Auditing Long and Short Term Plans: Mintec, Inc. Global Mining Software Solutions Since 1970
Auditing Long and Short Term Plans: Mintec, Inc. Global Mining Software Solutions Since 1970
Auditing Long and Short Term Plans: Mintec, Inc. Global Mining Software Solutions Since 1970
Page 1
Auditing Long Term and Short Term Plans
10. How do you know you have ramp access to all mining areas scheduled each year?
Have you mined out a ramp connection too early?
Mintec, Inc.
Global
Mining
Software
Figure 1. Comparing different representations of the same topographic surface.
Solutions
Audit Step 2: Checking Block Value Calculations Since
MSEP programs MSOPIT and MSVALP are used to calculate block values for use in pit 1970
optimization by either the Floating Cone or Lerchs-Grossmann method. Enter prices, costs
and recoveries, and the programs will calculate block values for each valid destination,
compare them, and select the highest block value and the corresponding destination for
storage back to the block model.
Page 2
Auditing Long Term and Short Term Plans
An audit file is created by these programs containing the block value calculation
input assumptions and calculation details for each valid destination for a pre-selected
vertical column of blocks in the block model. This file is named either workmsopit or
workmsvalp. It is worthwhile to check this file to verify that the input data is correct and
that the block value calculations are being done the way you anticipated.
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 3
Auditing Long Term and Short Term Plans
MSCompass procedure Compute Pit Slopes (pslope.dat) will determine the slope at
each exposed (x,y) grid location by evaluating its shell elevation and elevations at nearby or
adjacent grid points. The computed slope is stored in a gridded surface file item and can be
displayed as a model view for another type of visual check of slopes (Figure 2a).
Page 4
Auditing Long Term and Short Term Plans
Prior to reporting these cutoffs as part of your life-of-mine scheduling results, you can
check their operational viability by using them in Minesight’s more detailed scheduling
program MSSP. Reserve classes using the optimal cutoff values as grade bins are created by
MSCompass procedure Modcls.
Reserve classes are then mapped to stockpile or mill each year to duplicate the cutoff grade
strategy provided by MSVALP. MSSP is then run to confirm their viability.
Page 5
Auditing Long Term and Short Term Plans
Audit Step 9: Checking the Scheduled Mining of the Final Phases at the
Ultimate Pit Limit
The final phases in a mining schedule will be the lowest valued phases as they mine out
to the break-even limit of the deposit. In the schedule, the stripping of these final phases
is being done in periods when ore is being mined in preceding phases. In other words, the
stripping of the final phase is being paid for by ore in the previous phase when looking
at the annual cash flows in the schedule. Once the final phase is stripped, the stripping
requirements drop off dramatically and the mine finishes up by mining the ore benches in
the final phase.
A question that is usually raised regarding the final phases is whether or not the phase is Mintec, Inc.
economic on a stand-alone basis . Rather than the ore from a previous phase paying for the Global
stripping (as per the schedule), can the ore in the final phase pay for its own stripping based Mining
on the scheduled stripping and ore release and the inherent discounting that this entails (ore
Software
being mined later in time than the waste)?
Solutions
This question can be answered by using MSSP to do a stand-alone phase evaluation. The Since
bench-by-bench mining schedule for the phase being evaluated is specified in the program,
1970
all constraints are relaxed, and all other phases are locked out. MSSP will then compute
the NPV for the phase based on its scheduled mining. If it is negative, then the discounted
value of the ore in the phase cannot pay for its stripping and this phase is removed from
the schedule.
Another method for applying discounting considerations and their effects on final phase
economic viability is to consider discounting effects earlier in the process when determining
Page 6
Auditing Long Term and Short Term Plans
the LG ultimate pit limit. This can be done using MSEP vertical discounting option. The final
phases are then designed inside the discounted ultimate pit limit and, in theory, should then
be economic on a stand-alone scheduling basis.
Audit Step 10: Checking Mine Access at the End of Each Scheduling Period
Phase ramp access/design typically involves relocating existing ramps on to the pushed
back wall of the new phase design. This process can become complicated when phases only
push back a portion of the wall and connections have to be maintained between the old
ramp system and the relocated ramp system. A good way to verify that access is maintained
to all working areas over time is to create end-of-year maps of the status of the mine. These
maps will show the position of each active phase at these points in time and the positions
of the ramp systems designed for each phase. One can use these maps to trace the haulage
route from each active phase to the pit exit point and ensure that access to each active phase
is maintained throughout the schedule. An example of an end-of-year map is shown in
Figure 4 with a trace of the haulage route out of the mine shown in orange. These maps are
made using the MSSP Period Map tool in MS3D.
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Figure 4. End–of-year map with mine access ramp positions at this point in time.
Page 7
Auditing Long Term and Short Term Plans
Conclusion
This paper has presented a list of auditing steps that are typically done at Mintec when we
are either making a long term plan for a client or reviewing a client’s work at their request.
The paper has attempted to show most of the ways Minesight can be used to audit or check
your work as you do it in order to verify the schedule you present to management and,
sometimes, to third party auditors for their review. The auditing steps presented here have
focused on the long term planning tasks. Similar auditing work can be done with short term
plans using similar MS3D graphics tools and MSCompass procedures.
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 8