Gantt Chart

This Gantt chart outlines the timeline for constructing a proposed two-story house located in Cavite, Philippines. It includes tasks such as project approvals, preliminary design, bidding, construction processes like excavation and reinforcement, and finishes from October 2020 through June 2021. The construction process from December 2020 to June 2021 is the longest task, taking approximately 136 days to complete stages like electrical works, tiling, and garden installation. The chart provides a detailed timeline to plan and track progress of the house construction project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
506 views1 page

Gantt Chart

This Gantt chart outlines the timeline for constructing a proposed two-story house located in Cavite, Philippines. It includes tasks such as project approvals, preliminary design, bidding, construction processes like excavation and reinforcement, and finishes from October 2020 through June 2021. The construction process from December 2020 to June 2021 is the longest task, taking approximately 136 days to complete stages like electrical works, tiling, and garden installation. The chart provides a detailed timeline to plan and track progress of the house construction project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Gantt Chart

OWNER : Mr. & Mrs. De Rosa


PROJECT: PROPOSED TWO-STOREY (2) HOUSE

LOCATION : 148 Villa Catalina, San Agustin 3 Dasmariñas City, Cavite

Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21


TASK START FINISH DURATION
28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14
Project Approvals 9/27/2020 10/4/2020 6d
Planning and Formulation 10/5/2020 10/16/2020 6d
Space Planning 10/5/2020 10/12/2020 6d
Facilities Programming 10/8/2020 10/15/2020 6d
Capital Planning 10/9/2020 10/16/2020 6d
Capital Budgeting 10/9/2020 10/16/2020 6d
Preliminary Design 10/17/2020 11/13/2020 20 d
Design Planning 10/17/2020 10/24/2020 6d
Reviewed by Stakeholders 10/25/2020 11/1/2020 6d
Works out Major Design Elements 11/2/2020 11/9/2020 6d
Finish of Planning and Design 11/13/2020 11/13/2020 1d
Bidding 11/19/2020 12/4/2020 11 d
Construction Process 12/7/2020 6/17/2021 136 d
Marking the Layout 12/7/2020 12/24/2020 11 d
Exacavation of Footings 12/24/2020 1/8/2021 11 d
Reinforcement 1/8/2021 2/1/2021 18 d
Back Filling & Compaction 2/6/2021 2/18/2021 8d
Staging 2/20/2021 3/6/2021 11 d
Electrical Works 3/7/2021 3/22/2021 11 d
Window Fixing 3/22/2021 4/4/2021 9d
Tiles Flooring 4/4/2021 4/12/2021 6d
Plumbing Pipe Installation 4/12/2021 4/29/2021 11 d
Ceiling Installation 4/29/2021 5/10/2021 9d
Paintings 5/10/2021 5/22/2021 8d
Finishes/Fixtures 5/22/2021 5/30/2021 6d
Garden Works 5/31/2021 6/17/2021 11 d
Construction Closeout 6/18/2021 6/19/2021 1d