Method - Statement - For RCC in Beams and Slabs
Method - Statement - For RCC in Beams and Slabs
CONSULTANT
MAIN CONTRACTOR
Project Title
Sl.
No. Contents
1 Purpose
2 Scope
4 Reference Documents
5 Abbreviations
8 Work Permits
10
Housekeeping
11
Quality Assurance & Control
12
Materials
13
Manpower
14
Work procedure
15
1.0 PURPOSE
The purpose of this Method Statement is to define the procedure for sequence of RCC Beam
and slabs.
.
The purpose of this Method Statement is to describe the measures and ways of completing
Rebar work for footings and pouring of concrete on this project. The works shall be carried
out in compliance with the drawings and project specification. It is intended to cut and bend
rebar on site as per the bar bending schedules.
2.0 SCOPE
This Method Statement applies to all the civil works – RCC work for Footing including
Excavation, ground preparation, setting out / Layout, backfilling, soil compaction,
concreting, waterproofing, masonry, plastering, joinery, painting and GRC works - related to
the construction of building as per project requirements, referring with approved Civil and
IFC drawing.
The primary responsibility of carrying out all the activities mentioned in this procedure rests
with the site- in-charge unless mentioned otherwise.
Project Manager: Overall execution and administration of the project as per contract
requirements, specifications and the PQP (Project Quality Plan). Liaise with the Head
(Quality & HSE) for preparation and updating of PQP. Directly control the Construction
Manager and Supervisors. He is responsible to ensure that all the correct procedures are
followed and all necessary permits for the works are obtained in advance.
Material Engineer: Responsible for the monitoring and implementing of quality related
matters and ensure the works are being executed with the approved Project Quality Plan and
requirements of the Contract Documents approved method statement and ITPs.
HSE Manager: Responsible for monitoring and implementation of safety related matters
such as work permits, First Aid, approval of diversions, follow the safety and traffic
regulations by all the workmen during the construction, according to the approved project
HSE plan. First Aid boxes are readily available with HSE inspectors and for site
requirements.
Charge hand: Works shall be executed as per direction of Supervisors/Foremen for all
activities as per the planned schedule to achieve target. Coordinate with respective
disciplines of work and liaise with the Supervisors/Foremen for day to day activities.
Ensure pre task briefing is conducted prior to start of work at each session.
5.0 ABBREVIATIONS
Site inspection/approval shall be in accordance with the approved Inspection and Test Plan
for all activities in addition to the Quality Control Procedure and Project Quality Plan for the
Project.
All the required site test shall be conducted as per applicable Parts of PQP.
Temperature, slump, unit weight and air content of fresh concrete shall be measured at the
point of pour, prior to placement in forms. Concrete not conforming to the requirements of
the specification shall be rejected. Test sample cylinders will be collected in accordance with
project specifications. Temperature of fresh concrete will be recorded in accordance with
specification requirement. Test Cylinders will be dated and numbered consecutively.
7.0 Equipment & Tools
The following equipments and tools shall be used for the various activities.
All necessary work permits shall be obtained prior to the commencement of any activity at
site and shall remain valid throughout the entire duration of the operation.
Safety Barriers and Site sign boards will be installed prior to the work commencement.
Requirements of Health, Safety and Environmental for the project shall be in accordance
with approved Project HSE Plan, the contract document and Part-15 & 19, section 1 of QCS
2010.
Before commencing of any work, the required and applicable work permits shall be checked
and ensure all requirements of WP are complied and they are valid until completion of the
activity and as per approved HSE plan.
All personnel accessing their site will wear the mandatory PPE. All workmen and staff shall
wear the mandatory and job specific Personnel Protective Equipments. Pre-task briefing
shall be conducted on every day before starting the work. Experienced and HSE inducted
workmen shall be deployed for the work. All personnel shall be cautioned while working
near any live lines such as power cable, water lines, drainage lines, telecom etc.
Prior to commencement of work all workers shall be given pre-task briefing. Hazards
identified for the activity shall be disseminated during pre task briefing, especially for
underground services, slip & trip, improper access, excavation tools handling, no access or
aggress, vehicle collision, heat exhaustion, which shall be identified and documented
separately by permit to work system as per approved HSE plan.
First aid stations complete with all first aid equipments and trained first aiders shall be
maintained for the initial care.
Safety and security procedures shall be implemented as a minimal, warning signs and lights,
barricades, railing and other safeguards shall be provided as required by the nature and
location of the work.
The environmental risk assessment and environmental management plans have been
reviewed for the work activities proposed in the method statement and found to be suitable
and adequate.
Electrical waste will be segregated at source and transported to dedicated segregated waste
storage area and not be allowed to accumulate on site in undesignated areas. Concrete waste
will be removed from work areas at regular intervals to designated areas.
Construction waste will be disposed as per local laws & client guidelines by licensed carrier
to a licensed facility.
10. HOUSEKEEPING
Housekeeping is the act of keeping the working environment clean from all unnecessary
waste materials. The equipment/tools/materials required for the work shall be stored /stacked
in such a manner so as to give a safe working atmosphere to the workforce at site.
All workplace areas shall be maintained clear of debris, waste and other rubbish, which shall
be disposed of in segregated containers for disposal. An adequate number of containers
marked appropriate labels for storage and disposal of waste materials shall be strategically
placed throughout the construction areas at all time.
Any spillages, such as oil or grease shall be immediately cleaned up, by absorption in inert
sand or other suitable materials. The materials for the particular work shall be stored at site
so that no obstructions to the work or access to the workforce.
Debris, waste oil containers etc shall be stacked and placed in a barricaded location away
from the work areas and access routes. Adequate fire precautions shall be in place. Before
leaving the site, it shall be ensured by the responsible person that the site area is cleaned and
no obstruction is encountered for next day work.
The Quality Assurance and Control for the above mentioned activities shall be exercised and
recorded in accordance with the contract documents for Quality Assurance and the approved
Project Quality Plan for the project.
The quality assurance shall be ensured for workmanship, equipments and materials
conformance to the applicable standards and requirements at every stage of the construction.
This shall be monitored by quality control personnel on the site during the production /
operation.
Quality assurance requirements shall also be imposed upon sub contractors, suppliers,
manufacturers and any other parties associated and involved in the project. Non-conforming
materials shall be notified in writing to correct or remove the defective materials from the
work site.
All inspections and tests shall be conducted in accordance with written test procedures as
detailed in the Project Quality Plan and Inspection and Test Plan approved by CSC.
Applicable documents with latest version such as Inspection & Test Plan, Method
Statements shall be readily available and used by inspection and test personnel at the time of
inspection as referring documents.
12.0 MATERIALS
Approval shall be obtained for all the materials with reference to Client’s preferred vendor
list, prior to commencement of activities.
Material Inspection Request (MIR) will be submitted to client upon material arrival to
warehouse.
All materials must be stored properly as per the manufacturer’s recommendations and QCS.
The Material shelf life will be monitored as per Manufacturer’s data sheets.
Steel and B wires are used as materials.
F.F Steel, Amreli Steel and Agha Steel
DG Cement, Lucky Cement, Askari Cement, Maple Cement
Coarse aggregates and sand
Scaffolding and Shutering
13.0 MANPOWER
Site Engineer
Supervisor
HSE Inspector
QA/QC Inspector
Steel Fixers
Masons
Labours
.
Handling and stacking Reinforcement:
Number and spacing of supports will be such that there is no sagging of the stacked bars.
Stacked rebar will be covered with tarpaulins or such other means and protected from mud, oil or
any other thing that causes damage.
Standards as set out in the project specifications will be adhered to in handling and storage of
reinforcing materials.
Rebar will be fabricated according to the bar bending schedule supplied by the Contractor.
Each bundle of bars will be tagged to be identified by the design drawing number, the structure,
mark number, bar quantity and size.
The reinforcement will be cut and bent in accordance with the approved bar bending
schedules.
The bending of reinforcements will be done on the bending machine, producing a gradual
and even motion. Bars will be bent cold and at specified radii.
Receipt and Storage of Bars:
The rebar received from the supplier will be inspected. All defective materials will be repaired or
replaced by the supplier.
The storage of rebar will be arranged above ground on padded supports, using timber pieces or
sand bags. The rebar will be covered with dark light proof material to prevent rusting.
Quality Control:
The reinforcement will be inspected before concreting. It will be ensured that the surface of
reinforcement will be free from mud, oil, retarders, grease or any other substance which
would affect adversely the steel or concrete chemically or reduce the bond. Also it will be
ensured that it is placed in full accordance to the issued for construction drawings.
All the embedded items will be fabricated or procured prior to concreting and fixed in place
using suitable templates.
Suitable templates will be designed for the positioning and fixing of the embedded items.
Templates as supplied by the Contractor will be used in case of foundations for large Skirt
Mounted Vessels.
The adequacy and positioning will be checked by the supervisor before submitting a Request For
Inspection to the PMT’s (Project Management Team) QC. The QC will check them in turn
before forwarding this request to the QC of the Contractor. This procedure ensures the right kind
of embedded items are in right place and in right quantities.
Anchor bolts will be placed plumb well within the tolerances mentioned in project specifications.
14.6 CONCRETING
Transportation of Concrete:
Out of the available transit mixer trucks, at least one will be kept as stand by. Before the
departure of the loaded transit mixer, the delivery ticket will be handed over to the driver.
Delivery of Concrete:
Before discharging the concrete at the point of delivery, the driver will provide
the Material Engineer or Quality Control Engineer the delivery ticket identifying the material for
each batch of concrete.
The concrete will be conveyed to the place of placing in the following manner:
o Metallic or Metal-lined chutes
o Concrete Pump: The concrete pump will be of adequate pumping capacity.
Wherever required, the concrete will be pumped through steel pipes.
o Concrete Bucket: Metallic concrete buckets with bottom opening will also be used.
It will be carried to place of pouring by a crane.
Unless adequate protection is provided, concrete will not be placed during rain.
Curing of Concrete:
Immediately after placement, concrete will be protected from premature drying and
excessively hot temperatures and will be maintained with minimum moisture loss at
relatively constant temperature for a period necessary for the hydration of the cement and
hardening of the concrete.
The curing of concrete will be carried out by one of the following procedures:
The system to be used will depend on the nature of the structure. The above methods (2) and (5) will
be the mostly used.
Moisture loss from surfaces placed against wooden forms or steel forms, exposed to heating by sun,
will be minimized by draping forms with wet hessian covered with white polyethylene until they
can be safely removed. After forms are removed, the concrete will be cured up to the end of
prescribed period.
Quality Control:
In order to ensure a safe working environment during the entire construction period, the
following safety measures will be implemented.
Prior to use any machinery/equipment at site, it shall be inspected and certified by qualified
person.
Periodic Preventive Maintenance shall be made on all equipment and machineries.
All operators and driver are to be equipped with valid driver’s/operator’s license or permit
from concerned government agency.
Only authorized signalman shall be assigned together with the operator or driver.
All lifting equipment as well as its accessories such as sling wire, nylon sling, shackles,
chain blocks, crane hook and latch shall be inspected periodically.
PPE shall be issued to all workers such as safety shoes, hard hat, working gloves, ear plugs,
safety goggles and safety belt and or safety harness for workers who will be assigned in
elevated places.
Wearing of the basic PPE shall be enforced fully.
EMERGENCY CONTACTS
Sl.
Position Name Contact No.
No.
1 Project Manager
2 Construction Manager
3 HSE Manager