Factors Affecting Productivity: 1. Overtime
Factors Affecting Productivity: 1. Overtime
1. Overtime
Scheduling of extended work days or weeks exceeding a standard eight-hour
work day or 40- hour work week lowers work output and efficiency through
physical fatigue and poor mental attitude.
2. Morale and Attitude
Spirit of workers based on willingness, confidence, discipline, and
cheerfulness to perform work or tasks can be lowered due to a variety of
issues, including increased conflicts, disputes, excessive hazards, overtime,
over-inspection, multiple contract changes, disruption of work rhythm, poor
site conditions, absenteeism, unkempt workspace, and so on.
3. Fatigue
Fatigue can be caused by prolonged or unusual physical exertion.
4. Absenteeism and Turnover
There is a great deal of time and money lost associated with high turnover
and absenteeism on projects. Construction projects in certain areas with low
manpower and high demand for labor will usually be more impacted than
others. Extreme weather conditions (such as extreme heat or cold) will also
increase absenteeism and turnover. Replacement workers are usually not
familiar with the work or area, and require experienced workers to stop work
and show them what to do. The impact can be up to four days of lost work for
each worker.
5. Mobilize/Demobilize
This relates to moving resources on and moving off to projects as a result
from changes or delays, causing work disruptions. Productivity may drop
during these periods as time is lost when crews move from one area or work
assignment to another.
6. Errors and Omissions
Increases in errors and omissions impact on labor productivity because
changes are then usually performed on a crash basis, out of sequence, cause
dilution of supervision, or any other negative impacts.
7. Start/Stop
This results from a work stoppage or suspension of work, which may cause a
break in the schedule, usually triggering a start/stop of work activity. Stop-
starts can have an impact on productivity and cost of a project. Work
scheduled or reassigned during holidays such as Thanksgiving, Christmas,
New Year’s, and so on are often impacted with stop-starts. Workers tend to
discuss the time off and lose previous momentum with a drop in productivity
before they get back in routine.
8. Reassignment of Manpower
When workers are reassigned, they experience unexpected or excessive
changes, losses caused by move-on or move-off, reorientation, and other
issues that result in a loss of productivity.
9. Late Crew Build-up
This is caused when the planned project manpower loading is altered and
causes manpower loading to build up slower than planned due to availability,
shortage of resources, or competition from resources. Impacts can be in
excess of 10 percent.
10. Crew Size Inefficiency
This is when the optimal crew size is altered by adding or deleting crew
members. When workers are added or deleted from a crew, it breaks up the
original team effort and rhythm of the crew and results in loss of
productivity.
11. Site Access
This is a result of interferences to the convenient or planned access to work
areas. This can be due to blocked stairways, roads, walkways, insufficient
man-lifts, or congested work sites.
12. Logistics
Insufficient or poor material handling, owner-furnished material,
procurement practices, or a lack of controls can cause procurement or
delivery problems, as well as other issues. This then prevents, delays, or
disrupts the normal material workflow to a work area, warehouse, or laydown
yard. This can also be a result from the additional replacement or substitution
of material due to contract changes, defects, or delays at the work site.
13. Learning Curve
When crew turnover causes new workers to be added to a crew or additional
manpower is needed within a crew, a period of orientation occurs in order to
become familiar with changed conditions. They must then learn work scope,
tool locations, work procedures, and so on.
14. Hazardous Work Area
This is caused when working in an area that is classified as hazardous,
requiring special safety equipment and clothing. Restrictions may limit time
and exposure of workers to the area, resulting in less time on tools in the area.
15. Dilution of Supervision
This occurs when supervision is diverted from productive, planned, and
scheduled work to analyze and plan contract changes, expedite delayed
material, manage added crews, or other changes not in the original work
scope and schedule. Dilution is also caused by an increase in manpower,
work areas, or project size without an increase in supervision.
16. Weather and Season Changes
Performing work in a change of season, temperature zone, or climate change
resulting in work performed in either very hot or very cold weather, rain or
dust, or other changes in temperature or climate can impact workers beyond
normal conditions.
17. Rain, Dust
Most crafts do not work in the rain or dust , but many do, especially those
who live in wet or dray weather regions of the country and must work or risk
losing too much in wages. Work can, and does occur in the rain, but not
without inefficiencies due to rain gear, visibility, safety, morale, discomfort,
hazards, and other issues.
18. Shift Work
This is when work is performed at any time other than the first shift or the
morning shift of a work day. Work on second and third shifts are less
efficient and may even be based on a shorter work period. The reduced
daylight hours and problems trying to pick up where the last shift left off
results in less productivity.
19. Working in Operating Area
Inefficiencies can result when work is in close proximity to operating units
such as heat from boilers, smoke from emissions, explosion zones, and so on.
This can cause work stoppages, need for protective clothing, work permits, or
other requirements.
20. Tool and Equipment Shortage
This is caused when there is insufficient quantity or quality of tools and
equipment to meet the needs of the project.
21. Area Practices
This can be the result of added or extended coffee breaks, unique observance
or custom, or other practices unique to the craft, owner, country, project
location, or other customary practices in the area.
22. Proximity of Work
This is caused by working in a remote area, proximity of tools, break areas,
material laydown yard, or other resources causing a loss of time for access.
23. Alternating, Staggered, or Rotating Work Schedules
This usually results in unusual or unique scheduled work periods designed to
optimize craft hours worked, attract labor to remote sites, compete for labor
resources, and minimize fatigue. Examples include allowing half the work
force to take every other Friday off, or staggered crews of 4-12s (working on
four days and then four days off), or rotating crews to work a week and then
take a week off.
24. Learning Curve
When crew turnover causes new workers to be added to a crew or additional
manpower is needed within a crew, a period of orientation occurs in order to
become familiar with changed conditions. They must then learn work scope,
tool locations, work procedures, and so on.
25. Logistics
Insufficient or poor material handling, owner-furnished material,
procurement practices, or a lack of controls can cause procurement or
delivery problems, as well as other issues. This then prevents, delays, or
disrupts the normal material workflow to a work area, warehouse, or laydown
yard. This can also be a result from the additional replacement or substitution
of material due to contract changes, defects, or delays at the work site.
Input/output ratio (for example work hours per square feet of wall
painted), is mostly used for measuring productivity at an activity level
(labor productivity), and its lower values indicate better productivity-
performance. Furthermore, when measured by that method labor
productivity often depicts how efficiently labor is combined with
other factors of production, a clue which can be very useful for
activity planning and scheduling. Therefore, if productivity is
reported as work hours per unit, the cost engineer can easily determine
project costs by multiplying productivity times the estimated quantity
and the wage rate. The present form of measurement has the
disadvantage of being very simplistic, and it cannot depict the real
on-site situation by not taking into account any of the factors affecting
site activities. That model could be helpful for having an estimation
of labor productivity, but the same could not be claimed for the
productivity of organizational and off-site staff, management staff
(whose works’ input and output cannot easily be defined) , nor for
productivity at a firm level.
1. Communicate Clearly
Communication is the most important productivity booster in any job. No one
will get the job done well if they have no idea what’s going on.
It’s important you clearly communicate your goals to your crew before you
start a new project and continue keeping them updated throughout the
project.
Send out frequent emails and memos if there are any changes that might
affect your workers. Be considerate and never leave your employees in the
dark about what’s happening in a project.
3. Reward Regularly
Construction is often hot and tiring work. Your workers are putting in hour
after hour of manual labor.
In order to increase productivity, offer incentives in the form of rewards.
Whenever your crew meets a goal, treat them to pizza and beer at a local
restaurant.
This will make your workers feel appreciated and eager to push forward.
5. Listen Well
To be a good leader, you have to listen well to those you’re employing.
It’s not enough to communicate with people if you’re not open to hearing
their responses. Your workers will have a firsthand idea of what does and
doesn’t work on site.
They will sometimes come to you and tell you that a goal isn’t realistic, or
that they need new tools. Don’t brush these things off. Instead, take them
into consideration and try to find a solution for your crew.
The OSH Law also states in Section 16 (b) that all workers are
required to attend an eight-hour OSH seminar which should include
a joint employer-employee orientation on safety and health
standards.
http://bwc.dole.gov.ph/osh-law