Section D
Section D
1.0 General
This section shall apply to the construction of all structures or parts of structures to
be composed of concrete with or without steel reinforcement. The Work shall be
carried out all in accordance with this specification and the lines, levels, grades,
dimensions and cross-sections shown in the drawings and as required by the S.O.
2.0 Material
2.1 Cement
The S.O. may, without tests being made, order that any bag of
cement, a portion of the contents of which has hardened, or which
appears to be defective in any other way, be removed from the Site.
2.2 Aggregates
D/1
CONCRETE WORKS
Coarse aggregates shall comply with MS 29. For work below ground
level, only crushed granite shall be used. Unless otherwise specified
in the Drawings, tests shall be carried out according to MS 30. The
property limits shall be as specified in Table 1. The maximum
nominal size of aggregate shall be as specified in the Drawings.
2.2.3 Grading
D/2
CONCRETE WORKS
2.3 Water
Water shall comply with the requirements of MS 28. It shall be clean and free
from materials deleterious to concrete in the plastic and hardened state and
shall be from a source approved by the S.O. The S.O. may instruct the
Contractor to carry out chemical tests at any approved laboratory at the
expense of the Contractor. The Contractor shall make adequate
arrangement to supply and store sufficient water at the Site for use in mixing
and curing of concrete.
2.4 Admixtures
Suitable admixtures may be used in concrete mixes with the prior approval of
or as directed by the S.O.
The admixtures, the sampling and testing of the admixtures and the
information to be provided with the admixture supplied shall comply with MS
922.
Before allowing the admixture to be used in the Work, relevant tests based
on trial mixes shall be carried out. A control mix shall be made using a
conventional trial mix that is without using the admixture, to determine the
free water:cement ratio and mix proportion required to give the specified
strength with the required slump. Using the same mix proportion as in the
control mix but with a modified water:cement ratio whenever necessary, a
test shall be carried out using the recommended dosage of the admixture.
The results of the relevant test obtained from the control mix and test mix
shall be compared. The S.O. may allow the use of the admixture only when
the results are found to be satisfactory and comparable to the effects as
claimed by the manufacturer. The admixture acceptance test shall comply
with the requirements specified in Table 4
D/3
CONCRETE WORKS
The uses of admixtures that are chloride based are not permitted to be used
for structural concrete containing reinforcement, prestressing tendons or
other embedded metal. The Contractor shall submit documentary evidence
on the contents of the admixture to be used.
Condensed silica fumes (CSF) complying with ASTM C1240 – 93 or any other
equivalent standards may be used provided that the concrete complies with the
same grade as would be achieved by the Portland cement concrete complying
with MS 522 and prior approval of the S.O is obtained
Unless otherwise stated in the Drawings, the concrete mix shall be designed mix.
However, prescribed mix may be used provided: -
a) Notify the S.O. whether the designed mix is to be produced as site mix or ready
D/4
CONCRETE WORKS
mix.
b) If the Contractor chooses to use ready mix concrete, he shall notify the S.O. the
name of the supplier, location of the ready mix plant, journey time taken
to transport the concrete to the Site and production capacity of the plant.
c) Submit a mix design report covering all concrete mixes to the S.O. for
approval. The designed mix shall comply with the requirements specified
in Table 6.
d) The Contractor shall ensure that the S.O. be permitted to visit or station
his representative at the plant at any stage of the concrete production.
e) The sampling, making, curing and testing of the cubes shall be carried
out by the Contractor in accordance with MS 30 or as directed by and in
the presence of the S.O. or his representative. Test cubes shall be stored
by the S.O. at a secured place. The Contractor shall provide all facilities in
connection therewith.
D/5
CONCRETE WORKS
Where there are insufficient data to satisfy (i) and (ii) above, the
margin for the initial mix design shall be taken as 7.5 N/mm 2 for
concrete of grade 15 and 12 N/mm 2 for concrete of grade 20
or above. This margin shall be used as the current margin
only until sufficient data are available to satisfy (i) or (ii)
above. However, subjected to the approval of the S.O., when
the specified characteristic strength approaches the designed
target mean strength of concrete made with a particular
aggregate, a smaller margin not less than 5 N/mm2 for
concrete of grade 15 or 7.5 N/mm2 for concrete of grade 20
or above may be used for the initial mix design.
The Contractor shall submit for the approval of the S.O., prior to the
supply of any designed mix, the following information:
Unless otherwise stated and approved by the S.O in writing that the
Contractor has complied with the submission specified in 3.2.2, trial
mix shall be carried out.
The Contractor shall give early notice, to enable the S.O. to be present
at the making of trial mixes and preliminary testing of the cubes. The
D/6
CONCRETE WORKS
During production, the S.O. may require additional trial mixes to be made
before a substantial change is made in the materials or in the proportion
of the material to be used. Trial mixes need not be carried out when
adjustments are made to the mix proportions in accordance with 3.2.4.
D/7
CONCRETE WORKS
3.3.1 Workability
i) Slump
± 25mm or ± one third of the `designed workability’, whichever
is greater.
iii) Vebe
± 3 seconds or ± one fifth of the `designed workability’
whichever is lesser.
D/8
CONCRETE WORKS
The total chloride content of the concrete mix arising from the
aggregate or any other source shall not in any circumstances exceed
the limits in Table 7 expressed as a percentage relationship between
chloride ions and weight of cement in the mix.
4.1 General
D/9
CONCRETE WORKS
Notwithstanding this, compressive strength tests shall be carried out during the
progress of Work. The rate of sampling shall be as specified in 4.3. For each
sampling, three cubes shall be made from a single sample taken from a
randomly selected batch of concrete. The sample shall be taken at the point of
discharge from the mixer or, in the case of ready mixed concrete, at the point
of discharge from the delivery vehicle. All cubes shall be clearly marked with
undeletable paint with the date of casting and serial number. A record
shall be kept to identify each cube by date and by serial number relating to the
part of the work from which they are taken.
One cube from each sample batch shall be tested for the 7-day compressive
strength. The remaining two cubes from the sample batch shall be tested for
the 28-day compressive strength.
However, for designed mix, at least four samples (12 cubes) shall be taken
of concrete on the first day of concreting for each grade of concrete to be used in
the Work, irrespective of the volume of concrete produced or the sampling rate.
Subsequent rate of sampling shall be at least one sample from each source
of production on each day that concrete of any particular grade is used.
One cube from each sample batch shall be tested for the 7-day
D / 10
CONCRETE WORKS
compressive strength. The cube compressive strength shall not fall below the
corresponding values given in Table 8 for prescribed mix, and two-third of the
28-day compressive strength for designed mix.
The remaining two cubes from the sample batch shall be tested for the 28-
day compressive strength.
The average strength of the two cubes shall constitute the 28-day
compressive strength of the sample. When the difference between the
two results divided by their mean exceeds 15%, the test results shall be
deemed invalid.
a) The mean strength determined from the first two, three or four
consecutive test results, or from any group of four consecutive
test results complies with the appropriate limits in column A
of Table 8A. In this respect, consecutive samples are samples
taken at intervals for the day of concreting or one complete
continuous process of concreting
b) Any individual test result complies with the appropriate limits in
column B of Table 8A.
D / 11
CONCRETE WORKS
In the event that the compressive strength results of the test do not meet the
specified requirements mentioned in 4.4 and 4.5, or otherwise arising from the
result of the statistical analysis carried out in 4.11, the S.O. shall determine the
action to be taken.
If the 7-day strength is less than the specified strength requirements, no more
concrete shall be placed on the suspect concrete and no removal of propping
on the affected area shall be allowed until the 28-day strength result
compliance is available, or unless otherwise approved by the S.O in writing.
Alternatively, the S.O may direct other measures to be taken to make the works
secure. The S.O may instruct that additional tests be carried out on the hardened
concrete to determine the quality of the suspected concrete. The test may
include non-destructive methods (MS 26), taking cored samples (MS 26), load
test or combination of several methods. The results shall be assessed in
accordance with BS 6089. The results of any such tests shall not nullify the
establishment of non-compliance with 4.5.
All works instructed under this clause shall be at the Contractor’s expense and
no extension of time shall be granted for such works.
The extra cubes shall be identified at the time of marking and shall not be
used for normal quality control or compliance procedures.
D / 12
CONCRETE WORKS
All concrete cube test results and summary shall be recorded using
appropriate forms in a manner and format approved by the S.O. The 7-day
and 28-day strength results shall be recorded separately with its
corresponding cement content obtained from the batching record submitted
during delivery (if ready mix concrete is used) of fresh concrete. The
corresponding workability shall also be recorded.
a. The individual test result and the average values obtained from the
samples noting the validity values and to comply with column A of
Table 8A.
b. The group test results and analyse the mean values to comply with
column B of Table 8A.
Statistical analysis shall be carried out based on the test results recorded in
4.10. The Contractor shall submit to the S.O, the following analysis:
a) Running analysis of group test results and the mean values plotted
for normal distribution graph. Standard deviation (S.D) is then
calculated. The value of S.D obtained, when multiplying with 1.64
(statistical constant complying with MS 1195) will give the value of the
current margin.
b) The current margin value should not fall below the designed current
margin specified when performing the earlier trial mix. If the current
margin falls below the designed value, the S.O may inspect the plant
supplying the concrete, instruct the Contractor to redesign his mix
and to take appropriate action as per 4.7
5.1 Supervision
The Contractor shall ensure the required standard of control over materials
and workmanship. The S.O. shall be afforded all reasonable opportunities
and facilities to inspect the constituent materials and the production of
D / 13
CONCRETE WORKS
The batch weight of aggregate shall be adjusted to allow for the moisture
content of the aggregate being used. All measuring equipment shall be
calibrated on site or their calibration status established by certificates from
accredited laboratories.
The mixer shall comply with the requirements of BS 1305 where applicable.
The mixing time shall be not less than two minutes and not more than five
minutes or any other time recommended by the mixer manufacturer after all
the ingredients have been placed in the mixer.
Mixers that have been out of use for more than 30 minutes shall be
thoroughly cleaned before any fresh concrete is mixed. Unless otherwise
agreed by the S.O., the first batch of concrete through the mixer shall
contain only two thirds of the normal quantity of coarse aggregate. The mixer
shall be thoroughly cleaned before changing from one type of cement to
another.
Ready mixed concrete shall comply with the requirements of designed mix
as in clause 3.2 and MS 523. All concrete materials, including water and
admixtures shall be mixed in the plant and delivered to Site in purpose made truck
mixers. No extra water or admixtures are allowed to be added after the concrete
has left the plant.
D / 14
CONCRETE WORKS
ticket and manufacturer's batching record stating the details of mix proportions
by weight, the grade of concrete, type and size of aggregate, date and time
of loading at plant, type and dosage of chemical admixtures and other
relevant production details in suitable format, failing which the S.O, or his
representative, shall immediately reject the total load of the concrete. The S.O,
or his representative, and the contractor shall ensure the information provided
in the delivery tickets and the manufacturer’s batching record complies with the
details of the approved ‘designed mix’ and its corresponding ‘designed
workability’ as in 3.2.3 before discharging the concrete.
Rejected concrete shall be removed from the Site. The delivery ticket shall
be marked `REJECTED’.
5.4 Transporting
5.5 Placing
For all concrete whether mixed on or off the site of the Work, each
batch shall be placed and compacted within two (2) hours of adding
the cement to the dry aggregates and within 45 minutes (or any other
period of time based on the trial mix as per 2.4, 3.2.3 and approved by
the S.O. if an admixture is used) of adding water to the cement and
aggregate. Concrete shall not be placed in any part of the structure
until the approval of the S.O. has been obtained. If concreting is not
started within 24 hours of approval given, approval shall again be
obtained from the S.O.
Fresh concrete shall not be placed against in-situ concrete which has
been in position for more than 45 minutes (or any other period of time
D / 15
CONCRETE WORKS
based on the trial mix as per 2.4, 3.2.3 and approved by the S.O. if an
admixture is used) unless a construction joint is formed in accordance
with sub-section 6.1. When in-situ concrete has been in place for four
hours, no further concrete shall be placed against it for a further 20
hours. Where retarding admixture has been used, the S.O. may
approve variation to this limit.
Concrete shall not be dropped into place from a height exceeding 1.5
meters. However, higher drops may be allowed provided the mix has
been well designed and proportioned. When trunking or chutes are
used, they shall be kept clean and used in such a manner as to avoid
segregation.
c) Freshly placed concrete shall be protected from direct sunlight and from loss of
moisture by covering, shading or other means.
5.7 Compaction
D / 16
CONCRETE WORKS
have the required surface finish when the formwork is removed. Vibration
shall be applied continuously during the placing of each batch of concrete
until the expulsion of air has practically ceased and in a manner which does
not promote segregation of the ingredients.
The pan vibrator shall be placed on the surface of the concrete, which shall
have previously been tamped and leveled leaving an allowance in height for
compaction until the cement mortar appears under the pan. The vibrator
shall then be lifted and placed on the adjoining surface and this operation
shall be repeated until the whole surface has been compacted. Alternatively,
a vibrating screen spanning the full width of the surface may also be used.
Internal vibrators shall be capable of operating at not less than 10,000 cycles
per minute and external vibrators at not less than 3,000 cycles per minute.
Sufficient vibrators in serviceable condition shall be on Site so that spare
equipment is always available in the event of breakdowns. Vibrators shall be
operated by workmen skilled in their use.
D / 17
CONCRETE WORKS
All concrete work shall be cured for the full period of curing which shall not be
less than five (5) days for F1, F2, F3 and F4 surfaces, but not less than
three (3) days for F11, F12, F13, F14 and F15 surfaces.
Concrete, after it is placed and until the expiration of the curing duration,
shall not be allowed to dry out. Provision shall be made for adequate
protection against direct sunlight and wind to allow the process of curing to
complete within the specified period.
When the concrete has attained its final set, one of the following curing
methods shall be adopted:
The use of other methods of curing may be deemed necessary when the
concrete is subjected to high internal thermal gradient, or with large
exposed surface area. The Contractor shall submit a method statement to
the approval of the S.O.
D / 18
CONCRETE WORKS
In the event where the Contractor does not do proper curing, the S.O.
has the right to inspect and to carry out further tests which may
include destructive methods. All expenses incurred in carrying out
such sampling, testing and remedial works shall be borne by the
Contractor irrespective of whether the tests proved the structure to be
sound or otherwise.
The position and detail of any construction joints not described in the
drawings shall be to the approval of the S.O. and shall be so arranged as to
minimise the possibility of the occurrence of shrinkage cracks.
If for any reason the Contractor has to interrupt a planned pour for more than
45 minutes (or any other period of time based on the trial mix as per 2.4, 3.2.3
and approved by the S.O. if an admixture is used), additional construction
joints shall be positioned and constructed as directed by the S.O.
Concrete shall not be allowed to run to a feather edge and vertical joints
shall be formed against a stop board. The top surface of a layer of concrete
shall be level and flat unless design considerations make this undesirable.
Joint lines shall be so arranged that they coincide with features of the
finished work, wherever possible.
D / 19
CONCRETE WORKS
Where a kicker (i.e., a starter stub) is used for the construction of walls and
columns, it shall be at least 50 mm high, to be constructed monolithically with
the base concrete.
Where the S.O. considers that special preparation is necessary, e.g. for an
in-situ structural connection, preparation shall be carried out, preferable
when the concrete has set but not hardened, by spraying with a fine spray of
air and water or brushing with a stiff brush sufficiently to remove the outer
mortar skin and expose the larger aggregates without disturbing them.
Where this treatment is impracticable, sand blasting or a needle gun shall be
used to remove the surface skin and laitance. Hardened surfaces shall be
chipped manually or mechanically to be free from laitance and properly
roughened to the extent that the coarse aggregates are being exposed.
All fixing blocks, brackets, built in bolts, holes, chases, etc. shall be
accurately set out and formed and carefully sealed prior to the concrete
being placed. It is the responsibility of the Contractor to obtain all such
information for these items of work and obtain the permission of the S.O.
before incorporating such work prior to the concrete being placed.
Bolts and other inserts to be cast into the concrete shall be securely fixed to
the formwork in such a way that they are not displaced during the concreting
operations and that there is no loss of materials from the wet concrete
through holes in the formwork.
Temporary plugs shall be removed and the threads of built in bolts shall be
D / 20
CONCRETE WORKS
cleaned and greased before handing over any part of the Work.
6.4.1 General
6.4.3 Waterstops
7.1 General
7.2 Materials
Hot rolled mild steel and high yield bars shall comply with the requirements
of MS 146. Cold worked steel bars shall comply with the requirements of BS
4461. Hard drawn mild steel wire shall comply with the requirements of MS
144.
Steel fabric reinforcement shall comply with the requirements of MS 145 and
shall be delivered to the Site in flat sheets, unless otherwise specified.
D / 21
CONCRETE WORKS
Before any reinforcement steel is brought to Site, the Contractor shall furnish
the mill certificates of tests and these shall be submitted for acceptance by the
S.O. In addition the Contractor shall on request, furnish the S.O. with a test
sheet from approved laboratories for any batch of bars, giving the results of
each of the mechanical tests and/or chemical composition analysis required
under the Malaysian Standards or any equivalent international standards
approved by the S.O. The specified characteristic strength of steel
reinforcement shall be as given in Table 9.
During the course of the work, any reinforcement being found to be not in
accordance with the Malaysian Standards or British Standards, may be
rejected by the S.O. notwithstanding any previous acceptance on the
strength of the test certificates. The S.O. may call for additional tests to be
made at the Contractor=s expense on samples taken from the batch of the
defective reinforcement. If the samples do not comply with the Malaysian
Standards or British Standards, then the S.O. may reject the whole batch
and instruct its removal from the Site.
Steel reinforcement shall be stored in clean and dry conditions. When placed
in the work it shall be clean and free from loose rust, mill scale, oil, grease,
paint, dirt or anything which may reduce its bond with concrete. If directed by
the S.O., the steel bars shall be brushed or otherwise cleaned before use, at
the Contractor’s expense.
Binding wire shall be 1.6 mm diameter soft annealed steel wire complying
with the requirements of BS 1052.
Bars shall be of their correct lengths and bent to the exact shapes
required before being fixed in the work.
Bars shall be cut and bent cold by the application of slow, steady
pressure or in an approved bar-bending machine. Bending at
temperatures in excess of 100 0C may only be carried out with the
S.O.’s approval and under his supervision. Except where otherwise
indicated in the drawings, bars shall be bent and measured in
accordance with BS 4449.
D / 22
CONCRETE WORKS
Cold worked and hot rolled bars shall not be straightened or bent
again once having been bent. Where it is necessary to bend the free
end of mild steel reinforcement already cast in the concrete, the
internal radius of the bend shall not be less than twice the diameter of
the bar.
Special care shall be taken that the overall length of bars with
multiple bends is accurate and that after bending and fixing in
position the bars remain in place without wrap or twist.
The number, size, length, shape, type and position of all reinforcing
bars, links, spacer bars and other parts of the steel reinforcement,
shall be in accordance with the drawings.
The Contractor shall take particular care that the reinforcement is laid
out correctly in every aspect and temporarily suspended by annealed
wire or supported on concrete blocks or other approved spacers in
the forms to prevent displacement during the placing and compacting
of concrete. Links shall tightly embrace the longitudinal reinforcement
to which they shall be securely wired or spot welded. The top
reinforcement in slabs shall be rigidly supported on mild steel Achairs@
or equivalent spaced in each direction to prevent sagging during
concreting.
7.3.3 Splicing
D / 23
CONCRETE WORKS
8.1.1 Description
D / 24
CONCRETE WORKS
Metal ties may only be used with the prior approval of the S.O. Where
metal ties are permitted, the use of storey height steel soldiers shall
be used to reduce the number of tie bolts required. Tie bolts with
rubber or plastic cone against the form face are to be used to prevent
unsightly grout loss. No metal part of any device for maintaining
formwork in the correct location shall remain permanently within the
specified concrete cover to the reinforcement. Except for ties used for
anchoring void formers, all ties shall be at least 1.2 meters apart and
through bolts will not be permitted on exposed form finished faces. All
holes left by ties shall be made good within one day of the removal of
the formwork using a mortar of the same strength as the cast
concrete. Metal ties which allow for holes through the concrete being
cast shall not be permitted to be used in concrete for water-retaining
structure and walls.
D / 25
CONCRETE WORKS
(a) Class F1
(b) Class F2
(c) Class F3
D / 26
CONCRETE WORKS
After the concrete has been properly cured, the surface shall
be rubbed down where necessary, to produce a smooth and
even surface.
(a) Class U1
(b) Class U2
(c) Class U3
When the moisture film has disappeared and the concrete has
hardened sufficiently to prevent laitance from being worked to
the surface, a Class U1 surface shall be steel-trowelled under
firm pressure to produce a dense, smooth uniform surface
free from trowel marks.
(d) Class U4
The finished surface shall not deviate from the required profile
by more than 5mm over a 3m gauge length or have any
abrupt irregularities of more than 3mm.
The trial panels shall employ the materials, plant and concrete mix
D / 27
CONCRETE WORKS
proposed for the Works. They shall be at least a storey height and
1m wide. They shall be of similar thickness and similarly reinforced as
the elements they represent and shall incorporate all features which
contribute to the final appearance of the Works.
Before concreting, all forms shall be thoroughly cleaned out, free from
sawdust shavings, dust, mud or other debris.
The inside surfaces of forms shall, unless otherwise approved by the S.O.,
be coated with an approved non-staining form oil or other approved material
to prevent adhesion of the concrete. Such release agents shall be applied
strictly in accordance with the manufacturer’s instructions and shall not come
into contact with the reinforcement or prestressing tendons and anchorages.
For any exposed surface only one release agent shall be used throughout
the entire area.
The Contractor shall inform the S.O. and obtain his approval before striking
any formwork, but such approval shall not relieve the Contractor of his
responsibilities for the safety of the work.
The minimum periods between concreting and the removal of forms are
given in Table 10. The periods stated in this table are based on the use of
Ordinary Portland Cement. They may be changed with the approval of the
S.O., if other types of cement as described in 2.1, admixtures or additional
material as described in 2.4 and 2.5 are used. The result of the compressive
strength obtained from the additional cubes taken as described in 4.9 may
also be used for early removal of forms provided always the Contractor
provide proof of calculation to the S.O for approval.
Where it is intended that forms are to be reused, they shall be cleaned and
made good to the approval of the S.O.
Following the removal of forms, no further loads shall be imposed upon the
concrete until at least after the completion of the curing period or until such
later time as in the opinion of the S.O. the concrete shall have attained
sufficient strength to safely withstand such loads. Full design loads shall not
D / 28
CONCRETE WORKS
be applied to any structure until all loads bearing concrete is at least 28 days
old.
The surface of the concrete shall be inspected for defects and for conformity
to the surface finish specified and where appropriate, with approved sample
finishes.
Subject to the strength and durability of the concrete being unimpaired, the
making good of surface defects may be permitted but the level of
acceptance shall be appropriate to the type and quality of the finish specified
and ensures satisfactory permanence and durability.
Mass and lean concrete shall consist of cement, fine aggregate and coarse
aggregate in the nominal ratio by volume of 1:3:6 and 1:4:8 respectively. However
where a denser and more workable concrete can be produced by a variation in the
ratio of the fine aggregate to that of coarse aggregate, this ratio may be varied
within the limits (1:1½) and (1:3), provided that the volumes of fine and coarse
aggregate, each measured separately, shall nevertheless equal the sum of the
volumes of fine and coarse aggregate appropriate to the nominal mix. The concrete
shall be mixed as described for reinforced concrete.
11.0 Apparatus
The Contractor shall provide the following apparatus for use on the Site at all times:
-
(a) Concrete slump test apparatus or flow test apparatus complying with MS 26.
One set of the apparatus shall be provided for each concreting location.
(b) At least twelve (12) numbers of steel or cast iron moulds for casting 150mm
concrete test cubes and six (6) numbers of 100mm mortar or grout test cube
moulds complete with tamping bars and base plates in accordance with MS
26. A minimum number shall be provided such that no stripping of cubes is
required prior to 24 hours setting and hardening period.
D / 29
CONCRETE WORKS
the nearest 2.0 ml., for determination of silt content (field setting method).
D / 30
CONCRETE WORKS
D / 31
CONCRETE WORKS
10.0 mm 10 to 40 30 to 60 50 to 85 0 to 5 0 to 25 85 to 100
5.0 mm 0 to 5 0 to 10 0 to 10 - 0 to 5 0 to 25
2.36 mm - - - - - 0 to 5
D / 32
CONCRETE WORKS
10.0 mm 100 - - -
5.0 mm 80 to 100 - - -
300 µm 5 to 70 5 to 40 5 to 48 5 to 70
150 µm 0 to 15# - - -
# Increase to 20% for crushed rock fines, except when they are used for heavy-
duty floors.
* For prescribed mix only Grading Limit M is applicable. See also clause 2.2.3(b).
NOTE: Individual sands may comply with the requirements of more than one grading.
Alternatively some sands which satisfy the overall limits but may not fall within
any one of the additional limit C, M or F may also be used provided that the
supplier can satisfy the S.O that such materials can produce concrete of the
required quality.
D / 33
CONCRETE WORKS
Type 5: At least 1hr. Within 1hr. and Not more than 110 3 days
Retarding At least later than 3hrs. earlier 3hrs.later than 110 7 days 135 0.010
water- 5% control mix than control mix control mix 110 28 days
D / 34
CONCRETE WORKS
reducing
D / 35
CONCRETE WORKS
D / 36
CONCRETE WORKS
# or as approved by S.O.
D / 37
CONCRETE WORKS
b) soffits;
c) surfaces
exposed to
330 350 330 350 390 270 300 0.50
driving rain,
390
alternate
wetting and
drying, e.g, in
contact with
backfill.
d) surfaces
exposed to
360 380 360 380 420 320 350 0.45
the action of
D / 38
CONCRETE WORKS
D / 39
CONCRETE WORKS
D / 40
CONCRETE WORKS
N/mm2 N/mm2
20 and above First 2 1 3
First 3 2 3
Any consecutive 4 3 3
N/mm2 N/mm2
Below 20 First 2 0 2
First 3 1 2
Any consecutive 4 2 2
D / 41
CONCRETE WORKS
Note: This table is applicable only for Ordinary Portland Cement. Where other types of
cement, admixtures or additional material are to be used, the minimum periods between
concreting and removal of forms shall be as approved by the S.O.
D / 42
CONCRETE WORKS
APPENDIX C/1
1.0 Foundation
All reinforced concrete footings shall be constructed according to the drawings and to the
exact depths required. The Contractor shall supply, maintain and remove any necessary
planking and strutting, sheet piling and coffer dams, and shall by pumping or other
approved means keep the excavation free from water.
The bottom of excavation shall be cleaned or if in loose or disturbed ground shall be well
rammed, and the whole shall be approved before it is covered with a blinding layer of lean
concrete not less than 50 mm thick. The required cover of concrete under the
reinforcement shall be entirely above the blinding layer.
2.0 Floors
After initial set, the upper surface of cast-in-situ reinforced concrete floors shall be trowelled
smooth with a steel float to true level and even surface. No screeding of any kind shall be
applied to the floor slabs except where specified. Care shall be taken to ensure that the
steel reinforcement is not displaced or lowered during trowelling.
For areas, which are to receive rendering or other finishes, the fresh concrete shall be
trowelled to true level or as required using a long timber trowel. Before it hardens it shall be
brushed with a stiff broom in one direction to give a rough and tidy surface.
The reinforced concrete ground floor slab shall not be laid directly onto earth surfaces. A
blinding layer of 50mm minimum thick of lean concrete as specified in clause 9.0 shall be
laid on well prepared firm ground. Plastic sheeting or other suitable material with sufficient
overlaps at joints, shall be laid on the blinding layer before any reinforcement is placed in
position.
The Contractor shall ensure that all suspended floor for toilet areas are constructed to be
watertight and leakproof. All construction method or alternative details proposed by the
Contractor must be based on his acceptance of and compliance with the requirements for
watertightness. The Contractor shall ensure that holes and fixings are properly constructed.
The floor must be concreted in one sequence of operation. No construction joints for toilet
floor are to be allowed. All pipes and fittings encased in the concrete floor shall be provided
with sleeves to the approval of the S.O and shall be build in situ. No holes shall be left for
later incorporation of fittings and no subsequent hacking of floor shall be made. Not
withstanding whatever shown in the drawings, all toilet floor slabs shall have a minimum
thickness of 150mm.
D / 43
CONCRETE WORKS
The toilet floor areas should be ponded with water continuously over a period of 7
days. During this period the exposed soffit shall show no signs of leakage and
remain dry. If any area is found not to be watertight, the Contractor must repair at
his own expense.
D / 44