTION
Executive Summary
1) Brief Project Description
2) Brief Summary of Project’s IEE Process
3) Summary of Baseline Characterization
4) Summary of Impact Assessment and Environmental Management Plan
5) Summary of Environmental Monitoring Plan
3. PROJECT DESCRIPTION
3.1. Project Location, Area, ECA category (if applicable)
3.2. Project Rationale
3.3. Project Development Plan, Process/Technology and Project Components
3.4. Description of Project Phases (Activities/Environmental Aspects, Associated
Wastes and Built-in Pollution Control Measures)
6. BIBLIOGRAPHY/REFERENCES
7. ANNEXES
7.1. Scoping Checklist (optional, since Scoping is not required for IEEs)
7.2. Original Sworn Accountability Statement of Proponent
7.3. Original Sworn Accountability Statement of IEE Preparer
7.4. Baseline Study Support Information
Table of Contents
2 PROJECT DESCRIPTION
2.1 Project Location and Area (at the minimum, shown in an official NAMRIA
topographic or nautical map (whichever type is applicable and of appropriate
scale); Show title, legend, scale, project location and political boundaries
(from sitio/barangay to region); indicate any known ECA category
encompassing the project area
2.2 Project Rationale – state need for & purpose of the project., particularly
environmental enhancement or mitigation purpose of the project
2.3 Project Development Plan, Process and Components - Attach
tentative/option of Physical Plan/Site Development Map being considered at
the FS stage; briefly describe process/technology; list/describe and indicate
project components (facilities/infrastructures, other single projects supporting
the main project) on the topographic map
2.4 Description of Project Phases - For Group II and III non-covered
projects: focus on activities and processes which may cause residual impacts;
For Unclassified/Unlisted/New Technology Projects: focus on critical activities
and processes per phase which place a demand on local resource uses and
which generate emissions, effluent, hazardous waste, solid waste, other
wastes)
2.4.1 Operational phase – For Unclassified/Unlisted/New Technology
Projects: Specifically present if processes and substances to be used
are listed and fall within the limits covered by Environmental Risk
Assessment as enumerated in Section C of Annex 2-7a of the
Revised Procedural Manual )
2.4.2 Abandonment phase
EIS OUTLINE
NOTE: REFER TO ANNEX 2-7a (EIS SCOPING AND PROCEDURAL SCREENING CHECKLIST) FOR SPECIFIC
CONTENTS/REQUIREMENTS OF EACH SECTION
Table of Contents
Executive Summary
1) Brief Project Description
2) Brief Summary of Project’s EIA Process
3) Summary of Baseline Characterization
4) Summary of Impact Assessment and Environmental Management Plan
5) Summary of Environmental Monitoring Plan
6) EMF and EGF Commitments
PROJECT DESCRIPTION
4.11. Project Location and Area
4.12. Project Rationale
4.13. Project Alternatives
10. BIBLIOGRAPHY/REFERENCES
11. ANNEXES
11.1. Scoping Checklist
11.2. Original Sworn Accountability Statement of Proponent
11.3. Original Sworn Accountability Statement of Key EIS Consultants
11.4. Proof of Public Participation
11.5. Baseline Study Support Information
11.6. Impact Assessment and EMP Support Information
NOTE: The EIA review process will advise DOH if the project will pose a significant public health risk to the environment, e.g. public health
may be affected if the wastes/discharges are direct contributors to the leading causes of mortality/morbidity in the DIA, regardless of
environmental management measures. To assist EMB on its review, DOH shall coordinate with the DENR-EMB on the declaration of
Health Sensitive Projects and Health Sensitive Areas. Until such time, DOH shall review EHIA independently of the EIA Process,
consistent with the DENR-DOH MOA on EHIA. Further, workers’ HIA component of the EHIA is recommended to be coordinated by DOH
with DOLE for the latter’s consideration in its requirement of an Occupational Health and Safety Program from the Proponent.
32. The Philippine Government’s existing Initial Environmental Examination (IEE) and
the Environmental Impact Assessment (EIA) procedure generally conform with the
ADB’s environmental framework.
33. The environmental assessment and review procedures of ADB for the subproject
road upgrade under the sector loan conform with the existing DENR procedures.
34. The procedures conform closely with the ADB’s Environmental and Social Safeguard
policies, specifically in the requirements for structured consultation, they are a
component of a poverty reduction intervention, place greater emphasis on monitoring
and compliance with environmental requirements during project implementation, and
are structured as an ongoing process rather than a one-time event.