Document Submission Status: For Reference: Vung Ang 1 Thermal Power Plant 2 X 600Mw
Document Submission Status: For Reference: Vung Ang 1 Thermal Power Plant 2 X 600Mw
VIETNAM MACHINERY
INSTALLATIONCORPPORATION (LILAMA) WORLEYPARSONS PTE LTD
PROJECT TITLE
BOILER ISLAND
CONTRACT No.
180609 / LILAMA-BWBC
SCALE REV
DOCUMENT No. VA1-BWBC-00100-M-M1A-DAS-0002
A
B&WBC-RBC(W) 1
2x600MW PC Vung Ang 1 Power Project
B. DESIGN CONDITIONS
1 Ambient temperature ℃ 25
2 Relative humidity % 85
D. FLUE GAS
1 Exit gas temperature @ air ℃ 127
preheater outlet, with air leakage
2 Flue gas @ air preheater Nm3/h 2014×103
outlet(BMCR)
Flue gas @ air preheater Nm3/h 1563×103
outlet(75%RO)
Flue gas @ air preheater Nm3/h 1247×103
outlet(50%RO)
3 Flue gas density @ air preheater kg/Nm3 1.331
outlet
B&WBC-RBC(W) 1
2x600MW PC Vung Ang 1 Power Project Boiler Technical Data for Auxiliary Equipment Selection
E. AIR
1.1 Primary air BMCR
temperature @ air preheater inlet ℃ 33
flow @ air preheater inlet Nm3/h 309×103
temperature@ air preheater outlet ℃ 378
flow @ air preheater outlet Nm3/h 233×103
pressure drop, air preheater kPa 0.95
pressure drop, burner kPa 1.42
1.2 Primary air 75%RO
temperature @ air preheater inlet ℃ 33
flow @ air preheater inlet Nm3/h 274×103
temperature@ air preheater outlet ℃ 349
flow @ air preheater outlet Nm3/h 179×103
pressure drop, air preheater kPa 0.63
pressure drop, burner kPa 1.31
B&WBC-RBC(W) 2
2x600MW PC Vung Ang 1 Power Project Boiler Technical Data for Auxiliary Equipment Selection
B&WBC-RBC(W) 3
2x600MW PC Vung Ang 1 Power Project Boiler Technical Data for Auxiliary Equipment Selection
G. EMISSION
1 NOx(dry, Oxygen 6%, before SCR) mg/Nm3 1100
2 SO2(dry, Oxygen 6%) mg/Nm3 1453
3 Ash loading (dry, Oxygen 6%) g/Nm3 32.4
B&WBC-RBC(W) 4
2x600MW PC Vung Ang 1 Power Project Boiler Technical Data for Auxiliary Equipment Selection
Note: 1. All data list here are of BMCR load, only for the use of conceptual design and
auxiliary equipments selection; for performance guaranteed data, see Boiler Performance
Guarantees for 2x600MW PC Vung Ang 1 Power Project.doc.
2. Flue gas and air flow includes the air preheater leakage, but not include the
pulverizing system leakage.
B&WBC-RBC(W) 5