CVE511 Lecture Note
CVE511 Lecture Note
Synopsis
Professional and legal relationship in preparation of working drawings
Specification and bill of quantities
Types of contracts, contract documents
Advertisement and administration of tenders
Awards of contracts
Payments to contractors and consultants.
Content
1.0 Working Drawing
1.1 Client for building design and construction
1.2 The Traditional Roles of Professional Team Members
1.3 Consultant team for design and construction
1.4 Lead consultant for building design
1.5 Structural engineer
1.6 Cost consultant
1.7 Construction contractor
1.8 Sub-contractor
2.0 Statements of Work, Services and Technical Specifications
2.1 Technical Specification for construction
2.2 Types of specifications
2.3 Specification writing
2.4 Bill of quantities BOQ
2.5 Preparing bills of quantities
2.6 Approximate bill of quantities
3.0 Contract
3.1 Classification of Contract
3.2 Types of contracts
3.3 Contract Documents
4.0 Tender documentation for construction projects
4.1 Advertisement for Bids (Notice to Contractors, or Invitation to Bid)
4.2 Clarification
4.3 Submission
4.4 Programme
4.5 Settlement
4.6 Choosing the Contractor
4.7 Paying the Contractor
4.8 Calculating the Cost
4.9 The Duration of the Contract
4.10 Site Supervision
4.11 Construction Period
4.12 Schedule of Execution
4.13 Handover of the Completed Development
4.14 Monitoring Construction Process
5.0 PUBLIC-PRIVATE PARTNERSHIPS (PPP)
5.1 PARTNERING
5.2 Provisional sum
5.3 Prime cost sum
5.4 Contract sum
5.5 Contract sum analysis
5.6 Budget
6.0 As-built Drawings and Record Drawings
2
Common problems with working drawings include:
Poor co-ordination of information.
Errors and omissions.
Information not getting to the right people.
Poor presentation.
Responsibility for the preparation of production information will depend on the selected system of procurement and the chosen form
of contract. On traditional contracts (and management contracts and construction management contracts), production information may
be produced by a consultant team, working for the client. Some specialist elements of production information may be produced by
specialist contractors, coordinated by the lead designer. On other forms of contract, such as design and build, responsibility for
preparing and coordinating production information may lie with the main contractor.
Working drawings may be updated when the works are complete to show ‘as constructed’ information, reflecting changes to the works
that may have occurred during the construction process.
Carefully prepared working drawings can be very beautiful and the very best have been exhibited as works of art.
4
Public health consultant.
Rights of light surveyor.
Security consultant.
Site inspector (clerk of works).
Specialist contractor.
Surveyor.
Transport/traffic engineer.
For consultants to work effectively as a team they should adopt collaborative practices as early in the project as possible.
Some of these roles may appear to duplicate tasks undertaken by the project manager, however the project manager is acting as if
they were the client, whereas the lead consultant is co-ordinating the activities of the consultant team.
As the role of lead consultant involves additional services, beyond those that might be expected from a consultant that is not appointed
as lead consultant, it is important that it is discussed with consultants before they are appointed and their scope of services and fee
agreed. The client cannot assume that these services will be carried out within the agreed fee unless the role of lead consultant has
been allocated.
The lead consultant will often be the architect, however this is not necessarily the case and appointment documents for other
consultants will generally offer provision for them the be nominated lead consultant.
5
1.5 Structural engineer
Structural engineers design, assess and inspect structures to ensure that they are efficient and stable. Structural engineering was
traditionally considered a sub-discipline of civil engineering, however as it has developed as an important and complex specialism it
may now be considered an engineering discipline in its own right.
Structural engineers work on a very wide range of structures, including; buildings, bridges, oil rigs, ships and aircraft. It is both a
technical and creative role that involves close collaboration with professionals from other disciplines.
The scope of services provided by a structural engineer might include:
Site appraisals - strength of subsoil / ground.
Geotechnical and geological investigations - loading and foundation design.
Supervision of surveys.
Flood analysis.
Contributing to the preparation of briefing documents, feasibility studies and options appraisals.
Contributing to tender documentation and assessment of tenders.
Assessment and integration of work by specialists.
Environmental studies.
Investigating materials.
Ground improvement.
Roads, Retaining walls and Drainage.
Foundation design, Structural design and detailing.
Special loads.
Fire protection to the structure.
Demolition.
Building regulations submissions.
Risk assessment.
Value management.
Site inspection.
Witnessing tests.
Developing remediation solutions.
Expert witness testimony for courts, and insurance purposes.
Aesthetics and beauty.
Structural failure can be devastating. It is therefore important to select an individual or company that has a good track record and
experience in structurally similar projects. Suitably qualified people include Chartered and Incorporated Engineers who are members
of the Institution of Civil Engineers and/or the Institution of Structural Engineers.
It is good practice to employ a structural engineer based on the quality of their design rather than the lowest fee. A good design that
explores a wide variety of options to find the best solution can save significant cost over the design life of a building.
6
1.6 Cost consultant
Typically cost consultants are quantity surveyors by profession, but accountants and other professionals can also be effective cost
consultants.
The cost consultant provides estimates, and advice regarding the cost of construction works.
7
their experience can be used to improve the buildability and packaging of proposals as they develop. A construction manager may also
programme construction to begin before the design is completed. This requires careful planning of information release so that the
construction process is not delayed by lack of production information.
Management contractor. This is similar to the role of the construction manager but the trade contracts (or works contracts) are placed
with the management contractor rather than with the client.
Design and build contractor. Responsible for the completion of the design as well as construction.
Prime contractors. The client enters into a long-term multi-project relationship with a contractor in which competition is introduced at
the sub-contract level. Prime contracting is generally only appropriate for very large clients such as the Ministry of Defence which is
continually commissioning new buildings and refurbishment work.
Integrated supply team. This is favoured by the Government, and involves appointment of a full project team (including contractors,
suppliers, designers and sometimes facilities managers) to design and construct the works.
Design, build and manage contractors. The contractor is appointed not only to design and build the works, but also to manage them
during operation, sometimes providing operational services over and above building maintenance, such as supplying prison staff or
sterilisation of hospital instruments.
The contractor may also be designated the principal contractor under the CDM regulations to plan, manage and co-ordinate health and
safety while construction work is being undertaken.
Other terms used to describe contractors and sub-contractors include:
Specialist contractors.
Domestic sub-contractors.
Nominated sub-contractors.
Named sub-contractors.
Trade contractors.
Works contractors.
1.8 Sub-contractor
As buildings become increasingly complicated, so it becomes less and less likely that any one contractor will have the required skills
to carry out all of the works necessary to construct them, and it may not make good commercial sense to take on new employees for
one project that would then have to be laid off for the next.
Increasingly therefore, contractors will use sub-contractors to carry out particular elements of the works.
Elements of the works that might be awarded to sub-contractors might include; piling, roofing, cladding, civil engineering, steelwork,
plumbing, electrical services and so on.
8
3. Named sub-contractor: A sub-contractor for a particular package selected from a list of acceptable sub-contractors provided
by the client. Named sub-contractors are allowed for in the tender documents for the main contract in the form of a
provisional sum for which the main contractor makes allowances for mark up, attendance and programme within it’s tender
offer. Once appointed, the main contractor seeks tenders for the package from the named sub-contractors, places a sub-
contract with the successful tenderer, and the provisional sum is replaced with the tendered figure.
The use of sub-contractors enables the main contractor to undertake more complex projects whilst not unacceptably increasing their
risk, however, concerns have been expressed about the prevalence of sub-contractors because of a perception that the main contractor
has less control over the skills and training of sub-contractor employees and so there may be a negative impact on quality and health
and safety on site.
'Attendance' is the main contractor’s mark up for specific services it has to provide for individual sub-contractors. This might include
items such as material handling, scaffolding and rubbish clearance. Attendance can be 'general attendance' describing items available
site wide to all subcontractors, or 'special attendance' where items are specific to a particular contractor/subcontractor.
9
Large clients may be able to procure certain products at competitive rates themselves (for example the government).
Some designers may have particular experience of using a specific product (although some clients may not allow designers to specify
particular products as they believe it restricts competition and innovation and may relieve the contractor of their liability for 'fitness for
purpose').
The contractor may be best placed to specify products that affect build ability.
Specifications should be developed alongside the design, increasing in level of detail as the design progresses. They should not be left
until the preparation of production information. By tender they should describe every aspect of the building in such a way that there is
no uncertainty about what the contractor is pricing.
It should be possible to verify standards of products and workmanship by testing, inspection, mock-ups and samples, and
documentation such as manufacturers certificates.
10
2.4 Bill of quantities BOQ
The bill of quantities (sometimes referred to as 'BoQ') is a document prepared by the cost consultant (often a quantity surveyor) that
provides project specific measured quantities of the items of work identified by the drawings and specifications in the tender
documentation. The quantities may be measured in number, length, area, volume, weight or time. Preparing a bill of quantities
requires that the design is complete and a specification has been prepared.
The bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill of quantities assists
tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same
quantities (rather than taking-off quantities from the drawings and specifications themselves), it also provides a fair and accurate
system for tendering.
The contractor tenders against the bill of quantities, stating their price for each item. This priced bill of quantities constitutes the
tenderer's offer. As the offer is built up of prescribed items, it is possible to compare both the overall price and individual items
directly with other tenderers’ offers, allowing a detailed assessment of which aspects of a tender may offer good or poor value. This
information can assist with tender negotiations.
The priced bill of quantities will also:
Assist with the agreement of the contract sum with the successful tenderer.
Provide a schedule of rates assisting with the valuation of variations.
Provide a basis for the valuation of interim payments.
Provide a basis for the preparation of the final account.
11
P - Building fabric sundries.
Q - Paving, planting, fencing and site furniture.
R - Disposal systems.
S - Piped supply systems.
T - Mechanical heating, cooling and refrigeration systems.
U - Ventilation and air conditioning systems.
V - Electrical systems.
W - Communications, security, safety and protection systems.
X - Transport systems.
Y - General engineering services.
Z - Building fabric reference specification.
Bills of quantities are most useful to the contractor when they are prepared in work sections that reflect likely sub-contract packages.
This makes it easier for the contractor to obtain prices from sub-contractors and is more likely to result in an accurate and competitive
price.
The bill of quantities should identify the different kinds of work required, but should not specify them as this can lead to confusion
between information in the bill of quantities and information in the specification itself.
Disputes can occur where there is discrepancy between the bill of quantities and the rest of the tender documents (for example where
an item is included in the drawings and specification but not in the bill of quantities), or where there has been an arithmetical error.
Generally the priced bill of quantities will take precedent, and the client will be responsible for their own errors or omissions, which
may be classified as relevant events (or compensation events) giving rise to claims for an extension of time and loss and expense.
However if an ambiguity or error is noticed by the contractor during the tender process, it is best practice for them to tell the client,
even if there may be some commercial advantage to them not doing so.
Increasingly, software packages are available to assist in the preparation of preparation of bills of quantities, and building information
modelling systems can be used to produce bills of quantities from information already contained within the model.
Bills of quantities are normally only prepared on larger projects. On smaller projects, or for alteration work the contractor can be
expected to measure their own quantities from drawings and schedules of work. Schedules of work are 'without quantities'
instructional lists that allow the contractor to identify significant work and materials that will be needed to complete the works and to
calculate the quantities that will be required.
12
Approximate bills of quantities can also be used during the design process as a tool for controlling design. They are then sometimes
included in the tender documents as a guide with a caveat stating that responsibility for measuring quantities lies with the contractor,
and drawings and specifications take priority over any description in the approximate bills (see Approximate quantities cost plan).
3.0 Contract
For implementation of the construction works of a project, an agreement, commonly called a contract, between Client and Contractor
should be concluded which requires that certain legal formalities be observed by the parties.
What is a contract?
A contract is an agreement between two or more parties which creates reciprocal legal obligations to do or not to do particular things.
For it to be valid there must be mutuality of purpose and intention. The nature and content of contracts vary from country to country
and the terms of the contract should be precise and definite and there should be no room for ambiguity or misconstruction therein. To
avoid this contingency, the government department and agencies as well as the Association of Consulting Engineers or the Institutions
of Civil Engineers have established standard printed contract forms (Abrahamson, 1969).
13
(iii) The Contractors work out the unit prices of all items of the Bill of Quantities in order to put them in the bid. Thus, an unworkable
rated tender may be avoided, which leads to smooth progress and timely completion of the work.
2. Lump-sum contract
In this form of contract the Contractor is required to quote a fixed sum for execution of the work completed in all respects. For such a
contract, it is very important that the drawings and specifications be comprehensive and show in complete detail all features and
requirements of the work.
Advantages of lump-sum contract;
(i) The employer knows exactly what the work will cost.
(ii) Detailed measurements of the work executed are not required to be recorded except in respect of additions and alterations.
3. Contract with lump-sum and unit prices
In this form of contract the Contractor is required to quote partly a fixed sum for execution of an entire structure completely detailed
on the drawings, and partly unit prices which may be required for features of variable quantities such as excavation of drains for
ponds.
4. Negotiated contract
When work is awarded on contract by mutual negotiation between the parties without call of tenders, it is said to be a negotiated
contract. It may be in any of the forms mentioned above. Advantages of this contract are that it brings some economy in expenditure.
The parties selected being always reliable and financially sound, ensure interrupted work with less chance of dispute.
14
Tenders documents may include:
A letter of invitation to tender
The form of tender.
Preliminaries (including pre-construction information and site waste management plan).
The form of contract, contract conditions and amendments. This might include a model enabling amendment if building
information modelling (BIM) is being used, to make a BIM protocol part of the contract documentation.
Employer's information requirements if BIM is being used.
A tender pricing document (or contract sum analysis on design and build projects).
A drawing schedule.
Design drawings, and perhaps an existing building information model.
Specifications.
15
DEVELOPMENT
CORPORATION LIMITED.
IKOLE EKITI CAMPUS -751002
TENDER CALL NOTICE
No. CAD-385K: - Managing Director, FUOYE Fish Seed Development Corporation Limited. IKOLE EKITI CAMPUS-2, FUOYE
invites sealed tenders for the following work from the registered contractors of State Public Works (R & B) and Irrigation
Departments; Name of work:- Construction of 10 hectare fish seed hatchery project at Ikole Ekiti. Cost of tender paper:- N30,000 (Son
refundable). Class of Contractor:- 'A' Class & above. Time of completion:-Twelve months. The tender paper will be sold during the
office working days up to 9-12-15 and will be received on 10-12-15 at 2 p.m. and will be opened on the same day at 2.20 p.m. in the
presence of the tenderer or their authorised representatives. Certified copy of the Sales Tax and Income Tax clearance certificates are
also to be attached and the original to be shown at the time of opening. The authority reserves the right to cancel any or all the tenders
without assigning any reason thereof.
MANAGING DIRECTOR
For smaller projects, an invitation for bids is issued by the owner to a selected group of Contractors. It conveys much of the
information that would be included in an advertisement. In this case, instructions to bidders should be provided in the letter of
invitation to the Employer.
4.2 Clarification
Mid-tender interviews may be arranged to allow clarification of matters that might otherwise lead to an inaccurate tender being
submitted, they can also give the client insights into potential problems or opportunities in the project as it is described by the tender
documentation.
Responses to queries raised during the tender process can lead to clarification or amendment of the tender documentation which may
also result in an extension of the tender period. It is better to allow sufficient time during the tender process to investigate
opportunities and clarify problems, as the resulting tenders will then be better prepared and will be likely to save time and money later.
It is important that any clarification, additional information or changes to the tender documents are circulated to all of the tenderers to
ensure a level playing field. However this should not give away a particular supplier’s proposed methodology, commercial proposals
or programming advantages, which may have been divulged to the client consultants in interviews. Such information must be treated
as confidential.
4.3 Submission
In response to an invitation to tender, invited tenderers will submit their tender, which will include their price for supplying the goods
or services along with proposals for how the clients requirements will be satisfied if these have been requested.
The precise content of tenders will vary considerably depending on procurement route, however they might include:
A tender return slip, with details of the contract, return address, tender checklist etc.
A completed tender pricing document (or contract sum analysis on design and build projects).
Schedules of rates.
16
An initial construction phase plan.
Any design proposals or method statements that have been requested.
Alternative or non-compliant proposals. These should only be submitted if they have been requested and should be
accompanied by a compliant proposal.
4.4 Programme.
Procedures to be adopted such as procurement procedures, cost management procedures etc.
Demonstration of capability, for example design capability, systems used etc.
A BIM execution plan if building information modelling is being used.
Key project personnel.
Management organisation.
Plant and labour resources and availability.
Prior experience.
References.
4.5 Settlement
Once the client has identified the preferred tenderer (this may involve further interviews) they may hold a tender settlement meeting to
enter into negotiations. This may result in further adjustment of the tender documents and the submission of a revised tender.
Public Projects
On publicly-funded projects the procurement processes preferred by the Government Construction Strategy are all based on inviting
tenders from an integrated supply team (including designers, suppliers and contractors) to design, build and sometimes operate and
finance the development. On private finance initiative (PFI) projects, the process of securing offers from integrated supply teams is
referred to as 'bidding' rather than 'tendering'.
The prices submitted by each of the contractors are examined by the quantity surveyor and the project manager to ascertain what is
offered.
17
The reliability and financial stability of the contractor are vital considerations since the failure of a contractor is a major disaster from
the developer’s perspective as long delays occur while the legal position is resolved and another contractor is found to complete the
work.
18
The project manager should be continually satisfied about the arrangements made by the architect for site supervision during
construction.
The size and complexity of the scheme may merit the appointment of a full-time site supervisor, such as a clerk of works or a resident
engineer or indeed a resident architect.
19
4.13 Handover of the Completed Development
A short time before the date for completion and handover of the building from the contractor to the developer, the architect prepares a
list of all minor defects that must be remedied before handover occurs.
If the development has been pre-let or pre-sold to an owner-occupier, then the occupiers and/or their contractors may wish to have
access before formal handover by the main contractor working for the developer.
The project manager, with the architect, needs to attribute and resolve problems quickly.
The quantity surveyor should then be asked when any outstanding re-measurement work will be completed and be in a position to
agree the final account with the contractor, so that the architect may issue a final certificate.
The importance of inspecting the site and its immediate environs on the handover date should not be overlooked.
Where an occupier is not taking possession immediately, then the developer is responsible for a vacant building and a programme of
regular cleaning and maintenance should be instigated.
20
Any delays in completion or increase in costs will affect the profitability of the development; therefore it is essential that a developer
is kept regularly informed on progress and cost.
Typical reporting methods include: bar (or Gantt) chart (Figure 7.1), cashflow table and graph, financial report, checklist.
Whilst regular reporting on progress and cost is a way of keeping the developer informed, it also provides the project manager with an
essential tool, especially if the developer insists on regular reporting. The project manager will know whether the aims are being
achieved and it will bring into sharp focus the targets that need to be achieved and the problems that need to be tackled.
5.1 PARTNERING
Clients, designers and contractors have evolved their relationships with developments and developed different types of business
relationships, among these is partnering.
Partnering is a business relationship for the benefit of all parties, built on trust, openness and respect.
There is a requirement to develop an environment for long-term profitability and to encourage innovation.
Partners commit to improved project build ability and a lowering of project costs through the process of value management.
21
Provisional sums should not be confused with prime cost sums, which are allowances for the supply of work or materials to be
provided by a contractor or supplier nominated by the client. Prime cost sums might include items that have already been purchased
by the client, such as equipment, or a specific installation by a company with a strong existing relationship with a client organisation.
It should be noted that courts have generally taken the view that risk in relation to the performance of a nominated sub-contractor lies
with the client and not the contractor. This means that delay to the overall programme caused by a nominated sub-contractor can lead
to a claim for extension of time under the main contract and entitlement to consequential losses.
Prime cost sums should not be confused with provisional sums which are allowances for specific elements of the works not yet
defined in enough detail for contractors to price.
5.6 Budget
Budgets for projects should be set as early as possible.
A budget can be established by:
Assessment of projected income and expenses through the life of the project.
Comparison with similar projects.
Assessment of the funds available.
Pre-design analysis of requirements.
Analysis of preliminary design options.
The budget is set by the client and is distinct from cost plans prepared by a cost consultant which are likely to focus on the
construction cost.
The client's total project budget may include:
The construction cost.
Land or property acquisition and Approvals fees.
Planning costs or Community Infrastructure Levy).
Financing costs.
Site investigations.
Fixtures, fittings and equipment.
The cost of decanting and relocating, including costs associated with moving staff.
23
Contracts outside of the main works.
Insurance and Consultant fees.
Inflation and Contingency.
VAT.
It is important that the client makes clear what costs should be monitored by the cost consultant and what will remain within the
control of the client organisation.
24