LT - Fault Level Calculation
LT - Fault Level Calculation
100 x 1
% Impedance of the system at source = --------- = 0.2%
500
II. Fault level at SRIL:-
0.00652 x 1000
= ------------------ = 0.0054%
1
10 x 11 x 11
ACSR Resistance = 0.27450 x 0.2 = 0.0549Ω
= 0.128Ω
0.128 x 1000
= ------------------ = 0.1057%
10 x 11 x 11
Total impedance up to Plant Terminal Point: -
100
Fault Level = ---------- = 321.44 MVA
0.3111
321.44
Fault current = ---------- = 16.87 KA
√3 x 11
2
3.739
26.745
Fault current at Transformer LT side = --------- = 35.66
KA
√3 x 0.433
7.502 x 8
AC resistance for 8 M long busduct = -----------
S1000
= 0.060 Ω.
= 0.0601 Ω.
0.0601 x 1000
% Impedance of the busduct = -----------------
10 x (0.433)2
= 32.073
3
% Impedance of Busduct = 32.073
--------
35.812%
100
Fault level at PCC side = -------- = 2.792 MVA.
35.812
Since connecting the busduct the fault level becomes very low. Hence we have
not considered for the calculation purpose.
Hence Switch gear in PCC and Bus bars are rated for 50 KA for 1 Sec.
11KV Cable between the 11KV VCB Panel in the SRGEL Plant to upto 11KV
O/H Cable Termination Kit.
1750 KVA
Full load current capacity for Transformer = -------------- = 114.8 A
√3 x 11x 0.8
4
However, the selected size of the cable is 300 sq.mm Ar. Al. XLPE Cable.
%Z x 10 x (KV)2
Ohmic value of the Impedance of the supply system = ---------------------
KVA (Base)
3.739 x 10 x (0.433)2
= --------------------------
1000
= 0.007010 Ω
3 x 433
Earth fault current = 3E / ZE = --------------------
√3 x (3 + j 0.021030)
√3 x 433
= ------------ = 249.97 A.
3.0000756
= 0.25 KA.
Max. Earth fault current (due to variation in system voltage) = 0.25 x S1.1 = 0.275 KA.
5
= 0.0044 x 39220 x √5 sq. mm.
Hence the Neutral Bus used 75 x 6 (or) 50 x 8 Cu. (2400 sq. mm Cu).
9. Open air rating of Bus bars 2 nos-200x12 Al. mm Flat : 3060 x 2 = 6120 A
Correction Factors:
7 x 200 x 12
3. Enclosure correction factor : --------------- x 100 = 4.392 = 0.8
850 x 450
6
7. Current carrying capacity after de-rating = 6120 x 0.63432 = 3882 A.
Hence, the Bus bar size and size of enclosure are adequate and size of bus bars should
be not less than 4500 sq. mm.
A = (50,000/(14x104)x(1/{√(log-
10((200+258)/(85+258)}
= 650 sq. mm
1750
2. LV side full load current = ------- = 2334 A.
1.732 x 0.433
= 2600 A (Say).
Hence selected 3200 A, 50 KA TPN ACB is adequate.
7
During the fault (or) during maintenance of Main Transformer feeder, the
Emergency feeder can be operated for running emergency loads (or) running the
maintenance loads.
353.6
Full load current = ------------------------ = 578 A
1.732 x 0.415 x 0.85
Hence selected 630A SFU with 630A HRC Fuse for the Emergency Feeder is
adequate.
1.3 DG Incomer:
160
Full load current = ---------------- = 222.5 A.
1.732 x 0.415
Say = 600 A.
8
Hence selected 1000 A TPN 415V, 50Hz, 50 KA ACB.
500
Full load current = -----------------------
1.732 x 0.415x 0.8
= 869.5 A
= 956.45 A
Hence the selected one step higher size ACB rating = 1250A
200
Full load current = ----------------------
1.732 x 0.415x 0.8
= 347.8 A.
= 382.5 A.
Say = 230 A.
Hence selected SFU Unit rating 250A with 250 A HRC fuse rating is adequate.
9
2.5 For Power & Lighting Loads:
143
Max. Full load current = --------------- = 248 A.
Hence selected SFU switch rating 630 A and fuse rating 350 / 400 A HRC Fuse.
40
Max. Full load current = ---------- = 69.5A
√3 x o.415 x 0.8
General:
To measure the Power Digital Load Manager are provided for all the incomer
feeders in addition Ammeter, Voltmeter, Power Factor Meter, etc.
CABLE SIZING:
Selected cable size = 3.5C x 300 sq. mm Ar. Al. PVC Cable.
10
AC current rating in air = 315 A (as per IS: 1554).
De-rating Factor:
Hence min. 4 runs of 3.5C x 300 sq. mm Ar. Al. PVC Cable to be laid.
Selected cable size = 3.5C x 300 sq. mm Ar. Al. PVC Cable.
De-rating Factor:
i.e, Min. 3 runs of 3.5C x 300 sq. mm Ar. Al. PVC Cable to be laid.
Hence selected 4 runs of 3.5C x 300 sq. mm Ar. Al. PVC Cable considering the
switch gear rating. Regarding Short Circuit rating – 4 runs 3.5C x 300 sq. mm Ar. Al.
can withstand 90.92 KA for 1 Second.
11
Total load current including overloading, etc = 382.5 A
Selected cable size = 3.5C x 300 sq. mm Ar. Al. PVC Cable.
Select 2 runs of 3.5C x 300 sq. mm Ar. Al. PVC Cable which can withstand fault
current of 45.46 KA for 1 Second.
Selected cable size = 3.5C x 300 sq. mm Ar. Al. PVC Cable.
One run of 3.5C x 300 sq. mm Ar. Al. PVC Cable is adequate.
Basis:
b. For easy procurements and standarding the cable size, the following cable size are
selected.
After
De-rating
S. No. Cable Size In Air de-rating
Factor
(A) (A)
12
6 3C x 70 sq. mm Ar. Al. PVC Cable. 130 0.7 91
3C x 240 sq. mm Ar. Al. PVC
7 280 0.7 196
Cable.
3C x 2.5 sq. mm Ar. Cu. PVC
8 24 0.7 17
Cable.
Note:
Due to reliability of the system, we have not considered 3C x 2.5 sq. mm and 3C x 4
sq. mm Al. Cable which may easily break during laying and termination in the small
motor ends, also non-availability of space in the terminals.
1.1 For Raw Material Process Plant Loads (cabling between PMP-1 to various
loads):
1. For 15 KW Motors:
15
3. Full load current = --------------------------
√3 x 0.415 x 0.83 x 0.92
= 27.32 A = 28 A (say).
1.44
Applying the same = --------- x 28 x 210.
1000
= 8.467 V.
8.46
13
Percentage voltage drop under normal running condition = ------- x 100
230
= 3.6%.
2. For 11 KW Motors:
11
2. Full load current = --------------------------
√3 x 0.415 x 0.83 x 0.92
= 20.04 A
S2.29
Applying the same =--------- x 20 x 210 = 9.618V.
1000
9.618
Percentage voltage drop under normal condition = ------- x 100 = 4.18%.
230
14
6. BC-7 from Crusher House to Tr. House (9.3 KW).
3.60
Applying the same = ------ x 14 x 210 = 10.584V.
1000
10.584
Percentage voltage drop under normal condition = ------- x 100 = 4.6%.
230
15
6.02
For 3C x 6 sq. mm Cable voltage drop = ------ V/A/mtrs.
1000
6.02
Applying the same = ------ x 5 x 210 = 6.321V.
1000
6.321
Percentage voltage drop under normal condition = ------- x 100 = 2.74%.
230
4.67
Percentage voltage drop = ------- x 100 = 2.033%.
230
Hence the selected size of sCable is applicable for the following motor feeders.
16
1. Approximate route length = 210 mtrs.
0.77
Applying the same = ------ x 57.5 x 210 = 9.29 V.
1000
9.27
Percentage voltage drop under normal condition S= ------- x 100 = 4.0425%.
230
Which is just sufficient. Better to have next size cable.
7. For 22 KW Motor:
2.29
Applying the same = ------ x 23 x 210 = 11.06 V.
1000
11.06
Percentage voltage drop under normal condition = ------- x 100 = 4.809%.
230
Which is just sufficient. Better to have next size cable.
17
Following Motors are applicable
a. Bay Filter-1
b. Bay Filter-2
c. Bay Filter-3
d. Bay Filter-4
55
Max. Full load current = ---------- = 99.13A
√3 x o.415 x 0.83 x 0.93
3.5C x 120 sq. mm Ar. Al. Cable can carry in Air = 180 A
0.31
Voltage drop = ------ V/A/mtrs.
1000
0.31
Applying the same = ------ x 109 x 210 =7.0959 V.
1000
7.096
Percentage voltage drop under normal condition S=
------- x 100 = 3.08%.
230
Hence the cable size between 55KW Feeder from RMP Feeder Local Starter
3.5C x 120 sq. mm Ar. Al. cable is adequate.
1. Inverter:
18
The cable selected = 3C x 25 sq. mm Ar. Al. PVC Cable (which is already
been explained in the earlier pages).
The cable selected = 3C x 16 sq. mm Ar. Al. PVC Cable (which is already
been explained in the earlier pages) and following feeders are applicable.
The cable selected = 3C x 10 sq. mm Ar. Al. PVC Cable (which is already
been explained in the earlier pages) and following feeders are applicable.
The cable selected = 3C x 10 sq. mm Ar. Al. PVC Cable (which is already
been explained in the earlier pages) and following feeders are applicable.
S6.02
Applying the same = ------ x 7.5 x 100 = 4.515 V.
1000
19
4.515
Percentage voltage drop under normal condition = ------- x 100 = 1.96%.
230
Voltage drop is less than 5%. Hence cable size is adequate which is applicable
for the following Motor Feeders.
i. Coal Injector.
ii. Kiln Aux. Drive.
iii. Wet Sraper.
iv. Cooler Aux. Drive.
v. Dewatering Pump 1, 2 & 3.
vi. Volem Feeder.
vii. Kiln Transition Chute (2.2 KW).
viii. Kiln Thruster (2.2 KW).
ix. Cooler Thrust device (2.2 KW).
x. Power Pack (2.2 KW).
For smaller rating Motors below 1.5KW Motor can be used 3C x 2.5 sq. mm Cu. Cable.
The details already explained in the earlier working.
For,
1. WF1 to WF-5, (* 4C x 2.5).
2. Volem Feeder, (* 4C x 2.5).
3. Kiln inlet PV and outlet PV.
4. Kiln Lub Pump.
5. Cooler Thrust Brake.
6. Cooler Lubricant Panel.
7. Cooler Dish D.P.V.
8. ID Fan Damper.
9. L.D.O Pump 1 & 2.
Note: * indicates 4C x 2.5 sq. mm Cu. Cable & others are 3C x 2.5 sq. mm Cu. Cable.
Following Feeders from DRP-1 to various feeders Local Starter Panels cable
sizing.
20
6 DRP-1 MCC Air Compressor Panel 55KW 1x3.5C-120 sq. mm 40
1. For 75 KW Motors:
6. After de-rating = 91 A
Voltage Drop Check:
0.54
For 3C x 25 sq. mm Cable voltage drop = --------- V/A/mtrs.
1000
0.54
Applying the same = --------- x 78 x 140.
1000
= 5.89 V.
5.89
Percentage voltage drop under normal running condition = -------x 100 =2.5%.
S230
21
1.4 ESP PANEL:
2 KW Heater Loads:
22
Capacitor Selection:
i.e, 50 KVAR x 6
Hence, 2 set of Capacitor Banks of rating 300 KVAR & 200 KVAR respectively in steps
of 50 KVAR and max. Switch fuse rating required for 300 KVAR is 800 A and fuse rating
also 800 A and no. of runs cable between the Capacitor Panel to PCC – 4 runs x 3.5C x
300 sq. mm Cable and capacitor panel can be provided with Power Factor controller
relay to maintain the Power Factor at particular Power Factor.
23