Refinery Start Up Sequence
Refinery Start Up Sequence
A refinery consists of many other sub-units. Considering a optimum green refinery then
it may take Detailed Engineering = 24 months, Construction 24–36 months,
Commissioning = 6–8 months, Production in 24 + 36 + 8 = after 68 months. Considering
procurement to be in parallel to Engineering & Construction. (Procurement of material is
the biggest bottle neck which cannot be compressed & will depend from where it is
procured & what quality, being a variable did not add its duration).
It depends of course of size of the refinery. If we take average size (between 10-15
million ton of crude oil processing), it will take between 5-7 years to build greenfield
refinery.
Example: STAR refinery in process of building in Turkey is estimated to cost $5.5 bn with
10 million ton crude oil processing capacity. It was started in 2011 and expected to be
online at 2018.
Dear Uday san,
Please refer below prerequisite for AVU-IV,OHCU,ATU-II,PRU,LPG MOUNDED BULLETS & OFFSITES
UTILITIES for your information and further alignment of BR-09 integrated time line schedule.
AVU-IV: (EPCC-01A)
1) SWS-II (EPCC-03)
2) ARU-III (EPCC-03)
3) ARU-I (Existing) Alternate for ARU-III
4) RFCCU Revamp-LVGO,HVGO,VR,VS feed (EPCM-03)
5) Coker-B- VR FEED (EPCM-02)
6) ATU-II (EPCC-06)
7) DHDT-II(EPCC-05) AGO & Vac. Diesel feed
8) NHDT-II+ISOM-II (EPCC-04) Light Naphtha feed
9) LTU-I Tie ins with existing unit for treating AVU-IV LPG (EPCM-24)
10) BELCO- For spent caustic handling (EPCM-03)
11) Caustic Solution System (EPCC-07)- 45% Fresh Caustic supply
12) ETP (EPCC-15)- For spent caustic handling
13) ETP readiness for handling of Brine effluent from Desalter
14) OWS to ETP (EPCM-24)
15) CRWS to ETP to BTP Transfer facility (EPCM-11)(EPCM-24)
16) OFFSITE Tank farm (EPCC-11)-Crude Tanks, OHCU Feed tanks, SKO/PCK Tanks, SRN Tanks
17) Offsite Area Feed & Dispatch Pumps (EPCM-14)
18) ATF Tanks (EPCM-10)
19) Flushing Oil from Storage(EPCM-24)(EPCM-14)(EPCC-11)
20) Slop (EPCM-24)
21) FIRE WATER SYSTEM (EPCC-02)
22) FLARE (EPCC-09)- HC Flare & Acid Flare(EPCM-24)
23) Fuel Gas (EPCM-24)
24) Cooling Water- From PCT Cooling Tower (EPCC-10)
25) DM+CPU (EPCC-15)
26) BFW (EPCM-24)
27) Drinking water (EPCM-xx)
28) Power Import Facility
29) Instrument Air (IA) & Plant Air(PA) (EPCC-14)(EPCM-24)
30) Nitrogen (EPCM-24) & N2 plant on BOO basis
31) Service Water(EPCM-24)
32) HP,MP,LP Steam (EPCM-24)
1) LTU-II (EPCC-07)
2) RFCCU Revamp-Treated LPG feed (EPCM-03)
3) PP Unit (EPCC-08)
4) Caustic Solution System (EPCC-07)-Caustic supply
5) ATU-II (EPCC-06)
6) BELCO- For spent caustic handling (EPCM-03)
7) Existing LPG Bottling Plant & TTL facility Tie ins and connecting pipelines (EPCM-24)
8) Caustic Solution System (EPCC-07)-45% Fresh Caustic supply
9) ETP (EPCC-15)- For spent caustic handling
10) OWS to ETP (EPCM-24)
11) CRWS to ETP to BTP Transfer facility (EPCM-11)(EPCM-24)
12) Offsite Area Off spec LPG Pump (EPCM-14)
13) FIRE WATER SYSTEM (EPCC-02)
14) FLARE (EPCC-09)- HC Flare (EPCM-24)
15) Fuel Gas (EPCM-24)
16) Cooling Water- From Propylene Cooling Tower (EPCC-10)(EPCM-24)
17) DM+CPU (EPCC-15)
18) BFW (EPCM-24)
19) Drinking water (EPCM-xx)
20) Power Import Facility
21) Instrument Air (IA) & Plant Air(PA) (EPCC-14),(EPCM-24)
22) Nitrogen (EPCM-24) & N2 plant on BOO basis
23) Service Water(EPCM-24)
24) HP,MP,LP Steam (EPCM-24)
25) LABORATORY (EPCM-xx)
All Off-sites & Utilities including interconnection piping (EPCM-24) shall be made progressively ready
~4 months before mechanical completion of AVU-IV (MC-30 Months).
Also note that Interconnection Piping + Pipe rack (EPCM-24,25), Fire water system(EPCC-02), Flare
Package (EPCC-09) & DM+CPU (EPCC-15) plant are on critical path. Since execution of these systems
is linked to Refinery shut down & tight schedule.
AVU-IV Initial operation or 6 MMTPA case is no more applicable. Therefore it is considered that AVU-
IV shall be running to its design capacity of 9 MMTPA after commissioning.
Please update BR-09 integrated time line schedule based on above understanding.
For balance BR-09 units Muktesh san will issue details similarly with in today.