0% found this document useful (0 votes)
275 views3 pages

Office Automation Reference Answer

The document describes a proposal for a new computerized office system that includes a list of activities that must be completed for the project. The list includes 6 activities with descriptions, time estimates, minimum crash times, and crash costs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
275 views3 pages

Office Automation Reference Answer

The document describes a proposal for a new computerized office system that includes a list of activities that must be completed for the project. The list includes 6 activities with descriptions, time estimates, minimum crash times, and crash costs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

SOM 466 R.

Gunther
Spring 2010

Example Crashing Problem

Office Automation, Inc. has developed a proposal for introducing a new computerized
office system that will improve word processing and interoffice communication for a
particular company. Contained in the proposal is a list of activities that must be
accomplished to complete the new office system project. The activities follow:

Job Description Follows Time Min. Crash Time Crash Cost


A Plan needs ---- 10 8 $20
B Order equipment A 8 6 15
C Install equipment A 15 7 20
D Set up training lab A 7 6 10
E Conduct training D 10 8 12
F Test system C, E 3 3 10

Answer on next page.