Coastal Planning Management-Lesson4-Hydraulic Study
Coastal Planning Management-Lesson4-Hydraulic Study
Coastal Planning Management-Lesson4-Hydraulic Study
VDB 4233
Lesson – 4
Re-cap from previous session
2.0
1.5
1.0
0.5
0.0
-0.5
-1.0
-1.5
-2.0
12:00 12:00 12:00 12:00 12:00 12:00 12:00 12:00 12:00 12:00 12:00
2002-03-26 03-28 03-30 04-01 04-03 04-05 04-07 04-09 04-11 04-13 04-15
Overall Learning Outcomes
CLO1 Assess the influencing environmental factors and
related coastal processes, and analyze causes of
coastal erosion/sedimentation
• Understanding hydraulic
phenomena/problems
• Planning/design of
mitigation/improvement
works (design parameters)
• Impact assessment of
coastal development
• Monitoring feedback
Scientific Requirement vs
Engineering Application
• Knowledge is progressively
developing especially in fine
sediment dynamics.
Why Modelling?
Knowledge deficiency/gap
(regression using field data;
analytical solutions)
Guidelines on Erosion
Control For Development
Projects In The Coastal Zone
(Garispanduan JPS 1/97),
aims at ensuring proper
planning & implementation of
coastal development projects.
Guidelines
LITPACK
MIKE21
Model Setting-up
Data Collection & Simulation
&
Field Work Calibration & Verification
Production Run
Interpretation of Results
Modelling Technology
▪ Which model?
Coastal
Coastal
Hydrodynamics River
Morphology
Flow Regime Hydraulics
Sediment transport
Wave tranformation Back-water flooding
Coastline Changes
Advection/Diffusion
Coastal
Hydraulic Study Stage 3:
Work Flow Interfacing with Sub-Components
Typical Coastal / Marine Study
& Example Applications
Coastal Erosion Studies
Scope of work:
- primary & secondary data collection
- comprehensive hydraulic study of the coastal
area using numerical models
- propose feasible defence options & carry out
technical and financial evaluation of the
proposed alternatives
- detailed design of the selected option
2D Sediment Transport
- Existing Condition
- Most of the transport
bypassing Pengkalan Datu
breakwater travels on a bar
parallel to the coast prior to re-
attaching to the surf zone 1.5
to 2 km further along the coast
The Proposed Beach Protection Scheme
Erosion
Scope of work:
- collect, collate and calibrate data for hydraulic study;
- hydraulic modelling for analysis of currents, waves &
sediment transport
- identify sources of siltation material, predict volume
& rate of siltation within,around the channel due to
deepening
- analyse, propose requirements for
capital & maintenance dredging
and devise optimum dredging
strategy for the future 55
\\SHARIDZ\LPK\5122lpk(temp)\hkj_06Sep02\Mike21\Data\MedGrid\mtlm22.dfs2
N
-20
-5
5
-5 5
(kilometer)
40 50
20
50
5
plans 50 5
5
5
-5
-20
-5
5 5 20
35
5
- financial analysis
5 Net Sedimentation (mm)
5
-20
Above 100
20
5 50 - 100
5
30 5 20 - 50
5 5 - 20
-20 -5 - 5
-5
-20
-20
5
-20 - -5
-50 - -20
25 -5 -100 - -50
5
5
20 -20 -150 - -100
5
5
5
Below -150
10 15 20 25 30 35 40
(kilometer)
04/03/02 12:00:00
River Mouth Siltation Studies
Studies include:
• collect, collate and review relevant data necessary for the design and
modelling works;
• identify various river mouth improvement alternatives;
• conduct a hydraulic study using numerical models to assess
effectiveness and impacts of the improvement works on the hydraulic
regime and select the most suitable option;
• determine environmental parameters for the detailed design;
• perform detailed design for the river mouth improvement works.
Sediment Dispersion Studies
Powertek Berhad intended to convert the existing open cycle plant into a
combined cycle mode at its existing power plant at Teluk Gong, Melaka
Scope of work:
- numerical modelling to assess the
recirculation of cooling water
- investigate various options &
recommend the possible optimum
layout and lengths for the CW pipelines taking
into account the influence of proposed two land reclamation projects to
be constructed adjacent to the power plant
Typical Studies in a Project
Tasks:
- overall project planning
- total project management in producing masterplan
& justifying the project based on economic analysis and
other technical studies
- design, port layout, breakwater & wharf construction,
hydraulic aspects, environmental impacts, geotechnical
assessment, ship maneuvering, port management organization and core
activities
- evaluate options to privatise the port construction and management
- advise the client on overall project implementation at macro & micro levels
inclusive of cashflow and financial analysis
Hotel JAL Fujairah Resort & Spa, UAE
The Hotel JAL Fujairah Resort & Spa is built on a 540 m private beach and
is currently under construction. All of its nine buildings will be lined up facing
the beach. As such, the beach is a primary feature and attraction for the
hotel.
Scope of work:
- hydraulic model study to derive the main design parameters.
- detailed design of sill structure, groynes & beach nourishment
Project Area
Integrated Approach
Negeri Sembilan
Monitoring