Project Risk Management and Procurement Management: Outcomes
Project Risk Management and Procurement Management: Outcomes
Module 5
136
E2 Project Management
Unknown risks: Risks that were not identified or that could not be
reasonably identified. Example; assassination of
the head of a country that leads to chaos in that
country.
Fixed price or lump Contracts with a fixed total price for the delivery
sum contracts: of a well-defined product (e.g. $20 million for the
construction of a five-storey office building with
related specifications) or service ($2,000 per
machine for the rental and servicing of office
photo-copier machines).
Unit price contracts: Contracts where the total value of the contract is a
function of the quantities needed to complete the
work. Example; $1,200.00/ton of cement.
137
Module 5
Required Reading
Reducing Project Management Risk:
http://www.netcomuk.co.uk/~rtusler/index.html
Reading
138
E2 Project Management
A source of risk is any factor that can affect project performance, slow
down or stop the project. Considerations are probability of the occurrence
and the impact to the project should the risk occur.
6
PMI – Project Management Institute ™
139
Module 5
140
E2 Project Management
The project manager is responsible for initiating and leading the process
of project risk management. In other words, the project manager must
ensure that risk management happens. This would include ensuring that
risk management is integrated into all aspects of project management,
such as the project plan or the change control process.
While the project manager initiates, leads, and provides direction for risk
management, the team members are responsible for carrying out risk
management as they are also the ones who actually do the work. The risk
management activities carried out by the team would include performing
risk identifying and analysing risks, developing response strategies and
carrying them through when necessary, and controlling risk. The team
members must then communicate on a consistent and frequent basis to
the project manager, the findings, strategies, and actions.
The project sponsor and the project steering committee have a role in the
risk management process. They must agree to the risk management plan
developed by the project team and the project manager and these are the
people that the project manager notifies when a risk is identified.
Agreement is essential to ensure that both the sponsor and any steering
141
Module 5
committee understand the types and nature of the risks the project is
exposed to and how the team plans to address the risks. In essence,
agreement is a sign-off process thereby reducing the element of surprise
should a risk occur.
142
E2 Project Management
All processes interact with each other and with all knowledge areas
within the PMBOK. The PMBOK also defines inputs, tools and
techniques and outputs for each of the processes identified within risk
management.
143
Module 5
7
The Standish Group. (1996) Unfinished Voyages (www.standishgroup.com/voyages.html)
144
E2 Project Management
Risk identification
Risk events are specific things that may occur to the detriment of the
project (significant changes in project scope, strikes, supply shortages,
etc.). To characterise or define a risk event you need to examine and
document the following parameters.
1. What is the probability of occurrence?
2. What is the impact to the project or the outcome if it does occur
(severity)?
3. When might it occur?
4. How often might it occur (frequency)?
Risk symptoms are the indicators or triggers for the actual risk event. For
example, cost overrun may be symptomatic of poor estimation, or
product defects may be symptomatic of a poor quality supplier.
Identification and documentation of potential risk symptoms provides a
diagnostic tool for project teams and suggests potential corrective action.
Risk qualitative and quantification assessments
PERT Estimations
145
Module 5
Monte Carlo analysis also uses pessimistic, optimistic, and most likely
estimates and the probabilities of their occurrence. Simulations such as
these are a more sophisticated method for creating estimates than PERT
and can more accurately help determine the likelihood of meeting project
schedule or cost targets. Many organisations globally use Monte Carlo
simulation for risk analysis. PC software programmes like @RISK
provide Monte Carlo simulation capability to project management
software like MS Project and to standard PC spread sheets.
Expert Judgment
Many firms use the past experience and intuition of experts in lieu of or
as a supplement to quantitative risk analysis. One common approach to
gathering expert opinion is the Delphi method, used to derive a consensus
among a panel of experts to make predictions about future developments.
The method uses repeated rounds of questioning including feedback of
earlier responses to take advantage of group input to refine the response.
The process is continued until the group responses converge to a specific
solution. This method works well in developing probability assessments
for risk events.
Here we are 100 per cent aware of what the states of nature will be and
the respective outcome. Say we have three strategies and each one has the
146
E2 Project Management
States of Nature
Strategy N1 = Up N2= Even N3=Low
S1 $50 $40 -$50
S2 $50 $40 $60
S3 $100 $80 $90
Obviously strategy S3 will always yield high profits then other two. So a
project manager would always select S3 in this situation.
2. Decision-making under risk
States of Nature
Strategy N1 = Up N2= Even N3=Low
0.25 0.25 0.5
S1 $50 $40 -$50
S2 $50 $50 $40
S3 $100 $80 $90
Calculation:
So based on the expected value, the project manager will select strategy
S3 with highest yield $90.
147
Module 5
States of Nature
Strategy N1 = Up N2= Even N3=Low
S1 $50 $40 -$50
S2 $50 $50 $40
S3 $100 $80 $90
148
E2 Project Management
Regret table
Strategy N1 = Up N2= Even N3=Low
S1 $100-$50 $80 - $40 $90 - (-$50)
S2 $100 - $50 $80 - $50 $90 - $40
S3 $100 - $100 $80 - $80 $90 - $90
Regret table
Maximum
Strategy N1 = Up N2= Even N3=Low
regrets
S1 $140 $50 $40 $140
S2 $50 $50 $30 $50
S3 $0 $0 $0 $0
The savage criterion would select strategy S3, the minimum of all.
d. Laplace criterion (uncertainty is converted into risk)
We can explain this using the same example from section (2) with
probability 1/3.
States of Nature
Strategy N1 = Up N2= Even N3=Low
0.33 0.33 0.33
S1 $50 $40 -$50
S2 $50 $50 $40
S3 $100 $80 $90
Calculation:
149
Module 5
The following matrix depicts risk response strategies for technical, cost,
and schedule risks:
Technical Risks Cost Risks Schedule Risks
Emphasise team support and
Increase the frequency of Increase the frequency of
avoid stand-alone project
project monitoring project monitoring
structure
Increase project manager Use WBS and Network Use WBS and Network
authority Diagram/CPM Diagram/CPM
Improve communication
Select the most
Improve problem handling project goals
experienced project
and communication understanding and team
manager
support
Increase the frequency of Increase project manager
project monitoring authority
Use WBS and NETWORK
DIAGRAM/CPM
150
E2 Project Management
Contingency plans are predefined actions that the project team will take
if an identified risk event occurs.
Risk response control involves responding to risk events over the course
of the project by executing the risk management plan and risk
management processes.
This requires on-going risk awareness and monitoring. New risks may be
identified during the course of the project and should go through the same
risk assessment process as those identified in advance. When contingency
plans are not in place or an unplanned risk event occurs, a workaround or
temporary fix may need to be found.
Top ten risk item tracking is a communication tool used for maintaining
awareness of risk throughout the life of a project. It consists of a periodic
review with management and the customers of what they feel are the
period’s most significant risk items. A risk-tracking chart is developed
that shows current and previous month’s top ten risks.
151
Module 5
152
E2 Project Management
Procurement planning
Project procurement planning is the process of identifying which project
needs can best be met by using products or services outside of the
organisation. Key questions are:
1. Do we outsource?
2. How do we outsource?
3. What to outsource?
4. How much to outsource?
5. When to procure?
153
Module 5
Statement of Work
Solicitation planning
Solicitation planning involves preparing the documents needed for
soliciting goods or services and determining the evaluation criteria for
154
E2 Project Management
Solicitation
Solicitation involves obtaining proposals or bids from prospective
vendors. Organisations may advertise their desire to procure goods or
services in a number of ways including newspaper ads, Internet bid sites
or through private solicitation to a known and trusted vendor.
155
Module 5
Source selection
Source selection involves evaluating bidders’ proposals, choosing the
best one, negotiating the contract, awarding the contract and notifying the
successful and the unsuccessful bidders. Formal proposal evaluation
sheets help to quantify and simplify the selection process. Caution should
be taken not to place too much emphasis on the technical aspects of the
proposal. It also has to be well managed. If a number of proposals have
been received, an iterative selection procedure is often used in which a
short-list is created in the first round of evaluations and then a final
selection made from the short list. Short-listed candidates may be invited
to make a presentation to the evaluation/selection committee and/or asked
to prepare a best and final offer (BAFO). The final output from the source
selection is a contract that binds the vendor to provide specific goods and
services and obligates the buyer to pay for them. Unsuccessful bidders
should be notified and provided an opportunity to discuss the
shortcomings of their proposals.
Contract administration
Contract administration entails managing the relationship with the vendor
to ensure that the vendor’s performance meets contractual requirements.
A contract is a legal document and should have scrutiny by a legal
professional. The project manager and project team should be involved in
drafting and administering the contract.
156
E2 Project Management
Contract close-out
Contract close-out is defined as completion and settlement of the
contract, including resolution of any open items.
157
Module 5
Module summary
In this module you learned two broad and critical areas in project
management, namely risks management and procurement management.
Project risk management is both an art (personal judgement and
experience) and science (based on past data and calculation). Each
Summary complements the other in identifying, assessing and responding to project
risks. Project risk management is critically important at the planning
stage of a project where the major risks events are identified and counter
measures taken. But the risk management does not end at the planning
stage, it is continuously conducted throughout the project by the project
team.
Project procurement management covers the needs for procurement and
the key procurement processes. As the nature and needs of one project
tend to be different from another, most pure project-based organisations
tend to be “light” on assets, i.e. own few fixed assets. This has made
procurement management a critical function in securing the needed
resources to meet the needs of each new project. As you have seen,
procurement management serves as an important function to reduce costs
by maximising resource flexibility.
158
E2 Project Management
Assignment
1. With the aid of suitable examples, explain what types of purchases in
a project would be suitable for the following contracts:
a. Fixed price contract
b. Cost reimbursable contract
Assignment c. Unit price contract.
2. Why is risk assessment more difficult in a project environment when
compared to a non-project environment?
159
Module 5
Assessment
1. What is the importance of project risk management in project
management?
2. Identify the key stages of managing risk.
Assessment 3. How would a project team address an unanticipated risk event?
4. What are the implications of good risk management on the
organisation’s stakeholders?
5. Describe the different ways of solicitation in the procurement
process.
6. Why are the processes and procedures in project procurement
management important and what are the implications if they were
absent or not followed?
7. What are the advantages of outsourcing?
8. What are the downsides or risks of outsourcing?
160
E2 Project Management
Assessment answers
1. What is the importance of project risk management in project
management?
Risk is any factor that can affect project performance, slow down or
stop the project consequently threatening the goals and objectives of
the project. Risk management is critical to project management for
the following reasons:
Risk management is critical during the project planning
process as it may influence project design and project
activities throughout the life of the project
Risk management can anticipate future negative incidents
and their potential impact on the project. This will reduce
the amount of time spent on reactive and crisis management
The severity of risk impact increases as the project
implementation progresses and more resources (time and
money) are sunk in
Effective risk management raises the probability of
successfully meeting the project goals and objectives
Risk management impacts the stakeholders and project
sponsors by delaying delivery of products or services, and
reducing the expected returns of investments
Risk can be an opportunity. A superior technology untested
in the field is in itself a risk. Utilising the new technology
(should it prove to work well) will provide an opportunity
that the old technology is unable to provide.
2. Identify the key stages of managing risk
There are six main stages in the risk management process:
Risk Management Planning – deciding how to approach
and plan the risk
management activities for a project
Risk Identification – determining which risks might affect
the project and
documenting their characteristics
Qualitative Risk Analysis – performing a qualitative
analysis of risks and conditions to prioritise their effects on
project objectives
Quantitative Risk Analysis – measuring the probability
and consequences of risks and estimating their implications
for project objectives
Risk Response Planning – developing procedures and
161
Module 5
162
E2 Project Management
163
Module 5
164