Assignment 4 - Network Analysis
Assignment 4 - Network Analysis
________________________________________________________________________________________
Please note following:
t o = Optimistic time ; t m= Normal time; t p= Pessimistic time
Activity 1-2: Activity 1 must be finished before activity 2 start
Question 1
Activity to tm tp Activity t0 tm tp
1-2 1 2 3 5-7 4 5 6
2-3 1 2 3 6-7 6 7 8
2-4 1 3 5 7-8 2 4 6
3-5 3 4 5 7-9 4 6 8
4-5 2 3 4 8-10 1 2 3
4-6 3 5 7 9-10 3 5 7
Question 2
The activity data for a project are given below
Activity A B C D E F G H I
(1-2) (1-3) (1-4) (2-5) (2-6) (3-6) (4-7) (5-7) (6-7)
Least Time 5 18 26 16 15 6 7 7 3
Greatest Time 10 22 40 20 25 12 12 9 5
Most Likely Time 8 20 33 18 20 9 10 8 4
Determine the following:
a) Expected task time and variance
b) The earliest and latest expected time to reach each model
c) The critical path and
d) The probability of node occurring at the proposed completion date if the original contract time of
completing the project is 41.5 weeks
Page 1 of 2
Question 3
Consider the network consisting of the following activities
Activity t0 tm tp Activity t0 tm tp
1-2 1 2 9 4-5 4 6 8
2-3 1 4 7 4-6 3 5 7
2-4 2 4 12 5-6 ½ 1 3/2
3-4 0 0 0 5-7 5 7 15
3-5 2 3 4 6-7 3 5 13
3-7 6 8 16
Question 4
Following table list the data for PERT network
Activity (I-J) 1-2 1-3 1-4 2-3 2-5 3-4 3-6 4-6 5-6
O(days) 2 6 6 2 11 15 3 9 4
M(days) 4 6 12 5 14 24 6 15 10
P(Days) 6 6 24 8 28 45 9 27 16
a) Draw the network, estimate the earliest and least event times for all nodes and hence derive critical
path
b) Estimate expected duration of the project and the corresponding variance
c) What is the probability that the project duration will exceed 60 days?
Question 5
Table below gives list of activates along with predecessors and three time estimates
Activity Predecessors Activity Optimistic Dates Normal Dates Pessimistic Dates
1 - 2.5 4 6
2 1 5.5 7 9
3 1 3.5 5 7
4 1 4.5 6 8
5 2 0.5 2 4
6 3 1.5 3 5
7 5 3.5 5 7
8 2,6 9.5 11 13
9 7,8 5.5 7 9
10 3 2.5 4 6
11 4 1.5 3 5
12 9,10,11 2.5 4 6
Page 2 of 2