0% found this document useful (0 votes)
159 views1 page

Checklist For Excavation: Sl. No Description Points Yes No Remarks

This checklist provides instructions for excavation at the KMI Project Assembly Shop location. It includes 7 points to check such as barricading the area, following the excavation sequence, obtaining MEP clearance, ensuring proper trimming and leveling to specifications, dewatering if needed, compaction, and applying anti-termite treatments if required. The checklist is to be completed by the site engineer and L&W QA/QC engineer to ensure all excavation steps are properly followed.

Uploaded by

Gabriel Gabe
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
159 views1 page

Checklist For Excavation: Sl. No Description Points Yes No Remarks

This checklist provides instructions for excavation at the KMI Project Assembly Shop location. It includes 7 points to check such as barricading the area, following the excavation sequence, obtaining MEP clearance, ensuring proper trimming and leveling to specifications, dewatering if needed, compaction, and applying anti-termite treatments if required. The checklist is to be completed by the site engineer and L&W QA/QC engineer to ensure all excavation steps are properly followed.

Uploaded by

Gabriel Gabe
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CHECKLIST FOR EXCAVATION

Project : KMI Project - Assembly Shop


Location / Structure : Date :

Ref Drawing Number :

Sl. No Description Points Yes No Remarks

1 Check for Area Barricated.

2 Check for sequence of excavation.

3 Check for MEP clearence before excavation.

Check for trimmed and levelled to specific profile and


4
dimension.

5 Check for Dewatering.

6 Check for compaction.

7 Check for anti termite if required.

Site
L&W QA/QC Engineer HEC
Engineer