Daily Work Tracker - Nikhil

This document lists 33 tasks assigned between March 23rd and April 7th. It includes the task name and the target date for completion. The status column is updated periodically showing the progress of each task, with tasks marked as completed, in process, or to start. The tasks cover a range of activities including process documentation updates, equipment procurement, and quality control procedures.

Uploaded by

buntynikhil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
64 views15 pages

Daily Work Tracker - Nikhil

This document lists 33 tasks assigned between March 23rd and April 7th. It includes the task name and the target date for completion. The status column is updated periodically showing the progress of each task, with tasks marked as completed, in process, or to start. The tasks cover a range of activities including process documentation updates, equipment procurement, and quality control procedures.

Uploaded by

buntynikhil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 15

Assigned Task

Sr. No Date

1 23.03.20

2 23.03.20
3 23.03.20
4 24.03.20
5 24.03.20

6 24.03.20

7 25.03.20

8 25.03.20
9 25.03.20

10 25.03.20

11 25.03.20
12 26.03.20
13 26.03.20
14 27.03.20

15 28.03.20

16 30.03.20

17 30.03.20

18 30.03.20

19 30.03.20
20 31.03.20
21 31.03.20
22 01.04.20
23 02.04.20
24 03.04.20

25 06.04.20

26 06.04.20

27 06.04.20
28 06.04.20

29 06.04.20
30 06.04.20

31 06.04.20

32 06.04.20

33 07.04.20
34 09.04.20
anandsubramaniam/process-failure-modes-effects-analysis-pfmea

Assigned Task Target

Installation of Mobile hand set e-mails (Mass 360) 23.03.20

Data Collection from Office PC to personal e-mails and personal laptop 23.03.20
Data Compilation at personal laptop 23.03.20
New Machine for Superfinishing RFQ prepration 24.03.20
Prepraed the Contro plan for Upgraded 6*11 Bearing superfinishing 24.03.20
Reviewed the PC for CTRB Heat Treatment process for Carburising operation. 24.03.20
Correction made as per the input reieved from Plant
New Microne Machine (Centerless Grinder) PC Created, and reviewed for the cycle 25.03.20
time
Control Plan revise for UIC Cone/Cup MPI testting operation 25.03.20
Control Plan revise for UIC Cone/Cup UT testting operation 25.03.20

Control Plan revise for CTRB bearing for grinding operation as per plant inputs 25.03.20

PFMEA revision for CTRB Bearing for incoming inspection 25.03.20


Process Minutes verification for upgraded class E 26.03.20
PFMEA SME work, difference between 3rd to 4th revision prepared 26.03.20
PFMEA SME work, difference between 4th to 5th revision prepared 27.03.20

Learning PFMEA VDA 5th Edition TBD

Processng conditions for CTRB 6x11 Rollerface grinding updated asper plant input 30.03.20

PFMEA SME work_Basic Knowledge 09.04.20

Processing conditon for Roller Hardning & Tempering reviewed for HiTemp Furnace 30.03.20

LDB PFD for NH1044 & NU1096 reviewed and updated 30.03.20
Processing condition prepration for 6x11 cone superfinishing 31.03.20
Processing condition review for CTRB heat Treatment (GC Furnace) 31.03.20
Processing condition review for CTRB Heat Treatment for UBH Furnece 01.04.20
PFMEA updation for the CTRB Bearing 08.04.20
Carburising PC Review for CTRB Components 03.04.20

Complete PFMEA to reviewed for CTRB’s (Re-establishment) as per 4th Rev. of PFMEA std. 10.04.20

Complete PFMEA to reviewed for CRB’s (Re-establishment) as per 4th Rev. of PFMEA std. 11.04.20

CTRB's Job Heat treatment Processing conditions to be review and revision 10.04.20
Master List updating for all Control Plans 08.04.20

Master List updating for all Processing Conditions 08.04.20


Master List updating for all PFD's 08.04.20

Abberesive Standard to be prepare for all jobs in Railway 07.04.20

Optimised Profile, Grinding processing conditions to be review as per Plant input 06.04.20

Grinding Technology 14.04.20


Control Plan updation for CRB cone bore grinding 14.04.20
Status 23-Mar-2020 24-Mar-2020 25-Mar-2020 26-Mar-2020 27-Mar-2020 28-Mar-2020

Completed Conpleted - - - - -

Completed Conpleted - - - - -
Completed Conpleted - - - - -
Completed - Conpleted - - - -
Completed - Conpleted - - - -

Completed - Conpleted - - - -

Completed - - Conpleted - - -

Completed - - Conpleted - - -
Completed - - Conpleted - - -

Completed - - Conpleted - - -

Completed - - In Process In Process Conpleted -


Completed - - - In Process In Process Conpleted
Completed - - - Conpleted - -
Completed - - - - Conpleted -

In Process In Process In Process


- - - -
(30% Complete) (2% Complete) (5% Complete)

Completed - - - - - -

Completed - - - - - -

Completed - - - - - -

Completed - - - - - -
Completed - - - - - -
Completed - - - - - -
Completed - - - - - -
Completed - - - - - -
Completed - - - - - -

Completed - - - - - -

To Start - - - - - -

To Start - - - - - -
Completed - - - - - -

In Process
(75% Complete)
Completed

To Start - - - - - -

Completed - - - - - -

To Start - - - - - -
Completed - - - - - -
29-Mar-2020 30-Mar-2020 31-Mar-2020 1-Apr-2020 2-Apr-2020 3-Apr-2020 4-Apr-2020

- - - - -

- - - - -
- - - - -
- - - - -
- - - - -

- - - - -

- - - - -

- - - - -
- - - - -

- - - - -

- - - - -
- - - - -
- - - - -
- - - - -

In Process In Process In Process


- -
(5% Complete) (10% Complete) (12% Complete)

SATURDAY (OFF)
Completed - - - -
SUNDAY (OFF)

In Process Completed - - -

Completed - - - -

Completed - - - -
- In Process Completed - -
- Completed - - -
- - Completed - -
- - - In Process In Process
- - - - Completed

- - - - -

- - - - -

- - - - -
- - - - -
- - - - -

- - - - -

- - - - -
- - - - -
5-Apr-2020 6-Apr-2020 7-Apr-2020 8-Apr-2020 9-Apr-2020 10-Apr-2020 11-Apr-2020

- - - - - -

- - - - - -
- - - - - -
- - - - - -
- - - - - -

- - - - - -

- - - - - -

- - - - - -
- - - - - -

- - - - - -

- - - - - -
- - - - - -
- - - - - -
- - - - - -

In Process In Process In Process In Process In Process


-
(15% Complete) (20% Complete) (22% Complete) (25% Complete) (30% Complete)

- - - - - -
SUNDAY (OFF)

- - - Completed - -

- - - - - -

- - - - - -
- - - - - -
- - - - - -
- - - - - -
- In Process Completed - - -
- - - - - -

- - Completed - - -

- - - - - To Start

- - - - To Start
- - - Completed

In Process In Process In Process


- - (10% Complete) (30% Complete) (75% Complete)
- - Completed

- To Start

In Process Completed

- - - Completed - -
12-Apr-2020 13-Apr-2020 14-Apr-2020 15-Apr-2020

- -

- -
- -
- -
- -

- -

- -

- -
- -

- -

- -
- -
- -
- -
SUNDAY (OFF)
To Start
Remark
SAP not accessible, and not able to get
information from plant