Q.1. Prepare 2nd Running Bill of M/s. ACEEngineeringCo.of the Work“Construction Of Quarters ” paid vide
Vr. No. 28 dated 8-3-2015 from the followingdata:-
Quantities
Rat Upto
date Paid
Sr. Item of Work Unit e
Rs. Quantity
No. in last Bill
(i) Advance Payment of Rs. 100,000 and Rs. 80,000 was given in the last running bill against item No.
2 and 3 which is to be recovered in thisBill.
(ii) Further Advance of Rs. 350,000 is to be given against the item of R.C.C Work in thisbill.
(iii) Secured Advance of 50,000 Bricks was given in last bill at Market Rate of Rs. 8,000 per thousand
which is to be adjusted in thisbill.
(iv) Secured Advance against 20 Ton Steel is to be given in this bill at Market rate of Rs. 60,000
perTon.
(v) Add Premium @ 100% on all items except item No.6.
(vi) Deduct Security Deposit and Income Tax as perRules.
Solution
Note:
1.Unit rate for RCC is Rs per cft as per MRS whereas it has been taken as % cft, hence calculation made at % cft.
2.Similarly unit rate for fabrication of steel is per % kg as per MRS whereas it has been taken as per kg hence calculation made at % cft.
FORM 26
(For Contractors this form provides for (1) advance Payments (2) Secured Advances and (3) payment for measured works.)
No. and date of his previous Bill for this work 1st runningbill dated 25thFebruary2015
Work not yet Measured Items of work paid measurement Upto previous
3
bill
(grouped in last
P P P
Rs Rs Rs Rs s Rs s Rs s Rs
4,018,48
Total Total value of work done to date 0
(A)
1,870,53
(D) (B) Deduct value of work shown on 0
previous bill
2,147,95
Net value of work since previous 0
bill
(F)
4
1 2 3 4 5 6 7 8 9 10
Net amount since previous bill (in words) six hundred thousand (E) 600,000
IV MEMORANDUM OF PAYMENTS
1. Total values of work actually measured, as per Acct. 1 Col. 8 entry (A) 4,018,480
2
. Total “Up to date” Advance payments for work not yet measured, as per Acct. A col. 3 Entry (B) 350,000
3. Total “Up to date” Secured advances on security of materials, as yet Acct. II Col. 8 Entry (C) 900,000
4 Total (Items
. 1+2+3)
5
5 Deduct amount
. withheld Nil
“K
Total value of work done ” 5,268,480
“K
Total value of work done as per previous ” 2,350,530
3,063,848
Balance 2,917,950
Figures for P
Works Rs s
Abstra
ct
(
a this work
) ---------------------------------------
---------------------------------------------------
Total ……(G).
556,159
(
c
) By cheque . . . . . . . . . . . Total (H) 2,361, 791
6
Note: 1. Unit for item of works “RCC” has been taken as % cft instead per cft as provisions of MRS. However working has been made as per
provisions of question.
2. Similarly unit for Fabrication of steel is % kg instead of per kg. However working has been made as per provisions of question.
Q. Prepare the 2nd Running Bill of M/s. GRC from the data given below:
Quantities
Rate Quanti
ty as per
Sr. Item of Work Unit Rs.
No previous
upto
. date bill
i. Advance Payment of Rs. 150,000 and Rs.60,000 was given against 3 and 4 in the last running Bill which is to be
recovered in this Bill.
iii. In last bill Secured advance on 200,000 Bricks was given which has been utilized on the work. Full rate of Bricks
was 4,000.
iv. Further Secured Advance for 6 ton steel is to be given against item No. 4 at market rate of Rs. 60,000 Per Ton.
Solution
FORM 26
(For Contractors this form provides for (1) advance Payments (2) Secured Advances and (3) payment for measured works.)
No. and date of his previous Bill for this work 1st runningbill dated 5th July, 2019
Pay
ment
s on
the
basis
of
Quan actua
tity l
m
e
a
s
u
r Upt
e o
m
Items e prev
of n ious
work paid t bill
(grouped in last
Total
as under sub- Uni Rat
bill
Since Total t e Upto previous
per head and sub Since bill
previo up to Up to
previo us works of date previous bill
9
us
bill date
bill estimate)
P P P
Rs Rs Rs Rs s Rs s Rs s Rs
(A)
previous bill
bill
(F)
1 2 3 4 5 6 7 8 9 10
Net amount since previous bill (in words) six hundred thousand (E) (-)330,000
IV MEMORANDUM OF PAYMENTS
1. Total values of work actually measured, as per Acct. 1 Col. 8 entry (A) 6,533,680
2
. Total “Up to date” Advance payments for work not yet measured, as per Acct. A col. 3 Entry (B) 140,000
3. Total “Up to date” Secured advances on security of materials, as yet Acct. II Col. 8 Entry (C) 270,000
4 Total (Items
. 1+2+3) 6,943,680
5 Deduct amount
. withheld
Total amount of payments already made as per entry (K), of last Running 4,764,550
1,658,087
Figures for
Works 1,579,130
11
Abstra
ct
(
a this work
) ---------------------------------------
Total ……(G).
203,313
(
c
) By cheque . . . . . . . . . . . Total (H) 1,375,817
Q. Prepare the 2nd Running Bill of M/s. GRC from the data given below:
Quantities
Rate Quanti
ty as per
Sr. Item of Work Unit Rs.
No previous
upto
. date bill
vii. Advance Payment of Rs. 150,000 and Rs.60,000 was given against 3 and 4 in the last running Bill which is to be
recovered in this Bill.
viii. Further Advance of Rs. 140,000 is to be given against item no. 3.
ix. In last bill Secured advance on 200,000 Bricks was given which has been utilized on the work. Full rate of Bricks
was 4,000.
x. Further Secured Advance for 6 ton steel is to be given against item No. 4 at market rate of Rs. 60,000 Per Ton.
xi. Deduct Security Deposit and Income Tax as per Rules.
xii. Add 25 % premium on all items.