Project Management With Cpm/Pert
Project Management With Cpm/Pert
WITH CPM/PERT
1
Project Management
• Project Definition
• Consists of a series of tasks (or activities) with
following characteristics
• Starting and ending dates
• Well-defined objectives
• Unique endeavor
• Utilizing resources
• Primarily Management Functions
• Planning
• Organizing
• Controlling
2
Project Management Functions
3
Project Management
• When to use
• Complex projects
• Several parallel tasks
• Predefined deadlines and milestones must be met
• Estimate project completion time
• Difficult to know when project is in trouble
• Limited and conflicting resources
4
Examples
5
Project Planning Process
6
Typical Questions for PM’s
7
Project Management Techniques
8
Critical Path Method (CPM)
9
Precedence Relations
A (Start) 8
B A 6
C A 8
D A 10
E B,C,D 4
10
Simple Project Network
“Activity on Node” AON representation
Successor
Precedence relations
represented by “arcs”
B
Predecessor
A
D E
Project Network 11
Simple Project Network
“Activity on Arc” AOA representation
2
B
6
E
A C 3 4
0 1 4
6 8
D
10
4
12
Activity Start/Finish Times
(AON)
Activity Name Early
Early Finish
Start Time
Time
ES EF
LS D LF
Late Late
Start Finish
Time
Time
Activity
Duration 13
Finding the Critical Path
A C
C E
14
Forward Pass
8 B 14
6
8 C 16
0 A 8 18 E 22
8 4
8
8 D 18
105
15
Backward Pass
8 B 14
12 6 18
8 C 16
0 A 8 18 E 22
10 8 18 18 4 22
0 8 8
8 D 18
8 105 18
16
Finding Activity Slack
S =EF-ES = LF-EF
8 B 14 S =18-14=4
14 6 18
S =8-8=0 S =22-22=0
8 C 16
0 A 8 18 E 22
10 8 18
0 8 8 18 4 22
S =18-16=2
8 D 18
Critical Path: Path with 5
zero activity slacks 8 10 18 S =18-18=0 17
Example
18
Project Network
E Finish
Start
C
B
G
19
PERT (Program Evaluation and
Review Technique)
20
Dealing with Uncertain Activity Duration
21
A Simple Example
A 2 8 14
B 3 6 9
C 5 7.5 13
D 3 10.5 15
E 2.5 2.5 11.5
22
Distribution Assumption
Beta distribution
density
a m b
activity
Expected Time = a + 4m + b
6 duration
Variance = (b - a) 2
36 23
Expected Duration & Variance
Activity A
a + 4m + b 2+4(8)+14
ET = = = 8.0
6 6
(b - a)2 (14-2)2
Var = = =4
36 36
24
Expected Duration & Variance
Expected Critical
Activity Variance
Time Path?
A 8 4 ?
B 6 1
C 8 1.77
D 10 4 ?
E 4 2.33 ?
25
Probability of Completion
Expected Completion
Normal
Distribution
z Due Date
26
Completion Probability Example
24 - 22
z= = 0.624
4 + 4 + 2.33
From a Z-table for standard Normal distributions:
27
Considering Time-Cost Trade-offs
28
Time-Cost Relationship
29
Example
30
Crashing An Activity
• Resource leveling
• How to schedule resources (equipment, people)
to minimizes
• Multiple resource scheduling
• How to schedule resources when activities can
require more than one resource type
• Cash flow and budgeting
• Combine cash and budget information with
project scheduling to track expenditures,
project cash flows
32
Online Vidoes
https://www.youtube.com/watch?v=4DlSIlcy2RA (CRASH)
https://www.youtube.com/watch?v=GRlXRYok3oQ (ESEF)
https://www.youtube.com/watch?v=bobDz_Bh3tI (LSLF)
https://www.youtube.com/watch?v=4oDLMs11Exs (Critical Path /
Duration)
https://www.youtube.com/watch?v=jmCc5VIMOro (Float / Slack)
https://www.youtube.com/watch?v=ErsolVw9UKE (Free Float)
https://www.youtube.com/watch?v=NDa-Fq5jeuM (Free Float /
Slack)
33