Solar Panel Installation: Inspection and Test Plan

The inspection and test plan outlines 6 stages for the solar panel installation project: 1. Incoming materials will be inspected upon each delivery to ensure they conform to orders. 2. Storage and protection of materials will be inspected weekly to ensure items are safely and securely stored. 3. Preliminary activities will be inspected to confirm all tasks are completed. 4. A pre-start inspection will check that work is ready to commence per requirements. 5. Work will be inspected to verify compliance with trade codes, authority standards and that testing is completed. 6. Pre-handover activities will have a final inspection to ensure all items are finished per specifications.

Uploaded by

cool_yaar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (7 votes)
5K views4 pages

Solar Panel Installation: Inspection and Test Plan

The inspection and test plan outlines 6 stages for the solar panel installation project: 1. Incoming materials will be inspected upon each delivery to ensure they conform to orders. 2. Storage and protection of materials will be inspected weekly to ensure items are safely and securely stored. 3. Preliminary activities will be inspected to confirm all tasks are completed. 4. A pre-start inspection will check that work is ready to commence per requirements. 5. Work will be inspected to verify compliance with trade codes, authority standards and that testing is completed. 6. Pre-handover activities will have a final inspection to ensure all items are finished per specifications.

Uploaded by

cool_yaar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

INSPECTION AND TEST PLAN

SOLAR PANEL INSTALLATION


Customer: Work area: (Insert work area) Insert Contractor Identification and/or Logo
Contract Number:
Contract/Project Name:
Ref Operation or stage of work Stage/ Records Requirement/ standard/ specification Acceptance criteria Inspection/ test procedure Inspection Points
Description Characteristics frequency
Rimfire
Regulator
Client Rep.
Quality and Safety Rep.
Person
1 Incoming materials Conform to order Each Delivery Orders as placed Specification & codes Check against orders
inspection delivery dockets/
Checklist H S

2 Storage and As specified Each Checklist Specification, as attached Safe, secure/ adequate Visual
protection week protection
X S S

3 Preliminary Task completion Each Checklist Specification, as attached, WHS All tasks completed Visual
activities work area practice & Regulation
H W S

4 Pre-start Ready to Each Checklist Specification, as attached To authority requirements Checked


commence work work area
H W S

5 Carry out work To trade codes Each Checklist Specification, as attached Checklist and test panel Checked
and authority work area
requirements H(A) W S

6 Pre-handover All matters Each Wiring Specification, as attached All items completed to Final inspection
activities finalised, clean work area diagrams/ specification
and tidy Checklist H H H
1 Incoming Conform to Each Delivery dockets/ Orders as placed Specification & Check against orders
materials order delivery Checklist codes H S
inspection

2 Storage and As specified Each Checklist Specification, as attached Safe, secure/ Visual
protection week adequate X S S
protection

3 Preliminary Task Each Checklist Specification, as attached, All tasks Visual


activities completion work WHS practice & Regulation completed H W S
area

4 Pre-start Ready to Each Checklist Specification, as attached To authority Checked


commence work requirements H W S
work area

5 Carry out To trade Each Checklist Specification, as attached Checklist and Checked
work codes and work test panel
H(A) W S
authority area
requirements
6 Pre-handover All matters Each Wiring Specification, as attached All items Final inspection
activities finalised, work diagrams/Checklis completed to
H H H
clean and area t specification
tidy
INSPECTION AND TEST PLAN CHECKLIST for: SOLAR PANEL INSTALLATION
(To be completed by the person(s) directly responsible for the work)
Contract Number: Work area: Checklist Number:
Contract/Project Name:
Contractor:
Subcontractor:
Work Items/activities to be verified Reference Initialled/OK Comments
Preliminary Documentation requirements i.e. Drawings,
activities applicable documents including manufacturers
data,
Competency certificates/ licences of technicians
Calibration certificates of equipment
Access permission obtained
Access obtained
Equipment approved/on site -
Scaffold/ladders
Signage/barricades
Other
Materials approved/on site -

I have carried out all necessary inspections and verify that the above items/activities conform to the Name:
contract specification/documents Signature:
Date:
Pre-start Fixtures removed
Protective measures
Install temporary power (where necessary)

I have carried out all necessary inspections and verify that the above items/activities conform to the Name:
contract specification/documents Signature:
Date:
Carry out work Apply safety procedures at all stages
Protective measures
Carry out work as per specification, AS 3000
and other relevant codes

I have carried out all necessary inspections and verify that the above items/activities conform to the Name:
contract specification/documents Signature:
Date:
Pre-handover Carry out all testing and safety checks
activities Restore power supply to all isolated circuits
Remove temporary power supply
Remove protective measures
Final inspection confirms conforming
Remove scaffold/ladders, clean up etc.
I have carried out all necessary inspections and verify that the above items/activities conform to the Name:
contract specification/documents Signature:
Date:
I have carried out all necessary inspections and verify that the above work for this work area has been Name:
completed and conforms to the contract specification/documents Signature:
Date: