Example 3. CPM: Activity Duration (Days) Events Preceding Activity (Predecessor)

1. The document presents a CPM network diagram and table for a project with 9 activities (A to I). 2. The critical path passes through activities A, B, D, G, and H, which have a total project duration of 33 days. 3. Activities on the critical path have zero total float in the table.

Uploaded by

adnan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
654 views3 pages

Example 3. CPM: Activity Duration (Days) Events Preceding Activity (Predecessor)

1. The document presents a CPM network diagram and table for a project with 9 activities (A to I). 2. The critical path passes through activities A, B, D, G, and H, which have a total project duration of 33 days. 3. Activities on the critical path have zero total float in the table.

Uploaded by

adnan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

EXAMPLE 3.

CPM
1. Construct AOA network
2. Find ES, EF, LS and LF of all activities
3. Find total float of all activities (days)
4. Find the project duration (days)
5. Mark critical path on the network

Activity Duration Events Preceding


(days) Activity
(Predecessor)

A 3 1–2 None
B 5 2–3 A
C 8 2–4 A
D 10 3–6 B
E 5 3–5 B
F 7 4–5 C
G 12 6–7 D
H 8 5–7 E, F
I 3 7–8 G,H

E A EF
S
LS D LF

3 B 8 8 D 18 18 G 30
3 5 8 8 10 18 18 12 30
0 A 3
0 3 3
8 E 13
1 H 26 3 I 33
1 5 22
8 0
7
2 8 30 3 3 33
2 0

3 C 11 1 F 18
1
7 8 15
1 7 22
5
Activity Duration Predecessor Resorce ES EF LS LF TF
A 3 None   0 3 0 3 0
B 5 A   3 8 3 8 0
C 8 A   3 11 7 15 4
D 10 B   8 18 8 18 0
E 5 B   8 13 17 22 9
F 7 C   11 18 15 22 4
G 12 D   18 30 18 30 0
H 8 E,F   18 26 22 30 4
I 3 G,H   30 33 30 33 0

 Total Project duration is 33 days


 Critical path is Marked red in the diagram and zero float is the table.