Restaurant Management System (Task Assingment)

The document outlines the tasks, timelines, and assignees for developing a restaurant management system. It is split into four phases: requirement gathering and analysis from August 25th to September 11th; cost estimation from September 12th to 14th; system designing and architecture from September 15th to October 21st; and coding/implementation from October 13th to November 14th. The final phase, testing and deployment, will run from November 16th to December 10th. Each phase has specific tasks assigned to Moiez Hussain, Faiza Azhar, and Zehra Ali.

Uploaded by

Wasiq Karim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
76 views3 pages

Restaurant Management System (Task Assingment)

The document outlines the tasks, timelines, and assignees for developing a restaurant management system. It is split into four phases: requirement gathering and analysis from August 25th to September 11th; cost estimation from September 12th to 14th; system designing and architecture from September 15th to October 21st; and coding/implementation from October 13th to November 14th. The final phase, testing and deployment, will run from November 16th to December 10th. Each phase has specific tasks assigned to Moiez Hussain, Faiza Azhar, and Zehra Ali.

Uploaded by

Wasiq Karim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Restaurant Management System

Task Distribution:
Requirement Gathering & Analysis:
 Start Date: 25th Aug, 2019
th
 End Date: 11 Sep, 2019
 Duration: 18 Days

Tasks:
1. Analysis:
 Assignee: Moiez Hussain
2. Requirement Gathering:
 Assignee: Faiza Azhar
3. Prepare Documentation:
 Assignee: Zehra Ali

Cost Estimation:
 Start Date: 12th Sep, 2019
 End Date: 14th Sep, 2019
 Duration: 3 Days
 Assignee: Moiez Hussain

System Designing And Architecture:


 Start Date: 15th Sep, 2019
 End Date: 12st October, 2019
 Duration: 27 Days
Tasks:
1. Realization Class:
 Assignee: Zehra Ali
2. UseCase
 Assignee: Moiez Hussain
3. Class Daigram
 Assignee: Faiza Azhar
4. Activity Daigram
 Assignee: Moiez Hussain
5. Prototype
 Assignee: Faiza Azhar
6. Designing Database
 Assignee: Zehra Ali

Coding & Implementation:


 Start Date: 13th Octuber,2019
 End Date: 14th Nov,2019
 Duration: 34 Days
Tasks:
1. Development of System Modules:
 Assignee: Faiza Azhar
 Assignee: Zehra Ali
2. Integrates System Modules:
 Assignee: Moiez Hussain

Testing And Deployment:


 Start Date: 16th Nov, 2019
 End Date: 10th Nov, 2019
 Duration: 24 Days

Tasks:
1. UI Testing:
 Assignee: Faiza Azhar
2. Optiming Codes and Queries:
 Assignee: Zehra Ali
3. Deployment Software:
 Assignee: Moiez Hussain