Piping Design & Plant Layout Model Review Procedure: 1.0 Purpose
Piping Design & Plant Layout Model Review Procedure: 1.0 Purpose
1.0 PURPOSE
The purpose of this procedure is to establish responsibilities, timing, review techniques,
documentation requirements, methods of implementation of findings and guidelines related to
formal model reviews conducted using 3D electronic modelling systems.
2.0 SCOPE
This procedure applies to formal model reviews at the Study, 30%, 60% & 90% stages of design
completion. It is not intended to control normal daily, weekly or other regular reviews which
support design work.
3.0 DEFINITIONS
The following definitions are applicable to the Model Review Matrix:
Technical Term Explanation
Modelled Means built in the model but not checked for stress,
interferences, or other discipline spacing requirements
Designed Means stress is complete and the item is modelled and
considered frozen
Checked Means designed, modelled, clash checked and
considered final product
Code 1 Manufacturing may proceed without changes.
Submit Certified Drawing
Code 2 Correct & resubmit. Manufacturing may proceed subject
to incorporating comments.
Code 4 Information / record purposes only. Certified As-Built.
3.1 Project Engineer
Ensure that the reviews and pre-review clash checks are entered into the project
schedule.
Have a working knowledge of PEM 4206 and its attachments.
Manage the Model Reviews.
Ensure that the Discipline Leads design process meets the requirements for the
review as defined in Model Review Matrix. (See Appendices, 4206A)
Ensure that the design process meets the requirements for the review as defined in
the Model Review Matrix. (See Appendices, 4206A)
Prepare, schedule and chair the Model Review Readiness Checklist meetings and
ensure exceptions are clearly identified with the closeout date identified.
Prepare and issue an agenda for the review.
Notify and ensure that the appropriate client, third parties and IMV personnel will be
in attendance.
Arrange a meeting room for the review ½ hour before scheduled start to ensure that
model and projector are operating smoothly.
Take minutes of the model review meeting.
Ensure the reviews proceed in an expedited manner.
Coordination of the resolution of action items.
Proper filing of all documents.
Issue the model review minutes of meeting.
Issue a call to meeting to closeout action items prior to the next scheduled review.
NOTE: All readiness and model reviews will proceed in 30% and 60%, once the models are
available for review. There should be minimal delays in progressing reviews. Project
Engineers are to ensure the reviews proceed in an expedited manner
The review will start off with a walk through of all access / egress ways starting at
grade and progressing to higher elevations. It is important to inform the client that the
reserved volumes will be protected and included in all interference clash checks,
upon completion of the walk down the reserved volumes may be switched off.
The next step is a line by line review mainly to focus on location of valves and
smaller pieces of equipment for operation and maintenance. Any comments will have
the item number from the Model Review Log added to the review P&ID’s for
resolution later.
It should also be noted that acceptable layout and design should also be recorded as
such.
4.5 Description of Stages
For a 3D design, it is typical to review the models at the Study, 30%, 60% and 90% completion
stages. Each of the reviews requires specific tasks / progress to be completed prior to the review
so that the outcome / objectives can be achieved. These are outlined in the Model Review Matrix
Table. Please also refer to the Matrix Table for additional component details relating to each stage
(Study, 30%, 60%, and 90%).
For model reviews (over a 3 to 6 week span), a Readiness Checklist is completed first. Then an
internal team review is completed in order to determine the status of the model and the items
which need to be addressed; then a client review occurs. The time frame is flexible and needs to
be established at each model stage. The pre-work associated with model reviews is outlined in the
Model Review Matrix Table.
The Study Model Review (IFR model) is done with the Study Model. At this point, the high level
information is frozen (equipment location, building location, escape routes, etc). The basis of this
model is IFR P&ID’s. This is the best stage to resolve key design parameters / philosophies for the
purpose of minimizing the impacts at later stages. It is important to involve Civil Design and Stress
Design early in this stage, as the design criteria they require may impact future design. Reviews at
the study stage will be grouped by area.
The 30% Model Review (IFA Model) requires the IFD P&IDs and preliminary vendor drawings for
all major equipment. Operations and construction presence is required at 30% reviews. Reviews
at the 30% stage will be completed by work package as they are ready.
The 60% Model Review (IFD Model) is a progression of the design. Operations and construction
presence is recommended, but can be defaulted based on progress of the model. It may be
advisable at this stage to split reviews with the Design team (home office) and Operations /
Construction (field) and it is the responsibility of the Project Engineer to address this scheduling, if
deemed necessary. Reviews at the 60% stage will be completed by work package as they are
ready.
The 90% Model Review (IFC Model) is a final review of the design before piping, structural and
electrical drawing packages are issued. All vendor data must be firm and P&ID’s must be IFC.
Client participation for these reviews is not necessary. The attached table provides a detailed
breakdown of the objectives, outcomes and inputs into each model review.
4.6 Model Review Execution Process & Responsibilities
The requirements for the Model Review are covered in the Model Review Matrix Table (4206A).
The Matrix Table outlines specific requirements to effectively and efficiently complete a Model
Review at each stage.
The Interdisciplinary Review (internal) is a process which requires a full design review.
The Client Review is a process which requires a review on safety, operability, constructability,
accessibility and maintainability. All of these items are also covered during the Internal Review.
The key roles required for a model review meeting are:
Project Engineer - minutes of meeting (scribe), review notes and timer
Piping Area Lead – facilitator and works model (or assigns designate)
Model Review notes will be captured using the redline tagging tool within Navisworks. There is an
excel format in place that will be utilized, distributed and filed for further follow-up. Sign off will be
required by the Project Engineer.
4.7 Model Lockdown
Once a model reaches 90% model review and is checked, a lockdown security will be put in place
by EAS. This lockdown will only allow change access through an approval process with the
Project Engineer / Manager as noted below. There will be read access in place for the Piping
team.
If Piping or Civil requires change / edit access, a request will be made to the Piping Area Lead. In
turn, the Piping Area Lead will request approval from the Project Engineer / Manager.
5.0 APPENDICIES
Model Review Matrix Table
Study Model Readiness Checklist
Model Readiness Checklist (30%)
Model Readiness Checklist (60%)
Model Readiness Checklist (90%)
Model Review Log Form
Model Review Covenants
Acceptable Reasons for Model Review Changes