Sample Plan for the Plan
Task Name Duration Start Finish
Start 0 days Mon 1/04/16 Mon 1/04/16
Project Initiation Activities 2 days Mon 1/04/16 Tue 1/05/16
Draft and sign off on Project Scope Statement 1 day Mon 1/04/16 Mon 1/04/16
Draft and sign off on Project Governance 1 day Mon 1/04/16 Mon 1/04/16
Schedule and Conduct Project Kickoff Meeting 1 day Tue 1/05/16 Tue 1/05/16
Develop Requirements 19 days Wed 1/06/16 Mon 2/01/16
Complete current-state analysis 5 days Wed 1/06/16 Tue 1/12/16
Conduct impact analysis group session 1 day Wed 1/13/16 Wed 1/13/16
Conduct requirements development interviews & sessions 5 days Thu 1/14/16 Wed 1/20/16
Complete Data Dictionary 5 days Thu 1/21/16 Wed 1/27/16
Complete Use Cases 5 days Thu 1/21/16 Wed 1/27/16
Complete Work Flow Diagram 5 days Thu 1/21/16 Wed 1/27/16
Complete wireframes 5 days Thu 1/21/16 Wed 1/27/16
Complete Systems Requirements Specification (SRS) 2 days Thu 1/28/16 Fri 1/29/16
Conduct walk-through of SRS & acquire sign-off 1 day Mon 2/01/16 Mon 2/01/16
Product Design 16 days Tue 2/02/16 Tue 2/23/16
Draft Architecture Blueprint 2 days Tue 2/02/16 Wed 2/03/16
Build Data Model 5 days Tue 2/02/16 Mon 2/08/16
Draft Systems Design Specification (SDS) 5 days Tue 2/02/16 Mon 2/08/16
Develop Proof of Concept (POC) 10 days Tue 2/09/16 Mon 2/22/16
Conduct demonstration of POC 1 day Tue 2/23/16 Tue 2/23/16
Vendor Evaluation 14 days Tue 2/02/16 Fri 2/19/16
Draft and send RFI 3 days Tue 2/02/16 Thu 2/04/16
Collect RFI responses 10 days Fri 2/05/16 Thu 2/18/16
Draft Vendor selection criteria & scorecard 2 days Tue 2/02/16 Wed 2/03/16
Complete vendor selection scorecard (session) 1 day Fri 2/19/16 Fri 2/19/16
Develop Plan for Execution 40 days Mon 1/04/16 Fri 2/26/16
Conduct WBS Session 1 day Wed 2/24/16 Wed 2/24/16
Conduct PERT Chart session 1 day Thu 2/25/16 Thu 2/25/16
Draft Schedule 1 day Fri 2/26/16 Fri 2/26/16
Draft Quality Assurance Strategy 4 days Tue 2/09/16 Fri 2/12/16
Draft Deployment Strategy 4 days Tue 2/09/16 Fri 2/12/16
Draft Business Case 39 days Mon 1/04/16 Thu 2/25/16
Approval for Execution 1 day Mon 2/29/16 Mon 2/29/16
Present Busienss case and secure approval to proceed 1 day Mon 2/29/16 Mon 2/29/16
Finish 0 days Mon 2/29/16 Mon 2/29/16
PredecessoResource Names
1
1
3,4
5
7
8
9
9
9
9
10,11,12,13
14
15
15
15
17,18,19
20
15
23
15
24,25
26,21
28
29
19
19
1
33,30,31,32
35