1 TVF,TEF &TBF FlaktWoods Approved 11/4/2019 12/30/2019 3/2/2020 In Progress by 12/3/2019 3/17/2020 Awaited Issued 3/23/2020 Schedule Approval
01-04-2020 Requested
1.1 TBF -3300 N Witt & Sohn Submitted 2/20/2020 3/20/2020 3/16/2020 3/17/2020 Awaited
2 Air Cooled Chiller Trane Submitted 3/2/2020 4/10/2020 4/7/2020 Along with Technical Submittal NA
Schedule Approval
3 Tunnel Ventilation Dampers Trox Malaysia Approved 11/5/2019 12/28/2019 1/24/2020 2/10/2020 12/24/2019 3/17/2020 Awaited Issued 3/20/2020 Requested
4 ECS Fans Kruger India Submitted 2/14/2020 3/13/2020 2/22/2020 Vent Calc Approval +7 D D+7 Days
5 Pumps for HVAC System Grundfos(NS) Submitted 3/27/2020 5/7/2020 1/23/2020 Pump Head Calc Approval + 7 D D+7 Days
6 Air Handling Unit Waves Aircon Submitted 11/5/2019 12/23/2019 12/13/2019 Heat Load + Pressure Drop Calculation D+7 Days
+ 7D
8 Fan Coil Unit Waves Aircon Approved 11/5/2019 12/23/2019 2/13/2020 2/27/2020 12/13/2019 Heat Load Approval+ 7D D+7 Days Heat Load Approval
Pending
9 ECS Dampers( Non fire rated) Systemair Approved 11/4/2019 12/30/2019 1/25/2020 2/13/2020 12/31/2019 WRD Approval + 3D D+7 Days WRD Approval Awaited
10 ECS Dampers(Fire rated) Systemair Submitted 11/4/2019 12/30/2019 - 12/31/2019 WRD Approval + 3D D+7 Days
11 Compressed Air System Chicago Pneumatic Submitted 10/30/2019 1/1/2020 - 2/4/2020 VATA Approval + 3D D+7 Days
through OPC
12 MS & GI Pipes for HVAC & Fire Fighting Jindal Star Approved 10/7/2019 12/23/2019 2/3/2020 3/9/2020 PO Issued NA NA Issued 2/28/2020 WRD Approval Awaited
System 28-02-2020
13 Ducting Factory fabricated duct Waves Aircon Approved 11/4/2019 12/13/2019 1/7/2020 2/13/2020 12/9/2020 NA NA WRD Approval Awaited
15 Back Plate Damper (OTE) Systemair Approved 11/4/2019 12/30/2019 1/25/2020 2/13/2020 12/31/2019 3/27/2020 D+7 Days In Progess WRD Approval Awaited
MC to be issued in
16 Glass wool Insulation UP Twiga Approved 10/16/2019 12/23/2019 1/17/2020 2/13/2020 3/31/2020 NA NA eventual stages of the
project
MC to be issued in
17 Pipe Section Insulation Rockwool Approved 10/16/2019 12/23/2019 2/17/2020 2/27/2020 3/31/2020 NA NA eventual stages of the
project
MC to be issued in
18 Slab Insulation Rockwool Approved 10/16/2019 12/23/2019 2/11/2020 2/27/2020 3/31/2020 NA NA eventual stages of the
project
19 Sound Attenuator for ECS and TVS ETA Approved 1/10/2020 2/7/2020 2/17/2020 3/30/2020 Not Applicable Along with Technical Submittal D+7 Days
MC to be issued in
20 Grills & diffusers Systemair Approved 11/4/2019 12/23/2019 11/19/2019 05-04-2020 12/31/2019 RCP Approval + 7D D+7 Days eventual stages of the
project
21 UPE Grills Systemair Approved 11/4/2019 12/23/2019 11/19/2019 05-04-2020 12/31/2019 RCP Approval + 7D D+7 Days In Progess WRD Approval Awaited
Detailed Design to be
22 Tunnel Ventilation Nozzle WOLTER Ventilators Approved 12/18/2019 1/15/2020 2/26/2020 3/30/2020 1/2/2020 Nozzle Detailed Design + 7D D+7 Days submitted by ETA
24 ECS Valves ( Butterfly, Balancing & NRV) ADVANCE Approved 10/18/2019 12/16/2019 1/24/2020 2/7/2020 1/22/2020 WRD Approval + 7D D+7 Days Revised Schematics as per
DPS & ACC to be provided.
25 Motorised Butterfly Valve (ECS & FF) Belimo Approved 11/4/2019 12/16/2019 1/25/2020 2/10/2020 1/6/2020 WRD Approval + 7D D+7 Days WRD Approval Awaited
26 Fire Fighting Valve (BFV / NRV ) ADVANCE Approved 10/18/2019 12/23/2019 1/24/2020 2/7/2020 1/22/2020 WRD Approval + 7D D+7 Days WRD Approval Awaited
27 Flexible Coupling (ECS & FF) Resistoflex Approved 12/9/2019 1/6/2020 2/18/2020 4/3/2020 2/4/2020 WRD Approval + 7D D+7 Days WRD Approval Awaited
Combined Air & Dirt Separator, Gas In Progress by Revised Schematics as per
29 Flamcovent B.V. Approved 12/26/2019 1/23/2020 3/14/2020 4/2/2020 WRD Approval + 7D D+7 Days
Degasser 04-04-2020 DPS & ACC to be provided.
30 Drain Valve / Gate Valve / Ball Valve /Air Zoloto Approved 12/30/2019 1/27/2020 3/9/2020 4/5/2020 Direct PO shall be issued WRD Approval + 7D D+7 Days WRD Approval Awaited
Release Valve (ECS & FF) along with MC
31 Chemical Dosing Systems Water Engineers Submitted 1/3/2020 1/31/2020 Post Design Finalization NA NA
32 Y. Strainer (ECS & FF) SANT Approved 10/22/2019 12/16/2019 1/13/2020 2/14/2020 1/6/2020 WRD Approval + 3D D+7 Days WRD Approval Awaited
33 FCU Control Valve Advance/ Pettronolli Approved 11/5/2019 12/23/2019 2/13/2020 2/27/2020 12/13/2019 NA NA WRD Approval Awaited
1 ECS 33 33 0 6 26 24 11
2 TVS 4 4 0 0 4 4 1
3 E&M 17 17 0 4 10 10 8
4 Fire Fighting 10 10 0 2 9 9 6
5 BMS 1 1 0 0 1 1 0
Total 65 65 0 12 50 48 26
CE-23 : ICC & DHANSA 4/11/2020
MATERIAL TRACKING SCHEDULE
E&M
Electrical Panels & Distribution
1 Board Tricolite Submitted 12/31/2019 1/28/2020 3/3/2020 GAD Approval+3D D + 3 Days 4/15/2020 10-12 Weeks
Technical Submittal
2 DG Set Kirloskar Submitted 12/26/2019 1/23/2020 12/13/2020 Approval +3D D + 3 Days 5/4/2020 10-12 Weeks
Panel GAD
3 Bus Duct EAE Approved 12/9/2019 1/6/2020 2/20/2020 4/6/2020 2/18/2020 Approval+7D D + 3 Days 4/15/2020 10-12 Weeks
6 Pumps for Fire Fighting System Kirloskar Submitted 12/26/2019 1/23/2020 1/23/2020 Approval + 3D D + 3 Days 4/30/2020 12-14 Weeks
7 Pumps for Hydraulic System Grundfos Submitted 12/30/2019 1/27/2020 1/23/2020 Approval + 3D D + 3 Days 5/2/2020 14-16 Weeks
8 Lighting Systems BAJAJ Submitted 12/9/2019 1/6/2020
9 Lighting Systems HALONIX Submitted 1/30/2020 3/1/2020
Dialux Calculation
10 Lighting Systems SIGNIFY(Philips) Approved 2/4/2020 3/4/2020 3/6/2020 4/5/2020 1/16/2020 awaited from Vendor D + 3 Days 4/30/2020 08-10 Weeks
(Approval + 3D)
Scheme is not
Scheme is not finalized, finalized, Inputs is
11 UPS(NS) VERTIV Submitted 12/10/2019 1/7/2020 Inputs is required from D + 3 Days 14-16 Weeks required from
DMRC (Approval + 3D)
DMRC
12 Switches & Sockets NEPTUNE Submitted 12/9/2019 1/6/2020 3/11/2020 Approval + 3D D + 3 Days 5/10/2020 6-8 Weeks
WRD Approval WRD Approval
13 Cable Trays BEC Approved 10/4/2019 12/25/2019 12/20/2020 2/17/2020 1/15/2020 Awaited + 3D D + 3 Days 2/11/2020 Issued 6-8 Weeks Awaited
WRD Approval
14 Conduit BEC Approved 10/4/2019 12/4/2019 1/8/2020 2/14/2020 1/15/2020WRD Approval Awaited + 3DD + 3 Days 1/11/2020 Issued 4-6 Weeks Awaited
Earthing Materials (E&M and WRD Approval WRD Approval
15 ECS/TVS) BEC Approved 12/26/2019 1/23/2020 2/21/2020 3/30/2020 PO Issued Awaited + 3D D + 3 Days 4/2/2020 Issued 4-6 Weeks Awaited
FIRE TRACE
16 Panel Flooding System Through EKC Submitted 12/10/2019 1/7/2020 4/4/2020 GAD Approval+7D D + 3 Days 5/10/2020 10-12 Weeks
WRD Approval WRD Approval
17 GI Raceway BEC Approved 12/6/2019 1/4/2020 1/29/2020 3/19/2020 PO Issued Awaited + 3D 2/23/2020 Issued 4-6 Weeks Awaited
18 G I Structure for E&M and ECS Axxiom Submitted 12/26/2019 1/23/2020
19 G I Structure for E&M and ECS BEC Approved 2/5/2020 2/20/2020 2/21/2020 3/30/2020 PO Issued NA 4/5/2020 Issued 6-8 Weeks
20 G I Structure for E&M and ECS Newtech Approved 2/5/2020 2/20/2020 2/21/2020
21 Hydrant System Accessories AN Exflame Approved 11/19/2019 12/28/2019 2/22/2020 After Lockdown 2/23/2020 WRD Approval 4/25/2020 6-8 Weeks WRD Approval
Awaited + 3D Awaited
MC to be issued
22 Air Vessel Vir Engineers Approved 11/13/2019 12/28/2019 2/3/2020 4/5/2020 1/9/2020 NA NA 5/1/2020 8-10 Weeks with Hydrant
Accessories
23 Orifice Plate Vir Engineers Submitted 11/7/2019 12/28/2019 1/9/2020 Approval + 3D D + 3 Days 5/1/2020 8-10 Weeks
WRD Approval WRD Approval
24 FHC Door Vir Engineers Approved 11/7/2019 12/30/2019 11/29/2019 1/28/2020 1/9/2020 D + 3 Days 5/15/2020 8-10 Weeks
Awaited + 3D Awaited
WRD Approval WRD Approval
25 Fire Extinguisher A N Exflame Submitted 11/19/2019 12/30/2019 2/23/2020 D + 3 Days 4/26/2020 6-8 Weeks
Awaited + 3D Awaited
Cable Schedule Cable Schedule
26 Glands & Lugs Dowells Approved 12/2/2019 12/30/2019 2/18/2020 After Lockdown 3/11/2020 D + 3 Days 4/30/2020 6-8 Weeks
Approval + 3D Approval Awaited
27 Spray Nozzle HD Fire Submitted 12/3/2019 12/31/2019 2/28/2020 Approval + 3D D + 3 Days 5/5/2020 6-8 Weeks
28 Sprinkler HD Fire Submitted 12/3/2019 12/31/2019 2/28/2020 Approval + 3D D + 3 Days 5/5/2020 6-8 Weeks
29 Fire Alarm & Detection System Notifier Submitted 12/9/2019 1/6/2020 4/14/2020 Approval + 7D D + 3 Days 5/15/2020 10-12 Weeks
Scheme under Scheme under
30 BMS (Package) I2ST Approved 12/9/2019 1/6/2020 4/2/2020 4/5/2020 5/20/2020 10-12 Weeks discussion with
discussion with DMRC
DMRC
MANUFACTURING CLEARANCE STATUS