Project Risk Analysis: by Atul Pandey Shrija Konda Akanksha Sinha Harsha Aditi
Project Risk Analysis: by Atul Pandey Shrija Konda Akanksha Sinha Harsha Aditi
ANALYSIS
By
Atul Pandey
Shrija Konda
Akanksha Sinha
Harsha
Aditi
INTRODUCTION
• Through this presentation we will try to identify the underlying sources
of risk and explore the consequences.
• Risk is inherent in almost every business decision. More so in capital
budgeting decisions as they involve cost and benefits extending over a
long period of time during which many things can change in
unanticipated ways.
• The following slide suggests ways to handle risk in capital budgeting.
Techniques of risk
analysis
Break-even
Hillier model
analysis
Judgmental Evaluation
Risk-adjusted
discount rate
= Risk free
rate
+ Risk
premium
• If project risk is equal to the risk of existing investment of the firm, the discount rate
used is the average cost of capital of the firm.
• If project risk is greater than the risk of existing investment of the firm, the discount
rate used is higher than the average cost of capital of the firm.
• If project risk is less than the risk of existing investment of the firm, the discount rate
used is less than the average cost of capital of the firm.
The project is accepted if its NPV is positive:
NPV Σ At - 1
= t=1
(1+rk)t
D1
D2 D3
D22
C2
Stop
C21
C22 low
high
demand
demand
0.4
0.6
CERTAINITY EQUIVALENT METHOD
• It is a method which is used to calculate a guaranteed return that
someone would accept, rather than taking a chance on a higher, but
uncertain, return.
• Under this method NPV is calculated as
• NPV = sum(αt*At/(1+i)^t)-I
• αt=certainty equivalent coefficient(0.5-1)
• At=expected cash flow
• i=risk free interest rate
• I=initial investment
METHODS TO INCORPORATE RISK
• Conservative estimation of revenues: Revenues expected from a project
are conservatively estimated to ensure the viability of the project
• Safety margin in cost figures: A margin of safety is included in
estimating cost figures
• Flexible investment yardsticks: The cut off point for an investment varies
according to the judgment of management about the riskiness of the
project
Cont…