Campus Wireless Network Installation Proposal: Prepared For: Western Delta University, Oghara

This proposal outlines a wireless network installation project for Western Delta University's campus. It recommends installing 29 indoor and 4 outdoor access points, as well as switches, routers, fiber optic cabling, and other equipment. The total estimated cost is [Total. Cost] naira. The installation is scheduled to take 7 days for hardware positioning, 14 days for cable installation, 2 days for device installation, and 3 days for testing. Acceptance of the proposal requires signing and dating the document.

Uploaded by

Emmanuel Iyeni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
245 views6 pages

Campus Wireless Network Installation Proposal: Prepared For: Western Delta University, Oghara

This proposal outlines a wireless network installation project for Western Delta University's campus. It recommends installing 29 indoor and 4 outdoor access points, as well as switches, routers, fiber optic cabling, and other equipment. The total estimated cost is [Total. Cost] naira. The installation is scheduled to take 7 days for hardware positioning, 14 days for cable installation, 2 days for device installation, and 3 days for testing. Acceptance of the proposal requires signing and dating the document.

Uploaded by

Emmanuel Iyeni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

XXXXXXXXXXXXXXXXXXXXXXXXXXXXX

APRIL, 2019

Campus Wireless Network Installation Proposal

PREPARED FOR: WESTERN DELTA UNIVERSITY, OGHARA

PREPARED BY: MR IYENI EMMANUEL

13 EDO STREET, OFF


EKOSODIN, BENIN CITY, EDO
STATE

Phone: 08131030033
Email: [email protected]
INTRODUCTION

XXXXXXXX would like to thank Western Delta University for the opportunity to
submit a proposal for the provision of a new wireless network covering the entire
campus at her permanent location. XXXXXXXX a full-service IT services provider
specializing in network installation, support, and maintenance. Our headquarters are
located in Benin City. We support businesses in the following areas:
Server & desktop Infrastructure
Server Virtualization
Storage Solutions & Virtualization
Wireless Networks
Infrastructure Services
24/7 Monitored & Managed Support
SharePoint & Web Design Services
Local & Cloud Based Back-Up Solutions
Hosted Telephony Services
Remote & On-site Support
Our network engineers, designers, and installers are certified and licensed to install
computer networks in small businesses, multi-family residences, and large
institutions such as universities and hospitals. We’ve been delivering complex IT
infrastructure solutions since 2007 and we’ll bring this experience to your project
and apply it to your specific business needs.
In this proposal, you’ll find a summary of your network needs based on previous
conversations, our proposed network solution, and associated costs and installation
schedules. This proposal is valid until June,2019. Should you need to extend your
decision past that date, we’ll be happy to revisit this document to ensure all pricing
and installation schedules are accurate at the time of signing.

Regards,
Emmanuel Iyeni
08131030033
[email protected]
PROJECT GOALS/REQUIREMENTS

Optimum coverage and performance.


Roaming capability without losing connection.
Internet access across buildings (Admin Blocks, Hostels, Classrooms and
Entrepreneurship).
Ability to access File Server and other services remotely
Portal authentication login using web browser
RECOMMENDATIONS
Based on our analysis of this project we recommend the following;
Inter-building connectivity using underground optical fiber infrastructure
(pre-terminated passive fiber cabling and conduits).
Ensuring capacity by installation of 29 indoor access points within the seven
building locations.
Installation of 4 Outdoor access points diagonally across the open field
between the admin blocks and the hostels for ease of roaming.
Installation of switch and router at Admin block(IT-Centre).
Installation of wireless Lan controller (WLC) at Admin block (IT-Centre)
for ease of configuration, monitoring and maintenance of access points.
Installation of seven access switches in each building.
Installation of seven media Converters in each building.
Installation of Cat 6 Ethernet cables to connect media converters to switches.
Installation of PoE Splitter cables to provide power and Ethernet to the
access points from the switch
Implement network security by setting encryptions
Set minimum signal and data rate thresholds
Mikrotik portal authentication to authenticate users’ credentials through web
browser access
PROJECT DETAILS AND FINANCIAL SUMMARY

Pricing

Hardware

Name Price(#) QTY Subtotal

TL-AP1750C-PoE from TP Link (Indoor Access Point) 200.00 29 0.00

TL-AP300P-PoE from TP Link (Outdoor Access Point) 0.00 4 0.00

TL-SL1218MP Access Switch 0.00 7 0.00

TL-AC100 wireless controller 1

TL-SG5428 core switch 1

TL-SG5428 core router (optional) 1

Media Converter 6

Chassis media Converter (ADMIN block) 1

Fibers Single Mode Pre-Terminated Indoor/Outdoor Fiber Case Assembly (SC- 1


SC):2KM

Fibers Single Mode Pre-Terminated Indoor/Outdoor Fiber Case Assembly (SC- 5


SC):1KM

PoE Splitter cable 14

Cat 6 Ethernet Cable : 1000meters 1

Subtotal: #0
Total: #0

Total network installation cost: # [Total. Cost]

Disclaimer: The prices in the tables on this page are intended as estimates only. They in no way constitute a guarantee of final project costs.
Project costs are subject to change if specifications or product availability change prior to a binding contract being signed.
Services

Name Price QTY Subtotal

Civil Works $0.00 1 $0.00

Design $0.00 1 $0.00

Installation $0.00 1 $0.00

Support $0.00 1 $0.00

Subtotal: $0
Total: $0

Installation

Phase Duration

Hardware Positioning 7 days

Cable Installation 14 days

Device Installation 2 days

Testing 3 days

Disclaimer: The schedule above assumes that Western Delta University is able to provide xxxxxxxxxx with full access to the facility located at
Oghara, Delta State for the duration of the project/

Please sign and date this proposal to indicate your acceptance of the
hardware, pricing, and installation indicated above. This is not a legally
binding contract. Once this signed proposal is received, [Sender.Company]
will draft a contract for signature by both parties.