Cost and Quality Management: Outcomes
Cost and Quality Management: Outcomes
Module 3
79
Module 3
Life cycle costing: Considers the total cost of the project including
both development (capital) costs, support
Terminology (maintenance) costs and disposal costs (when the
project is no longer useful).
Internal rate of return: Discounted (interest) rate that would make the net
present value of a project equal zero.
Sunk costs: Money that have already been spent and are likely
to be not recoverable.
Bottom-up estimating: Costs are estimated for individual work items and
then summed to get a total costs for the project.
Applicable for small projects only.
80
E2 Project Management
Required Reading
Cost Estimation, COCOMO II:
http://sunset.usc.edu/csse/research/COCOMOII/cocomo_main.html
Quality Management Works by Tony Yep (if available)
Reading
The Deming System of Profound Knowledge:
http://deming.org/index.cfm?content=66
81
Module 3
Because projects cost money and take away resources that could be used
elsewhere in the organisation, it is important for project managers to
understand project cost management.
82
E2 Project Management
If you know who’s doing what in your project, you’re halfway to a decent
estimate. To start the process of resource allocation, there are some
fundamental questions that a project manager needs to ask:
1. What skill set do you require to complete the major project
activities?
2. Who is available to complete the activities?
3. Do the available resources have the required skill sets to
complete the activities?
4. What level of authority do you need to free up internal resources?
Procure external resources?
5. How will the resources obtained affect the schedules and costs?
6. How will you use these resources?
The answers to these questions will go a long way toward driving how
your project performs in terms of scheduling and cost control. To further
clarify resource requirements use the WBS to plan out your resource
requirements. Then ask the question:
7. What level of excellence is essential given the project constraints
and the tasks identified?
83
Module 3
Personnel affect schedules and costs based on their hourly rate and their
ability to handle the tasks at hand (skill sets). These issues often drive the
differences as to whether or not an organisation can meet schedule or
quality demands of a project. The best and the brightest in any field often
cost more than those who are less professionally adept, which in turn,
drives costs.
Another factor for the project manager to consider is that the best
resources are always in demand and become over-allocated very quickly,
as they are often assigned too many projects. The project manager needs
to ensure that there is a clear understanding up front on the availability
and commitment of these resources for their project.
Project: xyz
P = Participant
A = Accountable
R = Review
I = Input
S = Signature required
84
E2 Project Management
Project calendars
Once the project resources have been identified and committed the focus
is now on establishing a project calendar. In today’s flexible work
environment, project team members work many different hours, shifts
and days. Project calendars must be established up front. Consistent work
calendars are necessary to ensure that tasks and resources are not
scheduled and applied on non-workdays. Project calendars also establish
a common frame of reference with the project sponsor, customer and the
team. This makes it essential that the project manager develops a project
calendar related to each resource on the project in order to ensure that
there is an accurate assessment of the project timelines. Here are some
key concepts to consider:
1. What are the working hours?
2. How about the teams?
3. How many hours do they work? Depending on the organisation,
some employees work seven, eight or ten-hour days and modified
work weeks.
Definitions (durations)
Effort hours: Total resource hours required to complete a task (24 hours
= three resource days) e.g. effort is three resource days if three people
work on a task that can be completed in eight hours
Elapsed time: Calendar durations including weekends, holidays, and
breaks (24 hours = one day)
Working time: Activity duration based on number of hours in a workday
or work week (24 hours = three days)
Productivity: Rate at which work is produced, e.g. if a resource is twice
as efficient it can get the work done in half the time.
85
Module 3
Task durations
The project manager can use different approaches to modify the project
duration that may allow the project manager to buy some time he/she did
not know existed.
The project manager must examine the established time frame for the
project and then establish the time frames for individual activities/tasks.
The project manager will need specific and accurate information to
ensure that the activity/task is completed within the time allotted and to
the agreed upon specifications. This can be accomplished by developing
project completion criteria. It is important to establish clear and agreed to
completion criteria for the project. Completion criteria are developed
from clear objectives that are specific, measurable, agreed upon, realistic
and time constrained. Each project activity must produce a defined
deliverable.
If the ideal resources are not readily available, it is often necessary to take
on lesser-qualified individuals. The project manager is then faced with a
challenge. This is where reviewing approaches to task duration will assist
the project manager. Usually, we only ask the standard question of how
long an activity will take without clearly understanding all of these issues
which are critical in controlling the project. Looking at the options for
task distribution will provide us with some ability to affect change by
modifying an activity. For example:
Must the activity bear a contiguous duration? Must it keep going?
Is the activity/task Interruptible? Can it be broken up or
interrupted?
86
E2 Project Management
Acquiring resources
How can the project manager gain commitment from functional managers
for critical project resources? Good planning and communication will
provide you with the best tools to get what you need, when you need it!
A project organisation has staff aligned around major projects. All the
people required for the project are assigned full time to the project
manager. The project manager is the functional head.
Matrix
87
Module 3
Conceptual Design 10 5 8 3 8
Prototype specification 12 15 1 2 6
Prototype design 10 5 8 3 10
Prototype development 30 21 15
Coding 35 24 14
This is only one example of how you might visually view the task
assignments. Project management tools such as MS Project ™ have
facilities to provide resource allocation reporting as well. By using a tool
such as the TAM, the project manager can plan out the activities in the
project schedule against the defined task duration and resource. A great
negotiating and communications tool!
88
E2 Project Management
Cost estimating
89
Module 3
Cost estimation for large projects is Recognise the need to re-do estimates at
complex and requires significant effort. various stages of project completion.
Cost estimates are often asked for Anticipate that later more accurate
before there is a clear understanding of estimates will likely be larger than earlier
the requirements. estimates. Use progressive resource
commitment and ‘stage gates’ as decision
points to weigh costs against anticipated
benefits. Don’t get caught in ‘escalation of
commitment’. Be prepared to kill a project
if the benefits no longer outweigh the
costs.
Human nature is to underestimate costs. Get peers and senior managers to review
Also easy to forget items on a large cost estimates and ask questions to
project. improve accuracy.
Cost budgeting
Project cost budgeting is the process of allocating the overall project cost
estimate to individual work items to establish a baseline for measuring
project performance. Required inputs are the WBS to identify individual
work items and the project schedule to allocate costs over time.
Cost control
90
E2 Project Management
Note it!
91
Module 3
The earned value for the entire project is determined by summing the EV
values for the individual project activities.
Often, the easiest way to evaluate project status and performance over
time is by displaying some of these key performance indicators in a
graphical form. (See example)
92
E2 Project Management
Example 1
Given:
Original Total Project Budget (BAC = $250,000 for a two year or 24-
month project)
Calculations:
Earned Value
Cost Variance = CV
Schedule Variance = SV
93
Module 3
(In other words, at the rate we’re going we will end up $30,899 over
budget.)
(In other words, at the rate we’re going we will end up six months behind
schedule.)
Example 2
If the original project duration was 18 months and total budget was
$35,000, can you calculate the estimated cost of completion and
estimated time to complete?
Calculation:
Earned Value
Cost Variance = CV
Schedule Variance = SV
94
E2 Project Management
The project is doing fairly well in cost and in serious trouble in time
perspective based on the performance to date.
95
Module 3
Dr. W. Edwards Deming gained his reputation for his work on quality
control in Japan after World War II. He taught that higher quality resulted
in greater productivity and lower cost. This is captured in the phrase “it’s
cheaper to do it right than to do it over”. Deming is known for his ‘Cycle
for Improvement – plan, do, check and act’ and his 14 Points for
Management. Also visit the following websites: http://www.deming.org
and http://www.qualitygurus.com/gurus/list-of-gurus/w-edwards-
deming/.
Juran
He developed what is known as the Juran Quality Trilogy and the 10-step
programme for quality improvement:
1. Quality improvement
2. Quality planning
3. Quality control.
96
E2 Project Management
Crosby
Philip Crosby is best known for suggesting that organisations strive for
zero defects and that the costs of not doing the job right in the first place
are so high that companies can afford to spend unlimited amounts on
improving quality. His book Quality is Free was first published in 1979.
In it, he developed 14 steps for quality improvement. In 1995, he
published Quality is Still Free: Making Quality Certain in Uncertain
Times.
Kaoru Ishikawa developed the concept of quality circles and the use of
fishbone diagrams. Quality circles are groups of non-supervisors and
work leaders in a single organisation department who volunteer to
conduct group studies on how to improve the effectiveness of work in
their department. Fishbone diagrams trace complaints about quality
problems back to the responsible production operations. His ideas were
published in a 1972 book entitled Guide to Quality Control.
97
Module 3
Taguchi
98
E2 Project Management
Quality planning
Key quality aspects that should be clearly defined in the scope and
business requirements of information technology projects are:
Functionality – the degree to which a system performs its
intended function.
99
Module 3
100
E2 Project Management
Pareto analysis
Pareto diagrams are histograms (bar graphs) that help to identify and
prioritise problem areas. Problems are grouped into categories; totals are
calculated for each category and then graphed as bar graphs to illustrate
the relative magnitude of each problem area.
Statistical sampling and standard deviation
Processes are deemed to be “in control” when deviations from the mean
are caused by random events. When non-random events occur, the graph
will trend above or below the mean and the process is said to be “out of
control”. The seven run rule says that any time seven data points in a
row are all above or below the mean, or are all increasing or decreasing it
is likely a non-random event is occurring and the process will run out of
control if corrective action is not taken. Sample control chart – mean is
depicted by the X on the chart and UCL = Upper control limit, LCL is
lower control limit.
101
Module 3
There are several other factors that can contribute to the quality of
projects. These include strong leadership, understanding the cost of
quality, providing a supportive workplace and working towards higher
maturity levels in project management.
Leadership
Juran and other quality experts argue that leadership is key to improving
quality. Senior management must take responsibility for creating,
supporting and promoting quality programmes.
Cost of quality
The cost of quality is defined as the cost of conformance plus the cost of
non-conformance, where conformance means delivering products that
meet requirements and fitness for use. The cost of non-conformance
means taking responsibility for failures or not meeting quality
102
E2 Project Management
We can draw a cost of quality curve to have trade off among all the
failure costs discussed.
103
Module 3
3
DeMarco, Tom and Lister, Timothy, (1987) Peopleware: Productive Projects and Teams, New
York, Dorset House.
104
E2 Project Management
Module summary
This module explains the concept of project cost management, the
principles and processes of cost management. There are two important
aspects in cost management; resource planning and resource acquisition.
The functions of project calendar in resource planning are essential.
Summary Consistent work calendars are necessary to ensure that tasks and
resources are not scheduled and applied on non-workdays. Project
calendars also establish a common frame of reference with the project
sponsor, customer and the team. This makes it essential that the project
manager develops a project calendar related to each resource on the
project in order to ensure that there is an accurate assessment of the
project timelines. Elements in project calendar are definition on duration
and task durations. The next stage is resource acquisition. After resource
planning is made, the project manager must acquire proper and adequate
resources. One of the alternatives undertaken by the project manager is by
allocating the individual to resource responsibility using the resource
responsibility matrix. After allocating the resource responsibility, other
tools such as cost estimating, cost budgeting, and control are used for
managing project cost. This module also describes the project
performance measurement such as EVA, Time Cost Project calculations.
Finally, the module incorporates the quality management philosophy in
project management by introducing quality gurus, quality planning,
assurance, and control concepts, and quality control tools and techniques.
105
Module 3
Assignment
1. What do you understand by statistical sampling and standard
deviation, and how are they applied to improve quality management
in project?
2. Explain the following indicators of the performance of a project:-
a. the Cost Performance Index; and
Assignment
b. the Schedule Performance Index.
106
E2 Project Management
Assessment
1. Define the following terms: BAC, EAC and ETC.
2. Discuss the Earn Value Analysis concept. Indicate the formula for
using EVA.
Assessment 3. What are the quality principles highlighted by Feigenbaum and
Taguchi?
4. What is quality planning? Identify the key quality planning inputs
and outputs.
5. Explain in detail the purpose of using control chart .How does control
chart work?
6. Describe in your understanding the meaning of acceptance decisions,
rework, and process adjustments.
107
Module 3
Assessment answers
1. Budget at Completion (BAC) – the original time and cost estimate.
Estimate at Completion (EAC) – an estimate of what it will cost to
complete the project based on performance to date. Calculated by
dividing the original project budget by the cost performance index.
EAC = BAC (cost)/CPI
Estimated Time to Complete (ETC) – estimated time it will take to
complete the entire project based on schedule performance to date.
Calculated by dividing the original total time or duration estimate for
the project by the schedule performance index.
ETC = BAC (time)/SPI
2. EVA is a project performance measurement technique that takes into
consideration project scope, time, and cost and compares actual
performance to a project baseline. The baseline is the original project
plan plus any approved changes. Earned Value Analysis requires the
calculation of three values for each activity of summary activity from
the work breakdown structure:
Budgeted Cost of Work Scheduled (PV- Planned Value) –
the amount budgeted for that activity
Actual Cost of Work Performed (AP – Actual Cost) – the
actual cost (direct and indirect) for that activity over a given
time period
Budgeted Cost of Work Performed (EV) or Earned Value –
the percentage of the work actually completed multiplied by
the planned cost.
The formula is:-
EV = PV x per cent of work actually completed (Per cent
complete obtained from person working on the actual work
package).
3. Taguchi
Dr. Taguchi is best known for developing what are known as the
“Taguchi Methods” and what he calls “Robust Design” methods. The
key principles are:
Focus on eliminating defects by using a scientific approach
(proactive) rather than trial and error to control product
quality (reactive).
Quality should be designed into a product rather than
inspected into it.
Quality is best achieved by minimising deviation from the
target value.
108
E2 Project Management
Feigenbaum
A.V. Feigenbaum developed the concept of total quality control
(TQC). The key principles are:
Responsibility for quality should lie with the people who do the
work. Workers should be empowered to stop production when a
quality problem occurs.
Building quality controls into every phase of operations -
product and service development, production, engineering,
marketing, distribution, sales, customer service; and
Driving communication and the implementation of quality
control strategies down and across organisational lines,
mobilising commitment at every level.
4. Quality planning consists of identifying which quality standards are
relevant to the project and determining how to satisfy them. Design
of experiments is a quality technique that helps identify which
variables have the most influence on the overall outcome of a
process. Quality planning inputs include:
Organisational policies
Project scope statement and product descriptions
Related standards and regulations
Key quality planning outputs are:
Quality management plan
Project quality checklists
5. A control chart is a graphic display of data that illustrates the results
of a process over time. Control charts are primarily used as a
monitoring and preventative (what has gone wrong) rather than a
diagnostic tool (why it has gone wrong). They are typically used to
monitor manufacturing processes but can also be used to monitor
project change requests, documentation errors, costs, and schedule
variances etc.
Sample Control Chart – mean is depicted by the horizontal line X on
the chart and UCL = Upper control limit, LCL is lower control limit.
Processes are deemed to be “in control” when deviations from the
mean are within the UCL and LCL. Processes are also deemed to be
in control if deviations out of the UCL and LCL caused by random
events. For example, the regular machine operator is on medical
leave and his place is taken by an untrained operator, this constitutes
a random event. When non-random events occur, the graph will trend
above or below the mean and the process is said to be “out of
control”. The seven run rule says that any time seven data points in a
row are all above or below the mean, or are all increasing or
decreasing it is likely a non-random event is occurring and the
process will run out of control if corrective action is not taken.
6. The meaning of acceptance decisions, rework, and process
adjustments are:
109
Module 3
110