Assignment#3
Assignment#3
Submitted to:
Engr.Tanveer Younas
Submitted by:
Mahnoor Rauf
L1F17BSCE0013
3rd year (5th semester)
Section: CA
1
CONTENTS
1.Documentation 4
3.Materials Testing: 10
Tests of Aggregates 10
Crushing Strength 11
Los Angles Abration Value 12
Shape Test 12
Water Absorption Test 12
Tests of Concrete 12
5.Brick Masonry: 14
Procedure of Brick Masonry 14
6.Plaster: 14
Tools for Plastering 14
Methods of Plastering 14
7.CONSTRUCTION OF BUILDING: 15
Sub-structure 15
Shallow foundation 15
Individual footings 16
Strip footing 16
Combined Footing 16
Raft or Mat foundation 17
Deep foundation 17
Pile foundation 17
Basement 18
Super-structure 19
Excavation 19
2
Pit excavation 19
Trench excavation 19
Bulk excavation 20
Fill 20
Cart Away 20
Concrete Mixing Method 20
Batching 21
Curing of Concrete 22
Structural Work 23
Grade Beam or Plinth Beam 23
Reinforcement Steel Bar 24
Superstructure Beam 24
Ceiling and Wall Finishing 25
Floor Finishing 25
LIST OF TABLES
Sr.no: Name Page no.
1.1 Format of takeoff sheet we used in the site. 4
1.2 The format of bar schedule working paper we used at the site. 5
1.3 The format of bill of quantity we used at the site. 6
2.1 Composition of Portland cement 7
6.1 Different Coats of Plaster 13
3
LIST OF FIGURES
Sr.no: Name Page
7.1 Individual footing 14
7.2 Plinth beam in footing 14
7.3 Combined Footing 15
7.4 Combined Footing 15
7.5 Pile foundation 16
7.6 Pit and Trench Excavation and masonry work 18
7.7 Pit and Trench Excavation and masonry work 18
7.8 Tilt Drum Mixer Used in Site 19
7.9 Batching Box Used in Site. 20
7.10 Curing by Wet Covering 20
7.11 structural grade beam construction 21
7.12 Rebar at Plinth Level at Ground Floor for Parking 21
7.13 Reinforcement steel bar for beam 22
7.14 Ceiling and Wall Finishing 23
References:
Documentation
Office Work:
In my six months internship period I experience Office works that are worked mostly at the site this
includes some tasks performed by office engineer and quantity surveyor. Such as:
1. Taking off
2. Bill of quantity
3. Report writing
4. Reading and interpreting drawings
Taking off:
This is the process of preparing / defining a detailed list of all labor and materials necessary for the work
and entering the items on properly dimensioned 19 paper. The standard form used for entering the
dimensions taken or scaled from drawings to determine the accurate quantity in each trade of work,
except reinforcement steel, is called take off sheet or dimension paper. The main aim of this sheet is for
payment and cost estimation for purchasing and preparing bill of quantity.
4
Table: 1.1 Format of takeoff sheet we used in the site.
Column 1 is used for stating the number of times an item occurs and is called the time stating
column.
Column 2 is called dimension column as it is used to enter the dimensions of the items of works.
The dimensions are entered in the order indicated below: Length, Width, Height or thickness.
Column 3 is called squaring column. The stated dimensions in column 2 are multiplied to
determine the quantity of the work either in m, m 2 , m3 or in Pcs. or No.
Whereas column 4 is called description column and description of the work item is briefly
stated. Based on the above format I have calculated the quantity of concrete in 20 m 2 and in
m3 , formwork in m2 and excavation in m2 . We were to use m3 for depth greater than 30 cm
and if it is less than we use m2 .
A separate sheet (Bar Schedule) is used to prepare reinforcement quantities as shown below:
Bar schedule is used to know the amount of rebar used on the site and to tell the bar bender that the
amount of bar needed in some position of the building and its number. The following tasks are part of
the taking off (used to facilitate defining the quantities): Describing the item, bracketing (relating the
description to the quantity), dotting on, the ampersand (ditto), waste calculations, deduction of items,
correction of dimensions (nullifying).
5
Table: 1.2 The format of bar schedule working paper we used at the site.
Bill of Quantity:
The traditional purpose of bills of quantities is to act as a uniform basis for inviting competitive
tenders, and to assist in valuing completed work. Bills of quantity are first designed to meet the
needs of estimators, although some 21 estimators say the bill format has changed to assist the
consultants, in cost planning exercises through the widespread use of elemental bills. A
contractor can also make use of the bill of quantities in many ways, for example:
To plan material purchasing (note the danger in ordering from a bill: the contractor
should always order materials from drawn information and the specification, making the
contract administrator aware of any differences)
Preparing resourced programmes.
Cost control during the contract to ensure work is within budget.
Data collection during construction for bonus systems and feedback information for
estimators. It is the format which is used in a bill of quantity to list (include) a short
description of the specification along with its measuring unit, quantity and unit prices to
determine the total Cost for each trade of item. In the site the bill of quantity is done by
consultant with the contract document but at site we work it again for payment.
6
Table:1.3 The format of bill of quantity we used at the site.
There are four clearly defined steps in preparation of Bill of Quantities:
Taking off
Squaring
Abstracting
Writing the bill off quantity
Report Writing
Reporting is a controlling / informative mechanism which will help in evaluating the status of a
project. It entails us how we are accomplishing our set targets at the onset of a project. It will
also help decision makers to follow the status of the project without being present physically on
the site. The reports should explain the history of the project. It should be realistic and self-
explanatory. Numbers in a report are far important than number crunching. Putting numbers for
a report writer like 10% or 90% may be simple but the meaning for the decision makers is very
vital. Putting wrong figures knowingly or unknowingly are devastating.
Types of Report:
The types of reports to be submitted in a project depends on project type; complexity; working
habit etc. In our project we work the following reports
7
problems, Anticipated problems to be solved for the next week , next week plan and so on.
Monthly Progress Report: This is a report with a view of many eyes. This will be thoroughly seen
by second level observers. The contractor, the client and the Consultant’s representative will
make an in depth view of the report to have full information about the project status. This is a
report where major bottle necks of the project will be narrated and the performance of the
parties will be vividly seen.
Major Contents of Monthly Progress Report:
Accomplishment of monthly Plan, Monthly labor and Machinery Deployment, Material
Delivered to the site, major 23 Problems of the month , Solutions given to the major problems,
Anticipated problems to be solved for the next month , next month plan, Contractual matters
-Delay Notifications (if any) ,variations ( if any) and so on.
Reading and Interpreting Drawings:
Drawings are the means by which the designer conveys the physical, quantitative, and visual
description of the project to the contractor. The drawings are a two-dimensional representation
of the physical structure that meets the objectives of the owner. They are also known as plans
or blueprints In our site there were 4 types of drawing;
1. Architectural drawing
2. Structural drawing
3. Sanitary drawing
4. Electrical installation drawing
These drawings are the main language between the architect, designer and any worker at the
site or office to build the model in position as specified by the designer and the client, based on
the agreement. Thus, to work as an engineer in the construction site it is mandatory knowing
drawings and any other specification. Drawings are the most common means of communication
for all types and sizes of project. Thus, I understand each drawing and knew every symbol
abbreviation for every section and I was able to communicate with different workers using it.
8
53 Grades
33 Grade OPC is used for general construction works like plastering and finishing works in
normal environmental conditions. However, its use is virtually phased out today.
Coming to the 43 Grade OPC, it is the most commonly used grade for home construction. It
has its applications in plastering, finishing works, precast items, foundations, brick work, and
compound wall and so on. It has more strength development than the 33-grade cement.
53 Grade OPC develops strength very fast. High rise building constructions use 53 grade
cement. This is applicable for use in structures where high grade concrete is required.
At the site Portland cement of 53 grades (JK SUPER CEMENT) is used. The cost per beg = 275
rupees
The initial setting time of cement = 30 minutes (1/2 hrs.)
The final setting time of cement = 10 hrs.
AGGREGATE:
Aggregates are small pieces of broken stones in irregular size and shapes. Neat cement
is very rarely used in construction works since it is liable to shrink too much and become cracks
on setting. More over, it will be costly to use neat cement in construction work. Therefore
cement is mixed with some inert strong & durable hard materials. They also reduce the cost of
concrete because they are comparative much cheaper as cement.
TYPES OF AGGREGATES:
FINE AGGREGATE (SAND):
The aggregate, which pass through 4.75 mm, I.S. sieve and entirely retain on 75 micron
(.075mm) I.S. sieve is known as fine aggregate.
COARSE AGGREGATE:
The aggregate, which pass through 75 mm I.S. sieve and entirely retain on 4.75 I.S. sieve
is known as coarse aggregates. At the site the coarse aggregate was 10mm & 20mm (graded).
FUNCTION OF COARSE AGGREGATE:
The coarse aggregates are used in mixing of concrete. It is mixed cement, sand with
water. These aggregates increase the strength of bonding in aggregates. Coarse aggregates are
used in construction of plan cement concrete (PCC), foundation, beams and columns etc.
GRADING OF CONCRETE:
The art of doing gradation of an aggregate as determined by sieve analysis is known as
grading of aggregate. The grade of concrete is depends on size of aggregates. The principle of
grading is that the smaller particles will fill up the voids between large particles. This results in
the most economical use of cement paste for filling the voids & binding together the aggregate
in the preparation of concrete. Thus proper grading of fine & coarse aggregate in concrete mix
produces a dense concrete with less quantity of cement.
9
REINFORCEMENT:
The material that develops a good bond with concrete in order to increase its strength is
called reinforcement. Steel bars are highly strong in tension, shear, bending moment, torsion
and compression.
WATER:
It is an important ingredient of concrete because it combines with cement and forms a
binding paste. The paste thus formed fills up the voids of the sand and coarse aggregate
bringing them into close adhesion.
In this project source of water is a tube well which is closely spaced to the building. The
quality of water is good and can be used for drinking purpose aiso.
R.C.C.
Though plain cement concrete has high compressive strength and its tensile strength is
relatively low. Normally, the tensile strength of a concrete is about 10% to 15% of its
compressive strength. Hence if a beam is made up of plain cement concrete, it has a very low
load carrying capacity since its low tensile strength limits its overall strength. It is, there
reinforced by placing steel bars in the tensile zone of the concrete beam so that the
compressive bending stress is carried by concrete and tensile bending stress is carried by steel
reinforcing bars. Generally in simply supported and
Cantilever beams the tension zone occurs at bottom and top of beam respectively.
MATERIAL TESTING
TESTS OF AGGREGATES:
Below are some of the important test which are perform on aggregates at every construction site to
check the quality of the aggregate for better construction and fulfil the requirement of the client.
1. Crushing Test
2. Impact Test
3. LOS Angles Abrasion Test
4. Shape Test
5. Water Absorption Test
CRUSHING STRENGTH TEST:
Standard: IS: 2386 (Part IV)-1963 Methods of test for aggregate for concrete Part IV Mechanical
Properties.
Equipment used:
Steel Cylinder
Sieves (12.5mm,10mm)
10
Cylindrical metal measure
Tamping Rod
Balance (0-10kg)
Oven (3000c)
Compression testing Machine (2000KN) .
Procedure:
1. The cylindrical steel cup is filled with 3 equal layers of aggregate and each layer is tamped 25
strokes by the rounded end of tamping rod and the surplus aggregate struck off, using the
tamping rod as a straight edge.
2. The net weight of aggregate in the cylindrical steel cup is determined to the nearest gram (WA)
and this weight of aggregate is used for the duplicate test on the same material.
3. The cup is fixed firmly in position on the base of the machine and the whole of the test sample
is added in thirds, each third being subjected to 25stokes from tamping rod.
4. The surface is leveled and the plunger is inserted so that it rests horizontally on the surface.
The whole assembly is then placed between the platens of testing machine and loaded at a
uniform rate so as to reach a load of 40 tones in 10 minutes.
5. The load is then released and all aggregate is removed from the cup and sieved on 2.36 mm. IS
sieve until no further significant amount passes in one minute.
6. The fraction passing the sieve is weighed to an accuracy of 0.1 g (WB).
SHAPE TEST:
Equipment’s used:
Thickness/Flakiness Index Gauge
Length/Elongation Index Gauge
Aggregate sample to be tested
Shape of particle:
1. Rounded (river gravel)
2. Flaky (laminated rock)
3. Elongated
4. Angular( crushed rock)
11
Flaky:
A flaky particle is the one whose least dimension (thickness) is than 0.6 times
the mean size.
These are the materials of which the thickness is small as compared to the other
two dimensions.
Limit of flaky particles in the mixes is 30%. If the flaky particles are greater than
30% then the aggregate is considered undesirable for the intended use.
Flakiness Index: It is the percentage by weight of flaky particles in a sample.
Elongation:
These are the particles having length considerably larger than the other two
dimensions and it is the particle whose greater dimension is 1.8 times its mean
size. Limit of elongated particles in the mixes is 45%. Thus, if the elongated
particles are greater than 45%, then the aggregate is considered undesirable for
the intended use.
Elongation Index:
It is the percentage by weight of elongated particles in a sample. The Elongated
index is calculated by expressing the weight of Elongated particles as percentage
of total weight of the sample.
12
up to 1000kPa. MAIN ROADS Western Australia Water Permeability of Hardened
Concrete.
A pressure gauge to measure input pressure and a thermometer to measure
ambient temperature.
Data acquisition equipment to record, at suitable intervals of time, the pressure,
volumetric flow of water into and out of the concrete specimen and the
ambient temperature
1. Diamond cut saw.
2. Balance of suitable capacity readable to 0.1g with a limit of performance of not
more than 0.6g at the 99% confidence level.
3. Supply of de-aired water.
4. Vacuum pump.
5. Vernier callipers.
6. Diamond corer drill.
7. 100mm diameter concrete mould complying with AS 1012.8.
8. Worksheet (optional). A graphical representation of the data, including the
calculation of the D’Arcy Coefficient of Permeability is suitable.
SLUMP TEST:
Equipment’s used:
Slump cone,
Scale for measurement,
Temping rod (steel)
13
COMPACTORS:
When the concrete has been placed, it shows a very loose structure. Hence, it must be compacted to
remove the air bubbles and voids so as to make it dense and solid concrete to obtain a high strength.
There are two method- of compaction. Manual compaction Mechanical compaction.
Generally in large projects mechanical compactors are used . There are various mechanical compactors
which uses according to requirement as needle and screed vibrators needed to compact the column and
floor respectively.
BRICK MASONARY
PROCEDURE OF BRICK MASONRY:
In frame structure brick work starts after construction of foundation, column, beam, and slabs.
Following procedure is adopt to construct the brick masonry
1. Initially clean and wet the surface on which brick wall is be constructed.
2. Set a straight alignment by using threads in both side of a wall .
3. Prepare the cement mortar.
4. At this site cement sand ratio is 1:6 for all walls.
5. Mortar is laid on surface base and then bricks are laid over it .
6. Prepare a course and then again laid the mortar on existing course and provides bricks in such a
way that the vertical joint should not stand in a line.
7. To break the verticality of joints generally English or Flemish bond is adopted.
8. Use the plumb bob to check the verticality at regular interval.
9. Also use square to check the wall is constructing straight or not.
10. After each 1 meter height of wall provide a layer of reinforced cement concrete of 1.5 to 2
inches.
11. It will increase the strength of structure.
PLASTER
TOOLS FOR PLASTERING:
Gauging
Trowel
Metal Float
Floating Rule
Plumb Bob
Sprit Leve
Brushes
METHOD OF PLASTERING:
According to the thickness of wall there are three method of plastering.
One coat method
Two coat method
Three coat method
ONE COAT METHOD:
It is in the cheapest form of construction that plaster is applied in one coat. This method is quietly used
in rural areas for the construction of low category and cheap house.
14
TWO COAT METHOD:
Following procedure is carried out for two coating plaster work:
Clean the surface and keep it well watered on which plaster work to be done. If it is found that the
surface to be plastered is very rough and uneven, a preliminary coat is applied to fill up the hollows
before the first coat of plaster is put up on the surface. Now the first coat is applied on the surface. The
usual thickness of first coat for brick masonry is 9mm to10mm. Second coat of plaster is applied after
about 6 hours and the thickness of second coat is usually about 2mm to 3mm.It is finished as per
requirement.
THREE COAT METHOD:
The procedure for plaster in three coats is the same as above except that the num of coats of plaster is
three.
CONSTRUCTION OF BUILDING
Construction of the building is done in at least two steps. Which are following:
Sub Structure
Super Structure.
SUB STRUCTURE:
Foundation is a part of the sub structure. Sub structure is constructed according to soil quality at that
site. If soil have good bearing capacity than we use shallow foundation in construction. And if the
bearing capacity of the soil is not good or suitable than we use deep foundation at that site. Sub
structure is a load bearing structure and it is designed for load bearing.
FOUNDATION:
A foundation is the element of any structure which connects it to the ground, and transfers loads from
the structure to the ground. Foundations are generally considered either shallow or deep. The low
artificially built part of a structure which transmits the load of the structure to the ground is called
foundation. Foundation is a load bearing structure which bearS all loadS coming on the building or any
structure. Foundation is generally of two types: A. Shallow Foundation. B. Deep Foundation. Generally
foundation in building construction is Shallow foundation (Raft Foundation)
SHALLOW FOUNDATION:
Shallow foundations are also called spread footings or open footings. The 'open' refers to the fact that
the foundations are made by first excavating all the earth till the bottom of the footing, and then
constructing the footing. During the early stages of work, the entire footing is visible to the eye, and is
therefore called an open foundation. The idea is that each footing takes the concentrated load of the
column and spreads it out over a large area, so that the actual weight on the soil does not exceed the
safe bearing capacity of the soil. It includes some types of shallow foundation such as:
15
INDIVIDUAL FOOTINGS:
Individual footings are one of the most simple and common types of foundations. These are used when
the load of the building is carried by columns. Usually, each column will have its own footing. The
footing is just a square or rectangular pad of concrete on which the column sits. To get a very rough idea
of the size of the footing, the engineer will take the total load on the column and divide it by the safe
bearing capacity (SBC) of the soil. For example, if a column has a vertical load of 10T, and the SBC of the
soil is 10T/m2, then the area of the footing will be 1m2. In practice, the designer will look at many other
factors before preparing a construction design for the footing. Individual footings are usually connected
by a plinth beam, a horizontal beam that is built at ground or below ground level.
STRIP FOOTINGS:
Strip footings are commonly found in load-bearing masonry construction, and act as a long strip that
supports the weight of an entire wall. These are used where the building loads are carried by entire
walls rather than isolated columns, such as in older buildings made of masonry.
Combined Footing:
The following pictures show combined footing before concert cast and after cast: A combined footing is
usually used to support the columns of unequal loads. In such case, the resultant of the applied loads
would not coincide with the centroid of the footings and consequently the soil pressure would not be
uniform. Combined foundation is an efficient foundation solution is when there are two interior columns
which are so close to each other that the two isolating footings stress zones in the soil areas would
overlap.
16
Fig:7.3 Combined Footing Fig:7.4
17
it can support. This is very similar to how a friction pile works. In a friction pile, the amount of load a pile
can support is directly proportionate to its length.
Basement:
Multi storey car parks are essentially elementary building structures, albeit with certain specific
performance criteria that must be met. The overall structural form will be heavily influenced by the
design geometry adopted. Underground car parks will, to a large extent, be determined by the structure
above (for example a multi storey building or a public garden).
The structural frame can be either reinforced concrete (precast units or cast in-situ), steel or a
composite structure (steel beams and columns, supporting concrete floor slabs). Ribbed or coffered
slabs are often used. Lightweight-aggregate concrete can reduce overall loadings significantly, and has
better fire performance – but smaller span: depth ratios and additional shear reinforcement are needed.
Concrete must be designed to be durable against chemical corrosion attack. Non-slip finishes in
particular to ramps are also prudent, to prevent skidding. Heated structures are also possible, although
their effectiveness can be questionable.
Wind loads and vibration also need to be taken into account. Structural resistance to explosions (over
and above fire resistance) should also be considered. Underground car parks will need extensive
retaining wall design, incorporating tanking and land drainage.
18
SUPER STRUCTURE:
Super-structure is a part of structure that is above plinth level (P.L). Generally, columns and walls are
constructed in super structure. Following are the important parts of super-structure.
1) Floor
2) Roof
3) Lintel
4) Parapet
5) Sun Shade
6) Doors & Windows
Excavation
Excavation is the first step of construction. It refers to the process of removing soil or rock from its
original location, typically in preparation for constructing foundations, basements, and underground
utility lines and for grading of the ground surface. Excavated material required for backfill or grading fill
is stockpiled on the site for subsequent use. Excavation work I have seen was including bulk excavation,
pit excavation and trench excavation. The main aim of the excavation work is to remove organic soils or
unwanted soil for the safety of the building from chemical attacking. Excavation shall be carried out to
the lines, levels, width, depth and grades and shown 25 on the drawings, directed by the Engineer or as
appropriate to the works to be placed in the excavation.
Pit excavation:
It is an excavation made for foundation footing pad with column by considering working space of 200 up
to 300mm to each side of the dimension.
Trench excavation:
It is an excavation made for constructing foundation walls stone masonry with leaving working area for
both sides of the wall of specified width on the plan.
This depth is filled by the stone masonry which placed on 5cm thick lean
concrete
Stone masonry should be laid with specified mortar, well filled joint
The stone should be hard, sound, free from crack and weathering
It should be freshly quarried from an approved quarry
It is not round surface
19
Fig:7.6 Pit and Trench Excavation and masonry work. Fig:7.7
Bulk excavation:
It is an excavation made for making the ground level or an excavation made for filling selected material.
Or we can say that bulk excavation means removing black cotton soil because as you know black cotton
soil is very expansive and it has a low bearing capacity therefore we must remove it from the site and
the area is back filled with selected materials.
Fill:
Fill work will follow the erection of foundation column. Bulk, pit and trench excavations need to be back
filled with a better soil type, which will have better 26 compaction character and would bring the
minimum required proctor density. In order to attain the minimum standard as mentioned on the Bill of
Quantity, they deploy appropriate machineries.
Cart Away:
This is the disposing off extra excavated material away from the construction site. Cart away is
calculated by deducting the back fill from the total volume of soil excavated.
Where,
T.S =total soil, B.F =back fill, T.E = soil obtained from trench excavation ,P.E = soil excavated from pit
excavation, B.E = Bulk Excavated soil, N.B:-since cart away is measured by meter cube, all the other soil
amounts are changed to meter cube.
20
fresh and hardened properties. This has broadened the scope in the design and construction of concrete
structures. It has also introduced factors that designers should recognize in order to realize the desired
performance in terms of structural adequacy, constructability, and required service life. These are
translated into strength, workability and durability in relation to properties of concrete. In addition,
there is the need to satisfy these provisions at the most cost effective price in practice. Since our
building is a reinforced concrete structure the concrete work was commenced every day for
constructing/development of every part of the building.
Hand Mixing :
Hand mixing is practiced for small scale unimportant concrete works. As the mixing cannot be through &
efficient, it is desirable to add 10% more cement to compensate the inferior concrete produced by this
method.
Machine Mixing:
Machine mixing obviously gives better and uniform mixes than hand mixing and because of this reason,
it is generally recommended. There are different types of concrete mixers such as, Tilting drum mixer,
non-tilting drum type, pan mixer type, truck mixer, plant mixer etc.
21
Fig:7.9 Batching Box Used in Site.
Curing of Concrete:
Different method of procedures has been adopted for curing in the site. These are:
Spraying of water
Pounding of water
Wet covering
Sprinkling water on concrete
22
Structural Work:
23
Reinforcement Steel Bar
In the following figure we can see steel bars of beam:
24
Finishing:
Plastering:
Plastering work is the end work to bring construction decoration with plaster, such as a layer of plaster
on an interior wall or exterior walls. The process of creating plaster work called plastering. It has been
used in projects to fill rough and uneven surface. Cement mortar is a mixture of water, cement and sand
which is used for plastering purpose on the site.
Ceiling and Wall Finishing:
Gypsum chuck:
It can be considered as both internal walls finishing and ceiling finishing process. Gypsum chucking is
performed over well plastered wall or roof after all the moisture get dried. It is applied only for internal
walls since it is easily failed by dampness. Gypsum chucking means painting a thick gypsum paste,
gypsum with water, to create a smooth and good looking surface. It also helps to decrease paint
consumption of the wall by filling all the voids and creating a smooth surface.
Application procedure:
Mixing: -
To mix add the water into clean container then add the powder gypsum onto the water and mix slowly
until mix is homogeneous to avoid foaming. Paint the paste repeatedly through by squeezing over the
wall or roof to have a final smooth surface. The following picture shows gypsum work of ceiling and wall
finishing:
Floor Finishing:
Floor finish is one of the last steps of a construction. Among the floor finishing factor that will influence
the selection of floor finishing are as follows:
Function of the floor
Price
Maintenance
Comfortable
25
REFERENCES
Google.com
Wikipedia
Building By-laws
Books on Building Construction
QUESTION#2
26
2. In a market area, the plinth area should not exceed 75% of the area of site, provided sufficient
off-street parking facilities for loading and unloading of vehicles are provided on the same plot
as the building
27
a. Every habitable room which should have for the admission of air and light, one or more
apertures such as windows and fanlights, opening directly to the external air or into an
open verandah and of an aggregate area, inclusive of frames, of not les than i. One-
tenth of the floor area excluding doors for dry hot climate. ii. One-sixth of the floor area
excluding doors for wet/hot climate. No portion of a room should be assumed as lighted
if is more than 7.5m away from the door or window which is taken for calculation as
ventilating that portion. Cross-ventilation by means of windows and ventilators or both
shall be effected in at least living room of tenement either by means of windows in
opposite walls or if this is not possible or advisable, then atleast in the adjoining walls.
b. Bathrooms and water closets: The rooms should be provided with natural light and
permanent ventilation by one of the following means:
Windows having an area of not less than 10% of the floor area and located in an exterior wall
facing a street alley, yard or an air shaft whose dimensions in the direction perpendicular to the
window is not less than one-third the height of the building on which the window is located,
subject to a minimum limit of 1m and maximum 6m.
Skylights, the construction of which shall provide light and ventilation required in (i) above.
Ventilation ducts:
Provided such ducts have 130 square cm of area for each square meter of area with a minimum
total area of 300 square cm and least dimension of 9cm.
c) Stores, backrooms:
These will have at least half the ventilation required for living room.
d) Basement and floors: Basements and rooms located therein except room shall be lighten and
ventilated by windows in exterior walls having a ventilating area of not less than 2.5% of the
floor area.
e) Kitchen shall be ventilated according to standards prescribed for habitable rooms near the
ceiling as far as possible.
f) Stairways: every staircase should be lighted and ventilated from an open air space of not less
than 3m depth measured horizontally in case of ground and one upper floor structure, 4.5 m in
case of ground and two upper and in higher structure than this, the open air space shall not be
less than 6m, provided that the lighting area shall not be less than 1 sq.m per floor height. Every
staircase shall be ventilated properly.
28
Side open space:
Every residential building may have a permanently open air space not less than 1m in
width on one of its sides other than its front and rear and such side open space shall
form an inseparable part of the site. In case, side open air space is to be used for
ventilation, it shall be in accordance with the requirements mentioned in the previous
paragraph. In case, the side open space abuts a road, the width shall not be less than
3m.
29
(viii) Every building having a height of more than 25 Mts. shall be provided
with diesel generators which can be utilized in case of failure of the
electricity.
(ix) The standard of National Building Code must be adopted fully in
providing stair-case and alarm system.
(x) There should be Provision of dry-powder fire extinguisher to the extent of
two on each floor with a capacity of 5 kgs, in all the high rise buildings.
30