Methods of Splicing Reinforced Bars: Search

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 12

Search

Shop Merchandise














Home / How To Guide / Detailing Guide /Methods of Splicing Reinforced Bars

Posted in Detailing Guide, How To Guide, Structural Design, Structural Detailing, Structural Engineering

Methods of Splicing Reinforced Bars

Most of the reinforced concrete structures won’t be provided with full length
reinforced bars. The manufacture and transportation of long bars are difficult,
which limit the use of full length reinforced bars.
The method used to join the reinforcement bars, so that the force is transferred
effectively from one bar to the other is called as splicing. The integrity of the
concrete structure is dependent on proper splicing of the reinforcement bars.

Fig.1: Splicing of Reinforcement Bar

The forces are transferred from one bar to the other through bonds in concrete.
Force is first transferred to the concrete through bond from one bar and then it is
transferred to the other bar forming the splice through bond between it and
concrete. Thus, concrete at the point of splicing is subjected to high shear and
splitting stresses which may cause cracks in concrete. A properly designed
splicing is the key element in transmitting the forces through the reinforcement
bars by creating a proper load path.

Fig.2: Stirrups at splicing points


Methods of Reinforcement Splicing
1. Lap Splice

2. Mechanical Splice

3. Welded Splice
In India, the requirement of reinforcement bar splicing is covered in IS456
cl.25.2.5. The code also specifies that the splicing of flexural members should not
be at sections where the bending moment is more than 50% of the moment of
resistance, and not more than 50% of reinforcement bars should be spliced at any
given section. The splicing of bars should be carried out for alternate bars if more
than one bar has to be spliced.

1.Lap Splices
The lap splice is the most common and economic splice employed in the
construction. The welded splices and mechanical splices require more labour and
skill compared to lap splicing.

Fig.3: Splicing of bar >36mm diameter


The important points to be noted while providing lap splices in reinforcement
bars:

1. Laps in reinforcement should always be staggered. The center to center distances

of laps should not be less than 1.3 times the required lap length of the bars. The

bars to be lapped should be provided either vertically one above the other or

horizontally one beside the other.

2. The total lap length of bars including bends, hooks etc. in flexural tension should

not be less than 30 times the diameter of the bar of the full development length

Ld as calculated, whichever is greater.

3. Lap length in direct tension should be 30 times diameter of bar (30) or 2

Ld whichever is greater. Tension splices should be enclosed in spirals made from

6mm bars with pitch not more than 100mm. Hooks are also to be provided at the

end of the tension bars.


4. Lap length is compression should be more than 24 or Ld in compression. When

columns are subjected to bending, lap length may be also increased to the value in

bending tension if the bar is found to be in tension.

5. When two different diameters of bars have to be lapped, the lap length should be

calculated based on the diameter of the smaller bar.

6. Lap splicing of reinforcement bar more than 36mm in diameter should be

avoided. In case such bars have to be lapped then they should be welded. When

welding of cold bars is allowed, the special instructions applicable to these bars

should be followed.

7. Where the lapping of reinforcement bars have to be done in unusual

circumstances such as splicing in areas of large moments or more than 50% of the

bars have to be spliced, additional closely spaced spirals should be provided

around the lapped bars and the length of lap should be increased.

8. When bundled bars are to be spliced by lapping, one reinforcement bar at a time

is to be spliced and the splicing should be staggered.

9. If the general rules regarding laps cannot be obeyed in a construction, special

welded splices or mechanical connections should be provided (Cl. 25.2.5.2 of IS

456).

10. The use of lap splices will cause splice congestion issues that will demand for

some other splicing method. Congestion of rebars will create critical stress points

in rebars, difficulty for concrete to pass through, the splice length would be

insufficient.
2.Mechanical Splice
A mechanical splice or a joint make use of a coupler or a sleeve to splice two
reinforcement bars. The mechanical splicing is a new type of splicing in Indian
construction Industry.
Fig.4: Mechanical Joint >36mm diameter
The mechanical splice has many advantages compared to the conventional
method of overlapping. Some of them are:

 A continuous reinforcement bar is obtained through this coupler splicing. The

errors due to wrong lap length as in conventional method is avoided.

 The wastage of steel is reduced. Use of a mechanical joint helps to avoid lap

length. This will save appreciable amount of steel.

 We can use couplers as dowel bars. This will save the formwork material.

 The mechanical joints will not create any steel congestion as the lapping of bars

are eliminated.

 Couplers provides greater flexibility for the designers.

 The strength at the joint is easily analysed in the case of mechanical splice

compared to conventional lap joint.

Mechanical couplers are the most commonly used mechanical splice or joint for
reinforcement. The mechanical couplers can be of two types:

 Threaded Couplers

 Non-threaded couplers

Threaded Couplers: The threaded couplers are classified into two:

 Tapered Threaded Couplers: This type of tapered  couplers are fitted to one end of

the threaded rebar and the adjoining rebar is connected and tightened by means

of a calibrated torque wrench. The procedure is performed at the site.


Fig.5:Tapered Threaded Couplers (Image Courtesy : CSRI)

 Roll Threaded Couplers: In this type, the bars that are to be connected is pressed

by a set of rollers. These pressed ends are connected by a couplers with matching

and parallel threads.

Fig.6:Roll Threaded Couplers(Image Courtesy : CSRI)

Non-threaded Couplers: This type of couplers have variety of types which are
used in areas where the threaded couplers cannot be employed. The different
types are:

 Bolted Couplers

 Friction weld couplers

 Welded Couplers

 Swage Couplers
Fig.7:Swage Coupler (Image Courtesy: Incon)
The main application of non-threaded couplers are in repair works than new
construction works. These are higher in cost compared to threaded couplers and
hence are not extensively employed. The couplers used for this process are bulky
and installation process is slow.

3.Welded Splice
Welded splicing is not commonly used as it may affect the strength of the
reinforcement bars. Special conditions and rules are followed for welded splicing.

 The welded splicing is used for rebars with diameter greater than 36mm.

 If skilled labour is not there, the method is avoided

 Areas where there is rebar congestion and require greater moment strength, this

method is adopted.

 If we make use of bars that have bad specifications for weldability, this method is

not adopted.

Before undergoing welded reinforcement, it is necessary to have a proper


chemical analysis of the steel rebars, field inspection, the quality of the steel and
proper supervision.

Fig.8: Butt welding of reinforcement bar


 
Fig.9: Lap welding of reinforcement bar
 

 Facebook

Gopal Mishra
Gopal Mishra is a Civil Engineer from NIT Calicut and has more than 10 years of experience
in Civil Engineering and Construction. He is the founder of The Constructor.



Previous article

Curtailment of Reinforcement in Concrete Beams and Slabs

Next article

FIELD CONDITION SURVEY OF BUILDING


Related Posts

Corrosion Inhibiting Admixtures: Types, Dosages, and Applications

Functions of Admixtures in Fresh and Hardened State of Concrete


2 Comments

1.

Saw Yi Han

Added a comment on September 10, 2014 at 2:57 pm

I think no one is following this

o Login to Reply

o  Share
o

2.
Amit Patel
Added a comment on September 10, 2014 at 7:05 am

most of people not following this types in civil work.

o Login to Reply

o  Share
o
Leave a comment

You must login or register to add a new comment.


Login with:

Popular Articles

Concrete Mix Design Calculation for M20, M25, M30 Concrete with

Calculate Quantities of Materials for Concrete -Cement, Sand, Aggregates

Quantity of Cement and Sand Calculation in Mortar

Preparation of Bar Bending Schedule (BBS) and Its Advantages


Civil Engineering Tips - Points to Remember for Civil Site
Recent Articles

Corrosion Inhibiting Admixtures: Types, Dosages, and Applications


Functions of Admixtures in Fresh and Hardened State of Concrete

Factors Affecting Performance of Admixtures in Concrete

Precast Concrete Foundations- Features and Advantages


Injection Grouting: Purpose, Procedure, and Field Considerations

 Popular

 Answers

What are the difference between Tender and Contract Documents?

What are Bearing Capacity Values of Different Types of Soil?

What should be Minimum Ceiling Height for a Large Bedroom?

fly Ash Percentage in PPC Cements


Which Softwares are used to Estimate Project Time and Quantity in Construction?
 About Us
 Contact Us
 Privacy Policy
© 2009-2020 The Constructor. All Rights Reserved.

You might also like