MOS - Electrical Services
MOS - Electrical Services
MOS - Electrical Services
CONTRACTOR/SUPPLIER:
PESTECH SDN BHD
NO.26, JALAN UTARID U5/14, SEKSYEN U5
BANDAR PINGGIRAN SUBANG,
40150 SHAH ALAM, SELANGOR
CONSULTANT:
PROJECT:
SIBIYU 132/33 kV SUBSTATION PROJECT
PROJECT DETAIL:
SIBIYU 132/33 kV SUBSTATION PROJECT
SCALE: THIS SHEET:
TITLE:
1
Method Statement for Installation of Electrical System N.T.S
NEXT SHEET:
-
METHOD STATEMENT
MECHANICAL & ELECTRICAL
Standard practice for electrical system installation work including LV wiring, LV conduit,
cable tray and cable trunk.
3.3 MATERIAL
• PVC cables (1.5mm2 and 2.5mm2)
• Wire-tape, cable links, cable lugs, cable-ties, masking tape
• High impact UPVC Conduit
• Switchboard and distribution board
• G.I. conduit
• Cable tray
• Cable trunking
• Cables and wiring shall be laid continuous between their terminals unless
impractical. Method of connection (if needed) shall be proposed for approval.
Otherwise cables and wiring shall only be terminated at the terminals of the
accessories / equipment or using cable links.
• All cable and wiring shall be prepared in accordance to the approved drawings
/ layout after which preparation shall be inspected to ensure no damage to
the cable / wiring strands has occurred.
• Only approved type of lugs and clips are to be fitted to prevent strands from
spreading when terminals are tightened.
• Shop fabrication
➢ Conduit, cable tray and cable trunking are prepared to the required
length (no spare length is required).
• Slot draw cable into the first draw box until mandrill emerges at the other box.
• Unwind the cables to the desired length – ensure no debris or dirt on cables.
• Attached the cables to the mandrill, bind the cables with masking tape to
ensure smooth pulling through the conduit.
• Put up the required conduit, cable trunking and cable tray onto the
bracket/suspension rod/wall and tighten with bolt and nut.
• Continue by jointing the end of the conduit, cable trunking and cable tray with
the provided joint/socket and bolt and nut.
• Earth continuity conductor is provided for conduit, cable tray and cable
trunking.
• Upon completion of installation, check to ensure that conduit, cable tray and
cable trunking are properly secured on the brackets.
• To ensure housekeeping shall be done to prevent any mishap from happening.
• Request for inspection by client representative.
5.0 Organization, Responsibilities & Supervision
SITE TECHNICAL KEY PERSONAL
1. Project Manager • Responsible for overall planning, control and execution of the project in a cost-effective manner.
Mohd Najib • Overall authority in determination of all quality related matters affecting the project.
• Responsible to coordinate and handling with Employers for finalizing project and its related activities.
• Responsible to complete the Project within the schedule completion time frame.
2. Construction Manager • Managing construction activities to comply with schedule, budget and quality requirements.
Mohd Najib • Supervising and monitoring of all construction activities assisted by site engineer.
• To ensure all site staff are clear with the scope of works and time schedule.
• Organizing and managing all construction personnel, contractors and subcontractors for smooth execution of the project.
• Ensuring that all materials and equipment used in the construction work have passed all tests specified in the contract.
• Ensuring the sufficiency of resources to carry out the construction activities.
3. Project Engineer • Assist the PM to monitor project milestones and updating of project progress schedule together with scheduler.
(Electrical) • Attend progress meetings with the client and prepare minute of meeting.
Cliyopathra • Attend technical meetings and assist to resolve technical issues
4. QAQC Engineer • Coordination with Construction manager and project engineer on QAQC matters.
(Electrical) • To carry out stage and final inspection and Preparation of associated reports.
Cliyopathra • To raise NCR and initiate corrective action if the work done is not as per Specification, Method Statement or as per approved
drawing.
• Ensure that all materials used and work performed are in accordance with the specifications.
• Carry out internal inspection and after verifying the work done, raise Inspection for client/consultant Inspection.
• To check and ensure that the work done is as per Project Specification, Method Statement and as per approved drawings.
5. Site Supervisor • Assisting Site Engineer on Site Supervision and Construction work
Ahmad Fakhruddin • Coordinating all the related works between sub-contractors in order to ensure smooth flow of works.
6. Safety and Health • Compliance with the Employer's Environment, Health and Safety Policy
Officer • Implementation and management of the Contractor's Environment, Health and Safety Management Plan
Robert Kenny • Implementation and management of the Contractor's Emergency Planning and Response Plan;
7. Site Safety Supervisor To assist SHO for the following;
Alexander Empam • Compliance with the Employer's Environment, Health and Safety Policy
• Implementation and management of the Contractor's Environment, Health and Safety Management Plan
• Implementation and management of the Contractor's Emergency Planning and Response Plan;
6.0 QUALITY ASSURANCE
6.1 Inspection and Test Plan (ITP)
TEST TEST PERSONNEL INCHARGE INSPECTION FORM
No. ITEM ACCEPTANCE CRITERIA
METHOD FREQUENCY TESTED VERIFIED WITNESSED
1. Material Visual All • No visible damage. Site C.O.W / SEB Rep • Request for Inspection –
receiving • Approved /Accepted Material by Client Supervisor QAQC M&E Works
(SEB) / Site Engineer • Incoming Inspection
Engineer Checklist for Electrical
Equipment (Site)
2. Conduit, Visual Before, • No mechanical damage Site C.O.W / SEB Rep • Request for Inspection –
Trunking And during, and • Correct material type, size, location, Supervisor QAQC M&E Works
Cable Tray after quantity, and installation as per IFC / Site Engineer • Inspection Checklist -
Installation installation drawing and specification. Engineer Conduit, Trunking And
Works Cable Tray Installation
Works
3. Lightning Visual Before, • No visible damage Site C.O.W / SEB Rep • Request for Inspection –
protection during, and • Correct material type, size, location, Supervisor QAQC M&E Works
system after quantity, and installation as per IFC / Site Engineer • Pre-Installation Checklist
installation installation drawing. Engineer • Inspection Checklist -
Works • Test clamp installed at 1.5m from FFL. Lightning protection
• Exothermic Weld is properly done system
Earthing After work • The resistance of earth shall be less
Test complete than 1 ohms
4. LV Wiring Visual Before, • No visible damage to the cable's Site C.O.W / SEB Rep • Request for Inspection –
works during, and insulation Supervisor QAQC M&E Works
after • Correct cable size and type / Site Engineer • Pre-Installation Checklist
installation • Cable termination is properly fixed to Engineer • Inspection Checklist – LV
each socket/switch/equipment Wiring Works
Insulation After work • As per SEB project technical
Resistance complete specification.
Test
Continuity After work
Test complete
7.0 ENVIRONMENT, SAFETY AND HEALTH
7.1 Introduction
Occupational injuries and fatalities occur every day in the workplace. These injuries often
occur because employees are not trained in the proper job procedure. One way to
prevent workplace injuries is to establish proper job procedures and train all employees
in safer and more efficient work methods. Establishing proper job procedures is one of
the benefits of conducting a Job Safety Analysis (JSA) – carefully studying and recording
each step of a job, identifying existing or potential job hazards (both safety and health),
and determining the best way to reduce or eliminate these hazards.
Precautions are to be taken for protection of persons and properties from injury or
damage. All site personnel must adhere to safety requirements:
EMERGENGY
COMMANDER
INCIDENT SAFETY
EVACUATION SECURITY
CONTROLLER/ COUNTER &
CONTROLLER CONTROLLER
HISTORIAN FIRST AIDER
LEGAL REQUIREMENT
HAZARD IDENTIFICATION RISK ASSESSMENT RISK CONTROL/
RECOMMENDED ACTION
CONDITION
STEP SEQUENCE OF AND DATE PERSON
CURRENT RISK CONTROL ***
NO BASIC JOB STEP RISK RANKING IN CHARGE
* **
HAZARD EFFECT
LIKE SEV
SCORE
LEVEL
1 Excavation A R 1. Earth Major injury 1. Comply with SWMS and 3 3 9 M 1. Admin Control 1. Site Engineer
works collapse PTW system a. Tool box 2. Site
2. Fall in 2. Outage/ dead the power meeting Supervisor
3. Drowning supply b. PTW & S
4. Hit by 3. Tool box briefing before SWMS
5. Machinery start work c. Supervision
overturn 4. Competent operator d. House
5. Machinery checklist keeping
6. Proper supervision
7. Barricade with signage 2. PPEs
HAZARD IDENTIFICATION RISK ASSESSMENT
LEGAL REQUIREMENT
RISK CONTROL/ RECOMMENDED
CONDITION
ACTION AND DATE PERSON
STEP SEQUENCE OF ***
CURRENT RISK CONTROL RISK IN CHARGE
NO BASIC JOB STEP
* ** RANKING
HAZARD EFFECT
LIKE SEV
SCORE
LEVEL
2 Cutting floor A NR 1. Ear injury Major injury 1. Comply with SWMS 2 3 6 M 1. Site
using road 2. Eye injury 2. Inspect underground 1. Admin control Engineer
cutter 3. Lung utilities a. Tool box meeting 2. Site
infection 3. Safety briefing before start b. PTW & SWMS Supervisor
4. Flying work c. Supervision
objects 4. Proper supervisions d. House keeping
5. Vibration 5. Competent operator
6. Cut by 6. Machinery checklist 2. PPEs
7. Electrocuti 7. Proper PPEs: ear plugs,
on goggles, dust mask, cotton
glove
3 Mobilizing A NR 1. Hit by Minor injury 1. Comply with SWMS and 2 2 4 L 1. Admin control 1. Site
injection 2. Trip & fall PTW system a. Safety briefing Engineer
equipment to 2. Tool box talk briefing before start work 2. Site
cable cellar before start work b. PTW & SWMS superviso
3. Proper supervision r
4. Barricading with signage 2. PPEs
5. Proper PPEs
HAZARD IDENTIFICATION RISK ASSESSMENT
LEGAL REQUIREMENT
CONDITION
*** PERSON
STEP SEQUENCE OF RISK CONTROL/ RECOMMENDED
CURRENT RISK CONTROL RISK IN CHARGE
NO BASIC JOB STEP ACTION AND DATE
* ** RANKING
HAZARD EFFECT
LIKE SEV
SCORE
LEVEL
4 Cable laying A R 1. Ergonomi Minor injury 1. Comply with SWMS 2 2 4 L 1. Isolation 1. Site
c 2. Safety briefing before start a. Outage Engineer
2. Sharp work 2. Site
edges 3. Proper manual handling 2. Admin control Supervisor
3. Slip & fall 4. Use rubber stopper to a. Tool box meeting
4. Cut by cover sharp edges b. PTW & SWMS
5. Falling 5. Free supervisions
from 6. Proper PPEs 3. PPE
height
Conditions
R – routine
NR – non routine
Likelihood (L) Score
Most likely The most likely result of the hazard/ event being realized 5
Where L = Likelihood
S = Severity
Severity (S)
Likelihood (L) 1 2 3 4 5
5 5 10 15 20 25
4 4 8 12 16 20
3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
Type of job: Installation of Electrical System
Job Safety Analysis
Date: 13/9/2019
Personal Protective Equipment to be worn: Safety boot, safety vest, safety helmet & hand glove