Retrofit of The Heat Recovery System of A Petroleum Refinery Using Pinch Analysis
Retrofit of The Heat Recovery System of A Petroleum Refinery Using Pinch Analysis
Retrofit of The Heat Recovery System of A Petroleum Refinery Using Pinch Analysis
ABSTRACT
Energy efficiency has become an important feature in the design of process plants with the rising cost of energy and the
more stringent environmental regulations being implemented worldwide. In South Africa, as elsewhere, most process
plants built during the era of cheap energy place little emphasis on the need for energy recovery due to the abundance of
cheap utilities sources such as coal. In most of these plants, there exist significant potential for substantial process heat
recovery by conceptual design of the heat recovery system. By maximizing heat recovery from the processes, there will
be a reduction in the process utilities requirement and the associated environmental effects. Pinch analysis has been
demonstrated to be a simple but very effective tool for heat integration and optimization of chemical plants. This study
uses the pinch principle to retrofit the heat exchanger networks (HEN) of the crude distillation unit of an integrated pe-
troleum refinery to evolve a HEN that features optimum energy recovery. The network was further relaxed by trading
off energy cost with capital cost to obtain an optimal HEN topology not too different from the existing network. The
simulation works were implemented in AspenPlus v8.0 environment. Analysis revealed that 34 per cent saving on
energy usage per annum is realizable. This significant saving in energy also results in diminished gaseous pollutants
associated with energy usage.
Keywords: Plant Retrofit; Heat Integration; Crude Distillation Unit; Heat Exchanger Network; Pinch Analysis;
Optimization; Remaining Problem Analysis
[10] consumed the most energy in a refinery, consuming obtained. A detailed modelling and simulation of the unit
as much as 2 per cent of the total crude oil processed [11]. was carried out in AspenPlus v8.0 environment for con-
It is therefore expected that the use of PT to analyze the vergence test to reconcile the streams enthalpy data. The
energy recovery system of the CDU will reveal better enthalpy data required were extracted. This was done in
matches for process energy transfer, and hence saves on order to scope the existing network for potential energy
utilities usage and the associated environmental benefits, and cost savings. Thermodynamic profiles of the process
for instance, the emission of obnoxious pollutants. It in- streams using the Problem Table algorithms, Composite
vestigated the potential saving in utility usage in the crude Curves and Grand Composite Curves were studied to
distillation unit of a petroleum refinery. A preliminary determine the targets for the hot and cold utilities and the
energy audit of the plant was carried out using AspenPlus position of the pinch. This profile also indicated the
v8.0 to locate the unit with highest utility requirement maximum energy recovery possible at the chosen ∆Tmin..
and offers the most potential energy savings. The Re-
maining Problem Analysis (RPA) variant of the Pinch 3.2. Maximum Energy Recovery Network Design
Technology was applied to locate and reassigned only
The existence of a topology trap was first investigated by
the heat exchangers that are inefficiently placed.
studying the influence of ∆Tmin on the utilities require-
2. Process Heat Integration ment. This is also used to obtain an optimum ∆Tmin for
the retrofitting study.
A design of an efficient and cost effective process heat To achieve the target obtained above, a new heat ex-
recovery system employing series of heat exchangers will changer network featuring maximum energy recovery
promote efficient utilities usage and requirement leading (MER) was obtained using the remaining problem analy-
to savings in energy cost [12]. The practical importance sis approach as developed by Tjoe and Linnhoff [15].
of HENs can be found in the fact that most industrial Retroffiting of HEN is agreed upon (for instance [5]) to
processes involve transfer of heat, either from one process be more tasking than grassroot design. For the results of
stream to another process stream or from a utility stream the retrofit project to be implementable, the resulting
to a process stream [13,14]. Consequently, the target in networks while featuring significant energy savings must
any industrial process design is to maximize the process- not be markedly different from the existing networks.
to-process heat recovery and to minimize the utility re- Otherwise the modification required will be major and
quirements. To meet this goal, cost-effective HEN con- costly offsetting the targeted saving in energy cost. Re-
sisting of one or more heat exchangers that collectively main problem analysis as a technique for retrofitting of
satisfy the energy conservation task, is of particular im- the HEN is an essential principle to develop an optimized
portance. HEN close to the existing plant topology. This is neces-
The use of Pinch Technology (PT) for retrofitting and sary because of layout considerations and the cost impli-
grassroot designs, has been found to result in considera- cations of matches.
ble saving for instance in energy usage. This saving di- The methodology will keep as much as possible to the
rectly improves the economics of the plant. Pinch tech- existing topology of the plant, meaning the exchangers
nology is one of the least complicated and most effective that did not violate the pinch were left untouched. This
technologies for Heat Exchanger Networks (HEN) de- entails identifying the heat exchangers working across
sign in the energy recovery and optimisation of energy the pinch and hence inefficiently placed or streams that
within the chemical plant. It is based on sound thermo- were inefficiently matched while leaving the other heat
dynamic principles without including heavy mathemati- exchangers intact. The objective of the evaluation of the
cal calculations and interpretations. The use of pinch tech- existing network was to use the existing area within this
nology for plant modification is centered on the trade-off network more effectively. This was done to identify the
between the savings in utilities versus the cost of the area used due to criss-crossing [15]. The new network
proposed changes in the plant. The “pinch” point represents
features maximum energy recovery.
the bottleneck of heat recovery. The key concept of pinch
analysis is the setting of energy targets [9] with the aim
3.3. MER Network Relaxation
to achieve maximum energy saving by maximising process
to process heat recovery and minimising the use of hot An optimization of the process was done for possible
and cold utilities. network relaxation. A trade-off looking at the existing
process and the MER design was carried out focusing on
3. Methods the investment and energy costs. The MER network was
examined for possible network simplification, by identi-
3.1. Data Extraction and Energy Target
fying and removing loops to trade-off capital cost of the
The design and operating data of the refinery unit were required heat transfer unit and energy cost of the saved
utilities. This eventually entails reducing the number of ing these exchangers. Using the remaining problem analy-
the heat transfer unit thus reducing capital costs while sis approach, the network in Figure 4 was obtained. The
sacrificing some energy recovery. A comparison of the complete heat exchanger network design represents max-
cost implications of the various networks was presented. imum energy recovery of the process heat utilizing as
many as required heat transfers unit including heat ex-
4. Results changers, heaters/furnace and coolers. This network real-
The composite curve from the enthalpy data is presented ised the utilities targets set above.
in Figure 1. From the composite curve, it could be seen The relaxation process of the network is an important
that the overlapping of the cold composite and the hot part in the optimization of the network. The purpose of
composite curve indicates a high possibility of process to this step is not to eliminate all the loops and paths but to
process heat exchange. The minimum utilities require- rather reduce the paths and loops. This step involves the
ments for the plant are 72 MW and 64 MW for the hot removal of heat exchangers by allowing a small energy
and cold utility respectively at a ∆Tmin of 15˚C. This pre- penalties leading to a reduction of units within the net-
sented about 34 per cent potential reduction in utility work thus reducing capital costs. The ultimate aim is to
requirement. There is only one pinch point, 235˚C and find a balanced heat exchanger network, keeping as best
225˚C for hot and cold streams respectively. as possible the topology maximising the energy duties
In Figure 2, the plot of the cold and hot utilities at between the streams whilst not incurring heavy capital
different ∆T min shows a linear relationship with no dis- costs related to the heat exchanger areas. This network
continuity within the range. This signified the absence of has minimum impact on the current configuration of the
a topology trap. The absence of a topology trap means plant, whist giving a substantial 34 per cent saving on
that the need for a detailed cost analysis to determine the utilities.
optimum ∆Tmin using different algorithms and graphs is In the MER network, there are a number of loops and
not necessary. paths, the target of the relaxation step for this design is
The grid diagram for the existing network is presented not to remove some or all of these loops and paths. The
in Figure 3. It shows that seven exchangers are working final relaxed network is presented in Figure 5. This net-
across the pinch. Hence, there is no maximum energy work has six less heat transfer unit compared to the MER
recovery and there is no efficient use of the existing heat design.
exchangers. The cost implication of the various networks is as pre-
The focus of the study is concentrated only re-assign- sented in Table 1.
Figure 3. The existing heat exchanger network showing across the pinch violation.
5. Conclusion REFERENCES
In the current economic climate, with the rising cost of [1] D. S. Selvakkumaran and B. Limmeechokchai, “Energy
fuel that provides the industrial plants with their heating Security and Co-Benefits of Energy Efficiency Improve-
ment in Three Asian Countries,” Renewable and Sus-
and cooling needs, it has become imperative that the
tainable Energy Reviews, Vol. 20, 2013, pp. 491-503.
plant becomes more energy efficient. This study confirmed
that Pinch Technology is a very practical, easy and intui- [2] D. von Hippel, T. Suzuki, J. H. Williams, et al., “Energy
Security and Sustainability in Northeast Asia,” Energy
tive method for attaining better process heat integration. Policy, Vol. 39, No. 11, 2011, pp. 6719-6730.
The existing HEN had a number of heat exchangers http://dx.doi.org/10.1016/j.enpol.2009.07.001
working across pinch; these violations were eliminated [3] X. Liu, D. Chen, W. Zhang et al., “An Assessment of the
during the retrofitting. The final evolved HEN reveal a Energy-Saving Potential in China’s Petroleum Refining
potential 34 per cent energy saving in the plant section Industry from a Technical Perspective,” Energy, Vol. 59,
studied. A trade-off was explored to find a balance of 2013, pp. 38-49.
utilities usage, number of exchanger units and area. This [4] M. M. El-Halwagi, “Chapter 22—Macroscopic Approaches
was done by using the heat load loops and paths. The of Process Integration,” Sustainable Design through Pro-
effect of pressure in the evolved HEN network was not cess Integration, Butterworth-Heinemann, Oxford, 2012,
investigated. This must be considered before implement- pp. 375-391.
http://dx.doi.org/10.1016/B978-1-85617-744-3.00022-9
ing the recommendations. Alternative methods must also
be used to verify the findings of this study such as mathe- [5] Y. Kansha, A. Kishimoto and A. Tsutsumi, “Application
of the Self-Heat Recuperation Technology to Crude Oil
matical optimisation methodologies. In conclusion, pinch
Distillation,” Applied Thermal Engineering, Vol. 43, 2012,
technology is still an important method for evaluating pp. 153-157.
and scoping for potential energy saving in a chemical http://dx.doi.org/10.1016/j.applthermaleng.2011.10.022
plant. It is particularly relevant today, due to the high [6] H. Zhang and G. P. Rangaiah, “One-Step Approach for
cost of utilities and the adverse environmental impact of Heat Exchanger Network Retrofitting Using Integrated
energy usage by industries. Differential Evolution,” Computers & Chemical Enginee-
ring, Vol. 50, 2013, pp. 92-104.
6. Acknowledgements http://dx.doi.org/10.1016/j.compchemeng.2012.10.018
[7] M. Escobar and J. O. Trierweiler, “Optimal Heat Ex-
The authors acknowledge the supports provided by Cape changer Network Synthesis: A Case Study Comparison,”
Peninsula University of Technology, Nigerian National Applied Thermal Engineering, Vol. 51, No. 1-2, 2013, pp.
Petroleum Corporation (NNPC) and the management of 801-826.
Warri Refinery and Petrochemical Complex, Nigeria. http://dx.doi.org/10.1016/j.applthermaleng.2012.10.022
[8] M. Gorji-Bandpy, H. Yahyazadeh-Jelodar and M. Khalili, in Process Integration,” Energy Optimization in Process
“Optimization of Heat Exchanger Network,” Applied Systems and Fuel Cells, 2nd Edition, Elsevier, Amster-
Thermal Engineering, Vol. 31, No. 5, 2011, pp. 779-784. dam, 2013, pp. 465-474.
http://dx.doi.org/10.1016/j.applthermaleng.2010.10.026 http://dx.doi.org/10.1016/B978-0-08-098221-2.00012-6
[9] I. C. Kemp, “Pinch Analysis and Process Integration-A [13] P. Rašković and S. Stoiljković, “Pinch Design Method in
User Guide on Process Integration for the Efficient Use of the Case of a Limited Number of Process Streams,” Energy,
Energy,” Butterworth-Heinemann, 2007. Vol. 34, No. 5, 2009, pp. 593-612.
[10] M. Gadalla, D. Kamel, F. Ashour and H. M. El Din, “A http://dx.doi.org/10.1016/j.energy.2008.04.004
New Optimisation Based Retrofit Approach for Revamp- [14] S. Sieniutycz and J. Jeżowski, “13-Maximum Heat Re-
ing an Egyptian Crude Oil Distillation Unit,” Energy covery and Its Consequences for Process System Design,”
Procedia, Vol. 36, 2013, 2013, pp. 454-464. Energy Optimization in Process Systems and Fuel Cells,
[11] M. Errico, G. Tola and M. Mascia, “Energy Saving in a 2nd Edition, Elsevier, Amsterdam, 2013, pp. 475-497.
Crude Distillation Unit by a Preflash Implementation,” http://dx.doi.org/10.1016/B978-0-08-098221-2.00013-8
Applied Thermal Engineering, Vol. 29, No. 8-9, 2009, pp. [15] T. N. Tjoe and B. Linnhoff, “Using Pinch Technology for
1642-1647. Process Retrofit,” Chemical Engineering, 1986, pp. 47-
http://dx.doi.org/10.1016/j.applthermaleng.2008.07.011 60.
[12] S. Sieniutycz and J. Jeżowski, “12-Heat Integration with-