To set up a biodiesel processing plant, only three licenses are required - a factory license from the district inspectorate, an explosive license for methanol storage from the directorate of explosives, and pollution control board clearance since the plants are non-polluting. The document then provides frequently asked questions about land requirements, basic plant infrastructure needs like the factory shed, electricity, water, storage tanks, and the biodiesel processor unit. It outlines the step-by-step process for working with the company to set up the plant, including signing an agreement, placing an order, inspection, delivery, installation, commissioning, and after-sales service.

Uploaded by

cjksdbvjkcsb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
104 views3 pages

License Required

To set up a biodiesel processing plant, only three licenses are required - a factory license from the district inspectorate, an explosive license for methanol storage from the directorate of explosives, and pollution control board clearance since the plants are non-polluting. The document then provides frequently asked questions about land requirements, basic plant infrastructure needs like the factory shed, electricity, water, storage tanks, and the biodiesel processor unit. It outlines the step-by-step process for working with the company to set up the plant, including signing an agreement, placing an order, inspection, delivery, installation, commissioning, and after-sales service.

Uploaded by

cjksdbvjkcsb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

License Required

To start up any industry, any new venture, there is a long list of licenses and
approvals that are required from various government bodies and regulatory
associations. However to set up a Biodiesel Processing Plant, one doesn't have
to bother about such things. The Biodiesel Processing Plants manufactured by
us requires hardly three licenses. All the below mentioned licenses are easy to
get.

Factory Licenses: For setting up of any Factory, one needs to take an approval
from the District factory Inspectorate.

Explosive License: For storage of Methanol, one has to obtain an Explosive


License from the Directorate of Explosive. For Biodiesel, this license is issued
form Nagpur.

Pollution Control Board Clearance: Since our Multi-feedstock Biodiesel


Processing Plants are non-polluting, hence the same can be obtained easily.

Frequently Asked Questions (FAQ'S):


The basic requirement for setting up the plant that you require is Land. Now the
question that comes to your mind as to how much land will be required for
setting up the Plant. It is directly related to the capacity of the plant that you put
up.

However it is imperative that we provide you with the following details that will
provide you a basic layout of the things that are required for setting up the plant:
1. Requirement of land Ranges from 5 Acres
2. Factory Shed 15,000 Sq. Feet
3. Electrical 440V/250KVA
24 hours piped water supply with O/H storage
4. Water Supply
20,000 Litres
5. Stand By Power 150 KVA Genset
6. Analytical Laboratory Basic module will be set up by us
Will be dependent on the capacity of the
7. Set of storage Tanks
Processing Plant
Modular batch Transesterifier BDT5 MTPD to
8. Biodiesel Processor Unit 500 MTPD is capable of handling MULTI
FEEDSTOCK
The Plant supplied is also capable of handling Acid Oil with high FFA upto
9. 60%-90% in an Esterification and Transesterification Process. Animal Fat
with high FFA upto 5% is also successfully handled by the Plant.
Plant set up procedures

At Eastern Biodiesel Technologies Pvt. Ltd/Biodiesel Technologies, Kolkata


following is a step by step procedure of how to proceed with the concept of
understanding the biodiesel processing plant to the stage of setting up the plant
and commissioning the plant.

Here is a Step by Step Procedure that will help you to understand and to
proceed with setting up the plant:

STEP 1: Detailed discussion with the Team of Eastern Biodiesel Technologies


Pvt. Ltd after having gone through the General offer Letter, Quotation, and
Commercial Feasibility.

STEP 2: Signing of the Agreement:


At Eastern Biodiesel Technologies Pvt. Ltd, we use a very Transparent Method
of following Agreement. Once the customer decides to go ahead with the
project and places us the final order, we sign an agreement disclosing all the
details of how the project will be carried on. This agreement includes the
following:

1. Warranties and Liabilities


2. Scope of work
3. Technical Specification (Specification and scope of supply, Description
of equipment used)
4. Project implementation schedule
5. Commercial: It includes Price summary, Terms of Payment for the supply
of the Plant, Delivery Details, Validity, Reservation
6. After Sales service.

After the agreement is duly signed by both the Parties at our Kolkata Office, we
proceed with manufacturing the Biodiesel Processing Plant.

STEP 3: Placing the Order


Once the agreement is duly signed by both the parties, and modalities are sorted
out. The customer has to pay us advance money in order to go ahead with the
project and manufacturing the Processing Plant. (The advance money shall be
decided while signing the agreement.)
STEP 4: Once the customer places the order, he can go in for finding Land,
building, factory shed, formulating backward and forward integration of
feedstock and supply of finished product i.e., Biodiesel etc.

The Plant takes about 6 to 8 months of time to manufacture, and during this 6 to
8 months, the customer can look in to these details of Land, Licenses, Factory
Shed etc. So that by the time the customer is done with all the formalities we are
also done with the Plant and we can hand you an operational plant without
wasting anytime in between.

STEP 5: INSPECTION
Eastern Biodiesel Technologies Pvt. Ltd believes in the policy of absolute
transparency and customer satisfaction. We would like that our customer should
visit the plant before the delivery and be satisfied with the project.

STEP 6: DELIVERY
Once the plant is ready, and a date has been finalized by the customer, we will
dismantle the machine and it will be sent by our low trailers.

STEP 7: INSTALLATION AND COMMISSIONING


Once the plant reaches the customers site and the customer has arranged for
feedstock and other requirements, the entire team of Eastern Biodiesel
Technologies Pvt. Ltd will visit the Plant site and make the Plant operational by
running it for 72 hours and produce Biodiesel complying it with all national and
international standard.

STEP 8: AFTER SALES SERVICE


In future if the customer happens to face any problem in the technical running
of the plant or requires any kind of help, our team will be there to help you sort
out the problem.