A Bottom Area
1 Check the Cleaning of top Surface of P.C. C.
2 Treatment of Construction Joints.
3 Placing of Pressure release Pipes ‐ "B" class ‐ 25 mm dia, if any
4 Placing of Shahbad Stones :
a Check Mortar Proportion ‐ 1:4
b Check Admixture proportion ‐ / bag of Cement
c Check thickness of Tiles ‐ 15 ‐ 20 mm thk
5 Sealing of Joints between Tiles ‐ CM 1:1
6 Application of Final layer
a Check Mortar Proportion ‐ 1:3
b Check Admixture proportion ‐ / bag of Cement
c Check thickness of Final Layer ‐ 20 ‐ 25 MM
d Curing
B Dado Area
1 Cleaning the Surface of Raft, Retaining Wall
2 Hacking the R.C. C. Surface
3 Treatment of Construction Joints
4 Fixing of Shahbad Stones ‐ Max.1.00M ht in single day
5 Grouting of space between Wall & Tiles
a Check proportion of Cement Slurry with admixture ‐ / bag
6 Application of Water proof Plastser
a Check Proportion of Mortar ( 1:3 )
b Check Admixture proportion ‐ / bag of Cement
C SAFETY CHECKS
1 Ensure and check MSDS for the water proofing material is obtained.
Check the store personnel, employees handling this material are briefed the
2
safety requirements as per the MSDS.
Check that the material is stored at a designated place for prevention from
3
fire hazard etc.
INTEGRATED MANAGEMENT SYSTEM Doc. No.:
FORMATS Rev No.:
WATER PROOFING ‐ BASEMENT Rev Date:
Page No. ‐ 1 ‐ of
Name of Project Location Date
Name of Contractor: ‐
Check if the material is a flammable one. So smoking or any other hot work is
4
prohibited while handling, using or at the proximity of the material.
Check that the Employees using the water proofing material shall wear
5
rubber hand gloves, goggles/ face shield, Safety helmet and shoes.
Check that the Employees handling the material shall be dressed covering
6
them fully, to prevent the accident fall of the chemical on them.
Check and ensure Employees are informed the wash places to wash off the
7
chemical fallen on them.
Check If the water proofing work is done in a confined area the required
8
ventilation is ensured.