0% found this document useful (0 votes)
256 views33 pages

Project Management With Cpm/Pert

The document discusses project management techniques like CPM and PERT. CPM uses a network diagram to identify the critical path of a project, which is the longest sequence of dependent tasks. PERT adds uncertainty by using three time estimates per task, and calculates the expected duration and probability of on-time completion. Both techniques help plan projects, identify critical paths, and determine float or slack times. Time-cost tradeoffs can expedite projects by "crashing" tasks for added costs.

Uploaded by

Avanish
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
256 views33 pages

Project Management With Cpm/Pert

The document discusses project management techniques like CPM and PERT. CPM uses a network diagram to identify the critical path of a project, which is the longest sequence of dependent tasks. PERT adds uncertainty by using three time estimates per task, and calculates the expected duration and probability of on-time completion. Both techniques help plan projects, identify critical paths, and determine float or slack times. Time-cost tradeoffs can expedite projects by "crashing" tasks for added costs.

Uploaded by

Avanish
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 33

PROJECT MANAGEMENT

WITH CPM/PERT

1
Project Management

• Project Definition
• Consists of a series of tasks (or activities) with
following characteristics
• Starting and ending dates
• Well-defined objectives
• Unique endeavor
• Utilizing resources
• Primarily Management Functions
• Planning
• Organizing
• Controlling
2
Project Management Functions

 PM functions are to manage


 Cost and time
 Human resources
 Communication
 Contract/procurement
 Risk

3
Project Management

• When to use
• Complex projects
• Several parallel tasks
• Predefined deadlines and milestones must be met
• Estimate project completion time
• Difficult to know when project is in trouble
• Limited and conflicting resources

4
Examples

• Building a new airport


• Expanding a plant
• Designing a new product
• Construction projects of all types
• Maintenance projects
• R&D projects

5
Project Planning Process

 Define project objective(s)


 Identify activities
 Establish precedence relationships
 Make time estimates
 Determine project completion time
 Schedule activities
 Balance resources to meet objective(s)

6
Typical Questions for PM’s

 What is the the total time to complete a project?


 What are the scheduled start and finished dates for each
activity?
 Which activities are critical and must be completed on
time to keep the project on schedules?
 How long can noncritical activities be delayed before
they cause a delay in the project completion time?
 Is there any way to reduce the project completion time?
 How much money is needed to expedite the project
completion time?

7
Project Management Techniques

• Critical Path Method (CPM)


• Developed in 1950’s
• Planed and control maintenance job of a chemical
plant
• Reduced length of maintenance shutdown by 40%
• Project Evaluation and Review Technique (PERT)
• Developed in 1960’s
• Planed and control the Polaris missile project
• Speeded up project by 2 years

8
Critical Path Method (CPM)

• Graphical method of showing relationship of


project activities
• An activity or task --takes resources and time to
complete
• Precedence relations (some must be completed
before others can start) must be constructed
• Critical Path Method is the longest path through
the resulting project network

9
Precedence Relations

Activity Immediate Predecessor Duration (days)

A (Start) 8
B A 6
C A 8
D A 10
E B,C,D 4
10
Simple Project Network
“Activity on Node” AON representation

Successor
Precedence relations
represented by “arcs”
B
Predecessor

A
D E

Project Network 11
Simple Project Network
“Activity on Arc” AOA representation

2
B
6
E
A C 3 4
0 1 4
6 8
D
10
4
12
Activity Start/Finish Times
(AON)
Activity Name Early
Early Finish
Start Time
Time
ES EF

LS D LF
Late Late
Start Finish
Time
Time
Activity
Duration 13
Finding the Critical Path

A C
C E

14
Forward Pass

8 B 14
6

8 C 16
0 A 8 18 E 22
8 4
8
8 D 18
105
15
Backward Pass
8 B 14
12 6 18

8 C 16
0 A 8 18 E 22
10 8 18 18 4 22
0 8 8
8 D 18
8 105 18
16
Finding Activity Slack
S =EF-ES = LF-EF

8 B 14 S =18-14=4
14 6 18
S =8-8=0 S =22-22=0
8 C 16
0 A 8 18 E 22
10 8 18
0 8 8 18 4 22
S =18-16=2

8 D 18
Critical Path: Path with 5
zero activity slacks 8 10 18 S =18-18=0 17
Example

Consider the following activities of a project


Activity Predecessors Time (wks)
A. none 4
B. none 12
C. B 6
D. A 16
E. A,C 12
F. B 16
G. E,F 10
H. D,G 0

18
Project Network

E Finish
Start
C

B
G

19
PERT (Program Evaluation and
Review Technique)

• Similar to Critical Path Method (CPM)


• Uncertainty in activity duration
• Provides estimates of project duration
probabilities
• Best used for highly uncertain projects
• new product development
• first-time projects
• R&D projects

20
Dealing with Uncertain Activity Duration

 The PERT three-estimate Approach


 Most likely estimate (m)
 estimate of the most likely value of duration
 Optimistic estimate (b)
 estimate of the duration under the most favorable
conditions
 Pessimistic estimate (a)
 estimate of duration under the unfavorable
conditions

21
A Simple Example

Most Optimistic Most Likely Most Pessimistic


Activity (a) (m) (b)

A 2 8 14
B 3 6 9
C 5 7.5 13
D 3 10.5 15
E 2.5 2.5 11.5
22
Distribution Assumption
Beta distribution
density

a m b
activity
Expected Time = a + 4m + b
6 duration
Variance = (b - a) 2

36 23
Expected Duration & Variance

Activity A

a + 4m + b 2+4(8)+14
ET = = = 8.0
6 6
(b - a)2 (14-2)2
Var = = =4
36 36
24
Expected Duration & Variance

Expected Critical
Activity Variance
Time Path?
A 8 4 ?
B 6 1
C 8 1.77
D 10 4 ?
E 4 2.33 ?
25
Probability of Completion

Probability that a project will be completed by


a specified due date

Due Date - Expected Completion Date


z=
Sum of the Variances on the Critical Path

Expected Completion
Normal
Distribution

z Due Date
26
Completion Probability Example

What is the probability of completing the


project within 24 days?

24 - 22
z= = 0.624
4 + 4 + 2.33
From a Z-table for standard Normal distributions:

Probability of completion = 0.7324 = 73.2%

27
Considering Time-Cost Trade-offs

• If extra money is spent to expedite the project,


what is the least expensive way of attempting to
meet the target completion time?
• Define Normal and crash points
• Normal point shows the time and cost when an
activity is performed in the normal way
• Crash point shows the time and cost when an activity
is fully crashed

28
Time-Cost Relationship

• Assumed linear relationship

Crash (Crash cost-Normal cost)


Crash cost/wk=
Crash Cost (Normal time - Crash time)

Normal Cost Normal

Crash time Normal time

29
Example

Time (wk) Cost($1000)


Activity Normal Crash Crash Normal Max. Red. Cost/wk
A 8 6 10 8 2 2/2=1
B 6 5 7 5 1 2/1=2
C 8 5 10 4 3 6/3=2
D 10 9 8 6 1 2/1=2
E 4 3 7 6 2 1/1=1

30
Crashing An Activity

Activity Crash Path Path Path


to Cost ABE ACE ADE
Crash
18 20 22
A 1000 17 19 21
A 1000 16 18 20
D 2000 16 16 19
E 1000 15 15 18
31
Other Project Mgmt Techniques

• Resource leveling
• How to schedule resources (equipment, people)
to minimizes
• Multiple resource scheduling
• How to schedule resources when activities can
require more than one resource type
• Cash flow and budgeting
• Combine cash and budget information with
project scheduling to track expenditures,
project cash flows
32
Online Vidoes
 https://www.youtube.com/watch?v=4DlSIlcy2RA (CRASH)
 https://www.youtube.com/watch?v=GRlXRYok3oQ (ESEF)
 https://www.youtube.com/watch?v=bobDz_Bh3tI (LSLF)
 https://www.youtube.com/watch?v=4oDLMs11Exs (Critical Path /
Duration)
 https://www.youtube.com/watch?v=jmCc5VIMOro (Float / Slack)
 https://www.youtube.com/watch?v=ErsolVw9UKE (Free Float)
 https://www.youtube.com/watch?v=NDa-Fq5jeuM (Free Float /
Slack)

33

You might also like