MEP Preliminary Program R00 - Local Authority Matrix

This document outlines the planned and actual timelines for obtaining necessary approvals and inspections from local authorities for the MEP works at the Emirates Speciality Hospital project in Dubai. It includes milestones such as submitting designs for approval, completing civil works, inspections by authorities like DEWA, DM, Civil Defense, and Etisalat, and obtaining necessary sign-offs. The responsibilities of the client, consultant, MEP contractor and various authorities are also defined for each activity.

Uploaded by

Varun Arya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
309 views2 pages

MEP Preliminary Program R00 - Local Authority Matrix

This document outlines the planned and actual timelines for obtaining necessary approvals and inspections from local authorities for the MEP works at the Emirates Speciality Hospital project in Dubai. It includes milestones such as submitting designs for approval, completing civil works, inspections by authorities like DEWA, DM, Civil Defense, and Etisalat, and obtaining necessary sign-offs. The responsibilities of the client, consultant, MEP contractor and various authorities are also defined for each activity.

Uploaded by

Varun Arya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Project Name:- Emirates Speciality Hospital,Dubai

Client :- Emirates Hospital


Consultant :- IBA
MEP Contractor:- M/s IEMSC

Local Authorities Matrix ( MEP Preliminary program)

Planned Planned Actual


Utility & Activity Responsibity Actual Start Status Updates
Start Finish Finish

ELECTRICAL SYSTEM

RELATED TO ADDC

SUBSTATION ( HV SIDE)

Receive DEWA approved Design Drawings and NOC from Consultant DEWA/EHS 7-Jul-19 7-Jul-19

RMU Room & Transformer Room Ready for Civil Inspection DEWA/EHS 17-Aug-19 17-Aug-19

Estimate Amount Paid by Client DEWA/EHS 18-Aug-19 18-Aug-19

Apply to DEWA for RMU Room & Transformer Room Civil Inspection DEWA/EHS 19-Aug-19 29-Aug-19

DEWA inspection of RMU Room & Transformer Room and revceive


DEWA/EHS 31-Aug-19 29-Sep-19
comments

Incorporate DEWA Comments and apply for re inspection DEWA/EHS 30-Sep-19 28-Oct-19

Re inspection of RMU Room & Transformer Room by DEWA DEWA/EHS 29-Oct-19 23-Nov-19

Approval & Handover of RMU Room & Transformer Room to DEWA DEWA/EHS 24-Nov-19 24-Nov-19

Delivery of Transformers, RMU etc. by DEWA DEWA/EHS 25-Nov-19 22-Feb-20

Loading & Unloading of Transformers, RMU & Cable from Main Load to
DEWA/EHS 23-Feb-20 7-Mar-20
respective rooms by Main Contractor
11 KV Cable laying through cable ladder / Tray by
DEWA/EHS 8-Mar-20 14-Mar-20
CONTRACTOR
RMU & Transformer Termination by DEWA and MDB incomer cable
DEWA/EHS 15-Mar-20 21-Mar-20
available
MV Power ON/OFF & release of "Power Available in Premises
DEWA/EHS 23-Mar-20
Letter"

LV INSTALLATION ( LV SIDE)

Design NOC from DEWA with LDN approval EHS 7-Jul-19

Submission of Shop drawings for DEWA Approval IBA/EHS/IEMSC 27-Sep-19 6-Oct-19

Approval of Shop Drawings by DEWA DEWA/EHS 7-Oct-19 27-Oct-19

Completion of all LV works, related Civil Works & Readiness for


IBA/EHS/IEMSC 4-Feb-20 4-Feb-20
Inspection

Inspection application to DEWA IBA/EHS/IEMSC 5-Feb-20 8-Feb-20

1st Inspection by DEWA DEWA/EHS 9-Feb-20 12-Feb-20

Snagging & Desnagging IBA/EHS/IEMSC 13-Feb-20 21-Feb-20

2nd Inspection by DEWA DEWA/EHS 22-Feb-20 27-Feb-20

LV Installation Inspection approval 27-Feb-20

RELATED TO DM (MUNCIPALITY) DRAINAGE, STORM WATER

Recceipt of Design NOC EHS 7-Jul-19

Installation Completion for drainage &storm water IBA/EHS/IEMSC 16-Feb-19 16-Feb-19

Inspection application to DM IBA/EHS/IEMSC 17-Feb-19 19-Feb-19

Inspection and approval for connections IBA/EHS/IEMSC/DM 20-Feb-19 2-Mar-19

Final Connections by DM EHS/DM 9-Mar-19

FIRE FIGHTING & FIRE ALARM SYSTEM

RELATED TO CIVIL DEFENCE

Design NOC from Civil Defense EHS 7-Jul-19

Completion of all works & Readiness for Civil Defense Inspection IBA/EHS/IEMSC 9-Mar-20 9-Mar-20

Inspection Request to Civil Defense IBA/EHS/IEMSC 10-Mar-20 14-Mar-20

1st Inspection by Civil Defense DCD 15-Mar-19 17-Mar-19

Snagging & Desnagging IBA/EHS/IEMSC 18-Mar-19 25-Mar-19

Final Inspection by ADCD DCD 26-Mar-19 29-Mar-19


Completion Certificate release by Civil Defense 29-Mar-19

TELEPHONE SYSTEM

RELATED TO ETISALAT

Design NOC from ETISALAT EHS 7-Jul-19

Submission of Drawings to ETISALAT for Approval IBA/EHS/IEMSC 24-Sep-19 7-Oct-19


IBA/EHS/IEMSC/ETI
Approval of shop drawings by ETISALAT 8-Oct-19 31-Oct-19
SALAT
Readiness for Etisalat Inspection IBA/EHS/IEMSC 5-Feb-19 5-Feb-19

Installation Inspection request to ETISALAT IBA/EHS/IEMSC 6-Feb-19 13-Feb-20

Inspection by Etisalat ETISALAT 14-Feb-20 18-Feb-20

Page 1 of 2
Project Name:- Emirates Speciality Hospital,Dubai
Client :- Emirates Hospital
Consultant :- IBA
MEP Contractor:- M/s IEMSC

Local Authorities Matrix ( MEP Preliminary program)

Planned Planned Actual


Utility & Activity Responsibity Actual Start Status Updates
Start Finish Finish

Incorporate Etisalat/Du comments and reapply for inspection IBA/EHS/IEMSC 19-Feb-20 1-Mar-20

Reinspection by Etisalat/Du ETISALAT 2-Mar-20 8-Mar-20

Receipt of Etisalat/Du installation approval ETISALAT 9-Mar-20 14-Mar-20