TechnicalspecificationPartI PDF
TechnicalspecificationPartI PDF
TechnicalspecificationPartI PDF
COMMON DOCUMENT
TECHNICAL SPECIFICATION
VOLUME-II (PART-I)
CONTENTS OF THE TECHNICAL BIDDING DOCUMENTS (VOL-II)
COMMON DOCUMENT
TECHNICAL SPECIFICATION
VOLUME-II (PART-I)
Substation description:.................................................................................................................................5
Meteorological data......................................................................................................................................5
7. SPARES................................................................................................................... 7
7.3 Optional spares ( shall not be considered for evaluation purpose). ......................................................7
15.1 General..........................................................................................................................................12
System description
The following are the general particulars governing the design and working of the complete system of
which the Contract Works will eventually form a part:
Electrical energy is generated at a number of thermal and hydro power plants generally located in the
North, Central and Southern areas of Orissa State. The system is three phase, 50Hz and power is
transmitted at 400kV, 220kV and 132kV to the distribution system, via grid substations, which operate
at 33kV, 11kV and 400V. The 400kV and 220kV networks tie into the OPTCL's 400kV and 220kV grid
systems operated by OPTCL. The proposed works will increase the interconnection of, and will thus
reinforce the 400kV and 220kV networks within Orissa State. The detailed technical parameters of the
system are given in the schedules.
Substation description:
OPTCL has adopted the philosophy of installing open terminal air insulated substations. The busbars for
400 KV rigid type and for 220 KV flexible strain type depending upon the choice of the designer
considering the overall suitability and economy of the substation to be installed.
Layout arrangement
The Contractor shall study the details of layout arrangements already indicated in the schedules details
for the existing substations. The bay width and height of the conductors for these substations shall be
achieved by the Contractor in case of extension substations. However the Contractor shall finalise the
layout arrangements in case of new substations in line with this Specification with the approval of the
Engg Incharge ,which shall be meeting at least the basic minimum electrical clearances as specified in the
schedules.
Location and site description
Details of the sub-substation locations, their approach , geography and topography has been provided to
the extent possible. The Bidder shall make necessary visit to the substation sites and fully appraise
himself before bidding. Deviations on account of inadequate data for substation works shall not be
acceptable and the Bid shall not be considered for evaluation in such cases.
Meteorological data
Appropriate meteorological data is given in the schedules.
Soil data
Detailed soil investigations in respect of various substations have not been made. However the general
characteristics of the soil are given in the schedules. The Contractor shall investigate the properties of the
substations and measure the soil resistivity as part of the scope of work.
7. SPARES
7.1 General
The Contractor shall provide the mandatory spares detailed in the Schedules. Provide a list of
recommended spare parts (optional spares) together with their individual prices, but that will not be
considered for evaluation. The Employer may order all or any of the Optional spare parts listed at the
time of contract award . Mandatory spares shall be supplied as part of the Works under this
8 .0 TRAINING
The Contractor will be required to provide suitable training for selected staff both on site and at the
Contractor's place of work. Details of the training considered appropriate shall be stated clearly, at the
bidding stage, based on the number of trainees specified. The cost of training including all course fees
shall be included.
The areas in which it is considered training should be provided, and duration of the training courses, are
given in this section. Alternative arrangements, where considered appropriate, should be suggested.
Four categories of training are considered appropriate namely :
I. Hardware maintenance.
II. Operator familiarisation.
III. Software management.
IV. Installation and commissioning techniques.
15.0 INSURANCE
15.1 General
In addition to the conditions covered under the Clause titled insurance in the Special Conditions of
Contract, the following provisions will also apply to the portion of works to be done beyond the
Suppliers own or his sub-Contractors manufacturing Works.
COMMON DOCUMENT
TECHNICAL SPECIFICATION
FOR
............................................................................................................................. 1
16.1. General............................................................................................................................................... 33
1. GENERAL
The following provisions shall supplement all the detailed technical specifications and requirements
brought out in accompanying Technical Specifications. The Contractor’s proposal shall be based upon
the use of equipment and materials complying fully with the requirements specified herein. It is
recognised that the Contractor may have standardised on the use of certain components, materials,
processes or procedures different to those specified herein. Alternate proposals offering similar
equipment based on the manufacturers standard practice will also be considered, provided such
proposals meet the specified design standard and performance requirement and are acceptable to the
Engg. Incharge.
3.1 General
To ensure that the supply and services under the scope of this Contract, whether manufactured or
performed within the Contractor’s works or at his Sub-Contractor’s premises or at Site or at any other
place of work are in accordance with the Specification, with the Regulations and with relevant Indian
or otherwise Authorised Standards the Contractor shall adopt suitable Quality Assurance Programmes
and Procedures to ensure that all activities are being controlled as necessary.
The quality assurance arrangements shall conform to the relevant requirements of ISO 9001 or ISO
9002 as appropriate.
The systems and procedures which the Contractor will use to ensure that the Works comply with the
Contract requirements shall be defined in the Contractor’s Quality Plan for the Works.
The Contractor shall operate systems which implement the following:
Hold Point “A stage in the material procurement or workmanship process beyond which work shall
not proceed without the documented approval of designated individuals or organisations.”
The Engg. Incharge written approval is required to authorise work to progress beyond the Hold Points
indicated in approved Quality Plans.
3.7 Sub-contractors
The Contractor shall ensure that the Quality Assurance requirements of this Specification are followed
by any sub-contractor appointed by him under the Contract.
The Contractor shall assess the sub-contractor’s Quality Assurance arrangements prior to his
appointment to ensure its compliance with the appropriate ISO 9000 standard and the Specification.
Auditing of the sub-contractor’s Quality Assurance arrangements shall be carried out by the Contractor
and recorded in such a manner that demonstrates to the Engg. Incharge the extent of the audits and
their effectiveness.
4.1 General
Within one month of award of contract the Contractor shall produce a HSE Plan for the contract and
submit for the approval of the Engg. Incharge . The HSE Plan is described in the following sections.
The primary objective of the HSE Plan is for the contractor to demonstrate that he has the capability to
carry out the contract work in a cost effective manner, giving due consideration to the Health, Safety
and Environmental management of both his own employees, those of the Employer and anyone who
may be affected by his activities.
5 0 PROGRESS REPORTING
The Contractor shall submit for approval, within four weeks of the issue of letter of award, an outline
of the design, engineering, material procurement, production, site mobilisation, man and machine
deployment, delivery, erection, testing, commissioning, and handing over programme. Within a further
period of 4 weeks the Contractor shall provide a detailed programme of all these activities in a form to
be agreed by the Engg. Incharge . The Contractor shall submit monthly progress reports to the Engg.
Incharge office not later than the fifth day of the following month. The reports shall show clearly and
accurately the position of all activities associated with design, material procurement, manufacture,
works tests, shipping, site erection, testing and commissioning with regard to the agreed contract
programme.
In addition to the routine monthly progress report the Contractor shall also submit to the Engg.
Incharge by the 25th day of every month, a man hour schedule for the following month, detailing the
man hours scheduled for that month, skill-wise and area-wise.
The preferred format for presentation of programmes is MS Project version 4.0 or any latest. The
programmes and monthly updates shall be submitted on CD.
The design aspect of the progress report shall include a comprehensive statement on drawing and
calculations submitted for approval.
6 0 STANDARDS
Except where otherwise specified or implied, the Contract Works shall comply with the latest edition of
the relevant Indian Standards, International Electrotechnical Commission (IEC) standards and any other
standards mentioned in this Specification. The Contractor may submit for approval, equipment or
materials conforming to technically equivalent National Standards. In such cases copies of the relevant
Standards or part thereof, in the English language shall be submitted with the Tender. In case of conflict
the order of precedence shall be (1) IEC, (2) IS and (3) other alternative standard.
Reference to a particular standard or recommendation in this Specification does not relieve the
Contractor of the necessity of providing the Contract Works complying with other relevant standards or
recommendations.
The list of standards provided in the schedules of this Specification is not to be considered exhaustive
and the Contractor shall ensure that equipment supplied under this contract meets the requirements of
the relevant standard whether or not it is mentioned therein.
8.1 Correspondence
All correspondence shall be addressed to the Sr. G.M, TP, OPTCL / Sr. G.M, C.P.C, OPTCL
Three copies of all drawings shall be submitted for approval and three copies for any
subsequent revision. The Engg. Incharge reserves the right to request any additional information that
may be considered necessary in order to fully review the drawings. Drawings for approval shall be
submitted as paper prints and shall bear the approved contract references. Submittal should where
possible be staggered to facilitate maintenance of the above schedule.
If the Engg. Incharge is satisfied with the drawing, one copy will be returned to the Contractor marked
with “Approved” stamp. If the Engg. Incharge is not totally satisfied with the drawing, then “Approved
subject to comment” status will be given to it and a comment sheet will be sent to the Contractor. If the
drawing does not comply with the requirements of the specification then it will be given “Not
Approved” status and a comment sheet will be sent to the Contractor. In both the latter cases the
Contractor will have to modify the drawing, update the revision column and resubmit for final
approval.
Following approval copies of final drawings will be required as given below.
· Reproducible on Tracing Films or Papers : 3 copies
· Hard Copies on paper (Blue print or Xerox) : 20 copies
· Computer CD ROM : 1 copy
Any drawing or document submitted for information only should be indicated as such by the
Contractor. Drawings submitted for information only will not be returned to the Contractor unless the
Engg. Incharge considers that such drawings do need to be approved, in which case they will be
returned suitably stamped with comments.
Drawings, samples and models submitted by the Contractor and approved by the Engg. Incharge shall
not be departed from without the instruction in writing of the Engg. Incharge .
The Contractor shall be responsible for any discrepancies or errors in or omissions from the drawings,
whether such drawings have been approved or not by the Engg. Incharge . Approval given by the Engg.
Incharge (Divisional Engr.)to any drawing or sample shall neither relieve the Contractor from his
liability to complete the Contract Works in accordance with this Specification and the conditions of
contract nor exonerate him from any of his guarantees.
10 0 GENERAL REQUIREMENTS
10.2 Galvanising.
10.2.1 General
All machining, drilling, welding, engraving, scribing or other manufacturing activities which would
damage the final surface treatment shall be completed before the specified surface treatment is carried
out.
10.2.2 Galvanising
All metal surfaces shall be subjected to treatment for anti-corrosion protection. All ferrous surfaces for
external use shall be hot dip galvanised. High tensile steel nuts, bolts and spring washers shall be
electro galvanised to service condition 4. All steel conductors including those used for earthing and
grounding (above ground level) shall also be galvanised according to IS 2629.
All galvanising shall be applied by the hot dip process and shall comply with IS 2629, IS 2633, IS
4759, IS 1367 or IS 6745.
All welds shall be de-scaled, all machining carried out and all parts shall be adequately cleaned prior to
galvanising. The preparation for galvanising and the galvanising itself shall not adversely affect the
mechanical properties of the coated material.
The threads of all galvanised bolts and screwed rods shall be cleared of spelter by spinning or brushing.
A die shall not be used for cleaning the threads unless specially approved by the Engg. Incharge
(Divisional Engr.). All nuts shall be galvanised with the exception of the threads which shall be oiled.
Surfaces which are in contact with oil shall not be galvanised or cadmium plated.
Partial immersion of the work will not be permitted and the galvanising tank must therefore be
sufficiently large to permit galvanising to be carried out by one immersion.
Galvanising of wires shall be applied by the hot dip process and shall meet the requirements of
IS 2141.
The minimum weight of the zinc coating shall be 610 gm/sq.m and minimum thickness of coating shall
be 86 microns for all items thicker than 5 mm. For items of less than 5 mm thickness requirement of
coating thickness shall be as per BS 729. For surface which shall be embedded in concrete, the zinc
coating shall be a minimum of 800 gm/sq.m.
The galvanised surfaces shall consist of a continuous and uniform thick coating of zinc, firmly
adhering to the surface of steel. The finished surface shall be clean and smooth and shall be free from
defects such as discoloured patches, bare spots, unevenness of coating, spelter which is loosely
attached to the steel globules, spiky deposits, blistered surface, flaking or peeling off, etc. The presence
of any of these defects noticed on visual or microscopic inspection shall render the material liable to
rejection.
After galvanising no drilling or welding shall be performed on the galvanised parts of the equipment
excepting that nuts may be threaded after galvanising. Sodium dichromate treatment shall be provided
to avoid formation of white rust after hot dip galvanisation.
415V 411 — —
Miscellaneous
19 Control modules and console inserts Smoke grey 692 Light grey 631
20 Lighting package equipment outside Light grey 631 Light grey 631
21 Lighting package equipment inside Glossy white Glossy white
22 Water pipes sea green 217 sea green 217
23 Air pipes Sky blue 101 Sky blue 101
24 Transformer oil pipes Light brown 410 Light brown 410
25 Fire Installations Fire red 536 Fire red 536
26 Insulating oil/ gas treatment plant Gulf red 473 Gulf red 473
10.6 Padlocks
For each item of plant the Contractor shall provide a padlockable handle and a non-ferrous padlock with
different key changes in order to prevent access to control cabinets, cubicles and relay panels. The
Contractor shall provide two keys for each lock and a master key for each substation.
Cabinets for the accommodation of padlocks and keys, whilst not in use, shall be provided and shall be
suitably labelled so that keys will be readily identifiable.
10.7 Earthing
Metal parts of all equipment other than those forming part of an electrical circuit shall be connected
directly to the main earth system via two separate conductors of adequate capacity at two different
points.
All main members of structural steelworks shall be earthed by galvanised iron flat connections bonded
by welding or bolting to the steelworks.
Connections to apparatus and structures shall be made clear of ground level, preferably to a vertical
face and protected as appropriate against electrolytic corrosion. They shall be made between clean
surfaces and of sufficient size and pressure to carry the rated short circuit current without damage.
Earth bars installed directly into the ground should normally be laid bare and the trench back-filled
with a fine top soil. Where the soil is of a hostile nature, special precautions must be taken to protect
the earth bar, the method used being subject to the agreement of the Engg. Incharge (Divisional Engr.).
Joints in earth bars shall be welded and then coated with a suitable anti-corrosion protection treatment.
Facilities shall be provided on the earth bar run between equipment and the base of structures,
comprising a looped strip, so as to permit the attachment of portable earth connections for maintenance
purposes.
The cross sectional area of the earth bar and connections shall be such that the current density is not
greater than 100 A/mm2 for a 3 second fault duration.
10.8 Lubrication
Bearings which require lubrication either with oil or grease shall be fitted with nipples.
11.1 Castings
11.1.1 General
All castings shall be true to pattern, free from defects and of uniform quality and condition. The
surfaces of castings which do not undergo machining, shall be free from foundry irregularities. The
castings shall be subject to NDT, chemical, mechanical and metallographic tests. Details of the same
shall be furnished to Engg. Incharge (Divisional Engr.)for review/approval. Magnetic particle
inspection (MPI) test, wherever applicable, shall be carried out in longitudinal and transverse direction
to detect radial and axial cracks.
11.2 Forgings
When requested by the Engg. Incharge (Divisional Engr.), forgings will be subjected to inspection in
the regions of fillets and changes of section by suitable method. Magnetic particle, dye-penetration,
radiographic or ultrasonic, or any combination of these methods may be used to suit material type and
forging design.
The testing is to be carried out after the rough machining operation and is to be conducted according to
the appropriate ASTM standards.
MPI test on forging shall be carried out to detect both radial and axial cracks. Ferrous forgings shall be
demagnetised after such tests.
Any indentations which prove to penetrate deeper than 2.5% of the finished thickness of the forging
shall be reported to the Engg. Incharge (Divisional Engr.)giving location, length, width and depth. Any
indentations which will not machine out during final machining shall be gouged out and repaired using
an approved repair procedure.
Repair of rotating elements by welding will only be accepted subject to detailed examination of the
proposal by the Engg. Incharge (Divisional Engr.)prior to the repair being carried out.
The forging shall be tested for mechanical and metallographic tests as per ASTM. The details shall be
mutually discussed/agreed upon.
13 0 DEGREES OF PROTECTION
Degrees of protection shall be provided in accordance with IEC 144 and IEC 529 and be as follows:
· For outdoor applications, IP 55.
· For indoor applications where purpose built accommodation is provided, e.g. switch and control
and relay rooms in auxiliary plant buildings, IP 41.
· Where dust can adversely affect equipment within the enclosure, this equipment should be
separately housed with a degree of protection of IP 51.
· For indoor applications where the equipment is housed in the same building as that enclosing
water and steam operated equipment, the degrees of protection stated in the previous paragraph shall be
up-rated to IP 44 and IP 54 respectively.
Where more severe environments exist, e.g. steam and oil vapour or other deleterious chemical
environments, special measures will be necessary and the degree of protection required will be specified
separately.
The Contractor shall submit a schedule for providing the degree protection to various control boxes,
junction boxes etc. for the Engg. Incharge (Divisional Engr.)s approval.
14 0 SUPPLY VOLTAGE
All incoming supplies of greater than 125 V to earth shall have their termination shrouded by a suitable
insulating material.
16 0 ERECTION CONDITIONS
16.1 General
The following shall supplement the conditions already contained in the other parts of these
specifications and documents and shall govern that portion of the work on this Contract to be performed
at Site.
16.7 Security
The Contractor shall have total responsibility for all equipment and material in his custody, stored,
loose, semi-assembled and/or erected by him at Site. The Contractor shall make suitable security
arrangements including employment of security personnel to ensure the protection of all materials,
equipment and works from theft, fire, pilferage and any other damages and loss.
17 0 CONSTRUCTION MANAGEMENT
17.1 General
Time is the essence of the Contract and the Contractor shall be responsible for performance of his
Works in accordance with the specified construction schedule. If at any time the Contractor is falling
behind the schedule, he shall take necessary action to make good for such delays by increasing his work
force or by working overtime to accelerate the progress of the work and to comply with schedule and
shall communicate such actions in writing to the Engg. Incharge (Divisional Engr.), providing evidence
that his action will compensate for the delay. The Contractor shall not be allowed any extra
compensation for such action.
COMMON DOCUMENT
TECHNICAL SPECIFICATION
FOR
SYSTEM DATA
NIT NO. 07/2012-13 (Package-07/2012-13 VOL-II (TS) E3-SYSTEM DATA- Page 2 of3
19 Safety clearances
1. Section clearance metres 6.5 5 4 4
metres
2. Ground clearances( 8 5.5 5 4
between ground and bottom
most part of energised object) metres
3. Horizontal clearance As per I.E. As per As per As per I.E.
between the fence and metres Rules I.E. I.E. Rules Rules
energised object As per I.E. Rules As per
4. Horizontal clearance Rules As per I.E. Rules As per I.E.
between the road centre line I.E. Rules
and energised part of the Rules
nearby equipment
20 Bay width metres 27 18 11-13.1 5.5
21 Height of bus equipment metres 8 5.5 5 4
interconnection from ground
22 Height of strung busbar metres >15 10.5 8.5 5.5
TECHNICAL SPECIFICATION
FOR
GENERAL METEOROLOGICAL
DATA
Description Data
Annual mean of maximum monthly 50
average temperature.
Annual mean of minimum monthly 5
temperature in oC
Average rain fall in mm 1500
TECHNICAL SPECIFICATION
FOR
5.0 INTERLOCKING
5.1 General
The applicable recommended interlocking facilities of IEC 517 shall be provided. Padlocking to the
requirements of this specification shall be provided for operational and maintenance security.
Earth switches on line circuits shall be capable of interrupting the current induced in the line at the
voltage specified in the schedules. This current may arise by induction from a fully loaded line in
parallel with the earthed line. If earth switches without the rated breaking capacity are provided, the
interlocking arrangements shall ensure the interruption of this induced current by the circuit breaker
before the earth switch is opened. Interlocking facilities shall be provided to release the circuit breaker
for maintenance whilst maintaining the earthing of the incoming line.
5.2 Philosophy
All disconnecting and earthing devices within the substation shall be interlocked in a manner that
ensures that they always operate safely. The system employed shall satisfy two distinct categories:
· Operational interlocking: Interlocking associated with normal system operation and switching and
intended to ensure that a predetermined switching sequence is satisfied. Such interlocking shall be
achieved by electrical means in a manner that permits the equipment to perform any safe operation.
· Maintenance Interlocking: Interlocking associated with a series of switching operations to render
the equipment or sections of the substation safe for access and maintenance by personnel. Such
interlocking shall be achieved by mechanical interference type interlocks.
5.3 Principles
The design of the interlocking scheme shall be based upon the following principles:
a) Dis connectors are capable of switching the capacitive currents of associated connections.
b) Circuit breakers shall not be used as a point of safety isolation, this is the function of a
disconnecter.
c) Dis connectors have neither load making nor breaking capacity.
d) Dis connectors are not capable of making or breaking transformer magnetising current.
e) Dis connectors are capable of the duty imposed when operated under parallel switching
conditions.
f) It shall not be possible to close or open any earth switch unless the point of application is
disconnected from all possible sources of supply, and the power operating devices of such dis
connectors are selected to the local control position.
TECHNICAL SPECIFICATION
FOR
CIVIL WORKS
TABLE OF CONTENTS
2. SITE CLEARANCE 4
3. STANDARDS 5
4. SOIL INVESTIGATION 6
7. SITE SURFACING 14
8. SITE DRAINAGE 15
9. SEWAGE SYSTEM 17
16. FENCING 39
17. BUILDING 41
19. INTERFACING 48
2. 0 SITE CLEARANCE
2.3 Programme
The Contractor shall construct the works in compliance with the outline programme appended to
the Bidding Document, and shall submit for the approval of the Engg Incharge (Divisional Engr.)
a detailed programme in accordance with the requirements of this Specification.
3. 0 STANDARDS
All Civil works shall be carried out as per applicable Indian Laws, latest revision of International
Standards and Codes. All materials shall be of best quality confirming to relevant Indian
Standards and Codes.
Civil works shall be designed to the required service conditions and /or loads as specified
elsewhere in this Specification or implied as per National and International Standards.
A list of code of practice and standards used for civil works in general is enclosed for reference.
In case of any conflict between I.S. Code and the Procedures specified herein, the later shall
prevail.
4.1 General
The Contractor shall perform a detailed soil investigation to arrive at sufficiently accurate general
as well as specific information about the soil profile/strata and the necessary soil parameters of
the site in order that the foundations of the various structures can be designed and constructed
safely and rationally. Foundation systems adopted by the contractor shall ensure that relative
settlement shall be as per provision in IS 1904 and any latest IS and other Indian Standards.
This Specification covers all the work required for detailed soil investigation and preparation of a
detailed report. The work shall include mobilisation of necessary equipment, provision of
necessary engineering supervision and technical personnel, skilled and unskilled labour etc., as
required to carry out field investigation and tests, laboratory tests, analysis and interpretation of
data and results, preparation of detailed soil report including specific recommendations for the
type of foundations and the safe bearing capacity for different sizes of foundations at different
founding strata for the various structures of the substation. The Contractor shall make his own
arrangements for locating the coordinates and various test positions in field and also for
determining the reduced level of these locations with respect to the bench mark .All the test are to
be carried out before the OPTCL officials or before any agency engaged by OPTCL. Prior
intimation in this effect has to be given to OPTCL.
A report to the effect will be submitted by the Contractor for the Engg Incharge (Divisional
Engr.) specific approval giving details regarding his assumed data for Civil structures design.
Any variation in soil data shall not constitute a valid reason for any additional cost and shall not
affect the terms and condition of the Contract. Nothing extra what so ever shall be paid to the
Contractor on account of any variation in subsoil properties /or conditions. Tests must be
conducted under all the critical locations i.e. Control room building, autotransformer, lightning
mast, 400 kV/220 kV/132 kV column location etc. However, some of the soil parameters given
below for substations have to be determined and submitted to Engg Incharge (Divisional Engr.).
· Dry density
· Bulk density
· Angle of internal friction/cohesion
* Specific gravity
· Natural moisture content.
5.1 General
All materials used in the works shall be new and of the best quality of their respective kinds.
They shall comply with the requirements of the latest edition of any relevant Indian Standard or
Code of Practice where such exist, and current at the date of tendering.
All workmanship shall be of the highest standard, and shall be executed by competent men skilled
in their respective trades.
5.2 Samples
In addition to the special provisions made in this specification for sampling and testing of
materials by particular methods, samples of any materials and workmanship proposed to be used
in the Works may be called for at any time during the Contract by the Engg Incharge (Divisional
Engr.) and shall be furnished by the Contractor without delay and at the expense of the
Contractor. Samples when approved, shall be regarded as the acceptable standard, and any
material or workmanship subsequently not complying with that standard shall be rejected and
replaced by those of acceptable standard at the expense of the Contractor. Sample storage boxes
shall be provided by the Contractor free of cost if requested by the Engg Incharge (Divisional
Engr.).
6.5 Backfill
As soon as possible after the permanent works are sufficiently hard and have been inspected and
approved, backfill shall be placed where necessary and thoroughly consolidated in layers not
exceeding two hundred (200) millimetres in depth.
On completion of structures, the earth surrounding them shall be accurately finished to the line
and grade as shown on the drawings. Finished surfaces shall be free of irregularities and
depressions.
The soil to be used for back filling purposes shall be from the excavated earth or from borrow
pits, as directed by the Engg Incharge (Divisional Engr.).
6.7 Compaction
The method and equipment used to compact the fill material to a density that will give the
allowable soil bearing pressure required for the foundations, roads, etc. in each layer of fill
material. Each layer of earth embankment when compacted shall be as close to optimum
moisture content (OMC) as practicable. Embankment material which does not contain sufficient
moisture to obtain proper compaction shall be wetted. If the material contains an excess of
moisture, then it shall be allowed to dry before rolling. The rolling shall begin at the edges
Where compacted fill is required it shall consist of suitable sand, or other selective inorganic
material, subject to approval by the Engg Incharge (Divisional Engr.). The filling shall be done
with locally available sand. The filled in sand shall be kept immersed in water for sufficient time
to ensure compaction, if so desired by the Engg Incharge (Divisional Engr.).
7.3 Measurements
7.3.1 Payment of gravel filling
The measurement shall be based on square metre of finished area of minimum specified
compacted thickness of 100 mm above finished ground level. Nothing shall be paid extra for any
additional material labour etc. used for achieving the specified compacted thickness of 100 mm.
above finished ground level.
8.1 General
Adequate site drainage system shall be provided by the Contractor. The Contractor shall obtain
rainfall data and design the storm water drainage system, (culverts, ditches, drains etc.) to
accommodate the most intense rainfall that is likely to occur over the catchment area in one hour
period on an average of once per ten years. The surfaces of the site shall be sloped to prevent the
ponding of water.
The maximum velocity for pipe drains and open drains shall be limited to 2.4m/sec and 1.8m/sec
respectively. However, minimum non silting velocity of 0.6m/sec shall be ensured. Longitudinal
bed slope not milder than 1:1000 shall be provided.
For design of RCC pipes for drains and culverts, IS 456 and IS 783 shall be followed.
The Contractor shall ensure that water drains are away from the site area and shall prevent
damage to adjacent property by this water. Adequate protection shall be given to site surfaces,
roads, ditches, culverts, etc., to prevent erosion of material by water.
The drainage system shall be adequate without the use of cable or pipe trenches.
For pipe drains, concrete pipes of class NP2 shall be used. However, for road crossings higher
strength pipe of class NP3 shall be provided. For rail crossings, pipes conforming to railway
loading standards or at least NP4 class shall be provided. Manholes shall be provided at 30 m
intervals, at connection points and at every change of alignment. All manholes deeper than 1.2 m
shall be provided with galvanised M.S. foot rests. Foot rests shall be of 20 mm M.S. square bars.
8.5 Regulations
The regulations and recommendations of any relevant drainage or sanitary authority shall be fully
observed, and the Contractor shall be responsible for acquainting himself with any such
regulations.
11.1 General
The Contractor shall provide a permanent transfer track system integrated with the auto
transformer foundation to enable installation and the replacement of any failed unit with a spare
unit. The transfer track system shall be suitable to permit the movement of any failed unit fully
assembled (including OLTC, bushings) with integral radiators and oil, without the de-
energization of any other equipment in the station. The system shall enable the removal of any
failed unit from its foundation to a repair area and the installation of a spare unit. The system
shall not interfere with the normal internal road and trench system. If trench or drain crossings are
required then suitable R.C.C culverts shall be provided in accordance with IRC Code and /or
relevant IS.
Rail tracks shall be of RCC, M20(1:1.5:3 mix) grade. The space between the tracks shall be
suitably filled with local sand and 75 mm thick PCC of grade 1:3:6 placed over sand filling. The
top of PCC shall be up to the formation level. In case of road cum rail track, 75mm thick PCC of
12.1 General
Fire protection walls shall be provided in accordance with Tariff Advisory Committee (TAC)
recommendations.
12.5 Dimensions
Fire walls shall extend at least two metres on each side of the power transformers or reactors and
at least one metre above the conservator tank or safety vent.
These dimensions might be reduced in special cases, and if TAC permits so, where there is lack
of space. A minimum of two metres clearance shall be provided between the equipments e.g.
reactors, transformers and fire walls.
Building walls which act as fire walls shall extend at least one metre above the roof in order to
protect it.
12.8.1 General
Cable trenches and pre-cast removable RCC covers (with lifting arrangement) shall be
constructed using RCC of M20 grade.
The cable trenches shall be designed for the following loads.
· Dead load of 155 kg/ m length of cable support plus 75 kg on one tier at the end.
· Triangular earth pressure plus uniform surcharge pressure of 2 tonnes per sq.metre.
· Cable trench covers shall be designed for (i) self weight of top slab plus concentrated
load of 200 kg at centre of span on each panel and a surcharge load of 2 tonnes per sq.
metre.
Cable trench crossings of road and rails shall be designed for class AA, class A and class 7OR
loading of IRC or relevant IS Code and should be checked for transformer loading.
Trenches shall be drained. Necessary sumps be constructed and sump pumps shall be supplied.
Cable trenches shall not be used as storm water drains.
The top of trenches shall be kept at least 250 mm above the finished ground level. The top of
cable trench shall be such that the surface rain water does not enter the trench.
The covers of the slab are also of RCC with ratio mixing 1:1.5:3.The thickness of
the slab shall be 75mm for section 1-1(MS Rods to be used 10mm&8mm), section 2-2, 3-
3 shall be 60mm (MS Rod to be used 8mm) and section 4-4 shall be 50mm(MS Rods to
be used 8mm&6mm). The MS rods to be used shall be placed at 100 mm centre to centre
both way and properly binded .The cover slab shall have provision of lifting hooks at two
points for easy lifting of the slabs. Slabs having lifting hooks shall be placed at every 10th
slabs. The lengths of the cable trench cover slabs are as below.
Section Length of the slab Thickness of the slab
1-1 1600mm 75mm
2-2 1100mm 60mm
3-3 1100mm 60mm
4-4 400mm 50mm
12.9 Excavation
Excavation for cable ducts shall generally be carried out in accordance with Clause no. 6.2 of this
specification.
13.1 General
All foundations/RCC Design shall be of reinforced cement concrete. The design and construction
of RCC structures shall be carried out as per IS 456 and minimum grade of concrete shall be M20
corresponding to 1:1.5:3 (M20)nominal mix ratio with 12-20 mm coarse aggregate. Higher grades
of concrete than specified above may be used at the discretion of the Bidder without any financial
implication to the owner. Work covered under this clause of the specification comprises the
construction of foundations and other RCC constructions for switchyard structures,equipment
support,trenches,drains,jacking pad,pulling block,control cubicles,bus supports,Auto
transformer/power transformer/reactors, marshalling kiosks,auxiliary equipments and system
buildings, tank or for any other equipment or service and any other foundation required to
complete the work. Also applicable to other RCC constructions.
If the site is sloping, the foundation height will be adjusted to maintain the exact level of the top
of structures to compensate such slopes.
The switcyard foundations plinths and building plinths shall be minimum 300mm above finished
ground level respectively. Minimum 75 mm thick lean concrete shall be provided below
underground structures,foundations,trenches etc to provide a base for construction.
The design and detailing of foundations shall be done based on the approved soil data and sub-soil
conditions as well as for all possible critical loads and the combinations thereof. The special
footing or pile foundations as may be required based on soil/sub-soil conditions and superimposed
loads shall be provided.
Admixtures in concrete shall confirm to IS:9103. The water proofing cement additives shall
confirm to IS:2645. Concrete Admixtures/Additives shall be approved by the owner.
Limit state method of design shall be adopted unless stated otherwise in the Specification.
14.1 General
Work covered under this Clause of this Specification comprises the design, supply and
installation of foundations and other RCC constructions for switchyard structures, equipment
supports, trenches, rains, jacking pads, pulling blocks, fencing, control cubicles, bus supports,
transformers, marshalling kiosks, auxiliary equipments and systems, buildings and tanks, or for
any other equipment or service and any other foundation required to complete the work. This
clause is as well applicable to the other RCC constructions.
Concrete shall conform to the requirements of IS 456 and all the tests shall be conducted as per
relevant Indian Standard Codes.
If the site is sloping, the foundation height will be adjusted to maintain the exact level of the top
of structures to compensate for such slopes.
Switchyard foundation plinths and building plinths shall be minimum 300 mm and 500 mm
above finished ground level respectively.
A minimum of 75 mm thick lean mix concrete (1:3:6) shall be provided below all underground
structures, foundations, trenches etc. to provide a base for construction.
Concrete made with portland cement(OPC-43 grade) shall be carefully cured and special
consideration shall be given during the placing of concrete and removal of shuttering.
The design and detailing of foundations shall be done based on the approved soil data and sub-
soil conditions as well as for all possible critical loads and combinations thereof. Spread footing
foundations or pile foundations as may be required based on soil and subsoil conditions and
superimposed loads shall be provided.
If pile foundations are adopted, the same shall be cast-in-situ, driven, bored, precast or
underreamed type as per relevant IS. Only RCC piles shall be provided. Suitability of the
adopted pile foundations shall be justified by way of full design calculations. Detailed design
calculations shall be submitted by the contractor showing complete details of piles and pile
groups proposed to be used. Necessary initial load tests shall also be carried out by the contractor
at their entire cost to establish the pile design capacity. Only after the design capacity of piles has
been established, shall the Contractor commence of piling. All the design and testing work shall
be planned in such a way that these shall not cause any delay in project completion.
14.2 Cement
The cement to be used shall be the best quality of its type.
All cement shall be sampled and tested in accordance with Indian Standards.
The Portland cement(OPC-43 grade) used in concrete shall confirm to IS 269.
Requirement of sulphate resistant cement (SRC) for substructural works shall be decided in
accordance with the Indian Standards based on the findings of the detailed soil investigation to be
carried out by the contractor.
14.4 Aggregate
Coarse and fine aggregate shall conform to the requirements of IS 383-1970.
Sampling and testing of aggregates shall be in accordance with the relevant Indian Standard.
Fine and coarse aggregates shall be obtained from the same source and the Contractor shall
ensure that material from the source is known to have a good service record over a long period of
time.
Aggregate shall be hard and dense and free from earth, clay, loam and soft, clayey, shaley or
decomposed stone, organic matter and other impurities.
14.7 Water
Water used for mixing concrete and mortar shall be clean, fresh water obtained from an approved
source and free from harmful chemicals, oils, organic matter and other impurities. Normally
potable water may be considered satisfactorily for mixing and curing concrete and masonry work.
Only concrete or steel spacers shall be used to achieve the required minimum thickness of
concrete cover to reinforcement. Concrete spacers shall have non metallic ties. Timber blocks
for wedging the steel off the formwork will not be allowed.
14.13 Formwork
Form work shall be constructed from timber, metal, lined as necessary for special finishes and
designed with the quality and strength required to ensure rigidity throughout placing, ramming,
vibration and setting of the concrete, without detrimental effect.
Form work shall be erected true to line, level and shapes required using a minimum of approved
internal ties. Faces in contact with the concrete shall be true and free from defect, jointed to
prevent loss of water or fines, in panels or units which permit easy handling, and designed to
permit side forms to be struck independently of soffit shuttering. Ties or spaces remaining
embedded shall have the minimum cover specified for reinforcement. Forms for exposed
concrete beams, girder casings and columns shall provide for a twenty five millimetre chamfer on
external corners.
Wedges and clamps shall be kept tight during vibration operations. Before commencement or
resumption of concreting, the interior of forms shall be cleaned and free of sawdust, shavings,
dust, mud or other debris and openings shall be formed to facilitate this cleaning and inspection.
The inside of the forms shall be treated with a coating of an approved substance to prevent
adhesion. Care shall be taken to prevent this substance being in contact with the reinforcement.
14.18 Workability
The workability of concrete shall be checked at frequent intervals by slump test, where facilities
exist and if required by the Engg Incharge (Divisional Engr.), alternatively the compaction factor
test in accordance with IS 1199 shall be carried out.
14.31 Blinding
Blinding concrete shall be made with nominal aggregate sizes of both 20mm and 40mm diameter.
They shall be referred to respectively as grade M 10/20 and M 10/40.
Under all foundations and elsewhere as indicated on the drawings a layer of concrete grade M10
(1:3:6) shall be laid immediately the excavation is carried down to foundation level. The blinding
surface shall be thoroughly cleaned before foundation concrete is deposited thereon. Sumps shall
be provided where necessary to facilitate the control of drained water. The grade shall be applied
as shown in Table 15.31.1
15.0 0 FENCING
15.1 General
Fencing shall be designed for the most critical loading combination taking into account wind
forces, stability, tension on wires, minimum requirements as per this clause and relevant IS
recommendations.
The un climbable or security, or anti-intruder fencing shall consist of chain link mesh, all as soon
on the drawings and as specified below, supported on approved sections of structural steel. The
posts shall be erected truly vertical, and all posts and struts shall be set in concrete block
foundations.
Concrete kerbing shall be provided between the fence posts as shown on the drawings.
16.0 0 BUILDING
16.1 General
The scope includes the design, engineering and construction of control room and colony quarters
building. For control room and colony quarter building the tentative layout showing the facilities
to be provided is indicated some where and also to be proposed by the bidders for better utility
and aesthetic view. However, the size and layout of the building may be modified as per
requirements of Single Line Diagram (SLD) with the approval of the Engg Incharge (Divisional
Engr.).
16.3 Design
The buildings shall be designed:
· to the requirements of the National Building Code of India. and the standards quoted
therein
· for the specified climatic and loading conditions
· to adequately suit the requirements of the equipment and apparatus contained in the
buildings and in all respects to be compatible with the intended use and occupancy
· with a functional and economical space arrangement
· for a life expectancy of structure, systems and components not less than that of the
equipment which is contained in the buildings, provided regular maintenance is carried
out
· to be aesthetically pleasing. Different buildings shall show a uniformity and consistency
in architectural design
· to allow for easy access to equipment and maintenance of the equipment
· with, wherever required, fire retarding materials for walls, ceilings and doors, which
would prevent supporting or spreading of fire
· with material preventing dust accumulation
Suitable expansion joints shall be provided in the longitudinal direction wherever necessary with
provision of twin columns.
Individual members of the building frame shall be designed for the worst combination of forces
such as bending moment, axial force, shear force, torsion etc.
Permissible stresses for different load combinations shall be taken as per relevant IS Codes.
All cable vaults shall be located above ground level i.e. cable vaults shall not be provided as
basements in the buildings.
The building lighting shall be designed in accordance with the requirements of relevant section.
The building auxiliary services such as air conditioning and ventilation systems, fire protection
and detection systems and all other miscellaneous services shall be designed in accordance with
the requirements specified in relevant sections of this Specifications.
The doors and windows of the building shall be of aluminium extruded channels, angles etc. The
windows shall be provided with sliding shuttering facilities and also to be provided with
aluminium make grills.
16.10 Walls
Control room buildings shall have framed superstructure. All walls shall be non-load bearing
walls. Minimum thickness of external walls shall be 230 mm with 1:6 cement sand mortar. A 50
mm thick DPC shall be provided at plinth level before starting masonary work.
16.11 Plastering
All internal walls shall have minimum 12mm thick 1:6 cement sand plaster. The ceiling shall
have 6mm thick 1:4 cement sand plaster.
16.13 Roof
Roof of the building shall consist of cast in situ R.C.C. slabs. Extra heavy water proofing
treatment shall be done after grading underbed with 1:4 cement sand plaster of 25mm thickness.
The under bed shall be laid to provide an ultimate run off gradient of 1:120. The extra heavy
treatment shall be concrete based with water proof treatment as per the standard to protect the
roof from damage due to water logging. Proper slope and adequate no of water drains outlets
shall be provided for easy discharge of water from the roof. These drains shall be connected to the
main drain.
1.3 Flooring
Entire area around the control room building (out side)shall be provided with PCC paving starting
from the building upto 2 mtrs clear distance for the full length of the building.
The above specified PCC paving shall be with M15 mix grade concrete over suitable under bed
arrangement as specified for other ground floor slab.
Above the PCC paving suitable Cement pavers chequered plate of size as per the standard to be
provided. The colour of the chequered plate shall be fixed over the PCC paving by using cement
mortar and the colour of such plate shall be red.
The cable vault below the main control room shall have 50 mm thick smooth floor finish units of
cement concrete.
>The plinth area for the control room building shall be as below:-
Ground floor: 50mtrX25mtr
Ground floor portico: 5mtrX5mtr (at two locations)
First floor: 25 mtr X 25 mtr
i)Ground floor shall have cable vault, Battery room, Office rooms(3 nos),MCCB room,
Library, Conference room, Testing lab, Pantry room, Toilets and bath room(two nos
and one attached), Corridor with lounge, Portico at front and side, Ramp etc.
ii) First floor shall have control room, PLCC room, office room, toilets and bath room
etc.
* All internal walls shall 125 mm thick. (Excluding cement plastering)
* All external walls shall 250 mm thick. (Excluding cement plastering)
* For RCC works refer the relevant specification.
* The quarter shall be of framed RCC structure based.
* Concrete grade shall be 1:1.5:3 for all RCC works
* Reinforcement shall be Fe 415 Grade, confirming to IS:1786. All hooks,bands,laps shall
be as per IS:456-2000.All laps shall be staggered and minimum lap length shall be
50XDia of Bar.
* Clear cover to main reinforcement for footing = 50mm,column=50mm,beam=25mm &
slab=20mm.
* Rain water pipes 100 sq mm to be provided at suitable location.
* The stair case width=1100mm, Tread=300mm, riser=148/150mm and suitable platform at
different level.
>The plinth area for the control room building shall be as below:-
Ground floor: 42mtrX13 mtr =546 Sqm
Ground floor portico: 5mtrX5mtr
First floor: 21 mtr X 13 mtr=273 Sqm
i)Ground floor shall have Control room( also can be kept on the first floor for better
visibility of switch yard area),PLCC room, Battery room, MCCDB room, ,Toilets and
bath room, Verandah & Portico etc..
ii) First floor shall have office rooms (3 Nos), a Library, a Conference room, a Rest room,
,Pantry room ,toilets(2 No.) and toilet cum bath room (1 no.) etc.
* All internal walls shall 125 mm thick. (Excluding cement plastering)
* All external walls shall 250 mm thick. (Excluding cement plastering)
* For RCC works refer the relevant specification.
* The quarter shall be of framed RCC structure based.
* Concrete grade shall be 1:1.5:3 for all RCC works
* Reinforcement shall be Fe 415 Grade, confirming to IS:1786. All hooks,bands,laps shall
be as per IS:456-2000.All laps shall be staggered and minimum lap length shall be
50XDia of Bar.
* Clear cover to main reinforcement for footing = 50mm,column=50mm,beam=25mm &
slab=20mm.
* Rain water pipes 100 sq mm to be provided at suitable location.
* The stair case width=1100mm,Tread=300mm, riser=148/150mm and suitable platform at
different level.
* The stair case shall be RCC having Kotta stone fixing.
* The height of the ground floor of the building from the finished plinth level (minimum
1.0 mtr from the finished ground level) shall be 3.9 mtrs and the height of the parapet
wall shall be 750mm. The height of the first floor from the top of the roof of the first
floor shall be 3.4 mtrs and the height of the parapet wall shall be 750mm.The stair case
top shall be at a height of 2.75 mtrs from the top of the parapet top.
18.0 0 INTERFACING
Proper coordination and execution of all interfacing civil works activities such as fixing of
conduits in roofs/walls/floors, fixing of foundation bolts, fixing of lighting fixtures, fixing of
supports/embodiments, provision of cut-outs etc. shall be the sole responsibility of the contractor.
He shall plan all such activities in advance and execute in such a manner that interfacing activities
do not become bottlenecks and such that dismantling, breakage etc. is reduced to minimum.
23.0 PROVISION OF STORE SHED, PLAT FORM, RAMP AND WINCH FOR LIFTING
MATERIALS & VEHICLE PARKING SHED.
23.1 One no store shed of size 15X15 mtr having brick walls and plastering with RCC
roof of 15X15 meters. The flooring shall be of 75 mm thickness PCC (mix ratio1:2:4)
over RR masonry works (as per standard practice of flooring). Provision of adequate nos
of MS racks (proper paintings also to be done as per the direction of site in charge) for
keeping the spare materials. The height of the shed shall be 4mtrs above the plinth.
23.2 One no platform outside the store shed RR masonry (compacted) with PCC at the
top for storing the transformer bushings, Instrument transformers, transformer oil drums
etc. The size of the platform shall be 20mtrX15 mtr. Details of flooring as mentioned
under 24.1. The platform shall have top covers by using TATA GC sheets.
23.3 Provision of a RCC based ramp of adequate size for loading and unloading of the
materials from the lorry near the store shed.
23.4 A winch is to be provided near the ramp for lifting and lowering of materials up
to 5 tons capacity. The two side vertical pillars shall be by MS Rail/joist and the top
horizontal also of same type. A chain pulley of 5 ton capacity is to be provided at the
centre of the frame on the horizontal bar.
23.5 Erection of Isolator Mechanism Box.
Separate RCC foundation to be provided for the Isolator Mechanism boxes.
23.6 There shall be one no vehicle parking shed inside the sub-station area. The size of
the parking area shall be 15mtrs X 15 mtrs, out of the entire area there shall be provision
of shed for 5 mtrs X 15 mtrs and rest of the area shall be without shed. The flooring of
the entire area of the vehicle parking shall be as mentioned under 23.1.
SCOPE OF WORK
The contractor shall furnish all labour, equipment and materials required for complete
performance of the work in accordance with the drawings, specification and direction of
the Engg Incharge (Divisional Engr.).
General Requirement
The material required for site surfacing/gravel filling shall be free from all types of
organic materials and shall be of standard approved quality, and as directed by the Engg
Incharge (Divisional Engr.).
The Contractor shall furnish and install the site surfacing to the lines and grades as shown
in the drawing and in accordance with the requirements and direction of the Engg Incharge
(Divisional Engr.). The soil of the periphery area of the switchyard area shall be subjected
to sterilisation or anti-weed treatment before placing the site surfacing/gravel fill material
or strictly as per instruction or requirement of the manufacturer of the chemical required
for soil sterilisation or anti-weed treatment. After all the structures and equipment have
been erected and accepted, and soil sterilisation of the peripheral area (except the switch
yard area) as specified is complete, the site shall be maintained to the lines and grades
indicated in the drawing and rolled or compacted by using three ton roller with suitable
water sprinkling to form a smooth and compact surface condition which shall be
matching with finished ground level of the switchyard area.
Chemical to be used for soil sterilisation /anti-weed treatment:
The details of quantities and method of application of chemicals used for soil sterilisation
/and anti-weed treatment shall be as per manufacturer`s recommendations. Bidders are
required to submit the details of chemicals proposed to be used and recommendations of
manufacturer with required guarantee alongwith their bids for necessary approval of the
Engg Incharge (Divisional Engr.). Approval of the Engg Incharge (Divisional Engr.) by no
means shall relieve the contractor of their contractual obligations as stipulated in General
and Special Conditions of Contract.
Rainwater harvesting shall be done by providing two numbers recharge structures with
bore wells. The recharge structures shall be suitably located with in the S/S. Branch
drains from the main drain carrying rainwater from entire switchyard shall be connected
to the recharge structures.
The internal diameter of recharge shafts shall be 4.5 meter with 230mm thick lining of
brick work upto a depth of 2.0 meter from ground level and 345mm thick brickwork
below 2.0 meter depth. The brickwork shall be constructed with cement mortar 1:6 (1
cement : 6 coarse sand ). The overall depth of shaft shall be 5.0 meter below invert level
of drain. The shaft shall be covered with RCC slab for a live load of 300Kg. per Sq.m.
two openings of sizes 0.7X0.7 meter shall be provided in the RCC cover slab as shown in
the drawing. An iron cover made of 5mm thick chequered plate with hinges shall be
provided in the openings. Galvanized M.S. rungs of 20mm diameter at spacing of 300mm
shall be provided in the wall of the shaft below the opening of the RCC slab to facilitate
cleaning of shaft.
A 300mm diameter bore well shall be drilled in the centre of the shaft. The depth of bore
well shall be 5.0 meter more than the depth of the sub soil water.
A 100mm diameter medium duty MS pipe confirming to IS 1161 shall be lowered in the
bore well keeping bail plug towards bottom of bore well. The pipe shall have 1.58mm
holes for 4.0 meter length starting from 1.0 meter from bottom of bore well. Holes of
3.0mm dia. Shall be provided for a length of 2.0 meter starting from the bottom level of
coarse sand and downwards. The overall length of the pipe shall be equal to the total
depth of the bore well plus depth of shaft.
Gravel of size 3mm to 6mm shall be filled around 100 dia MS pipe in the bore well. The
shaft shall be filled with 500mm thick layers each from the bottom of shaft with boulders
of size 50mm to 150mm, gravel of size 5mm to 10mm, coarse sand having particle size
1.5mm to 2.0mm and boulders of size not less than 200mm respectively.
27.0 Fire water Tank: This is a lump-sum item. The contractor shall be required to
complete the work in all respect as per requirement.All the items including excavation,
compaction, brick work, roof truss, corrugated A.C.Sheet roofing, all types of
miscellaneous steel internal and external plastering, painting, etc shall be deemed to be
included in this lump-sum water tank. However the concrete (all types), reinforcement
and the steel embedments(except roof truss & purlins) shall be measured and paid on
lumpsum basis.
(i) Water shall be made available by Owner (unless stated otherwise elsewhere) at
any feasible point near scope boundary at single point to the contractor.
Contractor shall state the total water requirement both in terms of quantity and
head to the Owner.
(ii) The contractor shall carry out all the external plumbing/erection woks required for
supply of water to the control room building beyond the single point as at (i).
(iii) The contractor shall carry out all the plumbing/erection woks required for supply
of water to fire water tank beyond the single point as at (i).
(iv) A scheme shall be prepared by the contractor indicating the layout and details of
water supply which shall be got approved from the Owner before actual start of
work including all other incidental items not shown or specified but as may be
required for complete performance of the works.
(v) Bore wells and pumps for water supply is not in the scope of contractor.
1. 12mm cement plaster of mix 1:6 (1 cement: 6 fine sand) shall be provided on the
smooth side of internal walls.
2. 6mm cement plaster of mix 1:3 (1 cement: 3 fine sand) to all ceiling.
3. 15mm cement plaster of mix 1:6 (1 cement: 6 fine sand) on rough side of single or
half brick wall.
4.12mm thick per-laminated three layer medium density (exterior grade) particle board
Grdel, Type II conforming to IS: 12823 bonded with phenol formaldehyde synthetic
resin, of approved brand and manufacture shall be provided in paneling fixed in
aluminium doors, windows shutters and partition frames with C.P. brass/stainless
steel screws etc. complete as per architectural drawings and directions of engineer-in
charge.
5. Dis tempering on all internal walls and ceilings with oil bound washable
distemper of approved brand and manufacture to give an even shade (two or more
coats) over and including priming coat with cement primer.
7. Two or more coats of French spirit polishing with a coat of wood filler shall be
provided on the wooden doors of Control Room building.
9. Cement plaster skirting (up to 15 cm height) with cement mortar 1:3 (1 cement:3
coarse sand) mixed with metallic concrete hardener in same ratio as for floor finished
with a floating coat of heat cement. 21 mm thick in ACDB/DCDB room.
10. Floor tiles of Polished porcelain (vitrified) in different sizes with water absorption
less than 1% and flexural strength not less than 30 N/mm2 in all colours and shades,
laid on 20mm thick cement mortar 1:4 (1 cement: 4 coarse sand) including grouting
the joints with white cemen5t and matching pigments shall be provided as mentioned
in drawings. Size of Tile shall be 50X50 cm.
11. 1st Quality Ceramic glazed floor tiles (anti-skid) 300 x 300mm (thickness to be
specified by the manufacturer) of 1st quality conforming to IS:13755 of NITCO,
ORIENT, SOMANY, KAJARIA or equivalent shall be provided in toilet/pantry area in
all colour shades as approved by Engg-incharge laid on 20mm thick cement mortar
1:4 (1 cement: 4 coarse and) including pointing the joints with white cement and
matching pigment etc complete.
12. 1st quality ceramic glazed tiles confirming to IS:13753 of minimum thickness 5mm
of approved make like NITCO, ORIENT, SOMANY, KAJARIA or equivalent make
shall be provided in toilet/pantry area in all colours shades of any size as approved by
Engg-incharge in dados (height as specified in drawings) over 12mm thick bed of
cement mortar 1:3 (1 cement:3 coarse sand) and jointing with grey cement slurry
@3.3kg per sqm including pointing in white cement mixed with pigment of matching
shade complete.
13. 13mm polished granite in cement mortar 1:4, 20mm thick made to a level cut to
size shall be provided and laid as specified in drawings. The joints are filled with
jointing compound matching to the tiles. Wherever granite tiles are specified for the
floor, 100mm granite skirting shall be provided with the walls. The granite outer
surface shall be flushed to the plaster finish of the wall.
14. Granite counter shall be provided and fixed in the pantry with 18mm granite slab
mounted on 75mm RCC slab supported by 115mm brick wall plastered on all sides as
per the drawing. The shelves are made of 18mm thick well cut and polished white
marble slabs. The outer side of the brick wall and the RCC slab visible in the front is
finished with 18mm granite with edges molded on the exposed end. The shutters shall
be finished with 19mm particle finished laminate edge lapping. The shutters are to be
provided with 100mm handless and shutter locks. The inside of the shutter shall be
painted with synthetic enamel paint.
16. Anti termite treatment shall be carried out for all buildings.
17. M.S. Rolling shutters as per drawing shall be provided and fixed interlocked
together through their entire length and jointed together at the end by end locks
mounted on specially designed pipe shaft with brackets along with ball bearing for
rolling shutter, side guides and arrangements for inside and outside locking with push
& pull operation including the cost of providing and fixing necessary 15.5 cm long wire
springs grade No.2 and M.S. top cover of required thickness for rolling shutters. 80 x
1.25mm M.S. laths with 1.25mm thick top cover.
18. Circular/hexagonal M.S. sheet ceiling fan box shall be provided in the ceiling with
clam p of internal dia. 140mm, 73mm height, 3mm thick rim, top and bottom lid of
1.5mm M.S. sheet. Lids shall be screwed in to M.S. box by means of 3mm round
headed screws, clamps shall be made of 12mm dia M.S bar bent to shape s peer
standard drawing with over all length as 80 cm.
19. Anodised aluminum work for doors, windows, ventilators and partitions shall be
provided and fixed in control room building with extruded built up standard tubular and
other sections of approved make conforming to IS: 7333 and IS:1285, anodized
transparent or dyed to required shade according to IS:1868 (Minimum anodic coating
of grade AC 15) fixed with raw plugs and screws or with fixing clips, or with expansion
hold fasteners including necessary filling up of gaps at junctions at top, bottom and
sides with required PVC/neoprene felt etc and joined mechanically wherever required
including cleat angle, Aluminium snap beading for glazing/paneling, C.P.
brass/stainless steel screws including glazing and fittings as specified.
Shutters of doors, windows and ventilators shall be provided and fixed with
hinges/pivots fittings wherever required including PVC/neoprene gasket.
Anodised aluminum work for doors, windows, ventilators and partitions shall be
provided and fixed in control room building with extruded built up standard tubular and
other sections of approved make conforming to IS: 7333 and IS:1285, anodized
transparent or dyed to required shade according to IS:1868 (Minimum anodic coating
of grade AC 15) fixed with raw plugs and screws or with fixing clips, or with expansion
hold fasteners including necessary filling up of gaps at junctions at top, bottom and
sides with required PVC/neoprene felt etc and joined mechanically wherever required
Shutters of doors, windows and ventilators shall be provided and fixed with
hinges/pivots fittings wherever required including PVC/neoprene gasket.Anodised
aluminum work for doors, windows, ventilators and partitions shall be provided and
fixed in control room building with extruded built up standard tubular and other
sections of approved make conforming to IS: 7333 and IS:1285, anodized transparent
or dyed to required shade according to IS:1868 (Minimum anodic coating of grade AC
15) fixed with raw plugs and screws or with fixing clips, or with expansion hold
fasteners including necessary filling up of gaps at junctions at top, bottom and sides
with required PVC/neoprene felt etc and joined mechanically wherever required
including cleat angle, Aluminium snap beading for glazing/paneling, C.P.
brass/stainless steel screws including glazing and fittings as specified.
Shutters of doors, windows and ventilators shall be provided and fixed with
hinges/pivots fittings wherever required including PVC/neoprene gasket. with 5.5 mm
plain float glasses and rubber gasket with bottom three feet pre-laminated sheet of
12mm thick of colour grey,ivory Jindal/Indal/Hindalco make as per drawing.
Outer frames 2-1/2 x 1-1/2, 63.5 x 38.10 X 1.5mm, DP 1212, 0.700 Kg/mt, to
work as fixed partition & door with door verticals 44.45 x 47.62 x 1.5mm, DP 2022,
0,.850 Kg/mt, top and center pieces as per drawing.
20. Cement based water proofing treatment of roofs, balconies, terraces etc. shall be
provided with average thickness of 120 mm and minimum thickness at Khurra as 65
mm and laid consisting of following operations:
(a) A slurry coat of neat cement using 2.75 kg/m2 of cement admixed with
proprietary water proofing compounds conforming to IS: 2645 shall be applied and
grouted over the RCC slab including cleaning the surface before treatment.
(b) Plain Cement concrete 1:5:10 (1 Cement : 5 fine sand : 10 burnt brick aggregate
of 40 mm nominal size) admixed with proprietary water proofing compound conforming
to IS:2645 over 20 mm thick layer of cement mortar of min :5 (Cement :5 coarse sand)
admixed with proprietary water proofing compound conforming to IS: 2645 to required
slope an treating similarly the adjoining walls upto 300 mm height including rounding of
junctions of walls and slabs.
(c) After two day of proper curing, a second coat of cement slurry admixed with
proprietary water proofing compound conforming to IS:2645 shall be applied.
(d) The surface shall be finished with 20 mm thick joint less cement mortar of mix 1:4
(1 cement :4 course sand) admixed with proprietary water proofing compound
conforming to IS : 2645 and finally the surface shall be finished with trowel with neat
cement slurry and making of 300 x 300 mm square.
21. Unplasticised rigid PVC rain water pipes 110 mm dia shall be provided and fixed
on the wall face conforming to IS : 13592 type A as per drawing including jointing with
seat ring conforming to IS:5382 leaving 10 mm gap for themal expansion single
socketed pipes.
22. Unplasticised PVC Moulded fittings / accessories including 110 mm bend and
110 mm shoes shall be provided and fixed for uplasticised rigid PVC rain water pipes
conforming to IS : 13592 type A including jointing with seat ring conforming to IS : 5382
leaving 10 mm gap for thermal expansion.
· Unplasticised PVC pipe clips of approved design shallbe provided and fixed to
uplasticised 110 mm PVC rain water pipes by means of 50x50x50 mm hard
wood plugs, screwed with MS screws of required length including cutting brick
work and fixing in cement mortar 1:4 (1 cement : 4 coarse sand) and making
good the wall etc.
· Double action hydraulic floor spring of approved brand and manufacture IS: 6315
marked “hardwyn” make (model 3000) or equivalent for doors shall be provided
and fixed at the following door including cost of cutting floors as required,
embedding in floors and cover plates with brass pivot and single piece MS sheet
outer box with slide plate etc. as per the direction of Engineer- in charge. With
stainless steel cover plate:
· Coloured vitreous china pedestal type water closet (European type) with seat
and lid, 40 mm flush bend, overflow arrangement with specials of standard make
and mosquito proof coupling of approved municipal design including painting of
fittings and brackets, cutting and making good the walls and floors shall be
provided for all toilets.
· Coloured vitreous china wash basin of size 630 x 450 mm with C.I / M.S brackets
alongwith single 15 mm C.P brass pillar taps, Kingston / Gem / Techno / Parko.
32 mm C.P brass waste of standard pattern, shall be provided and fixed in the
toilets including painting of fittings and brackets, cutting and making good the
walls wherever required alongwith C.P brass trap and C.P brass union.
(b) Double type coat & hat hooks with flanges, fixed to wall / shutter, etc. with
necessary screws, washers & plugs.
(c) CP / PP liquid soap holder of approved make fixed with each wash basin to the wall
with necessary CP / PP brackets, CP screws, washers, plugs etc.
(d) 100 mm dia vitreous chinaware half round channel of approved make fixed to
correct grade, level, opening for floor trap below urinals set in CM 1:3 & pointed using
white cement etc.
(f) CP brass angle valve of 15 mm nominal bore provided and fixed in position for
basin and cistern points of approved quality conforming IS : 8931.
(g) Best quality marble partition slab provided and fixed in position for urinals, of size
610 x 1150 mm, 20 mm thick, polished on both sides & machine cut, exposed corners
rounded etc.
(h) Towel rail of approved make of 600 mm length, 25 mm dia with a pair of brackets
or flanges provided and fixed to wall beside each wash basin / set of wash basin with
necessary screws, plugs, etc.
(i) 6 mm thick beveled edge mirror 1000 x 600 mm shall be provided and fixed
mounted on 12 mm thick water proof plywood backing and hardwood beading all-
round and mirror fixed to the backing with 4 Nos. of CP cap screws & washers,
including fixing the mirror to the wall with necessary screws, plugs & washers etc, with
each wash basin.
(j) Salem Stainless steel A ISI 304 (18/8) Kitchen sink of 510 x 1040 mm Bowl depth
178 mm with drain board shall be provided and fixed as per IS: 13983 with C.I.
Brackets and stainless steel plug 40 mm including painting of fittings and brackets,
cutting and making good the wall.
iii) Wherever GI pipe are buried the same shall be provided and laid in position
including trenching sand cushion and refilling, painted with anticorrosive bitumastic
paint etc.
iv) Gun metal ball valve with operating levers, non-return valves conforming to IS
specification shall be provided and fixed in position as per drawing or direction of
Engineer-in-charge.
24) Masonry chamber for sluice valve shall be 600x600mm size in plan and depth
750mm, or matching with the site condition inside with 50 class designation brick
work in cement mortar 1:5 (1 cement :5 fine sand) with CI surface box 100mm.
Top diameter, 160mm bottom dia and 180mm deep (inside) with chained lid and
RCC top slab 1:2 :4 mix (1 cement :2 coarse sand: 4 graded stone aggregate 20
mm nominal size) necessary excavation foundation concrete 1:5:10 (1 cement:5
fine sand :10 graded stone aggregate 40mm nominal size) and inside plastering
with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick finished with a
floating coat of neat cement complete as per standard design with FPS bricks of
class 75.
25) Polyethylene water storage tanks (2 nos. of 2000 litres capacity each) shall be
provided and placed on roof of control room building of approved brand and
manufacturer with cover and suitable locking arrangement, float value and making
necessary holes for inlet, outlet and overflow pipes.
26) PVC floor traps of self cleansing design shall be provided & fixed in position with
outlet size of 75mm diameter of approved make, including making connection with
PVC soil/waste pipes using rubber gaskets, embedding the trap in 150mm thick
PCC 1:2:4, providing & fixing of top tile & strainer of CP or PVC on top of the trap
etc.
27) Square-mouth SW gully trap grade “A” 100x100mm size P type with FPS Bricks
class designation 75 shall be provided and fixed complete with CI grating brick
masonry chamber with water tight C.I. cover with frame of 300x300mm size
(inside) the weight of cover to be not less than 4.5 Kg and frame to be not less
than 2.70 Kg as per standard design.
28) Glazed stoneware pipes of 150mm diameter grade ‘A’ shall be provided, laid and
jointed with stiff mixture of cement mortar in the proportion of 1:1 (1 cement: 1 fine
sand) including testing of joints etc. complete.
29) Cement concrete 1:3:6 (1 cement:3 coarse sand:6 graded stone aggregate 40 mm
nominal size) shall be provided and laid around S.W. pipes including bed concrete.
30) Brick masonry manhole shall be constructed in cement mortar 1:4 (1 cement:4
coarse sand) RCC top slab with 1:2:4 mix (1 cement:2 coarse sand: 4 graded
stone aggregate 20mm nominal size) foundation concrete 1:4:8 mix (1 cement:4
coarse sand:8 graded stone aggregate 40mm nominal size) inside plastering
a) Inside size shall be 90 x 80 cm and 60 cm deep including CI cover with frame (light
duty) 455 x 610 mm internal dimensions total weight of cover and frame shall not
be less than 38 kg (weight of cover 23 kg and weight of frame 15 kg) and shall be
constructed with F.P.S. bricks with class designation 75.
31) MS foot of 20 x 20 mm square rests shall be provided and fixed in manholes with
20 x20 x10 cm cement concrete blocks 1:3:6 ( cement : 3 coarse sand : 6 graded
stone aggregate 20 mm nominal size) as per standard design.
32) Steel glazed doors, windows and ventilators of standard rolled steel section shall
be provided and fixed in FFPH building, joints mitred and welded with 15 x 3 mm
lugs, 10cm long, embedded in cement concrete blocks 10 x 10 x 10 cm of 1:3:6
(1 cement 3 coarse sand : 6 graded stone aggregate 20 mm nominal size0 or
with wooden plugs and screws or rawls plus and screws or with fixing clips or
with bolts and nuts as required, including providing and fixing of glass panes with
glazing clips and special metal sash putty of approved make complete including
applying a priming coat of approved steel primer, necessary hinges or pivots as
required.
33) Pressed steel door frames manufactured from commercial mild steel sheet fo
1.25 mm thickness shall be provided and fixed in FFPH building including hinges
jamb, lock jamb, bead and if required angle threshold of mild steel angle of
section 50x 25 mm or base ties of 1.25 mm pressed mild steel welded or rigidly
mixed together by mechanical means, adjustable lugs with split end tail to each
jamb including steel butt hinges 2.5 mm thick with mortar guards, lock strike-plate
and shock absorbers as specified and applying a coat of approved steel primer
after pre-treatment of the surface as directed by Engineer-in-charge.
34) Asbestos cement 6 mm thick corrugated sheets roofing shall be provided and
fixed with G, I, J or L hooks, blots and nuts 8 mm diameter G, I plain and bitumen
washers complete excluding the cost of purlins, rafters and trusses for water
tank.
(a) Earthwork
This shall include excavation in all kinds of soil including rock, all leads and lifts
including back filling, compacting, de-watering (if required) and disposal of surplus earth
to a suitable location. The quantity of excavation for foundations of towers, equipment
structures, all transformers, rail-cum-road, firewall, cable trenches, water tank, reactors
and buildings shall only be measured. The quantity of excavation for roads, drains,
rainwater harvesting, septic tank, soak pit, external water supply system, site surfacing
(b) PCC
Providing and laying Plain Cement Concrete of all types and at all locations
including all leads and lifts. The quantity shall be measured in cubic meters as per lines
and levels indicated in the drawings.
(i) PCC 1:2:4 (1 cement : 2 sand : 4 coarse aggregate 20 mm nominal size) shall be
measured in flooring of buildings, plinth protection, fencing, transformer foundation,
reactor foundation , rail track, drain, culverts, septic tank, chain link fencing, gate
etc. as indicated in the drawings.
(ii) PCC 1:4:8 (1 cement : 4 coarse sand : 8 stone aggregate, 40 mm nominal size)
shall be measured below all foundations of buildings, cable trench, roads, under
flooring, rail-cum-road, transformer foundation, reactor foundation, drain, water
tank, culverts, gate etc. as indicated in the drawings.
(iii) All other PCC required for the completion of the work including hold fasts of
doors / windows / rolling shutters, fixing of plumbing pipes, bedding concrete for
sewer lines, embedment of electrical conduits etc. shall not be measured and
deemed included in the composite rates quoted by the bidder for respective
works. Water proofing compound wherever specified shall be added without any
extra cost.
(c) RCC
Measurement of reinforced cement concrete at all locations shall be made and
shall include all leads, lifts, formwork, grouting of pockets and underpinning, (but shall
exclude reinforcement) of mix 1:1.5:3 (1 cement : 1.5 coarse sand : 3 stone aggregate
20 mm nominal size). This shall also include pre-cast RCC work and addition of water
proofing compound wherever required for which no additional payment shall be made.
The quantity shall be measured in cubic meters as per lines and levels indicated in the
drawings. No deduction shall be made for volume occupied by reinforcement / inserts
sleeves and for openings having cross-sectional area up to 0.1 sq.m.
1.2 Roads
The measurement for the concrete roads shall be measured on LOT basis along
with the entire line of the road and shall include all items such as excavation,
compaction, rolling, watering, WBM, Kerb stone, grating, inter locking tiles etc. complete
as per drawing but excluding concrete and reinforcement.
The measurement of bituminous road shall be measured on LOT basis along the
center line of the road and shall include all items such as excavation, compaction,
rolling, watering, sub case course, WBM, Bitumen, pre mix carpet complete as per
drawing.
1.3 Drain
The measurement of drains shall be measured on LOT basis along the center
line of the drain and shall include excavation, compaction, brickwork, plastering, grating,
weep holes etc. complete as per drawing but excluding concrete.
Hume pipe shall be measured diameter-wise and laid as per the drawings and shall be
measured in running metres. The item shall be inclusive of excavation, laying, back
filling, jointing etc. excluding concrete and reinforcement (if any).
(j) Building.
This is a lump sum item for each building. However, the quantity of excavation,
concrete, reinforcement below the plinth level shall be measured as per described
above. Quantity of concrete and reinforcement above the plinth level of the buildings
shall be measured and paid under item mentioned above respectively. External finishing
shall be measured and paid as mentioned in the BPS. The rest of the entire work
required to complete the building in all respect as per the drawings furnished by the
Owner shall be deemed to be included in this lump sum rate.
(h) The material specification, workmanship and acceptance criteria shall be as per
relevant clauses of CPWD specification and approved standard Field Quality Plan,.
Items/components of buildings not explicitly covered in the specification but required for
completion of the project shall be deemed to be included in the scope.
(IV) INTERFACING
The proper coordination & execution of all interfacing civil works activities like
fixing of conduits in roofs/walls/floors, fixing of foundation bolts, fixing of lighting fixtures,
fixing of supports/embedment, provision of cut cuts etc. shall be the sole responsibility of
the Contractor. He shall plan all such activities in advance and execute in such a manner
that interfacing activities do not become bottlenecks and dismantling, breakage etc is
reduced to minimum.
* Contractor shall comply with all the applicable statutory rules pertaining to factories act
(as applicable for the State). Fire safety Rules of Tariff Advisory Committee. Water Act
for pollution control etc.
* Statutory clearance and norms of State Pollution Control Board shall be followed as
per Water Act for effluent quality from plant.
* Requirement of sulphate resistant cement (SRC) for sub structural works shall be
decided in accordance with the Indian Standards based on the findings of the detailed
soil investigation.
* All building/construction materials shall conform to the best quality specified in CPWD
specifications if not otherwise mentioned in this specification.
* All tests as required in the standard field quality plans have to be carried out.
TECHNICAL SPECIFICATION
FOR
SWITCH YARD STRUCTURES
........................................................................................................................... 1
GENERAL ................................................................................................................... 3
0.1 Design of structures .................................................................................................................. 3
0.2 Conductor spacing and clearances ............................................................................................. 3
0.3 Applied loads ............................................................................................................................ 3
0.3.1 Wind loads........................................................................................................................ 3
0.3.2 Vertical loads .................................................................................................................... 3
0.4 Electro mechanical loads .......................................................................................................... 4
0.5 Construction ............................................................................................................................. 4
0.6 Material .................................................................................................................................... 4
3. 0 ERECTION. .......................................................................................................... 9
3.1 Safety precautions. ................................................................................................................ 10
3.2 Fire protection to steelwork. .................................................................................................. 10
GENERAL
1.5 Construction
The structures shall be of an approved design and construction. All stressed members (tension and
compression) of steel structures shall consist of rolled steel sections unless otherwise approved.
The material used for the members shall not be less than 6 mm thick except for unstressed members
where the thickness may be reduced to 4 mm.
No bolt hole shall be more than 1.5 mm larger than the corresponding bolt diameter. As far as possible,
bolt heads, rather than nuts, shall be on the outer or upper faces of structure connections.
1.6 Material
All rolled steel sections, flats, plates and bolt and nut bars used shall consist of steel manufactured by
an approved process and shall be to the requirements of ISO 630 (minimum yield strength 255 N/mm2).
The steel shall be free from blisters, scales, laminations and other defects. Steel sections shall
preferably be British Standard or metric standard sections chosen with a view to avoiding delays in
obtaining material.
All members shall be cut to jig and all holes shall be drilled or punched to jig. All parts shall be
carefully cut and holes accurately located so that when the members are in position the holes will be
truly opposite to each other before being bolted up. Drifting or reaming of holes will not be allowed.
Built members shall, when finished, be true and free from all kinks, twists and open joints, and the
material shall not be defective or strained in any way.
If the structures are fabricated or galvanised by subcontractors, the Contractor shall, if required by the
Engg Incharge (Divisional Engr.), provide a resident inspector at the works of each subcontractor
during the time that the steelwork is being fabricated or galvanised.
All bolts and screwed rods shall be galvanised, including the threaded portions; all nuts shall be
galvanised with the exception of the threads, which shall be oiled.
Except where specified to the contrary, all iron and steel used in the construction of the Contract works
shall be galvanised after all sawing, shearing, drilling, punching, filing, bending and machining are
completed.
Galvanising of all material shall be in accordance with the requirements of this Specification. The
preparation for galvanising and the galvanising itself shall not adversely affect the mechanical
properties of the coated material.
Sheradizing or other similar process shall not be used.
2.1 General
The scope of works covers design, fabrication, proto -assembly, supply and erection of galvanised steel
structure for portals (columns, girders), lightning masts and equipment support structures.
Portals (columns, girders), lightning masts, and equipment support structures shall be lattice type
structures fabricated from structural steel conforming to IS 226/2062. The design of all support
structures for 220kV, 132kV and 33kV equipment. The column and beam and lightning cum lighting
mast of 400 KV side shall be of lattice type. The equipment support structure for 400 KV shall be GI
Tubular pipe of adequate height and strength confirming to the latest IS. All the structural materials are
within the scope of the Contractor. The use of GI pipes conforming to IS 806 to support certain
equipment will also be considered. However approval of the Engg Incharge (Divisional Engr.) should
be obtained for the same before commencement of detailed design.
2.5 Assembly
2.5.1 General
The component parts shall be assembled in such a manner that they are neither twisted nor otherwise
damaged and shall be so prepared that the specified camber, if any, is provided. In order to minimise
distortion in members the component parts shall be positioned by using clamps, clips, dogs, jigs and
other suitable means. Fasteners (bolts and welds) shall be placed in a balanced pattern if the individual
components are to be bolted, paralleled and tapered.
Sample towers, beams and lightning mast shall be trial assembled keeping in view the actual site
conditions, before erection in the fabrication shop and shall be inspected and approved by Engg
Incharge (Divisional Engr.) before mass fabrication. Necessary erection marks shall be made on these
components in the shop before disassembly and despatching.
2.9 Grouting
The method of grouting the column bases shall be subject to approval of Engg Incharge (Divisional
Engr.) and shall be such as to ensure a complete uniformity of contact over the whole area of the steel
base. The Contractor will be fully responsible for the grouting operations. The mix for the grouting
shall contain one part of cement and two parts of coarse sand. Non shrinkage admixtures of approved
quality and of standard make shall also be added in adequate proportion as specified by the
manufacturers of the admixtures.
2.11 Painting
Where members of steel structures are required to be painted it shall meet the requirements as specified
in relevant sections of this Specification.
The preparation, protection and painting systems selected for ferrous surfaces provided inside the
switchyard shall provide a life to first maintenance of 20 years and for doors, windows, louvres etc., it
shall provide life to first maintenance of 10 years. Finish colour will be selected as per relevant
sections of this Specification.
4.0 ERECTION.
The Contractor should arrange his own erection plant and equipment, welding sets, tools and tackles,
scaffolding, trestles equipment etc. and any other accessories and ancillaries required for the work.
VOLTAGE LEVEL BAY EIDTH BOTTOM BUS HEIGHT TOP BUS HEIGHT
132 KV 11MTRS / 8.5 MTRS 13.5 MTRS
13.1 MTRS
Remarks: The structure height shall be maintained as per data provided for getting mnimum
clearance and sectional clearance and as OPTCL standard. Contractors to furnish the drawings
of all the structural items to the owner for according approval.
TECHNICAL SPECIFICATION
FOR
MANUFACTURERS DRAWING, TEST CERTIFICATES
AND
(O &M) MANUALS
2.0 DRAWING
2.1 GENERAL
All drawings to be furnished by the Bidder shall be in standard size of sheets with
maximum size being A0. Drawings shall contain the following particulars in the title
block at lower right hand corner in addition to the Bidder’s name, date, scale, drawing
number title, etc.
a) Client : OPTCL
b) Project Title:- PROJECT for System improvement for (*AS PER PACKAGE
DESCRIPTION)
A blank space of size 100 mm x 100 mm shall preferably be provided for the Employer’s
approval stamp and provision shall also be made by way of a block for details of
revisions to be recorded. The drawing number shall be marked with a subsequent revision
number every time the drawing is revised. The drawing title shall also identify name of
the substation/site.
The equipment/systems which are to be bought our from the sub vendors are also
required to be approved by the Employer prior to placement of order. The relevant
technical literature/drawings pertaining to such equipment/systems shall be submitted for
approval.
Six copies of each of the drawings are to be submitted for approval of Employer. Bidder
shall ensure that the contents of copies of drawings are legible and are complete with all
details. Drawings that are not legible or are incomplete will not be reviewed.
Two copies of approved drawings will be furnished to the Bidder. Drawings returned
“not approved”/ “approved with comments” shall be resubmitted with Revision No. for
approved till the final approval is obtained.
1. 0 DETAILED DRAWINGS
The bidder shall submit to the Employer all working drawings, equipment data and
detailed drawings. These shall include general arrangement, details of equipment,
foundations, cable routing, openings in walls and floors, wiring diagrams, cable
schedules, interconnection diagrams etc. necessary for the erection of plant. These
drawings/data having been corrected or amended as necessary based on the Employer’s
comments shall become the approved drawings/data to be used for manufacture and
erection of plant.
The activities for each of the items shall essentially cover time-table for activities
such as placement of order with sub-vendors, Empowering, submission of drawing,
review and approval by the Employer, manufacture, inspection, delivery, erection and
commissioning. All events shall be represented in a proper in proper sequence of
occurrence with due consideration for inter-dependent activities and all period shall be
counted from the start date.
2. 0 RECORD DRAWING
Within 6 (six) weeks of successful commissioning tests, the Bidder shall furnish the
‘Record’ (As Built) drawings. Submission to and approval by the Employer of the
‘Record’ drawing shall be pre-requisite for the ‘Taking Over Certificate.’ The drawing
shall show the whole sub-station as installed and shall include electrical/mechanical and
civil components with schematic and wiring diagrams for all items of electrical
equipment included in the works. Six sets of recur drawings shall be furnished in neatly
bound volumes. Reduced copies of the relevant drawings shall be included in the
operating and maintenance manual.
3. 0 SPECIFIC REQUIREMENT
a) LIGHTING SYSTEM
Lighting layout drawings for indoor and outdoor areas showing layout of lighting
fixtures, conduit/cables, lighting circuit distribution scheme, complete bill of materials,
locations of control switches, receptacles etc. and mounting details for fixtures, switches
and receptacles as well as manufacturer’s catalogues/literature.
Layout drawings for earthing and lightning protection system showing earthing grid,
locations of earth electrode3s, routes of conductor, interconnections, earth leads to
various equipments, bill of materials, etc.
c) MISCELLANEOUS SYSTEM
Detailed general arrangement, schematic and other drawings, bill of material and
manufacturer’s catalogues/literatures.
4. 0 SUBMISSION OF DRAWING
The list of drawings and the programme shall be submitted within 30 days from the start
date.
Routine test certificates for all the plant items and accessories shall be furnished.
Routine test certificates shall be furnished in addition to test reports which will be
collected at the time of inspection.
Routine test certificates shall be furnished for review by the Employer within seven (7)
days after completion of inspection of relevant item or as instructed by the Employer in
case of items for which witnessing of tests is waived.
Test certificates should be approved by the Employer for obtaining dispatch clearance of
any material.
Six (6) copies of approved test certificates should be submitted for record.
Documents in respect of lighting systems equipment shall include data in respect of each
type of lighting fixture/switch, receptacles/miniature circuit breaker and wires to be used
in circuit wiring. Data on lighting fixtures shall include dimensional drawings, cable
facility, mounting details and weight, light distribution diagrams, light absorption and
utilization factors, lamp data etc.
Bidder shall note that the documents mentioned above shall be made available along with
relevant drawings (listed in Clause 11.4 above items/ accessories components etc. as
supporting documents to facilitate expeditious review of such drawings.
The Contractor shall provide five bound sets of approved manuals written in English
language. All descriptive leaflets, instruction sheets, charts, lists, pamphlets and other
documents that are used in compiling each manual shall be contained in one or more
bundle designed to prevent loss of contents. Each binding shall be titled with a name of
the Employer, the name of the project the Contract Number, the name of the Bidder and
with information to identify the subject matter and shall include a detailed index to all the
literature contained therein.
The manuals shall be initially approved in draft form by the Employer and shall cover all
items of the works. For this purpose, three (3) draft copies shall be submitted to the
Employer. Final submission of manuals shall be done after satisfactory completion of
commissioning tests. A mere collection of manufacturer’s descriptive leaflets, will not be
acceptable in satisfaction of this clause. The manuals shall comprise both operating
instructions and maintenance instructions. The operating manual should also highlight
operation of the Plant in conjunction with the system. Thus, a general tie-up between
system and equipment shall be available in the manuals.
A separate section of a manual shall be devoted to each size and type of equipment. It
shall contain a detailed description of its construction and operation and shall include all
relevant pamphlets and a list of parts with procedure for ordering spares. Operation of
electrical equipment shall be described step by step giving the complete sequence of
operation. The detailed sections of the manual if necessary, shall contain further
maintenance instructions and fault location charts.
The manuals shall be printed on A4 size sheets and shall be bound. Reduced copies of
record drawings shall also be included in the manuals.
Step to step of the plant to work, listing all adjustment necessary for the correct
functioning of the plant alarms giving possible causes for alarm initiation and sequence
of remedial actions to be taken.
Instructions on monitoring of plant performance and sample log sheet for each plant item,
to be filled by operators on a routine basis.
“Do’s and Don’ts” in plant operations. Operations attention shall be drawn to all
operations considered to be dangerous to operators or likely to cause damage to the plant.
Checking, testing and replacement procedures to be carried out on all plant items on a
daily, weekly and monthly basis or at longer intervals to ensure trouble free operation.
Fault locations and remedy charts to facilitate tracing the cause of malfunctions or
breakdown and correcting faults.
A spares schedule which shall consist of a complete list of itemized spares for all plant
items with ordering references and part numbers.
Part list and drawings or exploded diagrams for such items of plant showing
manufacturing tolerances, matching clearances between machined components at the
time of supply, maximum wear and clearances permitted to facilitate replacement.
Complete list of recommended lubricants and lubricating charts insulating oil and
insulation checking/replacement chart.
TECHNICAL SPECIFICATION
FOR
ELECTRICAL EQUIPMENT
INSTALLATION AND
COMMISSIONING
1.1 SCOPE
This chapter describes board guidelines for installations, testing and
commissioning of electrical equipment. The work shall, however, be carried out
strictly as per the instruction of the MANUFACTURER / EMPLPOYER.
The CONTRACTOR shall furnish all tools, welding equipment, rigging materials,
testing equipment, test connections and kits, etc. required for complete installation,
testing and commissioning of the items included in the contract work.
The CONTRACTOR shall have a separate cleaning gang to clean all equipment
during erection and as well as the work area and the project site at regular intervals to the
satisfaction of the EMPLOYER. In case the cleaning is not to the Employer’s
satisfaction, he will have the right to carry out the cleaning operations and any
expenditure incurred by the OWNER in this regard will be the CONTRACTOR’S
account.
All external cabling including end connections and earthling shall also be carried
out.
2.1 POWER AND INSTRUMENT TRANSFORMERS
Physical inspection on receipt, storage, installation, testing and commissioning of
transformers shall be in accordance with the specified code of practice and
Manufacturer’s instructions.
Transformer may be delivered without oil filled with inert gas and without
bushings and external mounted accessories. As applicable, the CONTRACTOR
shall.
a) Assemble the transformers with all fittings such as bushings, cooler banks,
radiator, conservators, valves, piping, cables boxes, marshalling boxes OLTC,
cooling fans/pumps, etc.
b) Arrange for vacuum and oil filtration of the transformers. Oil filtration shall be
done as per the standard practice. Oil tanker in this effect are to be used and
filtration to be done while the oil is inside the tanker. On getting the standard
value of the oils the same shall be pushed into the main tank and other portion of
the transformer. Final filtration to be done after entire oil is filled in the
transformer. Prior to that vacuum treatment of the tank of the transformer with the
windings are to be taken up.
c) Provide wedges/clamps to rigidly station all transformers on rails.
d) Connect up the transformer’s terminals.
e) Lay and terminate cables/ conduits between all the accessories mounted on the
transformer tank/cooler and the transformer-marshalling kiosk and RTCC panels
etc.
f) Pre commissioning checks shall be carried out as per relevant standards and
Employer’s instructions.
The CONTRACTOR shall arrange the oil filtration equipment.
3.0 SWITCHYARD
The CONTRACTOR shall carry out switchyard installation as required as per
approved plan and elevation drawings of switchyard showing bus bar
configurations, sizes, tensions, insulator details, etc. All equipment including
connectors (unless otherwise specified) will be supplied by the VENDOR. The bus
bar arrangement shall be two Bus system, main Bus-1 and main Bus-2 for 220 KV
side and Main bus and transfer bus arrangement for 132 KV side.
The CONTRACTOR shall install complete set of bus bars and all bays’ conductors,
complete with tension with tension suspension insulator strings, bus-post insulators,
equipment connections, bus bar connections to equipment, lightning shield wires
including down comers up to a height of 1000 mm. From ground level where they
shall be connected to the Employer’s test links.
Installation work of breakers and isolators shall include adjustment/ alignments
necessary for proper operation of circuit breakers, isolators and their operating
mechanisms. All insulators and bushings shall be protected against damage during
installation. Insulators and bushings damaged due to negligence or carelessness of
the CONTRACTOR shall not be in any way accepted and shall be replaced by him
at his expense.
ii) Sharp bending, twisting and kinking of cables shall be avoided. The bending radius
for various types of cables shall not be less than those specified by cable
manufacturer.
iii) In each cable run, some extra length shall be kept at a suitable point to enable one
or two straight through joints to be made. Should the cable develop fault at a later
date.
iv) Cable joints in the middle of the run for control cables will not be a accepted.
vi) Metal sheath and Armour of the cable shall be bounded to the earthing system of
the sub-station.
ii) Conduits(thick and flexible PVC) and accessories shall be adequately protected
against mechanical damage as well as corrosion.
ii) The quantities, sizes and material of earthing conductors and electrodes to be
installed and routes of the conductors and location of the electrodes shall be as per
specification mentioned elsewhere and approved drawings for the optimal
capacity of the Sub-station taking the future requirement in to account..
iii) The scope of installation of earth conductors in outdoor areas, buried in ground
shall include excavation in earth at least upto 700 mm. Deep and 450 mm, wide
(unless otherwise stated), brazing/welding as required of main grid conductor
joints as well as risers of 500 mm. Length above ground at required locations and
back filling. Back filling material to be placed over buried conductor shall be free
from stones and other harmful mixtures. Backfill shall be placed in layers of 150
mm, uniformly spread along the ditch and tempered utilizing pneumatic tempers
or other approved means.
vii) The scope of installation of earth connection leads to equipment and risers on steel
structures/walls shall include laying the conductors, welding/ cleating, at specified
intervals, welding/brazing to the main earth grids risers, bolting at equipment
terminals and coating welded/brazed joints by bituminous paint. Galvanized
conductors shall be touched up with zinc rich paint, where holes are drilled at site
for holding to equipment/ structure.
viii) The electrodes shall be installed either directly in earth or in constructed earth pits
as shown in approved drawings.
ix) The scope of installation of lightning conductors on the roof of buildings shall
include laying, anchoring, fastening and cleating of horizontal conductors, grouting
of vertical rods where necessary, laying, fastening/cleating/welding of the down
comers on the walls/columns of the building and connection to the test links above
the ground level.
x) The scope of installation of the test links shall include mounting of the same at
specified height on wall/column by suitable brackets and connections of the test
link to the earth electrodes.
4.1 Earthing connections:
i) All connections in the main earth conductors buried in earth/concrete shall be
welded/brazed type,. Connection between main earthing conductor and earth leads
shall also be of welded/brazed type.
ii) Welding and brazing operations and fluzes/alloys shall be of approved standards.
iii) All connections shall be of low resistance. Contact resistances shall also be
minimum.
iv) All bi-metallic connections shall be treated with suitable compound to prevent
moisture ingress.
iv) Soil, salt and charcoal placed around the electrode shall be finely graded free from
stones and other harmful mixtures. Backfill shall be placed in the layers of 250 mm.
Thick uniformly spread and compacted. If excavated soils are found unsuitable for
backfilling, the contractor shall arrange for a suitable soil from outside.
i) The supplier shall supply, install, test and commission complete lighting system
and power receptacles in accordance with relevant Standards. Concealed conduit
wiring (thick flexible PVC pipes suitable for taking inside the roof and walls) shall
be adopted for the control building.
ii) Wiring shall be colour-coded so as to enable easy identification of phase and
neutral conductors, and DC wire (colour-coded as follows – white – phase wire,
black – neutral wire, grey / DC wires.)
iii) There shall be switch on each live conductor of supply mains at the point of entry.
The wiring throughout the installation shall be such that there is no break in neutral
wire in the form of switch or fuse unit.
iv) Fixtures shall be ground by 1.5sq mm .flexible PVC copper wires(green colour)
and taken to earth strips.
v) All fixtures, associated accessories, conduits, wires, junction boxes, cables,
switches, switch boxes, etc. required for complete wiring of the lighting system as
per approved drawings shall be supplied.