Harcomp Airflex Pvt. LTD., Project:-Amazon Sort Centre at Lucknow

This document outlines the schedule for ventilation and AC works for the Amazon Sort Centre in Lucknow from June 14 to July 30. It details the scope of work over six weeks including delivery and installation of ducting, grills, diffusers, VRV/split units, electrical works, insulation, and fans. Key milestones are the submission and approval of drawings, site mobilization, and building completion. The schedule notes that dates are subject to these factors and any changes to the design, and that delays may occur without timely processing of payments.

Uploaded by

Skill India
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
81 views1 page

Harcomp Airflex Pvt. LTD., Project:-Amazon Sort Centre at Lucknow

This document outlines the schedule for ventilation and AC works for the Amazon Sort Centre in Lucknow from June 14 to July 30. It details the scope of work over six weeks including delivery and installation of ducting, grills, diffusers, VRV/split units, electrical works, insulation, and fans. Key milestones are the submission and approval of drawings, site mobilization, and building completion. The schedule notes that dates are subject to these factors and any changes to the design, and that delays may occur without timely processing of payments.

Uploaded by

Skill India
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

HARCOMP AIRFLEX PVT. LTD.

PROJECT:- AMAZON SORT CENTRE AT LUCKNOW


Work Sechedule For Ventilation / AC Works
Date 14-Jun-18 24-06-2018 1-Jul-18 8-Jul-18 16-Jul-18 30-07-2018
Remarks
S.NO ITEM/WORK DESCRIPTION Scope of work/week
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6
Updated drawings as per revised scheme is
Client awaited
1 Drawings & BOQ
2 Technical Submission HAPL
3 Approval of Drawings and Technical Submittal HAPL/Client
4 Site Mobilisation HAPL
5 Cutouts/Foundations for All major equipments Client
6 Building Completion/Clear Work Front Client
6 VENTILATION / AC WORKS
I Ducting
Delivery HAPL
Installation HAPL
II Grills/ Diffusers / Dampers
Delivery HAPL
Installation HAPL
Testing and Balancing HAPL
III. VRV/Split Unitts
Delivery HAPL
Installation HAPL
Testing and Balancing HAPL
IV. Electrical cables/ cable tray / Earthing
Delivery HAPL
Installation HAPL
V. Insulation
Delivery HAPL
Installation HAPL
VI. Axial/Propellar Fan
Delivery HAPL
Installation HAPL
VII. Electrical Panel
Delivery HAPL
Installation HAPL
Power for testing and commissioning Client
Testing and Commissioning HAPL
6 Handing over HAPL/Client
Note:
1 All given Dates are subjected to Clear Work Front Availability / Building Completion etc and any change/modifications in scheme of System / Equipments will have further time implications
2 All dates are subject to approval of drawing/documents within 2-3 days otherwise Dates shall be shifted accordingly.
3 All above dates are subject to processing of running bills and receiving of our payments within 15-30 days
4 All given dates will shift accordingly in case of any last minute changes/modifications etc
5 Any change in drawing/layout will have additional time implication