19039-FIS-WI-30 - Packing, Marking & Shipping Procedure Rev 00
19039-FIS-WI-30 - Packing, Marking & Shipping Procedure Rev 00
19039-FIS-WI-30 - Packing, Marking & Shipping Procedure Rev 00
&SHIPPING Prepared By :
FOR Bijesh Kumar M.
ITEM:DERRICK STRUCTURE
AND ALL PROCESS ITEMS
B.Thomas 23-06-2019
PROJECT: MAADEN AMMONIA
Signature Date
III PROJECT
INDEX
1.0 SCOPE:
This procedure covers the procedure for packing, marking & shipping for Ma’aden,
Ammonia III Project – Road transport.
2.0 REFERENCES:
Client specification- MD-101-SPPM-PO-LO-PEI-0001
MD-522-7000-LO-LO-PRO-002
3.0 PACKING
• The equipment and/or materials such as fasteners, small loose parts, etc. will
be packed in wooden cases. Wooden boxes will be made by, new, solid and
type and class suitable for the weight being carried. All the packages shall be
adequate to allow stacking on top, supporting at least weight equivalent to
their own. Flat head nails will be used for closing. All boxes/cases shall be
built with rails or chocks on the base pallet platform or skid platform to allow
their handling with slings or forklift. Goods shall be loaded properly; any
voids or dead space are not permitted and bracing, and cushioning materials
shall be used as necessary to prevent movement and damage. If the load shall
be kept upright, the box/case shall be equipped with lift handles, skids, top
Doc. No. :19039-FIS-WI-30
PROCEDURE FOR PACKINGMARKING Page No. :4 of 6
Revision : 00
AND SHIPPING Date :23.06.2019
peaks or gables or some similar device to assure the box will be stowed and
loaded in an upright position.
• The equipment and/or materials packed in the wooden pallets, all bottom
pallets will be built with rails or chocks on the base pallet platform or skid
platform to allow their handling with slings or forklift. Materials to the pallets
shall be secured with a minimum of 2 nylon or metallic straps. All the pallets
after strapping shall be covered with plastic film.
3.2.4 Packing of Bulk Cargo, Shipped Loose - Vessels, Stacks, ducts, tanks
etc.
• Hazardous material could pose risk to health, safety and property. Hazardous
material shall be packed, marked, stored and transported in accordance with
local and foreign government and international transportation regulations.
SELLER shall inform PURCHASER about all shipments containing
Doc. No. :19039-FIS-WI-30
PROCEDURE FOR PACKINGMARKING Page No. :5 of 6
Revision : 00
AND SHIPPING Date :23.06.2019
hazardous materials at least one (1) month prior to submission of the READY
FOR SHIPMENT DECLARATION.
4.0 MARKING
5.1 The below mentioned contents / details must be shown in the respective
document:
Upon the receipt of Shipping Release Note (SRN) from the purchaser, materials
will be arranged for delivery/collection (subject to the scope of delivery).
ONE set of original Country of Origin, Commercial Invoice and Packing list
which will containing the details of; PO No., HS Code, Country of Origin,
Gross & Net weights, etc. will be submitted upon the receipt the consignee
details from the purchaser.