Cogeneration PDF
Cogeneration PDF
Rangan Banerjee
Energy Systems Engineering
IIT Bombay
PROCESS Electricity
Heat
Electricity
Heat
Fuel Heat
BOILER
Cogen Plant
Electricity
Fuel
Power Plant Fuel
Cogeneration
SHP
Cogeneration Concept
Boiler η 90% Power plant η 40%
Where is the scope for improvement?
Cogeneration- Simultaneous generation
of heat and power (motive power or
electricity) – CHP- Total Energy
Second Law of Thermodynamics –
Concept of Exergy
Early 19th century Cogeneration plant
Selection of Cogen Option
Heat/Power Ratio X (Range of values)
Fuel Availability
Costs
Decreasing X
Steam Turbine 5.9 ( 3-7)
Gas Turbine 1.5
Combined Cycle 1.2
D.G. Set 0.7
Evaluation Criteria
Relative Fuel Savings Rf – Fuel savings over
separate heat & power generation
Rf = ( Fnc – Fc) / Fnc
Fnc = Fboiler + Fpower plant
Fuel Chargeable to Power (FCP) – The
incremental fuel in cogeneration is charged to
the power generation.
FCP =( Fc – Fboiler)/ W
kg of oil/kWh, kJ/kWh, Nm3 gas/kWh,
kg of bagasse/kWh
Cogeneration Concept
Process boiler , sat steam at 180 °C
η 90% (1st law eff)
Tu= 180+273 =453 K, T0 = 300 K
ηII=Qu(1- T0 / Tu)/ Qinθ (for fuel θ≅ 1.0)
=0.9(1-300/453) =0.3 (30%)
Increase generation temperature to 400 °C
and pass through an expansion turbine
Back Pressure Steam Turbine System
HP Steam
Fuel Electricity
ST
Air
BOILER
Water
LP Steam to
Process
Steam Turbine Cogen
Configuration X
Decreasing X
Boiler ∞
BPT with extraction 10
Back Pressure Turbine
Condensing Turbine 3
Condensing Power Plant 0
Steam Turbine Calculations
h2
2
h2i 2i
Specific Entropy s
Example Problem
A process boiler generates 25T/hour of
saturated steam at 10 bar absolute. The
fuel used is LSHS. The boiler efficiency
is 90%. The power requirement of the
industry is 2.5 MW.
Evaluate the viability of using a high
pressure boiler generating steam at 50
bar 400° C and a back pressure turbine
GAS TURBINE BASED COGEN
Fuel
CC
Power
C GT ∼ Steam to
Process
Air
Stack
WHRB
Suppl Fuel
Feed water
Gas Turbine Cogeneration
Unfired Heat Recovery Steam Generator
(HRSG)
Supplementary Fired (Duct Burners)
Fully Fired HRSG
Steam Injected Gas Turbines (STIG)
Combined Cycle
Cogeneration
Self generated electricity in Chemical – 42%
of total elec, 86% from cogeneration plants
Average price – only 57% of grid price
Purchased electricity declining (-0.4%), self
generated elec increasing at 21.3% per year
Evaluate viability of Cogeneration
If heat/power loads small-Cogeneration for
group of industries
Operating Strategy
Standalone/ Isolated
Grid Interconnection
Parallel with Grid – Only Buying from grid
Buying and Selling to Grid
FEED
W ATER 2 7 T /h r
4 .5 T /h r 2 6 T /h r
F eed w ater
B O IL E R
0 .5 T /h r
PRDS
BA G A SSE
0 .5 T /h r
M IL L IN G
PRDS
6 a ta
P ro cess 2 .5 M W
STEA M
F la s h e d T U R B IN E
2 a ta
C o n d e n sa te
P ro cess
S c h e m a tic o f ty p ic a l 2 5 0 0 tc d S u g a r fa c to r y
Options
A- Replace mill turbines by motors + power
turbine by efficient motor
B- New Boiler 43 ata 480 C + additional TG
C- HP Boiler 65 ata 480 C + additional TG
D – C+ replace mill turbines with TG
E – similar to D but with condensing
extraction turbine
B O IL E R
F e e d w a te r
75 TPH , 65 STEA M
a ta , 4 8 0 O C T U R B IN E
9 .5 M W
13 M W P ow er export
BA G A SSE
( A lt e r n a t e f u e l) ~
6 a ta
4 .5 T P H 1 .0 M W
Condenser
M ill
PR O C ESS d r iv e s
2 a ta CO NDENSER
2 a ta
2 .5 M W
C a p tiv e
BFP lo a d
PR O C ESS
P R O P O S E D P L A N T C O N F IG U R A T IO N : O P T IO N 2
Comparison of Options
Case Output Export kWh
export /tc
A 5.4 MW 1.9 MW 18
B 7.5 MW+M 5.0 MW 48
C 6.8 MW+M 4.3 MW 41
D 10.7 MW 7.2 MW 69
E 13 MW 9.5 MW 91
Optimal Cogeneration Strategy
Decisions
Grid Electricity Bought/Sold
Equipment Mass Flow rates
Electric/Steam Drive
Constraints
Equipment Characteristics – Min/Max
Process Steam & Electricity Loads
Grid Interconnection
Objective Function
Minimise annual operating cost (Maximise
revenue)
Stack
Fuel, HSD WHRB-1
5.9 T/h G 136 T/h
1
20 MW
Gas turbine -1 Supp. Firing
LSHS 5.6 T/h
Grid Process Load,
Fuel, HSD WHRB-2 136 T/h 7.52 MW 60 MW
5.9 T/h
G
1
Gas turbine -2 20 MW Supp. Firing BUS
LSHS 5.6 T/h
SHP Steam 100 bar,500o C
60.6 T/h
131.7 T/h 117.1 Process Load,150 T/h 76.2 T/h
T/h 12.5
Boiler
MW
ST
Fuel, LSHS Process Load,125 T/h G4
PRDS-1
9.64 T/h PRDS-2
HP Steam 41b,400 oC 20 T/h
MP Steam 20b, 300 oC
25 21.6
20 17.6 peak
period
15 demand
10
11 MW
5
0
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time hours
Export power to the grid with
Cogeneration for a Petrochemical Plant
Peak
Export Power MW
40 period
flat tariff TOU tariff
30 demand
20 9.7 MW
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time hours
Summing Up
Even in industries with cogen – Retrofits for
additional power generation
Sugar –2500 tcd plant can generate 9.5 MW
surplus by using high pressure boilers
Grid Agreement –Parallel, Buying/Selling
Optimal operating strategy – can result in
significant savings
Significant potential in process industries
Thank You