Composite and Steel Construction Compendium: Part 4: Composite Beams Using Precast Concrete Units
Composite and Steel Construction Compendium: Part 4: Composite Beams Using Precast Concrete Units
Part 4
www.thestructuralengineer.org
Technical TheStructuralEngineer 41
Composite/Steel compendium April 2014
infill plus the width of the gap between the ends of the hollow-core between hollow-core units
42 TheStructuralEngineer Technical
April 2014 Composite/Steel compendium
W Figure 2
Cross section
through a joint between
solid planks
SCI
Figure 3
Push off test with precast units
Figure 4
End bearing of solid
planks on steel beam
75 mm
D. LAM, UNIVERSITY OF BRADFORD, UK
SCI
Shear connection there is sufficient gap to ensure correct compaction of the concrete.
Resistance of shear studs
Eurocode 4, like BS 5950-3.12, defines the resistance of a shear Minimum degree of shear connection
stud in a solid concrete slab (Clause 6.6.3.1), and gives reduction The minimum degree of shear connection rules given in Clause 6.6.1.2
factors kt and kl to apply to this resistance when the slab is formed of EN 1994-1-1 ensure that the shear studs have adequate deformation
using profiled steel decking (be it transverse to or parallel with the capacity, based on a characteristic slip capacity of 6mm i.e. they
beam axis, respectively). The reduction factors are based on tests guarantee that the connection will be sufficiently stiff to stop greater
comprising slabs of relevant form. A similar approach must be taken slip occurring. In order to ensure that 6mm slip can be accommodated,
to determine reduction factors relevant to slabs comprising solid or and so the use of these rules is justified for slabs using precast units,
hollow-core precast units, which can then be justifiably applied to the 16mm diameter high tensile transverse reinforcement bars should be
solid slab resistances given in EN 1994-1-1. used (passing between opposing units) when hollow-core units are
employed. The bars should be placed at least 15mm below the heads
For hollow-core units the reduction factor k is based on the results of of the studs (Fig. 1). This is not generally a problem because studs
push-out tests by Lam (Figure 3). It is a function of the gap between are typically 125mm high and the base of the opening is 30-40mm
the plank ends and the confinement of the stud within that gap (which above the base of a hollow-core unit. When solid planks are employed,
is traversed by reinforcement), and may be taken as 0.9 provided it is recommended that bars of at least 10mm diameter are used, in
the detailing rules on minimum gap width and bar size given in the conjunction with A142 fabric, in order to maintain 6mm slip capacity.
following sub sections are respected (more information is given in the
forthcoming SCI publication, P401: Design of composite beams using Special considerations for steel beam specification
precast concrete slabs in accordance with Eurocode 4). Minimum top flange width
The minimum acceptable beam (top flange) width depends on the
Tests have demonstrated that the reduction factor for studs type of slab, whether the shear connectors are to be shop-welded
embedded in slabs using solid planks is only a function of the gap or site-welded and whether the beam is an internal or edge beam.
between the solid planks. A value of k equal to 1.0 may be used when It is specified to ensure that the precast units will have sufficient
43
for. During this second phase, provided the precast units to either
side are of equal span, the beam will be verified for balanced
loading. There is no need to consider 'pattern loading' with the
construction loads placed to one side only.