Acknowledgement
We take immense pleasure in thanking for Dr. Fayadh (Ph.Dr. in Mchanical Engineerign Dept , Tikrit University )
for having permitted us to carry out to did this project .
This project would never be completed without support and Guidance of him .
Finally, many thanks to every member in this team for the helping each other to produce this
work in exceptional circumstances .
The Project Team
Team Members ;
1- Abdullah Drea . 6- Mufaid hamzaa .
3- Amer Khalf .
4- Mohammed Yaseen .
5- Arkan Alteif .
٢
Summary
Everyone is talking about biogas - politicians and ecologists, engineers and economists, and
experts. Biogas has become fashionable. The energy crisis of the next few years is the shortage
of fuel for the daily needs of millions of people. Simple biogas plants are intended to help solve
this problem. It is time to set about this task in a "professional" manner in the best sense of this
word.
Simple biogas plants are complicated enough to require total involvement with their
specific technology. After all, a biogas plant can only help to solve the problems of the future if it
works! But many plants work badly. They are operated wrongly, are deficient in detail and are
often incorrectly scaled.
Simple biogas plants have been constructed in Third World countries for about thirty
years. But good and bad solutions are featured side by side without comment in articles and
books. The same mistakes are repeated over and over again. This need not be the case. The
designer of a biogas plant must be able to distinguish between valid and invalid solutions.
٣
Introduction :
٤
Chapter (1)- Facts about Biogas Plant
1- 1 : Production
Biogas plant can be produced via
2- Human Manure .
3- Cow Manure.
Nitrogen N2 0 –10
Hydrogen H2 0 –1
Oxygen O2 0–0
٥
1-3 : Major Advantages:
No Major Advantages:
٦
1-4 : The Items used in the design and it costs ( Prices are according to the Iraqi Markets ) .
No Item Type Dimension Uses Qty Price (ID) Total Price (ID)
2. connecter +Nut +Washer BBR ½ Inch Gas outlet + drain + slurry exit 5 1000 5000
4. Connecter + Nut + Washer BBR 1 ½ Inch Over flow (Liquids outlet ) 1 1500 1500
5. Plugs BBR ½ Inch For closing the side holes 2 500 1000
9. Valve BBR 2 Inch Feeding inlet (Opening & Closing ) 1 5000 5000
11. Elbow BBR 1 ½ Inch Connecting the exit holes 2 1000 2000
12. Socket BBR 1 ½ Inch Connecting the exit holes 1 2000 2000
14. Socket BBR ½ Inch Connecting the gas hole 2 500 1000
15. Connector (reducer ) BBR ½ x ¼ Inch to connect the hose of gas consuming 1 500 500
16. Hose Rubber ¼ Inch to transfer the gas to the network 2M 500 1000
17. Rubber Tube Rubber size (16 ) to store gas 1 5000 5000
21. Silicon rod + Tefelon tape / / to reduce the clearance of fittings 1,1 3000 3000
٧
Chapter (2) - Construction
In this chapter , We explained the procedure of construction the Bio-Gas Plant ;
2- 1 : Making the Holes in the Barrel . by using the drilling machine .
1- In the upper cover of the barrel , Open (1 )hole Size ( 2’’ ) for feeding inlet .
2-In the upper cover of the barrel , Open (1) hole Size( 1 ½ ‘’) for outlet .
3- In the upper cover of the barrel , Open (2) holes Size ( ½ ‘’ ) , one hole for venting and the other for gas production .
When all the above steps done , it should be like the below photo :
٨
4 – In the side of the barrel , open ( 2 ) holes for exit size ( ½’’) . one at the upper and the other at the middle .
5- in the bottom of the barrel side , open a (1 ) hole size ( ½’’ ) for drain .
When all the above steps done , it should be like the below photo :
٩
2- 2 Connecting the Valves and Fittings .
1- connect the socket (2’’ ) with the reducer (4’’X2’’) and the valve (2’’) and use the glue and the Teflon tape to ensure no leakages in the
system .
2- connect the socket (1/2’’) with the reducer (1/2” X 1/4’’ ) with the valve (1/4’’ ) to make gas production outlet and connect the hose (
¼’’) . as in the below photo ;
١٠
3- connect the plugs (1/2’’) to the side holes (1/2’’ ) and they opened at need to flushing the barrel .
4- connect the drain hole ( ½’’ ) . when done , it should be like the below photo ;
١١
After we done , the schematic view of the barrel should be like the below photo ;
Drain
(1/2’’)
١٢
2-4 : Connecting the rubber tube ;
1-after completing the above steps , now it’s the time to connect the rubber tube .
3- connect the metal valve ( ¼’’ ) to the rubber hose with the gas production hole and connect the assembly to the rubber tube .
١٣
2- 5 : Final assembly :
The final plant should be cleaning (flushing ) by water to ensure not wastes stay in the pipes or the fittings , in addition it should be tested
by by water and maintain the leakages , we may use the silicon or glue to ensure no leakages in the plant .
١٤