Construction of 132/33kV GIS Substation at Sundarnagar: Jharkhand Urja Sancharan Nigam Limited BGR Energy Systems Limited

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Jharkhand Urja Sancharan Nigam Limited Construction of 132/33kV GIS Substation at Sundarnagar BGR ENERGY SYSTEMS LIMITED

ID Task Name Duration Start Finish Predecessors January July January July January July
E M B E M B E M B E M B E
1 Project Schedule : 132KV GIS Subsation, Sundernagar 810 days Sat 3/16/19 Fri 10/15/21
2 Project Key Dates 60 days Thu 1/30/20 Wed 4/8/20
3 Award of Contract 0 days Thu 1/30/20 Thu 1/30/20 1/30
4 Acceptance of Contract by BGR 2 days Thu 1/30/20 Fri 1/31/20 3
5 Submission of PBG to JUSNL 26 days Thu 1/30/20 Fri 2/28/20 3
6 Kickoff Meeting 26 days Thu 1/30/20 Fri 2/28/20 3
7 Site handover of land for Construction with Co-ordinates of 1 day Sat 2/29/20 Sat 2/29/20 6
Boundary marks
8 Contract Agreement Signing 26 days Thu 1/30/20 Fri 2/28/20 3
9 Soil investingation & Earthing Resistivity - Investigation and 27 days Sat 2/29/20 Tue 3/31/20 8
Report submission
10 Contour Survey - Submission 15 days Sat 2/29/20 Tue 3/17/20 8
11 Contour Survey - Approval 15 days Wed 3/18/20 Fri 4/3/20 10
12 Site Mobilisation 60 days Thu 1/30/20 Wed 4/8/20 3
13 Civil works 810 days Sat 3/16/19 Fri 10/15/21
14 Cutting / Filling 90 days Sat 4/4/20 Fri 7/17/20 11
15 Borewell 30 days Sat 4/4/20 Fri 5/8/20 14SS
16 Construction of Boundary Wall 90 days Sat 3/16/19 Fri 6/28/19
17 Construction of GIS Building 363 days Sat 7/18/20 Tue 9/14/21
18 Excavation 10 days Sat 7/18/20 Wed 7/29/20 14
19 PCC 3 days Thu 7/30/20 Sat 8/1/20 18
20 Fixing Water Proofing Membrane for Basement Raft Water 3 days Thu 8/6/20 Sat 8/8/20 19FS+3 days
Proofing
21 Screed over Water Proofing Membrane 3 days Mon 8/10/20 Wed 8/12/20 20
22 RCC for Basement - Raft 20 days Thu 8/13/20 Fri 9/4/20 21
23 Wall & Column 1st Lift - 4 Part (2days/Lift) 14 days Tue 9/8/20 Wed 9/23/20 22FS+2 days
24 Wall & Column 2nd Lift - 4 Part & Staircase 14 days Thu 9/10/20 Fri 9/25/20 23FS-12 days
25 Roof Slab 1st Part RL (+) 101.200 M & Staircase & Lift Wall 15 days Fri 9/18/20 Mon 10/5/20 24FS-7 days

26 De-Shuttering 5 days Thu 10/22/20 Tue 10/27/20 25FS+14 days


27 Roof Slab 2nd Part RL (+) 101.200 M & Staircase 15 days Mon 9/28/20 Wed 10/14/20 25FS-7 days
28 De-Shuttering 5 days Sat 10/31/20 Thu 11/5/20 27FS+14 days
29 Fixing Water Proofing Membrane for Basement Raft Side & 7 days Fri 11/6/20 Fri 11/13/20 28
Wall
30 Protection Brick Work 7 days Mon 11/9/20 Mon 11/16/20 29FS-5 days
31 BackFilling 7 days Tue 11/17/20 Tue 11/24/20 30
32 Column - 12 nos - 1st Lift (1st Part) 2 days Fri 10/9/20 Sat 10/10/20 25FS+3 days
33 Column - 12 nos - 2nd Lift (1st Part) 2 days Mon 10/12/20 Tue 10/13/20 32
34 Roof Slab 1st Part RL (+) 105.400 M & Staircase 15 days Wed 10/14/20 Fri 10/30/20 33
35 De-Shuttering 5 days Tue 11/17/20 Sat 11/21/20 34FS+14 days

Task Project Summary Manual Task Start-only Deadline

Project: Civil Works Split Inactive Task Duration-only Finish-only Progress


Date: Tue 3/31/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
Jharkhand Urja Sancharan Nigam Limited Construction of 132/33kV GIS Substation at Sundarnagar BGR ENERGY SYSTEMS LIMITED

ID Task Name Duration Start Finish Predecessors January July January July January July
E M B E M B E M B E M B E
36 Column - 18 nos - 1st Lift (2nd Part) 6 days Mon 10/19/20 Sat 10/24/20 27FS+3 days
37 Column - 18 nos - 2nd Lift (2nd Part) 6 days Wed 10/21/20 Tue 10/27/20 36FS-4 days
38 Tie Beam 2nd Part RL (+) 105.400 M & Staircase 15 days Fri 10/23/20 Mon 11/9/20 37FS-4 days
39 De-Shuttering 5 days Thu 11/26/20 Tue 12/1/20 38FS+14 days
40 Column - 12 nos - 1st Lift (1st Part) 2 days Wed 11/4/20 Thu 11/5/20 34FS+3 days
41 Roof Slab 1st Part RL (+) 108.600 M & Staircase 15 days Fri 11/6/20 Mon 11/23/20 40
42 De-Shuttering 5 days Thu 12/10/20 Tue 12/15/20 41FS+14 days
43 Column - 18 nos - 1st Lift (2nd Part) 4 days Fri 11/13/20 Tue 11/17/20 38FS+3 days
44 Tie Beam 2nd Part RL (+) 108.600 M & Staircase 15 days Mon 11/16/20 Wed 12/2/20 43FS-2 days
45 De-Shuttering 5 days Sat 12/19/20 Thu 12/24/20 44FS+14 days
46 Column - 12 nos - 1st Lift (1st Part) 2 days Fri 11/27/20 Sat 11/28/20 41FS+3 days
47 Roof Slab 1st Part RL (+) 111.800 M & 8Staircase 15 days Mon 11/30/20 Wed 12/16/20 46
48 De-Shuttering 5 days Sat 1/2/21 Thu 1/7/21 47FS+14 days
49 Column - 18 nos - 1st Lift (2nd Part) 4 days Mon 12/7/20 Thu 12/10/20 44FS+3 days
50 Tie Beam 2nd Part RL (+) 111.800 M & Staircase 15 days Fri 12/11/20 Mon 12/28/20 49
51 De-Shuttering 5 days Thu 1/14/21 Tue 1/19/21 50FS+14 days
52 Column - 12 nos - 1st Lift (1st Part) 2 days Mon 12/21/20 Tue 12/22/20 47FS+3 days
53 Column - 12 nos - 2nd Lift (1st Part) 2 days Wed 12/23/20 Thu 12/24/20 52
54 Roof Slab 1st Part RL (+) 116.000 M & Staircase 15 days Fri 12/25/20 Mon 1/11/21 53
55 De-Shuttering 5 days Thu 1/28/21 Tue 2/2/21 54FS+14 days
56 Column - 18 nos - 1st Lift (2nd Part) 6 days Sat 2/6/21 Fri 2/12/21 55FS+3 days
57 Column - 18 nos - 2nd Lift (2nd Part) 6 days Tue 2/9/21 Mon 2/15/21 56FS-4 days
58 Roof Slab 2nd Part RL (+) 116.000 M & Staircase 15 days Thu 2/11/21 Sat 2/27/21 57FS-4 days
59 De-Shuttering 5 days Wed 3/17/21 Mon 3/22/21 58FS+14 days
60 Column - 12 nos - 1st Lift (1st Part) 2 days Fri 1/15/21 Sat 1/16/21 54FS+3 days
61 Column - 12 nos - 2nd Lift (1st Part) 2 days Mon 1/18/21 Tue 1/19/21 60
62 Roof Slab 1st Part RL (+) 120.200 M & Staircase 15 days Wed 1/20/21 Fri 2/5/21 61
63 De-Shuttering 5 days Tue 2/23/21 Sat 2/27/21 62FS+14 days
64 Column - 18 nos - 1st Lift (2nd Part) 6 days Thu 3/4/21 Wed 3/10/21 58FS+3 days
65 Column - 18 nos - 2nd Lift (2nd Part) 6 days Sat 3/6/21 Fri 3/12/21 64FS-4 days
66 Roof Slab 2nd Part RL (+) 120.200 M & Staircase 15 days Tue 3/9/21 Thu 3/25/21 65FS-4 days
67 De-Shuttering 5 days Mon 4/12/21 Fri 4/16/21 66FS+14 days
68 Column - 12 nos - 1st Lift (1st Part) 2 days Wed 2/10/21 Thu 2/11/21 62FS+3 days
69 Column - 12 nos - 2nd Lift (1st Part) 2 days Fri 2/12/21 Sat 2/13/21 68
70 Roof Slab 1st Part RL (+) 124.40 M & Staircase 15 days Mon 2/15/21 Wed 3/3/21 69
71 De-Shuttering 5 days Sat 3/20/21 Thu 3/25/21 70FS+14 days
72 Column - 18 nos - 1st Lift (2nd Part) 6 days Tue 3/30/21 Mon 4/5/21 66FS+3 days
73 Column - 18 nos - 2nd Lift (2nd Part) 6 days Thu 4/1/21 Wed 4/7/21 72FS-4 days
74 Roof Slab 2nd Part RL (+) 124.400 M & Staircase 15 days Sat 4/3/21 Tue 4/20/21 73FS-4 days

Task Project Summary Manual Task Start-only Deadline

Project: Civil Works Split Inactive Task Duration-only Finish-only Progress


Date: Tue 3/31/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
Jharkhand Urja Sancharan Nigam Limited Construction of 132/33kV GIS Substation at Sundarnagar BGR ENERGY SYSTEMS LIMITED

ID Task Name Duration Start Finish Predecessors January July January July January July
E M B E M B E M B E M B E
75 De-Shuttering 5 days Fri 5/7/21 Wed 5/12/21 74FS+14 days
76 Column - 6 nos - 1st Lift (1st Part) 2 days Mon 3/8/21 Tue 3/9/21 70FS+3 days
77 Column - 6 nos - 2nd Lift (1st Part) 2 days Wed 3/10/21 Thu 3/11/21 76
78 Roof Slab 1st Part RL (+) 128.600 M & Staircase 10 days Fri 3/12/21 Tue 3/23/21 77
79 De-Shuttering 5 days Fri 4/9/21 Wed 4/14/21 78FS+14 days
80 Column - 7 nos - 1st Lift (2nd Part) 2 days Sat 4/24/21 Mon 4/26/21 74FS+3 days
81 Column - 7 nos - 2nd Lift (2nd Part) 2 days Tue 4/27/21 Wed 4/28/21 80
82 Roof Slab 2nd Part RL (+) 128.600 M & Staircase 10 days Thu 4/29/21 Mon 5/10/21 81
83 De-Shuttering 5 days Thu 5/27/21 Tue 6/1/21 82FS+14 days
84 Finishing Works 90 days Wed 6/2/21 Tue 9/14/21 83
85 Construction of Operation Buildings 272 days Thu 7/30/20 Fri 6/11/21
86 Excavation 7 days Thu 7/30/20 Thu 8/6/20 14FS+10 days
87 PCC 5 days Mon 8/3/20 Fri 8/7/20 86SS+3 days
88 Raft 5 days Thu 8/6/20 Tue 8/11/20 87SS+3 days
89 Column upto Plinth Beam 10 days Wed 8/12/20 Sat 8/22/20 88
90 Plinth Beam 10 days Mon 8/24/20 Thu 9/3/20 89
91 Column upto Lintel Beam 10 days Fri 9/4/20 Tue 9/15/20 90
92 Lintel Beam 10 days Wed 9/16/20 Sat 9/26/20 91
93 Column upto Ground Floor Roof Slab 10 days Mon 9/28/20 Thu 10/8/20 92
94 Ground Floor Roof Slab 15 days Thu 10/1/20 Sat 10/17/20 93FS-7 days
95 Column upto First Floor Roof Slab 15 days Mon 10/19/20 Wed 11/4/20 94
96 First Floor Roof Slab 15 days Wed 10/28/20 Fri 11/13/20 95FS-7 days
97 Column upto Second Floor Roof Slab 15 days Sat 11/14/20 Tue 12/1/20 96
98 Second Floor Roof Slab 15 days Tue 11/24/20 Thu 12/10/20 97FS-7 days
99 Brick Work 60 days Sat 11/14/20 Fri 1/22/21 96
100 Internal & External Plastering 60 days Wed 1/6/21 Tue 3/16/21 99FS-15 days
101 Internal & External Painting 60 days Fri 3/5/21 Thu 5/13/21 100FS-10 days
102 Finishing Works 120 days Sat 1/23/21 Fri 6/11/21 99
103 Equipment Foundation & Cable Trenchs 120 days Sat 9/26/20 Fri 2/12/21 14FS+60 days
104 Construction of DG Buildings 120 days Sat 8/22/20 Fri 1/8/21 14FS+30 days
105 Tower Foundation and Structures 120 days Sat 9/26/20 Fri 2/12/21 14FS+60 days
106 Road & Drain works 150 days Sat 2/13/21 Fri 8/6/21 105
107 Final Levelling and Metal filling 60 days Sat 8/7/21 Fri 10/15/21 106
108 Plumbing Works 120 days Sat 2/13/21 Fri 7/2/21 14FS+180 days

Task Project Summary Manual Task Start-only Deadline

Project: Civil Works Split Inactive Task Duration-only Finish-only Progress


Date: Tue 3/31/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3