Prof. Sam.: Prof. Indrawansa Samaratunga PHD, DSC
Prof. Sam.: Prof. Indrawansa Samaratunga PHD, DSC
Prof. Sam.: Prof. Indrawansa Samaratunga PHD, DSC
This would be the last Q&A for about another month, as I would be busy with the Spring
2008 Class. Thank you for recommending the Class to your colleagues. It was over-
booked and many could not get places. I am considering advancing the Summer Class to
Mid-June in order to give them an opportunity to attend. If anyone is still interested,
please ask them to register early to avoid disappointment.
Regards,
Prof. Sam.
-----Original Message-----
From: mohamed salah [mailto:[email protected]]
Sent: 12 April 2008 10:57
To: [email protected]
Subject: Nominated subcontractor
Dear Sir,
Please advice me on the following - Fixed unit price equip supply contract, unit prices and
guidance quantity listed in the contract document. No design change / original scope change /
location - project title change, all remain same situation. No binding for variation quantities within
the contract, no reference to the FIDIC norms.
We have a Supply contract, without a defined Delta Value % for variations. The contract clause
for variation is calling for a firm unit price till the validity of entire contract duration Should have
asked for a definition of the expression “Contract Duration” before signing the Contract. At
present the contract is running on a prolongation period ( since Feb. 2007 ). The market rate for
the supply items has gone up like anything and the currency fluctuation also effecting our firm
supply price a lot.
1. Is there any way to raise a claim for obtaining a revised supply price to the contractor ?
You can raise a claim giving your opinion of the expression “Contract Duration”
to be “Time for Completion” and requesting additional costs for excess supplies
beyond that period, but it is unlikely that the Employer/Engineer would construe
that expression in the same manner. You may have to seek equitable relief in law
after obtaining legal advice from a local lawyer.
2. Is there any chances of getting a loss and expense claim for our overheads since Feb.
2007 ? Yes, if the Employer is responsible for the delay.
3. Is there any chances of terminating / binding this original contract by not accepting
the additional requests ( PMI ) ? You have to first establish what the original scope is.
Thereafter, if you can prove that the additional requests are not necessary or appropriate
to complete the original scope then you can refuse them. If there are no provisions
in the Contract for termination, then you have to get a court order to terminate.
Request your valuable comments for the same.
Regards
Sunil Menon, AIQS
-----Original Message-----
From: Chandrasekaran, K S - (TIME) [mailto:[email protected]]
Sent: 06 April 2008 17:47
To: [email protected]
Subject: RE: Q&A 7
Dear Dr.Sam,
Our warm thanks for all the Q&A which are being received via email . We will be certainly
interested in the advance course too as and when you conduct.
I anticipate that this will be during the comming RAMDHAN afternoons.
By the by i have a querry from the answers given by you below.
Omit 83 x 95 and add 83 x 87.2 and also adjust the Overheads and profit
accordingly. (This is the way PC rate adjustment is made under Lump Sum
Contracts . Is it true that this rule applies only when there is no "any adjustment in
the BOQ" ? No.
If clause 58.2 of GOC in a lumpsum contract reads as " The contractor shall be
entitled to only the actual cost thereof in lieu of the PC setout in the
corresponding item in the BOQ", Does the above rule apply? Yes.
Thank You.
Best Regards,
K.S.CHANDRASEKARAN
SENIOR QUANTITY SURVEYOR