2-Table of Contents

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 4

CONTRACT NO : CHO/2012/SKO-BIE/1000

PROVISION OF ICMS FOR PCSB

INSPECTION REPORT REPORT NO. :


PAGE NO. : 2
REV NO : A

TABLE OF CONTENTS

1.0 INTRODUCTION 3
2.0 INSPECTION SUMMARY 3
2.1 Background 3
2.2 Scope Details 3
2.3 Restriction And Limitation 3
2.4 Inspection Tools And Methods 4
2.5 Outstanding Work 4
2.6 Platform Overview 5
2.7 Platform Data 5
3.0 INSPECTION RESULTS 6 - 27
3.1 Detailed Results 6 - 27
1. Jacket Leg A1 7 - 11
2. Jacket Leg A2 12 - 16
3. Jacket Leg A1 17 - 21
4. Jacket Leg B2 22 - 26
3.2 Brief Summary 27
4.0 REFERENCES 28
4.1 Ultrasonic Thickness Measurement Procedure 29
4.2 List of Drawing 30

OC/ICMS-PCSB/F/1.3 REV. 00
CONTRACT NO : CHO/2012/SKO-BIE/1000
PROVISION OF ICMS FOR PCSB

INSPECTION REPORT REPORT NO. :


PAGE NO. : 3
REV NO : A

1.0 INTRODUCTION
Inspection Reference
Platform ID BEP-A Region Betty ( Baram Delta
Operation )
Platform Name Betty Production - A
Inspection Start Date 24th February 2015
Inspection Finished Date 25th February 2015
Inspection Headline Jacket leg Inspection
Type of Inspection Close Visual Inspection ( CVI ) & UT Wall Thickness Measurement

2.0 INSPECTION SUMMARY


2.1. Background
BEP-A is a four legged production platform. The structure was installed on the year 1978 and located in the
Betty field in 72.85m water depth. The piles are 30 inch outer diameter. The platform is bridge linked to
BEDP-A, a drilling platform. The platform supports one 6 inch, one 8 inch, one 12 inch, one 16 inch and
three 10 inch risers. It also support one 24 inch sump pump pipe and a boatlanding. The boatlanding is
located between row 1 and 2 off face A. The topsides comprises of a Main Deck (EL +14.889m), Cellar Deck
(EL +10.973m), and sump pump deck (EL +3.05m). The main deck also provides support for a mega skid
which is cantilevered towards Platform North. The platform has a number of 52 anodes for cathodic
protection.

2.2. Scope Details


The scope of the inspection includes but not limited to UT Thickness Measurement. For the purpose of this
inspection. This report shall address remaining thickness of the following:
1. Jacket leg A1
2. Jacket leg A2
3. Jacket leg B1
4. Jacket leg B2

2.3. Restrictions and Limitation


Nil.

OC/ICMS-PCSB/F/1.3 REV. 00
CONTRACT NO : CHO/2012/SKO-BIE/1000
PROVISION OF ICMS FOR PCSB

INSPECTION REPORT REPORT NO. :


PAGE NO. : 4
REV NO : A

2.4. Inspection Tools and Methods


UT thickness measurement was performed by using 45MG and 0 probe. The UTTG reading was taken on
the external surface of jacket leg. Tools used in the inspection are listed below:-
1. 45MG
Serial No.: 130159606
Calibration date: 14th August 2014
Calibration due date: 13th August 2015
2. Carbon Steel Calibration block
3. Step wedge block
4. Camera

2.5. Outstanding Work


Nil.

OC/ICMS-PCSB/F/1.3 REV. 00
CONTRACT NO : CHO/2012/SKO-BIE/1000
PROVISION OF ICMS FOR PCSB

INSPECTION REPORT REPORT NO. :


PAGE NO. : 5
REV NO : A

2.6. Platform Overview

Photo 1: Platform North View

2.7. Platform Date


Platform ID BEP-A
Platform Name Betty Production Alpha
Platform Function Production
Legs 4
Field Betty
Year Installed 1978
Manned No
Bridge Linked (Location) Yes (BEDP-A to BEP-A)
Crane 1