Boiler Hydro Test-Steps
Boiler Hydro Test-Steps
Boiler Hydro Test-Steps
Test Pressure:-
1.25 times the maximum working pressure, if all components as per Regulation 268 are
tested.
1.5 times the maximum working pressure, if any of the components as per Regulation268
are not tested.
At the first hydraulic test of a boiler deflection measurements shall be made before,
during and after test of each furnace length, fire – box and flattened or other plates.
Should any part of the boiler show undue deflection or indication of permanent set during
the progress of the test, the pressure shall be released immediately such indications are
observed. The working pressure for the part shall-be 40 percent of the test pressure
applied when the point of permanent set was reached. This procedure shall apply to any
boiler at any test.
The Hydro test of Boiler is done in two stages:
Stage-1:
Hydro test of complete water and Super heater steam circuit including drainable and
non-drainable sections of Boiler up to Boiler Stop valves. Thus this will include:
a. Economizer,
b. Boiler Drum,
c. Down comer sand Water walls,
d. LTSH,
e. Platen Superheat (Non drainable),
f. Final Super heater (Non drainable) the hydro test pressure is chosen as the 1.5/1.25
times the maximum of maximum working pressure of components participating.
Stage 2:-
This covers there heater circuit. The QC NRV of re-heater does not participate and CRH
section up to this point is blanked. One Intercept or valve blanking device is also
installed. Thus the circuit comprise of CRH lines from QC NRV to Re-heater, Re-heater
and HRH lines up to IV.
The hydro test pressure is chosen as the 1.5/1.25 times the maximum of maximum
working pressure of components participating.
Services:-
Standard Pressure gauge–one at drum and one near pressurizing pump-Calibrated at
NABL accredited laboratory with least count of 1KSC.
Chemicals–
AmmoniaandHydrazineHydrateinquantitysuchthatwaterbeingfilledshallhave200ppmofhy
drazineandpHof9.5-10
Services:-
Pressurizing Pump – Of suitable capacity for pressurization
Boiler Fill Pump – For initial filling, Temporary Chemical Dozing Scheme
Flood Lights and 24V hand lamps, Reliable Communication System
Ambulance and Fire Tender State of the plant
Erection of Boiler PPs and piping is complete as per drawing.
All necessary welding jobs are complete, stress relieved and X-rayed
All necessary valves including drain valves are installed and kept closed
All safety valves are installed and hydro static plugs assembled
The isolating valves provided in all other branches viz. soot blowing tapping, SH spray
connection, RH spray connection are closed tight. They are tested separately at specified
pressures.
The Boiler system is filled with fill pump from bottom using drain cum fillings with the
treated DM water.
Completion of filling of various circuits is ensured by water coming out of vents.
Close and open the vents ever al times to ensure proper venting.
The pressurizing pump is started and pressure is raised up to 25KSCand thorough
inspection is made.
Pressure should be raised in steps and held for 10minutes at 100 and 200KSC.
Average rate of rise of pressure shall be 10KSC/minuteupto80% of test pressure.
Afterwards, it should be 2KSC/minute.
At test pressure pressurizing pump shall be stopped and drop in pressure shall be
monitored for 30minutes.
Completion Criterion – The drop rate should not be more than 1KSC / minute and no
appreciable deflection of components
After completion of test Boiler shall be de-pressurized at the rate of 1KSC/minute using
vents.
At a pressure of 50KSC, the pressure is held and Boiler is thoroughly inspected.
If found satisfactory, full de pressurization and draining can be done
At 2KSC the vents are left full opened.
Note: During raising pressure for the first time no person should be allowed to enter
Boiler after 50KSC.
1 week –1 month
Water filled surface: - Hydrazine –300 ppm and Ammonia–10 ppm, PH 9.5-10 pressure
5-10 KSC
SH Surface: - Hydrazine –300 ppm and Ammonia–10 ppm, PH 9.5-10 pressure 5-10
KSC
RH Circuit: - Hydrazine –300 ppm and Ammonia–10 ppm, PH 10-10.5 Under N2
capping of 0.35 KSC
1month –6 months
Water filled surface: - Hydrazine –700 ppm and Ammonia–10 ppm, PH 9.5-10 pressure
5-10 KSC
SH Surface: - Hydrazine –700 ppm and Ammonia–10 ppm, PH 9.5-10 pressure 5-10
KSC
RH Circuit: - Hydrazine –700 ppm and Ammonia–10 ppm, PH 10-10.5 Under N2
capping of 0.35 KSC
> 6 months
Water filled surface: - Hydrazine –1000 ppm and Ammonia–10 ppm, PH 9.5-10 pressure
5-10 KSC
SH Surface: - Hydrazine –1000 ppm and Ammonia–10 ppm, PH 9.5-10 pressure 5-10
KSC
RH Circuit: - Hydrazine –1000 ppm and Ammonia–10 ppm, PH 10-10.5 Under N2
capping of 0.35 KSC